C. 2008 Street Reconstruction Project: Update on Feasibility Study & Citizen Comments
CITY OF
CHANHASSEN
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317
Administration
Phone: 952.227.1100
Fax: 952.227.1110
Building Inspections
Phone: 952.227.1180
Fax: 952.227.1190
Engineering
Phone: 952.227.1160
Fax: 952.227.1170
Finance
Phone: 952.227.1140
Fax: 952.227.1110
Park & Recreation
Phone: 952.227.1120
Fax: 952.227.1110
Recreation Center
2310 Coulter Boulevard
Phone: 952.227.1400
Fax: 952.227.1404
Planning &
Natural Resources
Phone: 952.227.1130
Fax: 952.227.1110
Public Works
1591 Park Road
Phone: 952.227.1300
Fax: 952.227.1310
Senior Center
Phone: 952.227.1125
Fax: 952.227.1110
Web Site
www.ci.chanhassen.mn.us
e
......, .Ml
MEMORANDUM
Paul Oehme, Director of Public Warks/City Engineer \f? OJ .
TO:
FROM:
Alyson Fauske, Assistant City Engineer
o~
DATE:
December 10, 2007
SUBJECT: 2008 Street Reconstruction, Project No. 08-01: Update on
Feasibility Study & Citizen Comments
BACKGROUND
On September 24, 2007, City Council awarded the consultant contract to Kimley-
Horn and Associates and authorized the preparation of a feasibility report.
A neighborhood meeting was held on November 14,2007. Eighty-six (86)
notices were sent out far the meeting. Approximately 40 residents attended the
meeting.
DISCUSSION
The City's pavement management program recommends that streets in the Laredo
Drive area be reconstructed in 2008. City Staff receives more complaints about
the condition of Laredo Drive from residents and the traveling public then any
other street in the system. The public utilities in the area are old, have had many
problems and should be replaced or repaired. Approximately 1.35 miles of streets
are proposed to be reconstructed. The area for improvements include: Laredo
Drive, Laredo Lane, Longview Circle, Cimarron Circle and Highland Drive (west
of Laredo Drive).
The streets are proposed to be reconstructed. approximately the same.vvtclthBs the
existing streets, 28' wide. Laredo Drive betweenWest78thStreetandFrp):'ltier
Trail is proposed to be built to a 31-foot wide urban streeFsection.The
reconstruction project will include the improvement or replacement of mOSt
public utilities within the reconstruction project area. A map of the 2008 Street
Reconstruction Project Area is attached. More detail about the project is available
in the Council background for acceptance of the feasibility study.
QUESTIONS/CONCERNS RAISED AT THE NEIGHBORHOOD
MEETING
Staff received many questions and comments regarding the project from property
owners at the neighborhood l1}e,e,ti'llg..,..,~9~.~ofthe questions were answered at the
meeting. Other specific property questions were answered with individual
property owners at a later date.
The City of Chanhassen · A growing community with clean lakes, quality schools, a charming downtown, thriving businesses, winding trails, and beautiful parks. A great place to live, work, and play.
Paul Oehme
2008 Street Improvement Project WS Update
December 10,2007
Page 2
Below are most of the questions and comments that were received:
Pavement Condition
. Why has the street been allowed to deteriorate to this condition?
. The quality of the current road is an issue. Is the City obligated to award
the contractto the lowest bidder? How do we know the lowest bidder will
construct a quality street?
. Why doesn't the City restrict the number of waste haulers? These trucks
wreck the street.
Street design
. It is dangerous to take a left turn off of Laredo Lane on to Laredo Drive.
Will this be fixed?
. Will the road width change?
. What percentage of streets are rural sections (i.e. no curb and gutter)?
. What if we do not want curb and gutter? If we're paying 40% of the street
cost, we should be able to vote on whether curb and gutter is installed.
. Instead of installing curb and gutter, why can't rain gardens be installed?
. How much of our yard will be impacted by adding curb and gutter?
Assessments
. No one will argue that Laredo Drive needs to be improved, but we're all
shell-shocked with the price.
. Why doesn't the City pay 100% of the project cost? In the past the City
didn't assess for street projects.
. What is the assessment methodology?
. Do surrounding communities assess for street improvements?
. Why aren't assessments based on traffic volumes?
. Would my assessment decrease if Laredo Drive [between West 78th Street
and Frontier Trail] wasn't included in the project?
. How many residential properties are being assessed?
. When will we know the exact amount of the assessment?
. My property taxes just increased by $1,000.00 last year. I may not be able
to afford the proposed assessment.
. I am a senior citizen on a fixed income and may not be able to afford the
assessment.
. If our property values increase as a result of the project, our property taxes
will also increase.
. Are assessments tax deductible?
. Does the City make any money on the 6% interest that is charge with the
assessment?
Utilities
. How far back from the curb will the sanitary sewer be replaced if there is a
problem?
G:\ENGIPUBLIC\_2008 Projects\08-01 2008 Street lmprovements\12-1O-07 worksession.doc
Paul Oehme
2008 Street Improvement Project WS Update
December 10,2007
Page 3
. Will small utilities have a chance to upgrade their infrastructure?
. Will the overhead utility lines be buried?
. Are street lights included in the project?
Miscellaneous
. Will a sidewalk be installed on Laredo Drive north of Frontier Trail?
. Will traffic count data be presented at the public hearing?
. Will we have to take down our mailboxes?
. Will driveways be replaced?
. Will trees and landscaping be replaced?
. What happens if my boulevard tree dies as a result of the project?
. How will the street project affect the groundwater levels?
. What happens to my in-ground sprinkler system?
. I want a guarantee in writing from the City that the City will pay to
replace my underground sprinkler system that is within the public right of
way.
. How would the project affect the 4th of July parade route?
Staff will give a brief update to the council on the project at the work session and
briefly address the questions listed above.
Attachment
c: Chadd Larson, Kimley-Hom
Kim Benson, Kimley-Hom
G:\ENGIPUBLICI_2008 Projectsl08-01 2008 Street Improvementsll2-1O-07 worksession.doc
~ l-OneSIOlga~'
~ --t~
Q)
.c
Q; -r? -/'1./'\
~ 9 I
>--<: ---,
'---
I
"
,
'--Oar(
/
~
~
"'-'
4
~~q
~0<'
,<,0
5
3
".'" ~ '1
~~ r 00'00' ,,"
45~ ~
~ ~ 13\ 12 11 10 \
47 40 >----
- - r-----
__-- \ a~~ ~ :: 114 ~\16 17 ~ 1
~ 1) ~ ~35\34\33A .....18 19 20 21 ::.(2.3
J.......1 ~--I 51 36 ~
~ _ ) \ \12 ~8 59 '" 32 31 30 29 28 27 26125\24
~ _ -\ <"57\:>- 'b
ChippewaCI ,u \; 56 T. 60 \; V
_ __ V =---- M 5 61 Del Rio Drive
----c:. ~ ~2 'r 55 62
- lr r 73r........~, 63
~r---- 0L 74/:;[!1r~ 64
/ ~ T I a _unve ~ 65
'" ~ra Drive ~ 66
~~. In 75 68('.. 0
~6>1s ~ Del.-- ~ ,"Ia Fe
<9,... ~
~ ~
!~\j
~
5t Village Road
m
~
2
I
7
6
9
8'
----:: 1
L-
Highland
Drive
'"
o?~.
~
~
~
)
r ~\ 7 ~~l
~WD ~~ btc j
~ 2-r--
'" ffil -1
Trail(/) (/)- ""[ _
,...--
I
w
76th
5t
-
76
86
a
.0
C
o
0;
~
-
85
c
a
:J
- 'm
,=~
84
]
77
83
82
81
-
OJ
----J
80
-~ -- ~
~~~c
l 1
I II~
L~
Chan View
78
79
-
'--
=
-
-
(W 78th 51)
W 78th 5t
J f
I
I __JI I T
I
~
I
T I
I I
N
+
2008 Street Project
300 150 0
1""'"\....--
300
I Feet
November 5, 2007
g:\eng\public\08-01 2008 Street Improvements\MapslAssessment Map.mxd