DATE: September 24. 1990
MOTION BY: Dimler
RESOLUTION NO:
90-119
SECONDED BY:
Workman
A RESOLUTION RE-INITIATING THE FEASIBILITY STUDY FOR THE
WEST 78TH STREET DETACHMENT PROJECT, PHASE I,
IMPROVEMENT PROJECT NO. 87-2
WHEREAS, the feasibility study for the West 78th Street
Detachment project was originally completed in July, 1987; and
WHEREAS, on August 28, 1989 the City Council reinitiated the
project because construction bids were not let within one year of
authorizing the project as required by State Statute.
WHEREAS, this proj ect has encountered numerous delays and
obstacles surrounding the development proposals for this segment of
West 78th Street between Kerber Boulevard and County Road 17.
NOW, THEREFORE, BE IT RESOLVED BY THE CHANHASSEN CITY COUNCIL
that. the feasibility study update for the West 78th Street
Detachment Project 87-2 as prepared by BRW, Inc., is approved.
Further, that a public hearing is hereby scheduled for October 8,
1990.
Passed and adopted by the Chanhassen City Council this 24th
day of September, 1990.
ATTEST:
la~
Don Ashworth, ity Clerk/Manager
.
YES
NO
ABSENT
Chmiel
Johnson
Dimler
Workman
None
None