4b. Public Works Facility Site Plan Review
CITY OF
CHANHASSEN
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317
Administration
Phone: 952.227.1100
Fax: 952.227.1110
Building Inspections
Phone: 952.227.1180
Fax: 952,227.1190
Engineering
Phone: 952.227.1160
Fax: 952,227.1170
Finance
Phone: 952,227.1140
Fax: 952.227.1110
Park & Recreation
Phone: 952,227.1120
Fax: 952,227.1110
Recreation Center
2310 Coulter Boulevard
Phone: 952.227,1400
I
Fax: 952.227.1404
Planning &
Natural Resources
Phone: 952.227.1130
Fax: 952,227,1110
Public Works
1591 Park Road
Phone: 952.227.1300
Fax: 952.227.1310
Senior Center
Phone: 952.227,1125
Fax: 952.227.1110
Web Site
WNW.ci .chanhassen .mn. us
4b
~I\~z.
MEMORANDUM
TO:
Todd Gerhardt, City Manager
FROM:
Bob Generous, Senior Planner
o~'
DATE:
January 26,2009
SUBJ:
CHANHASSEN PUBLIC WORKS FACILITY
Planning Case #08-25
PROPOSED MOTION
A. "The Chanhassen City Council approves a Site Plan for an 82,500 square-
foot, one-story office/warehouse building with a mezzanine storage area and
setback Variances from the creek and wetland for the parking lot area, plans
prepared by Oertel Architects and the City of Chanhassen, dated 12/05/08,
subject to conditions 1 - 24 of the staff report.
B. "The Chanhassen City Council approves a Conditional Use Permit for
outdoor storage, subject to condition 1 of the staff report."
And,
Adoption of the attached Planning Commission Findings of Fact.
City Council approval requires a majority vote of City Council present.
EXECUTIVE SUMMARY
The City's Public Works Department is requesting site plan approval for an 82,500
square-foot public works building with a conditional use permit for outdoor storage
areas. The variance requests are to permit the parking lot to be closer to the wetland
and the creek than is permitted by ordinance. In developing the plan for the site, the
City did investigate several site plan configurations for the project. The site plan
configuration being reviewed includes the minimum variance request while
providing for the needs of the public works operation.
While the ordinance specified 70 trees for the parking lot, the City is preserving
the large wooded area to the west of the building. In the past, staff has allowed
the clustering of required plantings on site to meet ordinance requirements.
Therefore, staff has determined that the approximately 5 acres of preserved
woodlands west of the building satisfies the City requirements for landscaping.
Chanhassen is a Community for Life - Providing for Today and Planning for Tomorrow
Todd Gerhardt
January 26, 2009
Page 2 of 2
PLANNING COMMISSION SUMMARY
The Planning Commission held a public hearing on January 6,2009 to review the proposed project.
The Planning Commission voted 4 for and 0 against a motion recommending approval of the public
works facility site plan with variances, and the conditional use permit to allow the outdoor
storage.After hearing the justification for the variance request, the Planning Commission did not
have any issues or concerns regarding approval of the project.
RECOMMENDA TION
Staff recommends adoption of the motion as specified on pages 13 - 14 in the staff report dated
January 6,2009 approving the Chanhassen Public Works Facility, Planning Case #08-25.
ATTACHMENT
1. Planning Commission Staff Report Dated January 6, 2009.
g:\plan\2008 planning cases\08-25 public works facility site plan\executive summary. doc
PC DATE: January 6,2009
OJ
CITY OF CHANHASSEN
CC DATE: January 26,2009
REVIEW DEADLINE: February 3, 2009
CASE #: 08-25
BY: AF, RG, TJ, ML, JM, JS
PROPOSED MOTION: "The Chanhassen Plafl.-Hng Commissiofl reeoffimoo.ds that City Council
approves the Site Plan for Planning Case #08-25, for an 82,500 square-foot, one-story
office/warehouse building with a mezzanine storage area with a Conditional Use Permit for
outdoor storage, and setback Variances from the creek and wetland for the parking lot area, plans
prepared by Oertel Architects and the City ofChanhassen, dated 12/05/08, subject to the
conditions of the staff report."
And adopts the attached Planning Commission fmdings.
SUMMARY OF REQUEST: The City ofChanhassen Public Works Department is requesting
a Site Plan Review with Variances for an 82,500 square-foot public works building with a
Conditional Use Permit for the outdoor storage areas - CHANHASSEN PUBLIC WORKS
FACILITY.
LOCATION: Lots 5 & 6, Block 1, Chanhassen Lakes Business Park 5th Addition (7901 Park
Place)
APPLICANT: City of Chanhassen
7700 Market Boulevard
P.O. Box 147
Chanhassen, MN 55317
(952) 227-1100
PRESENT ZONING: Industrial Office Park (lOP)
2020 LAND USE PLAN: Office/Industrial
ACREAGE: 11.95 acres DENSITY: 0.16 F.A.R
LEVEL OF CITY DISCRETION IN DECISION-MAKING:
The City's discretion in approving or denying a site plan is limited to whether or not the
proposed project complies with Zoning Ordinance requirements. If it meets these standards, the
City must then approve the site plan. This is a quasi-judicial decision.
The City's discretion in approving or denying a variance is limited to whether or not the
proposed project meets the standards in the Zoning Ordinance for a variance. The City has a
relatively high level of discretion with a variance because the applicant is seeking a deviation
from established standards. This is a quasi-judicial decision.
The City has limited discretion in approving or denying conditional use permits, based on
whether or not the proposal meets the conditional use permit standards outlined in the Zoning
Ordinance. If the City finds that all the applicable conditional use permit standards are met, the
permit must be approved. This is a quasi-judicial decision.
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 2 of 15
The public hearing notice has been mailed to property owners within 500 feet of the proposed
development.
PROPOSAL/SUMMARY
The City's Public Works Department is requesting site plan approval for an 82,500 square-foot
public works building with a conditional use permit for outdoor storage areas. The variance
requests are to permit the parking lot to be closer to the wetland and the creek than is permitted by
ordinance.
The proposed development will occur on
two lots of record: Lots 5 and 6, Block 1,
Chanhassen Lake Business Park 5th
Addition. All this area is zoned lOP. The
property to the north of the site contains
Paisley Park. The property immediately
to the east is a City owned outlot
containing woodlands and Riley Creek.
The property to the south is vacant and
contains portions of a large wetland
complex which crosses over onto this site.
The property to the west across Audubon
Road contains Pillsbury, a vacant
industrial property, and a day care facility.
Water and sewer service is available to the
site in Park Place. Access to the site will
be provided via Park Place.
The high point of the property is on the west side with an elevation of974. The low point is in the
south central portion of the property in the wetland with an elevation of approximately 920. While
there is over a 50-foot elevation change on the property, there are no bluffs on the property since the
slope does not exceed 25 percent (a bluff must have both an elevation change of25 feet or more and
a slope of30 percent or greater). The western half of the property is heavily wooded. A wetland
exists in the south central portion of the property and extends onto the property to the south. A
wooded corridor along Riley Creek is located to the east of the properties.
Staff is recommending approval of the Site Plan Review to permit an 82,500 square-foot public
works building with variances from the wetland setback and creek setback, and a conditional use
permit for the outdoor storage. As part of the process, the City will create a zoning lot of the two
lots creating, in effect, one building site. Additionally, the City must vacate some drainage and
utility easements and a portion of the right-of-way.
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 3 of 15
APPLICABLE REGUATIONS
Chapter 20, Article II, Division 3, Variances
Chapter 20, Article II, Division 6, Site Plan Review
Chapter 20, Article IV, Conditional Uses
Chapter 20, Article VI, Wetland Protection
Chapter 20, Article VII, Shoreland Management District
Chapter 20, Article XXII, lOP Industrial Office Park District
Chapter 20, Article XXIII, Division 7, Standards for Commercial, Industrial and Office-Institutional
Developments.
BACKGROUND
On September 8,2008, the City Council approved an Interim Use Permit to permit up to 15,000
cubic yards of fill on the site.
On March 17, 1986, the Chanhassen City
Council approved the plans and specifications
for Chanhassen Lakes Business Park 5th
Addition, which constructed Park Place.
On August 19, 1985, the Chanhassen City
Council approved the Chanhassen Lakes
Business Park 5th Addition (Subdivision #85-9)
creating seven lots in two blocks, one outlot and
right-of-way for Park Place. Such subdivision
re-platted Lots 2 through 10, Block 1,
Chanhassen Lakes Business Park.
~
~
.~:-.~~
~f~~
:?'"'~--..,
On July 2, 1979, the Chanhassen City Council approved the development contract for Chanhassen
Lakes Business Park.
On June 4, 1979, the Chanhassen City Council approved the final plat for Chanhassen Lakes
Business Park.
On April 17 , 1978, the Chanhassen City Council approved the rezoning of the property from R -1 A,
Agricultural Residence District, to P-4, Planned Industrial District and preliminary plat approval of
the proposed plat (PUD #75-1). Additionally, the City approved Resolution 78-18 authorizing the
proposed North Lake Susan Sanitary Sewer, Water, Street and Storm Sewer Improvement Project
#78-3 and Resolution 78-19 establishing the centerline for the right-of-way for the extension of
Powers Boulevard from Highway 5 to Lyman Boulevard.
In 1976, the City approved a Comprehensive Plan Amendment changing 150 acres in this area from
Low Density Residential to Industrial.
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 4 of 15
GENERAL SITE PLAN/ARCHITECTURE
~
The applicant is requesting site plan approval for an 82,500
square-foot, one-story office/warehouse building with a
mezzanine storage area with outdoor storage areas to the rear
of the building and setback variances for the parking lot area
from Riley Creek to the east and the wetland to the south.
I- 0.' C
I
II.
..., (
I
I
.1
. ai~
I'
:.,
I.
I
ARCHITECTURAL COMPLIANCE
Size Portion Placement
The main entrance to the building is located in the southeast comer of the building. The building
entrance consists of full-story store front, glass windows and doors. A metal canopy is proposed
over the entrance.
Material, Color and Detail
Materials consist of ribbed, insulated, precast tip-up concrete panels with exposed aggregate
incorporating random smooth banding and brick. The office area and all portions of the building
that project from the plane ofthe building are completely in brick. The concrete would be light
gray with a buff-colored stone exposed aggregate. The brick we are proposing is a modular-
sized brick in a dark brown earth tone with a color-matched mortar. The majority of the pre-
finished metal (overhead doors, coping, fascia, etc.) will be a charcoal gray color with dark
bronze accents at elements such as signage and window trims.
Clerestory windows are provided around the building with the use of large window areas over
the office area and the vehicle maintenance bays. These upper level windows will permit natural
lighting. Full-length store-front type windows are included in the office area of the building in
addition to the more traditional aluminum-framed windows in the offices and multi-purpose
room. The proposed glass is a low-e I-inch insulated glass with a medium bronze tint. The
Height and Roof Design
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 5 of 15
window frames will be anodized aluminum. Soldier courses of brick are proposed above the
windows and at the top of the brick walls.
The building height varies depending on the area of the building. Building roofs are proposed to
be flat. Parapet heights go to 26 feet in the vehicle maintenance and welding bays, 24 feet in the
vehicle storage and shop areas, 20 feet in the wash bays, and 14 and 19' 8" in the office areas.
The varying roof heights provide architectural interest to the building.
Mechanical equipment, if visible to the public, will be screened with prefinished metal screening.
Facade Transparency
Over 50 percent of the first floor elevation in the office area that is viewed by the public includes
transparent windows and/or doors. All other areas shall include landscaping material and
architectural detailing and articulation.
For buildings with a use or function that does not readily allow windows, e.g., cooler or freezer
areas, mechanical rooms, security areas, storage areas or warehouse or manufacturing space in
commercial or industrial buildings, the fenestration standards may be reduced. However, the
architecture detailing must be provided by the use of upper level windows, the use of spandrel
glass or architectural detailing which provides arches, patterning, recesses and shadowing that
provide aesthetic interest.
Site Furnishing
Community features may include landscaping, lighting, benches, tables, etc. The development
has a proposed patio area on the east side of the building. Additionally, a significant landscape
area is being preserved at the southeast comer of the building.
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 6 of 15
Loading Areas, Refuse Area, etc.
Screening of service yards, refuse
and waste removal, other unsightly
areas and truck parking/loading
areas is provided by locating such
areas on the north side of the
building. Since this site is at the end
of a cul-de-sac, the public will not,
generally, be able to view these areas
without entering the site.
Lot Frontage and Parking Location
Parking areas are located to the east and south side of the building. Due to the site's location at
the end of a cul-de-sac, only a few parking stalls are provided between the right-of-way and the
building.
LIGHTING/SIGNAGE
Area lighting is provided in the parking lot islands east of the building as well as at the refueling
station. Lighting height is 30 feet with shoebox type fixtures and high-pressure sodium light
bulbs. Additionally, wall-mounted light fixtures are proposed on the building with architectural
sconce lighting and arm-mounted box lighting.
The plans show a wall sign on the east side of the building just north of the entrance with a
maple leaf and 12-inch high aluminum letters. Signage shall require a separate sign permit
review to determine compliance with City ordinance.
COMPLIANCE TABLE
lOP
Public Works
Building Height
4 stories
50 feet
1 story
26 feet
Building Setback
N - 10' E - 50'
W - 25' S - 40'
N - 70' E - 145'
W - 370' S - 140'
Parking Stalls
59 stalls
60 stalls
(Municipal building 1/500 with 8,475 sq. ft. of office equals 17 stalls. Warehouse 1/1,000 for
first 10,000, then 1/2,000 thereafter with 74,025 sq. ft. of warehouse equals 42 stalls.)
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 7 of 15
Parking Setback
lOP
N - 10' E - 50'#
W - 25' S - 40'#
Public Works
N - 5' E - 25' #
W - 370' S - 0' #
Hard Surface Coverage
70%
57%
#Variances from the setbacks to Riley Creek and the wetland for the parking lot area are
included as part of the development review application.
ACCESS
Access to the site is provided via Park Place.
LANDSCAPING
Minimum requirements for landscaping include 17,696 square feet oflandscaped area around the
parking lot, two landscape islands or peninsulas, 70 trees for the parking lot, and bufferyard
plantings along the property lines. The applicant's proposed as compared to the requirements for
landscape area and parking lot trees is shown in the following table.
Required Proposed
Vehicular use landscape area 17,696 sq. ft. >17,696 sq. ft.
Trees/parking lot 70 trees 22 trees
Islands or peninsulas/parking lot 2 islands/peninsulas 2 islands
The minimum requirements for the parking lot trees have not been met. The applicant is
proposing to preserve a large wooded area to the west of the building and will be installing
bufferyard plantings where necessary. The proposed islands do not meet ordinance
requirements for minimum interior width. Staff recommends that the southern island meet the
10- foot minimum and the north island with the proposed trees have a 15- foot interior width.
Bufferyard requirements:
Bufferyard B - north prop. Line, 400'
Bufferyard B - south prop. Line, 200'
Bufferyard B - east prop. Line, 400'
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 8 of 15
Bufferyard B - west prop. Line, 400'
STREETS, SITE ACCESS AND SITE CIRCULATION
There are no public streets proposed or required for development of this site. Park Place
provides access to the site. No right-of-way acquisition is required for the public street.
The existing terminus of Park Place is a 100-foot diameter cul-de-sac within a l20-foot diameter
right-of-way. The entire paved cul-de-sac will be removed and some paving will be necessary in
the right-of-way.
The southern access is 36 feet wide and will provide access to the cold storage area of the
building. The northern access is shown as approximately 47 feet wide. The northern access
must be revised so that the maximum width does not exceed 36 feet.
A portion ofthe parking area lies within the existing l20-foot diameter cul-de-sac right-of-way.
The proposed public use ofthe property does not necessarily warrant vacating the cul-de-sac
right-of-way; however, should the property be sold in the future, the parking lot improvements
may need to be removed and a standard public cul-de-sac installed. An encroachment agreement
is required for the portion of the parking area that lies within the public right-of-way.
GRADINGIDRAINAGE
The site was mass graded under an Interim Use Permit approved by City Council on September
2, 2008. Final grading will occur with the construction of the building and parking lot. Runoff
from the majority of the site will be conveyed to the off-site stormwater treatment pond southeast
of the site via storm sewer.
Roof drains along the west side of the building will outlet to a drainage swale on the west side of
the building which discharges to the wetland south of the building.
Runoff from the access to the cold storage area is proposed to outlet to the wetland. If feasible,
this runoff should be conveyed to the existing storm sewer so that it can be treated by the
existing stormwater basin.
Revised drainage calculations and storm sewer sizing must be submitted to ensure that the
existing downstream infrastructure can accommodate the proposed runoff.
Three retaining walls are proposed on the site. A 280-foot long wall is proposed along the north
side of the paved area with a maximum height of 14 feet. This wall will be constructed within
the existing drainage and utility easement and will therefore require an encroachment agreement.
Chanhassen Public Works Facility
Planning Case 08-25
January 6,2008
Page 9 of 15
The second wall is a 100-foot long wall around a 45-inch oak tree on the south side of the
building with a maximum height of four feet. A lIS-foot long wall is proposed on the south side
of the access to the cold storage area; the maximum height of this wall is four feet.
The proposed top and bottom of wall elevations must be shown. Walls taller than four feet must
be designed by an engineer registered in the State of Minnesota and require a building permit.
According to the recorded plat, there were no drainage and utility easements platted along the
common lot line. The site plan must show the dimensions of the lots.
UTILITIES
Metropolitan Council Environmental Services has a 30-inch diameter sanitary sewer interceptor
that runs along the east side of the site. The City of Chanhassen has a 21-inch diameter trunk
sanitary sewer along the east side of the site as well. A 10-inch sanitary sewer extends west from
the City's trunk line, then to the southwest within a 20-foot wide drainage and utility easement.
A portion ofthis pipe has been abandoned, therefore, a portion ofthe drainage and utility
easement must be vacated.
A lO-inch watermain was installed on the east and north side ofthe site with the Chanhassen
Lakes Business Park 5th Addition improvements. A portion of this watermain has been
abandoned.
The existing drainage and utility easements and abandoned utilities must be labeled on the plan
sheet.
Storm sewer will be installed to serve the proposed development. This storm sewer will connect
to the existing public utility. The utility plan must include a note regarding the connection to the
existing storm sewer.
EROSION AND SEDIMENT CONTROL
A NPDES Phase II Construction Site Storm Water Permit has been obtained from the Minnesota
Pollution Control Agency (MPCA) for this site. The Storm Water Pollution Prevention Plan
(SWPPP) has been prepared and supplied to the Carver Soil and Water Conservation District for
their review and comment.
The SWPPP needs to include the total area disturbed, the total change in impervious surface as
well as all pertinent contact information. The SWPPP should be amended to include sequencing
of events during the construction of the site. All wetlands need to be clearly labeled in the
erosion control plan.
As indicated on the plan, erosion control blanket shall be installed on all slopes greater than or
equal to 3: 1. At a minimum, this includes those slopes immediately east of the existing wetland
basins. This appears to have been addressed in the erosion control plan. All exposed soil areas
shall have temporary erosion protection or permanent cover year round. The NPDES permit has
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 10 of 15
been revised such that all slopes must be protected within 14 days regardless of the grade unless
special provisions are applied.
These areas include, but are not limited to, constructed storm water management features side
slopes, and any exposed soil areas with a positive slope to a storm water conveyance system,
such as a curb and gutter system, storm sewer inlet, temporary or permanent drainage ditch or
other natural or manmade systems that discharge to a surface water.
Inlet protection may be needed prior to installation of the castings for the curbside catch basins.
In that case, all storm sewer inlets should be protected by at least fabric draped over the manhole
with a steel plate holding the fabric in place.
WETLANDS
One jurisdictional wetland exists on site. The wetland was delineated by Terry Jeffery in August
of 2008. At this time, an historic review of aerial photography, USGS topographic maps and
civil engineering plans was performed. It was determined, based upon this review, that the
wetland increased in size as a result of grading changes to the topography of the area and new
directed inputs from land development.
The wetland is classified as Manage 2 in the Chanhassen Surface Water Management Plan. This
management classification requires a 20-foot wetland buffer and a 30-foot setback from this
buffer.
It appears that, in part due to the desire to preserve a significant oak tree on the site, the buffer
will be as narrow as 16.5 feet for a length of95 feet. Additional buffer should be set aside so
that the buffer is the same by unit area. A 20- foot buffer on the property would amount to 9,777
square feet. The proposed buffer encroachment amounts to 321 square feet. The buffer should
be expanded to mitigate for at least this 321 square feet of area.
Further, the drive aisle is located entirely within the 30-foot setback from the buffer's edge. A
30-foot variance will be needed for the construction ofthis drive aisle. In the event that a
variance is granted, any design should seek to mitigate for the lost functions and values from the
encroachment into the setback zone.
A portion ofthe stormwater is to be directed to the pond located east of Park Place. This is
identified as a Manage 2 wetland in the Surface Water Management Plan. However, the historic
review clearly shows that this area was excavated for the express purpose of addressing
stormwater management for the development of the business park and is not a jurisdictional
wetland under the Wetland Conservation Act of Minnesota. This pond is tributary to Riley
Creek and Lake Susan. Therefore, all reasonable efforts should be taken to assure that the input
of new stormwater does not result in downstream degradation of water quality.
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 11 of 15
PUBLIC WATERS AND BLUFFS
There are no bluff zones located on or immediately adjacent to the property. There is one DNR
stream that flows along the eastern property boundary. This stream is Riley Creek. This reach
of Riley Creek is not listed as impaired. Riley Creek from Lake Susan to the Minnesota River is
impaired as is the Minnesota River. No additional stormwater or surface drainage should be
directed to the creek and the watershed should be modified as little as practicable to achieve the
development goals.
The channel and the immediate top of bank have been degraded due to past land use in the area.
Much of the degradation can be seen in the form of debris within and adjacent to this channel.
This debris needs to be cleaned up as part of the site development. Further, several reaches of
Riley Creek have been denuded of vegetation or is dominated by invasive species such as
buckthorn and garlic mustard. Vegetation management should occur adjacent to the channel to
assure that an adequate and beneficial buffer is maintained along the channel. Work with the
Environmental Resources Specialist and the Water Resources Coordinator to design and manage
this work.
SURFACE WATER MANAGEMENT PLAN (SWMP) CONNECTION CHARGES
No SWMP fees are required for this project.
OTHER AGENCIES
The applicant shall apply for and obtain permits from the appropriate regulatory agencies (e.g.,
Minnesota Pollution Control Agency, Minnesota Department of Natural Resources (for
dewatering)) and comply with their conditions of approval.
MISCELLANEOUS
The buildings are required to have automatic fire extinguishing systems. Building plans must be
prepared and signed by design professionals licensed in the State of Minnesota. Retaining walls
over four feet high must be designed by a professional engineer and a permit must be obtained
prior to construction. Detailed occupancy related requirements will be addressed when complete
building plans are submitted. The owner and/or their representative shall meet with the
Inspections Division as soon as possible to discuss plan review and permit procedures.
VARIANCE
Chanhassen code requires that structures be set back from the top of bank of streams a minimum
of fifty (50) feet. Based upon the plans provided, the back of curb for the parking area is less
than 50 feet from the channel in at least two places. The more northerly encroachment would
require a 25-foot variance and the more southerly encroachment would require a IS-foot
variance. The applicant is requesting a 3.5-foot encroachment into the minimum wetland buffer
requirement. The applicant is requesting a 30-foot variance for the wetland setback.
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 12 of 15
The meandering nature of the creek to the east of the property does not permit a uniform parking
lot drive aisle design. The wetland on the south restricts the location of buildings and access
drives on the site. The tree-covered slope on the west also constrains the development of the
property. In order to avoid setback variances, the building would have to be shifted to the west,
requiring extensive grading in the tree-covered slope.
The channel and the immediate top of bank have been degraded due to past land use in the area.
Much of the degradation can be seen in the form of debris within and adjacent to this channel.
This debris needs to be cleaned up as part of the site development. Several reaches of Riley
Creek have been denuded of vegetation or is dominated by invasive species such as buckthorn
and garlic mustard. Vegetation management should occur adjacent to the channel to assure that
an adequate and beneficial buffer is maintained along the channel. Work with the Environmental
Resources Specialist and the Water Resources Coordinator to design and manage this work.
Staffhas reviewed the files to determine if there have been any other variances in the area. Out of
the 500-foot search area, there was one setback variance #88-14:
Case # Address Request Action
10- foot side yard setback
88-14 1430 Park Court variance for the parking Approved
lot (0' setback)
CONDITIONAL USE PERMIT
Screened outdoor storage requires a conditional use permit. Outdoor storage areas are an
integral component of the public works operation. The City must be able to store materials and
supplies to fulfill its obligations to the public.
Sec. 20-308. Screened outdoor storage.
The following applies to screened outdoor storage:
(1) All outdoor storage must be completely screened with one-hundred percent opaque fence or
landscaped screen.
The areas to the north, west and east of the storage area are heavily wooded. The building,
located to the south, will screen the storage area from the public right-of-way. The proposed
development must comply with the approved site plan.
Chanhassen Public Works Facility
Planning Case 08-25
January 6,2008
Page 13 of 15
RECOMMENDATION
Staff and the Planning Commission recommends that the PlaBfling Commission City Council
adopt the following motions and adoption of the attached findings of fact and recotnmefldation:
A. "The Chanhassen Plaaning Commission recomHl€lnds that City Council approves a site plan
for an 82,500 square-foot, one-story office/warehouse building with a mezzanine storage area
and setback variances from the creek and wetland for the parking lot area, plans prepared by
Oertel Architects and the City of Chanhassen, dated 12/05/08, subject to the following
conditions:
1. The developer shall provide exterior benches and/or tables.
2. Signage shall require a separate sign permit review to determine compliance with City
ordinance.
3. The applicant shall mitigate for the lost functions and values of any buffer variance by replacing
an equivalent area of buffer in a location which will provide the maximum water quality benefit.
Preliminary review indicates that area to be northeast of the wetland.
4. The applicant shall restore the stream channel as well as the top of bank and flood plain for
Riley Creek including the removal of any construction and other debris in the area.
5. The applicant shall prepare a vegetation management plan for Riley Creek. This
management plan shall be created in conjunction with the landscaping plan and the
Environmental Resources Specialist and Water Resources Coordinator should be consulted in
the creation of this plan.
6. The applicant will modify the existing NPDES permit to identify the construction manager
for the project.
7. The applicant will provide adequate treatment for drainage directed to the wetland.
8. The applicant should look for ways to promote infiltration and incorporate alternative
stormwater management best management practices into the site design and build. One such
measure is the construction of a bio-infiltration feature at the outlet from the drive aisle
northeast of the wetland. Other features to investigate include pervious pavement systems,
cisterns, biofiltration trenches, preservation or re-establislnnent of vegetation, etc.
9. The final 200 feet of the swale located west of the proposed facility needs to be protected
with Category 2, Wood Fiber 1 S Erosion Control Blanket.
10. Those areas to be planted in BWSR seed mix U7 should be seeded at a rate of 15LBS
PLS/acre where PLS means "Pure Live Seed".
11. The buildings are required to have automatic fire extinguishing systems.
Chanhassen Public Works Facility
Planning Case 08-25
January 6,2008
Page 14 of 15
12. Building plans must be prepared and signed by design professionals licensed in the State of
Minnesota.
13. Retaining walls over four feet high must be designed by a professional engineer and a permit
must be obtained prior to construction.
14. The 51-inch and 45-inch oaks located near the northwest and southeast comers of the
building shall be protected by fencing throughout construction.
15. The site plan must show the dimensions of the lots.
16. The northern access must be revised so that the maximum width does not exceed 36 feet.
17. An encroachment agreement is required for the portion of the parking area that lies within the
public right-of-way.
18. If feasible, the runoff from the cold storage area access should be conveyed to the existing
storm sewer.
19. Revised drainage calculations and storm sewer sizing must be submitted to ensure that the
existing downstream infrastructure can accommodate the proposed runoff.
20. An encroachment agreement is required to construct the northern retaining wall within the
drainage and utility easement.
21. The proposed top and bottom of wall elevations must be shown.
22. The drainage and utility easement over the abandoned portion of the sanitary sewer must be
vacated.
23. The existing drainage and utility easements and abandoned utilities must be labeled on the
plan sheet.
24. The utility plan must include a note regarding the connection to the existing storm sewer."
B. "The Chanhassen Planning Commission reeommends that City Council approves a
conditional use permit for outdoor storage, subject to the following condition:
1. The proposed development must comply with the approved site plan, plans prepared by
Oertel Architects and the CityofChanhassen, dated 12/05/08."
Chanhassen Public Works Facility
Planning Case 08-25
January 6, 2008
Page 15 of 15
ATTACHMENTS
1. Findings of Fact and Recommendation.
2. Reduced Copy Site Plan.
3. Reduced Copy Grading Plan.
4. Reduced Copy Landscape Plan.
5. Reduced Copy Floor Plans.
6. Reduced Copy Building Elevations.
7. Letter from Chip Hentges, Carver Soil & Water Conservation District, to Robert Generous
dated 12/23/08.
8. Public Hearing Notice and Mailing List.
g:\plan\2008 planning cases\08-25 public works facility site plan\staff report pw site plan. doc
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
FINDINGS OF FACT
AND RECOMMENDATION
INRE:
Application of the City of Chanhassen for Site Plan Review for a Public Works Facility,
Planning Case #08-25, for an 82,500 square-foot, one-story office/warehouse building with a
mezzanine storage area, a conditional use permit for outdoor storage and setback variances from
the creek and wetland for the parking lot area.
On January.6, 2009, the Chanhassen Planning Commission met at its regularly scheduled
meeting to consider the application of the City of Chanhassen for a site plan review for a public
works facility for the property located at Lots 5 & 6, Block 1, Chanhassen Lakes Business Park
5th Addition (7901 Park Place). The Planning Commission conducted a public hearing on the
proposed site plan which was preceded by published and mailed notice. The Planning
Commission heard testimony from all interested persons wishing to speak and now makes the
following:
FINDINGS OF FACT
1. The property is currently zoned Industrial Office Park, lOP, District.
2. The property is guided by the Land Use Plan for Office-Industrial uses.
3. The legal description of the property is: Lots 5 & 6, Block 1, Chanhassen Lakes Business
Park 5th Addition
4. Site Plan Review
a. The proposed project is consistent with the elements and objectives of the city's
development guides, including the comprehensive plan, official road mapping, and other
plans that may be adopted;
b. The proposed project is consistent with this division;
c. The proposed project preserves the site in its natural state to the extent practicable by
minimizing tree and soil removal and designing grade changes to be in keeping with the
general appearance of the neighboring developed or developing or developing areas;
1
d. The proposed project creates a harmonious relationship of building and open space with
natural site features and with existing and future buildings having a visual relationship to
the development;
e. The proposed project creates a functional and harmonious design for structures and site
features, with special attention to the following:
1) An internal sense of order for the buildings and use on the site and provision of a
desirable environment for occupants, visitors and general community;
2) The amount and location of open space and landscaping;
3) Materials, textures, colors and details of construction as an expression of the design
concept and the compatibility of the same with adjacent and neighboring structures
and uses; and
4) Vehicular and pedestrian circulation, including walkways, interior drives and parking
in terms of location and number of access points to the public streets, width of interior
drives and access points, general interior circulation, separation of pedestrian and
vehicular traffic and arrangement and amount of parking.
f. The proposed project protects adjacent and neighboring properties through reasonable
provision for surface water drainage, sound and sight buffers, preservation of views, light
and air and those aspects of design not adequately covered by other regulations which
may have substantial effects on neighboring land uses.
5. Variance: The Board of Adjustments and Appeals shall not recommend and the City Council
shall not grant a variance unless they find the following facts:
a. That the literal enforcement of this chapter would cause an undue hardship. Undue
hardship means that the property cannot be put to reasonable use because of its size,
physical surroundings, shape or topography. Reasonable use includes a use made by a
majority of comparable property within 500 feet of it. The intent of this provision is not
to allow a proliferation of variances, but to recognize that there are pre-existing standards
in this neighborhood. Variances that blend with these pre-existing standards without
departing downward from them meet this criterion. The meandering nature of the creek
to the east of the property does not permit a uniform parking lot drive aisle. The wetland
on the south restricts the location of buildings on the site. The tree-covered slope on the
west also constrains the development of the property. Based on the revisions to the plans,
the variance request has been reduced to a minimum.
b. The conditions upon which a petition for a variance is based are not applicable, generally,
to other property within the same zoning classification. This condition is unique to this
property which abuts Riley Creek. In order to avoid setback variances, the building
2
would have to be shifted to the west, requiring extensive grading in the tree-covered
slope.
c. The purpose of the variation is not based upon a desire to increase the value or income
potential of the parcel of land, but rather minimize the impacts to the water resources and
to avoid additional impacts on the wooded slope. Because of the nature of the facility,
vehicle size, outdoor storage, etc, need large space, turning radius of tandem axle
vehicles, storage of salt, pea rock, mulch, and trailers
d. The alleged difficulty or hardship is not a self-created hardship, but is due to the unique
site features which include a creek to the east, just east of the public street, a wetland on
the south, a tree-covered slope to the west and converging side property lines.
Additionally, the City has attempted to save a 45 inch oak tree southeast of the building.
e. The granting of the variance for the construction of a public works building will not be
detrimental to the public welfare or injurious to other land or improvements in the
neighborhood in which the parcel is located, but will facilitate the provision of a required
public service. In addition, the City will be implementing several mitigation measures
which should improve the natural environment including:
. Currently from the top of bank for Riley creek west is either denuded of vegetation or
dominated by invasive plant species
. Currently the channel and the area immediately adjacent to the channel has a
substantial amount of construction debris
o The plan will involve cleaning all debris away from within the channel and
between the proposed back of curb and top of bank.
o This area will be planted with native trees, shrubs, forbs and grasses - a detailed
vegetation management plan will be created
o Areas of scour which have developed in the channel will be stabilized.
. The buffer will be expanded both northeast and northwest of the wetland so that total
buffer will be far greater than what is required under City code.
. Much of the buffer is dominated by reed canary grass - an invasive species. This will
be replaced by a special BWSR seed mix.
. An engineered wetland will be created northeast of the wetland to treat runoff from
the driveway prior to entering the wetland.
. A bio-filtration swale will be created west of the building to treat roof runoff prior to
entering the wetland.
f. The proposed variation will not impair an adequate supply of light and air to adjacent
property or substantially increase the congestion of the public streets or increase the
danger of fire or endanger the public safety or substantially diminish or impair property
values within the neighborhood.
3
6. Conditional Use Permit:
a. The proposed outdoor storage will not be detrimental to the public health, safety, comfort,
convenience or general welfare of the neighborhood or the city.
b. The proposed outdoor storage will be consistent with the objectives of the city's
comprehensive plan and this chapter.
c. The proposed outdoor storage will be designed, constructed, operated and maintained so
to be compatible in appearance with the existing or intended character of the general
vicinity and will not change the essential character of that area.
d. The proposed outdoor storage will not be hazardous or disturbing to existing or planned
neighboring uses.
e. The proposed outdoor storage will be served adequately by essential public facilities and
services, including streets, police and fire protection, drainage structures, refuse disposal,
water and sewer systems and schools; or will be served adequately by such facilities and
services provided by the persons or agencies responsible for the establishment of the
proposed use.
f. The proposed outdoor storage will not create excessive requirements for public facilities
and services and will not be detrimental to the economic welfare of the community.
g. The proposed outdoor storage will not involve uses, activities, processes, materials,
equipment and conditions of operation that will be detrimental to any persons, property or
the general welfare because of excessive production of traffic, noise, smoke, fumes, glare,
odors, rodents, or trash.
h. The proposed outdoor storage will have vehicular approaches to the property which do
not create traffic congestion or interfere with traffic or surrounding public thoroughfares.
1. The proposed outdoor storage will not result in the destruction, loss or damage of solar
access, natural, scenic or historic features of major significance.
J. The proposed outdoor storage will be aesthetically compatible with the area.
k. The proposed outdoor storage will not depreciate surrounding property values.
1. The proposed outdoor storage will meet standards prescribed for certain uses as provided
in the City Code.
7. The planning report #08-25 dated January 6,2009, prepared by Robert Generous, et aI, is
incorporated herein.
4
RECOMMENDA TION
The Planning Commission recommends that the City Council approve the site plan review
for an 82,500 square-foot, one-story office/warehouse building with a mezzanine storage area, a
conditional use permit for outdoor storage and setback variances from the creek and wetland for
the parking lot area.
ADOPTED by the Chanhassen Planning Commission this 6th day of January, 2009.
CHANHASSEN PLANNING COMMISSION
BY:
Its Chairman
5
OI~~__"~
I\) If !ill
CD fl. ~i
~~:~
21:*
i!I l!
s~
~.:.;:.:'.:i:;..'"
.~~~.~:. ~~. .
... . ., ...' ~
.,. .... .,.... ':l::: I~
q .
I
q q
I 1
0)
88 q
8 I
~
I
.
.
88q
. 1 "
8 ~ " ~i~
'"
"
~ ~
1 <D
1 VI
0
8 8;
~ I
~ 8
1 ;
1
,..... ~~
q
~
8 u-_
88
~
I
~
18
Ii
1
8
-0
~
1-0
~
i!~~i~;;IIIIIIIIIIII!I!~1 I
~.;gl~~;f ~i ~ ~ !~~ ~
I ~I~~E ;~!.
1",160..1011!I+oI11111! i I~
I IIIII IIII I! I~
11.,!..~.1.1!!I+o!1111! !II~
I · IIIII IIII! I ~
DATE
RE'JlSlONS
.&
~ 5IAKA
BY
CITY OF CHANHASSEN
PUBUC WORKS FACIUTY
7901 PARK PLACE
1.......'oriIylMtWOplcn. ............
=~=!=--r...,
IG-."'''~or~
SITE PLAN
ENGINEERING DEPARTMENT
0A1E--12.4DAlL-uc.1IO.~
~...........--"~
~I~.
B ~S
"
!.
"
. . .
~~~~~~~~ ~~~~~~;i:~~ ~I~~ ~!~I~~~~~~~~~ ~~ ~!i~~j~~~~~ ~~~ ~
~~I~;~I~ ~~I~~~~;~~~ ~:~I ~~~:~li~~I:~1 ~~I :~m~a~~a~~~ ~i~ t
~~ ~~~~~ .~~~i~~~~e ~z~ a~~~~~;m~~~~ ~! ~~~~~~~~~~~ ~;~ ~
~~~~~~~~ ~~~~~~~i~E ~~~~ ~ig~;~~~~~~~~ ~~ ;;~~~2~~~~~ ~~2 S
~i~ '~~ ~~~~~ ~~ Z a~~~ ~Q~~ ~~2S~a~~ ~ ~ 3~~~i~~~~~~ ~~~ ~
~I~:iii; ~I~~i~~~!~ :i~j i~~~~~i;~~~~a ~;~ . ~~~~~~~~i: ~i~ ~
~~~>-~~~ ~. Za o~~~~ 8~~~ ~~~~~m~~ffl~~~ :J~~ ~~~~~~m~~ ~~~ ~
~~~~i~~; ~~~~~:i~~~ :aa~ ~~~~i~~~~~~:~ ~~~ ~~~~~2~~~i ~~~
~~~~~~~~; ~;~~~~~2~. ~~ ~g~; ~~~m~~:~!~2;~ a: ~~~~6~~~;~ ~i~
~ ~~~~:J~ ~~eo~ ~ ~~ e~~o ~ ~- ~~ ~R;;l ~~ ~Z_~~~~_~~ ~o
P M~~~2 e~ ~B~z i2 ~~ i~~a~~~s2 ~a ~g ~~~~~~~~~~ g~
~~~~~2 ~ ~~~~iP~ > B~~ >~ ~~~~~ ~ ~E ~z EI~ e~
a~~ ~ ~~ o~ ~~m ~~ a~ ~m ~ ~6 ~ i~ ~
DAlE RE\!SlONS OY CITY OF CHANHASSEN
li> I PUBUC WORKS FACIUTY
7901 PARI( PLACE
/
+/
,...-""--;---?
/ I
/. .0
/ ~
./
"/
I
iiii~~~~i~I~GII~1 I
;glii~illllii ii
I
!IAo..1 i~ II! !I~
II I! I~
II. ,UI! III ~
ir~. h\\ ii ~
CD
GRADING AND EROSION CONTROL PLAN
. a:=.
Ihftblorifyl;hal;lhIIplOII.~
~r~=!:--r.~1
....._thlI...._~
....
. f
e
~I
oIll:iU'I1:5HAII.A
EMGIIERlNO DEPNmIEMT
DATE J2.4llUM.- uc. 1IO.-'I2ill...-
~.........--"~
~ ~:
i Q
.~ II
~
a s
'i'
:;;.
51
!;
."
."
r'1
~~~
q
. "
8 ......
+. 'it
, .. '
ir<"1. ' ,
'ct:? + of +
, +0" +
. ,',',
. ,
, , ,
co
VI
o
~~
, ,
'Ii ' ,
+1+ .;.+.. G+"
G h' , ,
.. \...Jl .. . +
.. .... i:'1+
.. .. .. .. t.....( ..
ftt.li.t r;"1
++++1++ ~
.. of .. .. .. .. ..
m~ ~m
l'l~ ,,~
!:ill] :i!o
~a ~~
rn~ ~iB
~~ ~l'l
~~ ~~
~ ~~
! !i
~ ~2
~ i
~ ~
~ .
~ i
~
i
a 0
nnl p~l:
;;p m ;1 m ~
u
~
i;~iii~~IIIIIII~~III!II~1 I
~~;giEE~1 ~ ~ I~ ~~i i
~I mali:! I~!~
11.,160..lo!1!!+.!!111 I! i I~
I 1 IIII IIII I! Ir
11.'!..'.!I.!!!!..!!!II! !II~
I · IIII IIII! I ~
DAlE
REVISIONS
BY
CITY OF CHANHASSEN
PUBUC WORKS FACIUTY
7901 PARK PLACE
co !iiI
!
G l-' cgl
LANDSCAPE PLAN
. a:=.
"""""...........-.
~-n
mr
~8
~;u
-0
r
)>
Z
);Y~~)y~/i/ /
/ I I I II II/II/III
""""
/f----i "
/ I I
, I ~
A
,
"
~
-.
I ! ~ ." () ! i'" ~
-n , i c I 'I :l':l:(")O
0 0> )>
)> 5 ~ '" r- Z -- E.r tI1
...... 0 ^ () I pi h ~~e
. '" g VI )>
...... ." 0 ~ VI i'i! lit> tr1m
> ~ -~ 0 VI ~I ~t""'
z ~ ~ . m
!; & ~ Z ~ en
w
, ~
~
~;
,
, I' u
.l>. (JJ '"
l);m ~~ 'm ~~
~:;; m::;;
~~ ~~ ~~ ~~
~-i .-i ~~ .-i
20 ~~ ~o
z z z
~ ~i;~ !~~ ~ ~
.!~5 ~~
.~
" " " "
~ ~ ~ ~
I I ! " ~ -0 () ! P::; ~
, , i ~ c ::c ! :l':li 0
m 0 <70 >
)> ~~ 0 ~ r- .1 .. !'~ (ltI1
~ ,2 ^' () z pI n ~ClG
w >;;1 ^ ::c
3 VI
-< '" Iii ~ >
..... 66 " ~ VI .. u > tI1 tI1
z'" C ~ao VI ~I Q r<
CIl ~ ~ ~ m
!; ~ Z ~ u:l
~
~\1\g c.~
.( ,.
tIJ 1946 ..
a IJ
O""ty S\~O
219 East Frontage Road
Waconia, MN 55387
Phone: 952-442-5101
Fax: 952-442-5497
CO.SI.VAf'O. JISf.'Cf
htto:/Iwww.co.carver.mn.uslSWCD/SWCD main.html
Mission Statement: To provide leadership in conservation and teach stewardship of the soil, water, and related resources through a
balanced, cooperative program that protects, restores, and improves those resources.
December 23, 2008
Robert Generous, Senior Planner
City of Chanhassen
7700 Market Boulevard
Chanhassen, MN 55317
Re: Chanhassen Public Works Facility
The SWCD has reviewed the above mentioned development plan for erosion and sediment controls.
Following you will find my comments.
-A National Pollution Discharge Elimination System permit will be required for this development.
-The General Contractor who has overall charge of day to day operations needs to be on the NPDES
Permit as the contractor. The Owner and or General Contractor have the responsibility for the NPDES
permit. An individual qualified to complete stormwater inspection must complete reports weekly, and
after each Yz inch rainfall event. A box will need to be placed on site for these specific documents, and or
kept in the project office.
The Carver SWCD will be completing inspections of the rules ofthe NPDES permit and city ordnances
to see if the owner and or contractor are in compliance with the permit. This permit is a self
maintained permit. Guidelines of the permit can be found at the following web site:
htto:/ /www.pca.state.mn.us/water/stormwater/stormwater-c.html
Erosion Control
1. Unless I missed it, the SWPPP only discusses stabilization of slopes - does not indicate what types of
stabilization is needed and timing of placement.
Sediment Control
1. Inlet protection is needed on all stormwater conveyance systems prior to casting. The SWPPP
discusses inlet protection, but no mention of what detail is needed. Inlet protections need to be
installed within 24 hours of placement
2. After installation of curb and gutter, all positive slopes to the street with exposed soils will need to be
stabilized. Curb and gutter / inlets are "surface waters" which need protection from exposed soils
with a positive slope within 200 linear feet.
3. Concrete washout plans are included, but needs to have the block layers with there Spec Mixes areas
contained also.
4. The General Contractor must discuss De-watering plans with all Sub-Contractors to make sure they
are aware of the NPDES requirements.
5. During construction, the roof water draining area will need to have temporary sediment measures
installed, bio-rolls are noted on page 4 of 9, but does not indicate when it should be applied.
6. Flared end section outletting into swale that flows to the wetland needs to be stabilized immediately
once pipe is connected.
AN EQUAL OPPORTUNITY EMPLOYER
Please include me with any correspondences of changes to this original concept plan, and also of any pre-
construction meetings prior to start of construction.
Sincerely,
Chip Hentges CPESC
Conservation Technician
CITY OF CHANHASSEN
AFFIDA VIT OF MAILING NOTICE
STATE OF MINNESOTA)
) ss.
COUNTY OF CARVER )
I, Karen J. Engelhardt, being first duly sworn, on oath deposes that she is and was on
December 24, 2008, the duly qualified and acting Deputy Clerk of the City of Chanhassen,
Minnesota; that on said date she caused to be mailed a copy of the attached notice of Public
Hearing for the Public Works Facility - Planning Case 2008-25 to the persons named on
attached Exhibit "A", by enclosing a copy of said notice in an envelope addressed to such owner,
and depositing the envelopes addressed to all such owners in the United States mail with postage
fully prepaid thereon; that the names and addresses of such owners were those appearing as such
l;.,.
by the records of the County Treasurer, Carver County, Minnesota, and by other appropriate
records.
Karen J. Engelhardt, Deputy Clerk
Subscribed and sworn to before me
this _ day of , 2008.
Notary Public
0)
c
:s
CI)
:2:
0)8
.= 'w
~.~
CI) E
:I:E
.2 0
:CO
::JO)
o.c
-'c
o c
CI) as
0-
:;:0.
o c
ZCI)
U)
U)
as
..c
c
as
..c
o
0)
c
:s
CI)
:E
c
0)0
c'-
._ U)
... U)
as.-
CI) E
:I:E
.2 0
:cO
::JO)
0..=
-c
o c
CI) as
0-
._ a.
.....
o c
zCI)
U)
U)
as
..c
c
as
..c
o
~ ID 00 0 ~
c ~ t ~ID 00 ~
Q - g~~ ~5 _ m ~ ~
Cti 0 .- Q) c.. !!! (5 C ~'o a. Q.) ctS .2
CD Q)"O Cii'~ ro a.. Q.) ~ <( .5 0 :5 c .c C
~SQ.) ~Q)oo Q.)_ = ~ ~~ ~'~.Q
~ ~:s Q) ~ ~ :5 ~ ~2 Co ~.~ $::J 13
c,Eg Ecti~<U>-.2:" ctS~~ cO> Q)O~
~., 2 ~ ~ e 8.~ t"g ai ~ Q.E.... Q);; Co ~~
~ ~~ern~'~E;o~ -- w-c
~gs ~~aE~EwwuE 6., "..,
en'~ 2 ro Q) OJ -g ~ Q) -5 ~ B t ~ ~ ~ g :5
m~'~ ~.~:5ro=li.5~w~ 'G~ ~~g
~ou m~~E~E~oo:5Q) ~~ 0-0
E~.~ c~2Q)~~'5~~O -0 ~>-Q)
'~::J~ g=m~~ctS~uE~ ~~ c~E
~~~ ~$~:5~j~g~'2 ~= ~~~
u~:5 ~~&~ESo.5~~ S~ ~:5g
~'5o ~.~~B~~~€~a.. gs ~B~
ca g 1ii c>> C 1D - .~ E CD ~ 3: Q) ~ 0 en 5 -g Ci
c....Q)cQ)Q.).~u.~E.~u~- m~ 00.=
Qm-~~E~~~-gc~S:5 ~m o~s
:g as 8 OJ ID C 5. ca ~ Q) Q.) ~ .~'3: 'S: 0 .?:- Q) if)
cE~Ea~.,ol~~UE~ e~ G5g
8-g~~~.~:5'~~Q.)~K>-~ c..~ Q)C~
u>~j;~~~~~~EQ)~~ ~.~ ~~~
~<(>-ffi-gouo>-~.g~a.~ <1>:5 g-gCl.
'~~i~~~~~~~~;~~ ~~ ~TI~
II 0 g- 0 .- C ~ 5..~ Q) ~ C () en :J :0 Q) .5 :::
cU....-Cii.EoQ)gC/)E2~C/) B~ .cQ)~
~-g~j:5~~:5g~~.~~~ci~~ ~~c
Cl.ctfcu"5cQ.._t1>()cQ.>- g'~(J)'- :J'~o
2!B ~.~ .g Q) 3 (J) >.~ E &.9 t- Q)'-"O a. 0
.- C'- en ro:..c :>.Q.... ~ ro: <tI Q) a. Q) Q) 0 Q):5 ~
~Q)~.~g=~~B~~~~~~~~ 5~~
-E ~ ~ ~ 8:<(.~ ~ ~.~ :J en ~.c'o c.8 ~ ~ a
Q)ffila.~~~:5~2~.~~g~~~.~&~
KEgi~~~'~~Q)~~~28~~~.c<tl8
O~<tI""~rr.(J)g~"OQ).2..c>.a.C~~Q)ID
~c.5~~Q)c'~~ .c'-a-~~Q)o,-St-
><tI"O'-(J)'-.QEoc<tlma.Eo~..c(J)~om
~~~*~~~oog~~:iQ)~~~'~.5S
~.~~'~~~~~~~.~~E~~~j"O~~~
.. => ~ 0 ~ 0 ~ E..c 0 Q) 2 .$ ~ ::.g ~Q) * 0 g> ~
~i!~ .~'~~~~E~2 .gojQ)~g'-~
~C!~~o.<tIo~0~_SE.g~&E.$'2~~
~~o.~E!~~~-oiOO~g~(J)g.5cC.~
Uo~EE~<tI<tIro:g:5~~.$coQ)u"O>.~~m
~ oE:>en(J)u'-~enQ)ro:<tIc..coQ)c~c~
~~o cQ)tco.<tI~_~~._OOO<tlQ)oo
C ~ 0.- '- 0 <tI 0"0 0'0 UJ ..c UJ -E r:!..c ..c a.:::
== .2 ~ 0 :5 ~ a. t::.5 ffi'oo c: S :2 .~ -g 0 :J.-== - ~ C
~~.5~~~!0~E~~~-:><tI~8~~~:2
~~:5'2.~~~~~EEo~~:5~.~~~~8~
OC~~~~E!Q)Q)8~~~'~~~~~'~~~~
~oo~~<tIoo~S5~OO~~o.~~<tIo.m<tl(J)
5.. ...
o (I)
o Q)-g~ ~ c:O>.
o Q) ..c0- ~; ~ >. -c C\1C\1
l!) ~ -..c-o ~.- -.0 =~
o ~(I)~ -~C\1 ~ > 3::Q)~ Q)Q)C\1Ul
c roUlO ~ ::J0Q) ::J Q) ::J-ocE..c>~
~ 0.0_ - U ~ OO)~.~_t-C\1~
c:1l c:;)"(U .::Jt. .o..c_ U .~ C\1 >.c::J~C\10(l)J:
E C\1.- ~ C\1 0) = Q) ~ Q) ~_........ ~ a. ~ ..0 I-
' - ~ C\1 ~ .Q)- 3::'~ ...... ~ ..... c:::> ~
g>.g5 o:g en 0.. ~ e t5 c Ci ...; t5 E > Q) ~ _ (I)
.- C ..... 0 ::J ~ 0 c ,: a. .~ 0 C\1 .:~"O._ = J:
to ~ -0 Ul .- -0 ~ >. Q) C\1 -0 0 '00 0) E -c c E Q) a. 3:" .
Gl~>(I)~C Q) E..c..c ~ c..c- Q)~..c0 (I)~
.c'"_u~- ~-O Q)o..~ '+=- o~""'-uE>i:'
~Glmc--O ~ ~OE ~ uE Q) l!)u~::Jo 0-
:E :S _ C\1 0 Q) ~ ,2 ..... Q) 00 0 Q) = .- Q) C\J Q) C\1 ~ - Q) .! ..0 Ci)
I- - Q) .- 0 C ::J '0 .f; e -5 ~ g- -5 -g EE' ~..c 0 >. ~.- C\1 (I)
o.::Jt.~ 0 m co- -Q)~co.o roC\1C-o.>Ul E
E'~~>C\1~ ~ 0_-0)-0.0 0 Q) ~Q)C\1Q)oe'=~
~ -0--- Q):c ::Jc~ Q) -5 CCii5~uo.:=.!c
ci ~ ~ E ~ ~ j ~ '~.~:a5 g> ~ ~ -5 ~ ~ ~ tf'13 ~ ~:= 0 ~ .2
g :S 0 3: - g- Gl C C ~.~ - ~ E -0 0.. ""3; Q) @ U 0 3:: - (I) ~
~g~~~~ i 1~~Q)g~~g~ ~~I~~g~i~i~
~ g ~ .s:;g c ~ Gl ..c 0 -5 .2 .~ Q) -oQ) -0 ~ ~ -- a. 0 >. C\1 C/) a...o E
m~~(I)::Jo ..c-~uoO)Q)~~>Q) cC\1~~~_..c (1)(1)0
oc~~.oQ) cQ)Gl>=_c..cQ)~-~ C\1 ::J~Q)-o ~~
o ~ .0 ~ 0) C\1 ~ Gl .0 -0 ';;:: - > a. Q) .Q Ci a. C - c ,.... - ci> = > 0
C\JGlEC.::Jt.! ..c-~::Jc::J..co__uQ)u Q).oQ)E~~M~~~~~
_"OC\1_C\1~oo 00..-'0. ~ ~'=',...._ ~....;:::'
- - C\10~c-~~ ..c>cO'O,....o.~Ul(l)~
CD ...;..c 0.. :0: en c _ .::Jt.:5 ~ _ ::J C\1 3:: Q) .- - > Q).o _ Q) .- _
>.,~ 0 (I) u Q) Q) ,.... ~ c ~ ~ ,0 _ ~ 0) Q) ~ C\1 ~ ~ Q) (I) 0 ..
~i-~=-o ~.::Jt.~o-Q)t5~~CC\1~ Q)t5~Q)=C\J..cE~~~
::J>goo.o~ ~u 0-::JQ)--C\1SC\1~~Q)C\1cC\1~~Q)1- -
c Gl ::J C\1 ::J - jg 0 ,.... ';:: 0 g'o 0) O),g c Q) U o'o..c 0 E C\J _..c . (I) 0..
-Glo o.::J cffio~Q)~~c=o.Q)..c~-~cQ)Q)l!)--cJ:(I)
w .c ~ _ 0 ~ C\1 m caE ~ 0.'- .- '0' a. C\1 - 0 ..
~-0.2go~..c0~ o~~~3::~Eu~E~..cE>.m~o~cS
~~"(Uen~-OO~c~~~~~~Q)E~;1~3i.o~~!~oo
-o$IQ)Q)"~- 0 ::Jw- _..c0::J -uo..cQ)EcE(I)"
~~ ::J~~.::Jt.ol!)Eio.,gs,gc/)~Oo..-5::JG~_~c C\1E~~
~:;:;~g::Jm~~S"OoQ)o.o.o ~Q)~.::Jt.~oE>oc'-
~ 50a: go..o..<3.3~:;(~ ~-g i5.~NC'"5.,f ::::-5 ~]i<-E.8-g0 0 0.
t::
c:1l
u;
a;
E
j::
~
(I)
..
C\1
C
UlC)
C C
(1)._
a."
a. (I)
C\1 (I)
J::iE
..(I)
C\1~
~..
~10
.j.;
c
C\1
.~
18
c:(
>-c
t:o
(I);
a.C\1
o u
~ 0
0.....1
C
o
;
C\1
U
o
...J
C\1
Ul
o
a.
o
~
0..
o Q)-g~
o Q) ..cO- ~
l!) ~ -..c-o Q)
o ~(I)~ -~C\1 ~
c ro UlO l!) 5.8~ ~
ia' C:;)"(U .::Jt. .o..c_ - u
E. C\1 _ .;;:: ~ C\1 0) = UQ) ~
<1l ~C\1- w ::J~3:: ~
g>"O 0 C ~ 0.. '0 ~
.;ij i - 0 -5 ~ ~ c .~ ~ ~ C
Gl -0 Ul(l) ; c ~ Q) ..c ~ 'o~ .Q
.c~.2: u:s- Q) E-5o Q) ~ . ~
~~mcc-O ~ ~OEQ) ~o.u-
.c-_C\10Q) ~ ~o--co..coooQ)=E
I- '0 ~ .;:: 0 6 m .- ~ _ a. o...c.o E
E.~....C\1C\1N ~ cO:::::cil2e~i5.0
~C\1> >. Q) '!!!-::Jc~o.o 0
a., o~ "'" J: -0 t .::Jt..c ~ a. ,- ~ Q) Q)
.::::: C .. .- c -......, ~..c Q)
oGlO~C\1~ 5 ~O)-i~-5c--5
o :S 0 > - 0 Gl .f; c E 3:: - ~ E ~
" c t-- ~ 0) ~ C "C ~.- 0 ......
t-- 0 t-- (I);> ,f; a. Q).- C\1 C\1 .Q a. 0 c
~ -._-oc ~ UlQ):OQ)(5:O:-':::C\1
wc~>=o ~ ~..co-5-~~-o-o
m~ID(I)EQ) ..cm~uoO)Q)>~Q)>Q)
OGl.o~ 0) cu>=-c..c~Q)Q) ~
o E ~C\1 C\1C\1Gl.o-o.-- ~~o
C\JGl ~~~ ..c-~::Jc~..c6o.uu
_"OC\1_00 Oo..Glo.C\100) =Q)
CD ...c 0.. :0: en _ .::Jt.:5 ~ _ ::J C .~ ~ .~
>..!;; 0 (I) u Q) ,.... ~ c ~ ~ . 0 C\1 Q) 0)
~ c = .. .- -0 .::Jt. o..C\1 0 - ~ t5 ~ Q) E ~ c
C\1 Gl u ,'ft :0 .- u 0 - ~ Q) - > C\1 .;;::
::J > C VI ::J ~ 0 ,.....- 0 o-.~ 0)'- u S C\1 -
cGl::JC\1o.S ffiO Q)~ecO)=cQ)U
~ ~ 0 ~ _ 0 m ca ~ a..;;:: := a. Q) ..c .Q)
_~0.2 0 ~o....c0~E o_~ ~ C\1 3:: o.E U e
>.._= -.2.200 c 0.-'- Q) C\1 .-
~_~C\1~~~__~6R~~-5..c~Q)E:OQ)
...... I ~E ol!)-~o.u-u-..co::J..c
~..!S! ::JC\1 .::Jt. ~:t::() =::J=(f.)~Oo.._
~ 'E :t:: g 6- m ~ .- (5 :g ,g ~ &.8 -g
~~Oa:~o..o..O~<<~C\1C\1o.~NC'"5.,f
t::
c:1l
u;
~
Ul,f!!
c c
o (I)
;E
m E
~ 0
00
o (I)
_ ~ >. .f; :0 >-
:~ .~ .0 55 ~ ~
>Q)~ E..cQ)>C\1~
Q) ::J.- 0 c
~ 00)~2t-C\1~
C\1 >.5::J :~ C\1 0 (I) J:
Q) _.....c~o.-..ol-
Ci -t5E~Q)~-(I)
--= ctS ~"'O Q):=.c
0) SEc'E Q) '0. 3: ..
.f; ..c Q) .o..c 0 (I)
~ 8~::J-uE>c
Q) ~Q)~~.8Q).!,g~
E . ~..c 0 >.~.- C\1 (I)
roC\1C-o.>Ul E
Q) OQ)C\1Q)oO'-~
-5 CCii5 ~ u ~S.! c
Q) ~ -.....: 0 Q) = ... Ul 0
~ t5u..cc'-O::'-
.2 00""3; Q)@uo3::- (I) ~
Q)~ ID'O~::J Q):;;;t::t::.E-
.0 ~~::JO>wOUl
~ ~-- a. 0 >. C\1 Ci5 a...o E
c......,~~~_..c (1)(1)
~~~~~-:o '=~3:8
a. C-Q)""'-O)
Q).g E S M ~ .f; C\1 t)
..c 3:: c o.o;::'5.~U; (1).5
- Q).o_ I Q) Q) (I)'oc
iS~C\1C\1t--..cE~~c
~ ~ ~ ~ 'ia ~ ~ Q) I- a.]!
o '~..c 0 E I .- ..c (I) 0..
......ecQ)Q)~:t::-cJ:(I)
E a. jg E >. m en"' '0 .Q -;;; J:
-~"O~-- ~ ..
.U. '-:: .....C\1cQ)~oo
:0: c'(3 ~ ..c Q) u '-E (I) ..
::J 0'- . 0 - Q) E c c ~
o 3:: - Q) C E C\1 E'- 0
>'Q)3::~~~ -6Oc';::
::::-53::19< 0.8 C\10 0
UlC)
a; c c ~
(1).-
E a." Ul,f!!
.. a. (I)
j:: c C\1 c >-c C\1 (I) C c
0 Ul C\1 t:o J::iE o (I)
~ ; 0 .~ (I); ..(I) ;E
(I) C\1 a. a.C\1 C\1~ m E
.. u 0 o u ~.. ~ 0
C\1 0 ~ ... 0 ~10
c ...J 0.. c:( 0.....1 00
.,
00 Q) 00 g ~
:5 S d~t '2~ $ ~ u..c
~ 0 .2 <1> ~ ~:::: c >.'- 2i. Q) ~ .9
Q5 CD U co'~ <tI a: 0 <tI c: g' .Q f; c .J:: C
~SQ) UQ)UJ 2 ~<(.- Q)~ Q).~o
<Q); ~><tI ~o a.E ~Q) ~~;
-g 0'"5 E ~ (ij <tI ;. ~ g.~ ~ U'S; S:J.~
~ Q) ~ E 2 ~ Q) t:C -= Q) a ~ rE ~ ~ g.:s
Q)~.o ~ ~ e7d ~'~:5 -; ~ ~ 5 s UJ ~ g
~.~.9 '-<tIo.EoE~enoE ~ ~~!
~m~ ~~!~~~~~.9i ~g .5~~
cn..c~ C'i5>~ <tic o.s:J~ Q. U <tI ~ 0 0
~uu ~_~E~~~w-" .,> .u~
E:=.~ C:::0~:;:(J)'C3~:50 s<tI o>.m
'cg~ .g:fi.~~<tIQ5uE~ o~ c~E
2 a. en cocu~..c:OQ)Eo-,- -<tI (J)O~
~<tIQ) E~<tI-o~Em~~ oen ~Q)c
U ~:S ~ ~ ~ ~ E - 0 .S: ~ <tI S ~ "0 :5 0
~'5o ~.~~~~~~~~~ :5s ~g~
- g - c>> c ~ +-'.~ E Q):::: 3: Q)! U (/) c t
~t-Q)C:Q)<1>uut-E<tIu~~ m. 50~
.Q!B~~~E~~~~~~SS ~~ O~S
:g ~ 8 <D i c: a ro: ~ <D Q) ~ iU"~ 'S: 0 ~ Q) (f)
cE~Eo.'~<Do~~~OE~ e~ 55
8~~~~'~S'~~Q)~K>.~ o.~ Q)c~
~~j;i~~m~~EQ)j~ g~ 5~~
~ <( >. 53 -g 0 :; ~ ~-6 g ~ a~ ~ S g>~ a:
'-Q)t=-O<D~<tIc~-Eo 00 'c~~
~"OQ)mgo~gE<tIceno~ ~c mgs
(( 0 8-0'- c a. 0.== Q) Q) C 0 en :J:.o Q).-~
cOt--~'20Q)g(J)Eg.~en 8~ ..cQ)~
~~~$~~2=~~~~~~~ffi~ g~c
~::'~.~~~~O~~~~~~.~~ ~'i8
~E,~'~~!~.Q~~~~Q)~mIDO Q)g~
m,,~-u-EuGw"=~"E2~ ~-~
~E<D>.~~m= g~<tI"OS_m'- -mID
E~t-~a =~~'2:Joo~..c'oc2 ~g-
<D~~o.~~~:5~2~~.2~~i~.~&t
KEg~~~~'OO~Q)~~rne8~~~~mo
.Q<(<tI~Err..~g((~Q)~5>.o.c~:5Q)ID
<DcB~:J~cE~ .c'-~ ~~<Do'-S'-
~ ~"E ~ en >.g E 0 :5 ro: ~ ~ ~ () ~ S f!? .~ o~
oaoc~~~oo~~~Q)~Q)g.c&E.~~
~ ~ z..- - ~ c () ~.g .~ ..- E C = '- ~ E "E .5
c'ooG~C~<DEQ)Bcc~o~t-&~~orn~
..=>c ~o~ .c Q)2.$OO3:..Q(J)Q)~()5rQ)
ei!~ .~'~~~~E~2 .g~~Q)!~,--g
~c~.Q~a<tlo~o~-SE$=&E$'2~~
i~o..~E~~~~-oioo.gg~(J)g.~ccE
g~EE~m<tl~g:5~~.$crnQ)~"o>'~~~
~~8Ec~!~~~~~~~.~~g&~~go
c: _0'- '- 0 CIS 0"0 0'0 UJ..c UJ-E~..c.s= 0.-
==.2 ~():5 ~o.t.5 53'00 c s:c.~-g 0 :J.-== ~ ~ c
.! .~ c g>:.+::: ~ ~ 0 Ca E.~ g ~ - <tI ~ 8 3: ~ t::2
~ :6 'g 'c.~ ~ ~ ~ ~ E E 0 ~ ~ 5 ~ .2> ffi ~ ~ 8 ~
~g~~a~~~Q)8~~.5'~~rn~~'~~~~
~~oc~~~~55~OU~;:~w~~arn~w
G
CORE MPLS INDUST PORTF ETAL
C/O CORE REALTY HLDGS MGMT INC
1600 DAVE ST #450
NEWPORT BEACH, CA 92660 -2447
CAMPBELL PROPERTIES LP II
C/O KNOWLEDGE LEARNING CORP
ATTN TAX DEPT
PO BOX 6760
PORTLAND, OR 97228 -6760
ROBERT D & CARMEN J CHRISTIANS
6851 CARDINAL COVE DR
MOUND, MN 55364 -9535
LOVE 4 ONE ANOTHER CHARITIES
7801 AUDUBON RD
CHANHASSEN, MN 55317 -8205
DAVID SWARTOUT
10028 INDIGO DR
EDEN PRAIRIE, MN 55347 -1206
PRINCE R NELSON
7801 AUDUBON RD
CHANHASSEN , MN 55317 -8201
K & L PARTNERS
7870 PARK DR
CHANHASSEN , MN 55317 -9500
ALFRED A IVERSEN
PMT CORPORATION
1500 PARK RD
CHANHASSEN, MN 55317 -8200
PRN MUSIC CORPORATION
7801 AUDUBON RD
CHANHASSEN , MN 55317 -8201
PEERLESS INDUSTRIES INC
1969 WEST COUNTY ROAD C2
ROSEVILLE, MN 55113 -1246
TWO S PROPERTIES INC
DEPT PT MN 08305
PO BOX 25025
GLENDALE, CA 91201 -5025
MUSTANG LLC
7860 PARK DR
CHANHASSEN , MN 55317 -9294
MCGLYNN BAKERIES INC #366
C/O GENERAL MILLS TAX DEPT
PO BOX 1113
MINNEAPOLIS, MN 55440 -1113