90-125 A e , " e e ~~ City of Chanhassen Carver and Hennepin Counties, Minnesota DATE: October 8. 1990 RESOLUTION NO: 90-125A MOTION BY: Johnson SECONDED BY: Dimler A RESOLUTION APPROVING CONTRACT AMENDMENT NO.2, COUNTRY HOSPITALITY SUITES PROJECT 89-25 WHEREAS, Contract Amendment No. 2 to the Country Hospitality Suites Project 89-25 is described in detail in a letter from BRW dated October I, 1990 (attached). The overall changes result in a total deduct of $3,940.06. NOW, THEREFORE, BE IT RESOLVED by the Chanhassen City Council that Contract Amendment No.2 resulting in a deduct of $3,940.06 is hereby approved, decreasing the total contract amount to $320,097.89. Passed and adopted by the Chanhassen City Council this 8th day of October, 1990. ATTEST: Ll~ Don Ashworth, City Clerk/Manager YES NO ABSENT Chmiel Johnson Workman Dimler None None ... . :~glll~'" ~._-~ PLANNING TRANSPORTATION ENGINEERING URBAN DESIGN SRW INC THRESHER SOUARE 700 THIRD STREET SOUTH MINNEAPOLIS MINNESOTA55415 PHONE 612370-0700 FAX 612/370 1378 October 1, 1990 Mr. Gary Warren, PE City Engineer City of Chanhassen 690 Coulter Drive Chanhassen, MN 55317 CITY OF CHANHASSEN rnm~mnWl~m OCT 031990 RE: COUNTRY SUITES HOTEL C. P. 89-25 CONTRACT AMENDMENT NUMBER TWO ENGINEERING DEPT. Dear Mr. Warren: Please find enclosed six copies of Contract Amendment Number Two for the above referenced project for your approva 1. The amendment has been prepared to i nc 1 ude new bid i terns and rev i sed cont ract quant it i es as requ i red by the fo 11 owi ng modifications to the project: e A. Watermain Repair - Dinner Theatre The plans and specifications specified the installation of Ball Joint Watermain pipe to address concerns about the stability of the fill area where the watermain was to be constructed. Subsequent to receipt of bids, we reviewed the cost of Ball Joint Pipe, the site, and discussed this further with the contractor. It was our conclusion that restrained joint -watermain was a more cost effective solution for this installation and we directed the contractor to proceed with the installation of restrained joint rather that Ball Joint Pipe. B. Subgrade Correction - Country Suites Hotel Site preparation and subgrade correction were the responsibility of the developer prior to the construction of the Parking Lot Base by this contractor. However, this work was not completed by the developer. - -They requested that this work be completed by the City contractor in order to save time and to allow improved coordination of the work. e At the request of the developer and your direction we directed the contractor to proceed with subgrade excavation and the restoration to subgrade uti lizing Geotexti le Fabric and extra depth aggregate base as summarized by Item Number Two of Contract Amendment Number Two. AN AFFILIATE Of THE BENNETT RINGROSE WOLSFELD. JARVIS INC GROuP DAVID J BENNETT DONALD W RINGR05E RICHARD P WOLSFELD PETER E JARVIS THOMAS F CARROlL CRAIG A AMUNDSEN DONALD E HUNT MARK G SWENSON JOHN B McNAMARA RICHARD D PILGRIM DALE N BECKMANN DENNIS J SUTLIFF JEFFREY L. BENSON RALPH C BLUM DAVID L GRAHAM GARY J ERICKSON MINNEAPOLIS DENVER PHOENIX TUCSON ST. PETERSBURG SAN DIEGO e e e P' .. Mr. Gary Warren September 28, 1990 Page 2 C. Watermain Repair - Dinner Theatre An existing hydrant along the Dinner Theatre lot remained connected to the old watermain (to be abandoned) in order to provide fire protection service. Once the new watermain was constructed, the old hydrant was disconnected from the old watermain and reconnected to the new watermain. This work had not been included in the contract documents previously. D. Remove Bituminous Pavement - Animal Fair Removal of existing bituminous pavement and site preparation was the responsibility of the developer prior to the construction of the parking lot by this contract. This work was not completed by the developer. They requested that this work be completed by the City contractor in order to save time and to allow improved coordination of the work. We recommend approval and payment of this contract amendment. Sincerely, riGhq~ Project Manager GAE/lml cc: Mr. Jim Thompson, Alber Construction , Mr. Greg Roy, BRW, Inc. Fil e 7-9007