88-22 A - e e ~ CITY OF CHANHASSEN CARVER AND HENNEPIN COUNTIES, MINNESOTA DATE: March 14, 1988 RESOLUTION NO: 88-22A MOTION BY: Hamilton Boyt SECONDED BY: A RESOLUTION APPROVING CHANGE ORDER NO. 1 DOWNTOWN REDEVELOPMENT PROJECT 86-11A WHEREAS, Change Order No. 1 to the Downtown Redevelopment Project Phase I is necessary to cover items of work not covered by the original contract bid items, as well as to modify those current bid items which have significantly changed through the course of the project. All change order items are summarized in a letter from Gary Ehret from BRW, Inc., dated March 9, 1988. NOW, THEREFORE, BE IT RESOLVED BY THE Chanhassen City Council that Change Order No. 1 in the amount of $291,201.66 be approved and a revision of the total contract amount to $2,725,772.96. Passed and adopted by the Chanhassen City Council this 14th day of March , 1988. ATTEST: Don&th'~ dl YES ABSENT NO Hamilton Boyt Johnson Horn Geving None None e ffir ]...~ ~~i~: ~:- ""';,~~L~ I, r~". " ~ ~ \a-' PLANNING TRANSPORTATION ENGINEERING ARCHITECTURE BENNETT. RINGROSE. WOlSFELD. JARVIS. GARDNER. INC . THRESHER SOUAHE . 700 THIRD STREET SOUTH . MINNEAPOLIS. MN 55415 . PHONE 612/370-0700 March 9, 1988 City of Chanhassen 690 Coulter Drive Chanhassen, MN 55317 Attn: Mr. Gary Warren, P.E. City Engineer CITY OF CHANHASSEN oorn@rnuwrnoo MAR 1 0 1988 ENGINEERING DEPT. RE: Contract Status Downtown Redevelopment Project CP 86-11 Dear Mr. Warren: e Partial Payment #6 for Shafer Contracting was submitted to your office for review, approval, and payment in the amount of $100,158.21 on March 8, 1988. This payment is based upon $1,728,953.62 of approved work todate on the downtown project. The partial payment has been made based upon completed work items which have contract unit bid prices. Several areas of work have been completed but contract unit bid prices are not in force so these items have not been paid. Change Order Number One (1) to the downtown project is being submitted for approval and City Council action at this time. This change order is intended to cover items of work not covered by the original contract bid items, as well as to modify those current bid items which have significantly changed thru the course of the project. This letter and change order are intended to provide both you and the City Council the following information: 1. Contract Status Update 2. Projected Contract Status 3. Summary Explanation of Change Order Number One In regard to the contract status update, upon approval of the City Council, the revised contract will be: Original Contract Amount Change Order Number One (1) Revised Contract Amount $2,434,571.30 291,201.66 $2,725,772.96 e DAVID J BENNE TT DONALD W RINGROSE RICHARD P WOLSFELD PETER E JARVIS LAWRENCE J GARDNER THOMAS F CARROLL CRAIG A AMUNDSEN DONALD E HUNT MARK G. SWENSON JOHN B McNAMARA DONALD L CRAIG RICHARD D PILGRIM DALE N BECKMANN DENNIS J SUTLIFF MINNEAPOLIS DENVER PHOENIX .~-..,..::." . . .... ,;~ :\ I I I I I I I I I I I I I I I I :1 11. Mr. Gary Warren . March 9, 1988 Page 2 e Change Order Number One addresses all significant contract additions or increases todate; however, it does not address contract deletions, reductions, or potential changes this spring. We have reviewed the contract as well as the work completed todate and have found that there will be additional significant changes to the contract prior to completion of the project. Included in these changes are contract quantity underruns, change order deductions, and reduced compensation due to the contractor's failure to meet the project specifications. In order to illustrate the projected contract status we offer the following surrmary: PROJECTED CONTRACT STATUS $2,434,571. 30 291,201.66 5,000.00 <29,000.00> <3,500.00> <18,750.00> $2,679,522.96 Original Contract Amount Add Change Order Number One (1) Add Change Order Number Two (2) (Future) Deduct Projected Quantity Underruns Deduct Contractor Penalties Deduct Future Change Order Ie It is important to note that this projected contract status is based wholly upon the scope of work identified in Shafer Contracting1s current contract. Any scope of work changes, whether reductions or additions, obviously have an impact on this projection. Finally, we offer an encapsulated explanation of the changes illustrated in Change Order Number One, which is attached to this letter. As you are aware, we have reviewed each of the change order items with you previously and BRW will provide detailed support documentation for each of the changes. We offer the following line item sunmary by bid schedule and item number: J I I I I I I I- I Bid Schedule A - General Work Item No. Change Sunmary Quantity understatement in bid documents. 3, 4 22 28, 29, 31 Fencing salvaged for construction of north side parking lot. Quantity overruns precipitated by substantially increased areas of excavation due to expansion of work or the revised roadway section which included a uniform two-foot subcut over a substantial portion of the project. e Mr. Gary Warren March 9, 1988 Page 3 Item No. Change Summary Aggregate Class Two was used with limited discretion, assisting business traffic, both customers and owners/ operators, in traveling to the downtown businesses. 33 37 Water was used with limited discretion in attempting to control dust throughout the project. Old building rubble was excavated from the site of the tem- porary north side parking lot. 40 41 Overtime costs incurred, due to authorization to contractor to work overtime to complete TH 101 improvements as quickly as possible. Signage used throughout the project area to alert motorists to the special conditions in the downtown area. 42 43 Detour signage necessary at railroad crossing with Great Plains Boulevard/TH 101. e 44, 45, 46 47 Items of work without a contract bid price. The contract specified disposal of excavated material within 1/2-mile of project site. 6,255 cubic yards were hauled to sites outside of the 1/2-mile radius. '* Please note approximate parking lot project. that costs associated with Items 22, 28, 31, 33, and 40, in the total amount of $11,000.00 are a part of the temporary north side construction and as such should not be charged to the downtown Bid Schedule (B) - Roadway/Parking Lot Item No. Change Summary Additional aggregate base has been used in several areas out- side of the original contract including the paved median areas, access road, and north side parking lot. 1 22 Item of work without a contract bid price. Used for dust control. 23, 24 Protective fencing used for pedestrian traffic control in uncompleted work areas during winter shutdown. e -.- :.:.". t I I I I I I I I I I I I I I I I I I J' ~ I I I I I I I Ie I I J I I J I Ie I Mr; Gary Warren March 9, 1988 Page 4 25 26 Traffic barrier as required by MnDOT for railroad detour. Extra costs associated with placement of concrete curb and gutter after November 1, 1987. * Please note that a portion of the costs ~ssociated with Bid Item Number 1 in the amount of $9,300.00 is a part of the temporary north side parking lot construction and as such should not be charged to the downtown project. Bid Schedule (C) - Storm Sewer Item No. Change Summary Quantity understatement in bid documents 22 38 Buried concrete chunks discovered, excavated, and disposed of while excavating for storm sewer. Item of work not covered by contract bid price. Used to con- nect Chanhassen State Bank roof drains to storm sewer system. 39 40 Specially constructed manhole used in storm sewer alignment offset at Laredo Drive (Manhole 11X). 41 Interim connections between new and existing storm sewer at Great Plains Boulevard and TH 101 for winter shutdown. 42 Item of work not covered by contract bid price. Used to con- nect Chanhassen State Bank roof drains to storm sewer system. 43 Item of work not covered by contract bid price. Special casting used for driveway change at Browns Amoco. Bid Schedule (D) - Sanitary Sewer Item No. Change Summary Trench stabilization rock overrun due to very poor soil con- ditions encountered while installing sewer. 14 29 thru 38 Items of work not covered by contract bid price. 39 Sanitary sewer backfill behind Colonial Square used to replace unsuitable material. . Mr. Gary Warren March 9, 1988 Page 5 e Bid Schedule (E) - Watermain Item No. Change Surrmary Items of work not covered by contract bid price. 41 thru 46 47 Costs incurred when a stop order was given the contractor upon commencement of jacking excavation on TH 101. Repairs to existing water services for KlingelhutzRealty when services failed at connection to old main. 48 Bid Schedule (F) - Site Work. Item No. Change Summary Contractor reinstalled existing Type C signs for winter operation. 16 Please advise me if I can offer additional clarification to any of the change order items, or if further definition of the contract status is desired. e Sincerely, ~RINGRO~LSF ~ ~tqE. Project Engineer INC. GAE/sk Attachment e -1 --- I I I I I I II II II I I I I II 'I ....j:..:~}.J .~I')PY t ,-,,- "'", '1 ~ '. ,"'''! \-,,,P CITY OF CHANHASSEN ':;or.tractor Copy !nspector Copy I- CONTRACT CHANGE ORDER Project: Downtown Redevelopment Project - Improvement Project No.: 86-11 Change Order No.: One (1) Date: March 14, 1988 I Contractor: Shafer Contracting, Inc. I Description of contract changes: ADD I Bid Schedule (A) - General Work Unit 1 Item No. Item Unit Quantity Price Extension 3 Clearing Tree 200 $ 50.00 $ 10,000.00 I 4 Grubbing Tree 200 50.00 10,000.00 22 Salvage Split Rail Fence LF 500 1.50 750.00 28 Common Excavation CY 8,159 2.00 16,318.00 29 Subgrade Excavation CY 11 ,000 2.00 22,000.00 l J 31 Granular Borrow CY 9,650 5.00 48,250.00 33 Aggregate Surfacing Cl. 2 Ton 1,550 7.00 10,850.00 37 Water 1,000 300 10.00 3,000.00 Ie 40 Rubble Excavation CY 1,259 5.00 6,295.00 41 . Overtime Costs LS 1 7,487.56 7,487.56 42 Specialty Signs LS 1 7,500.00 7,500.00 43 Railroad Detour Signage LS 1 8,350.00 8,350.00 J 44 Salvage Castings EA 14 150.00 2,100.00 45 Abandon Manhole EA 4 200.00 800.00 46 Abandon Hydrant EA 1 150.00 150.00 I 47 Excavation Haul Premium CY 6,255 1.35 8,444.25 $ Subtotal 162,294.81 I ADD Bid Schedule (B) - Roadway/Parking Lot I Unit Item No. Item Unit Quantity Price Extension I 1 Aggregate Base Placed Ton 13,000 $ 6.10 $ 79,300.00 Cl. 5 I 22 Calcium Chloride (80#) Bag 6 50.00 300.00 23 F & I Plastic Snow Fence LF 100 2.50 250.00 24 F & I Wood Snow Fence LF 250 2.50 625.00 25 F & I Precast Barrier LF 110 25.00 2,750.00 I 26 Winter Concrete Costs LS 1 500.00 500.00 I- Subtotal Addition $ 83,725.00 1 of 3 I .J 1, '~"'..' ~ ADD - Bid Schedule (C) - Storm Sewer e Unit Item No. Item Unit Quantity Price Extension 22 72" RC Pipe Sewer LF 110 $ 155.00 $ 17,050.00 38 Concrete Excavation CY 360 14.00 5,040.00 39 12" PVC Storm Sewer LF 252 14.00 3,528.00 40 Construct Special Manhole EA 1 1,865.00 1,865.00 41 Connect to Existing EA 2 500.00 1,000.00 Storm Sewer (Special) i 42 Construct MH - Design H EA 1 650.00 650.00 43 Install Special Casting EA 1 162.18 162.18 Subtotal $ 29,295.18 I ADD Bid Schedule (D) - Sanitary Sewer I Unit J Item No. Item Unit Quantity Pri ce Extension - 14 Crushed Rock Pipe Bedding Ton 350 $ 20.00 $ 7,000.00 I 29 6" PVC Sani tary Sewer LF 57 11.00 627.00 . I 30 6" PVC Bend EA 5 25.00 125.00 31 8" PVC Tee EA 1 40.00 40.00 e 32 8" PVC Bend EA 2 50.00 100.00 I 33 10" PVC Wye EA 2 100.00 200.00 34 6" CI Plug EA 4 50.00 200.00 35 6" CI Wye EA 3 150.00 450.00 I 36 6" CI Bend EA 1 125.00 125.00 37 8" CI Plug EA 2 75.00 150.00 38 Reconstruct Manhole LF 13 200.00 2,600.00 39 Trench Backfill CY 350 2.00 700.00 I Subtotal $ 12,317.00 ADD I Bid Schedule (E) - Watermain I Unit Item No. Item Unit Quantity Price Extension - I 41 6" Hydrant Extension EA 2 $ 450.00 $ 900.00 42 Stop Box Rods EA 8 15.00 120.00 43 6" Cl Sleeve EA 2 100.00 200.00 I 44 8" CI Sleeve EA 3 100.00 300.00 45 1011 Cl Sl eeve EA 1 150.00 150.00 46 1011 MJ Pl ug EA 1 100.00 100.00 I 47 WM Conflict/Jacking LS 1 200.00 200.00 48 Watermain Services Repair LS 1 949.67 949.67 e Subtotal $ 2,919.67 J 2 of 3 J . ~ A , I I I I I I I . I I I I I I I Ie I ./) ", .. 'ADD Bid Schedule (F) - Site Work Item No. Item Y.!li! Quantity 16 Reinstall Existing Type C Sign EA 13 CONTRACT SUMMARY Current Contract Amount Schedule (A) Additional Schedule (B) Additional Schedule (C) Additional Schedule (D) Additional Schedule (E) Additional Schedule (F) Additional Contract Change Order No. 1 Total Additional $162,294.81 83,725.00 29,295.18 12,317.00 2,919.67 650.00 Amended Contract Amount Current Completion Date Additional Days Due to Change Order Amended Completion Date June 1, 1988 o June 1, 1988 APPROVALS: ISSUED BY: Beff~Ringros BY: /r Unit Price - Extension $ 50.00 $ 650.00 Subtotal $ 650.00 $2,434,571.30 $ 291,201.66 $2,725,772.96 ~ ~ -Jarvis-Gardner. Inc. ~~ " Date: 3 /.1 ?Y / ACCEPTED BY: Shafer Contracting, Inc. BY: Date: APPROVED BY: City of Chanhassen BY: Date: 3 of 3