91-28
-
City of Chanhassen
Carver and Hennepin counties, Minnesota
DATE: April 8. 1991
MOTION BY: Winq
RESOLUTION NO:
91-28
SECONDED BY:
Chmiel
A RESOLUTION APPROVING CONTRACT AMENDMENT #1, AUDUBON ROAD
SOUTH, PROJECT 89-18
WHEREAS, Contract Amendment No. 1 to the Audubon Road South
Project 89-18 is necessary because the original engineer's estimate
for professional services did not include costs for survey
construction staking. Additionally, an amendment to the contract
is necessary to complete work on the project in the spring of 1991.
These items are detailed in the letters from Chester Harrison,
Project Engineer, HNTB dated April 2 and March 28, 1991.
NOW, THEREFORE, BE IT RESOLVED by the Chanhassen City Council
that Contract Amendment No. 2 is hereby approved, increasing the
total contract amount to $65,600.
e Passed and adopted by the Chanhassen City Council this 8th day
of April, 1991.
ATTEST:
I{l.
Don Ashworth,
(~
---:.--~
C1ty Clerk/Manager
NO
YES
ABSENT
Chmiel
Dimler
Mason
Winq
Workman
None
None
.