2009-33
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE:
Aoril13. 2009
RESOLUTION NO:
2009-33
MOTION BY:
Litsev
SECONDED BY:
Tiornham
A RESOLUTION ACCEPTING REMAINING BIDS AND QUOTES FOR
THE PUBLIC WORKS MAINTENANCE FACILITY
PROJECT NO. 08-03
WHEREAS, pursuant to advertisements for the Public Works Maintenance Facility Project
No. 08-03, bids and quotes were received, opened and tabulated according to law.
AND WHEREAS, it appears that the attached are the lowest responsible bidders per RJM
Construction's letter of recommendation
NOW THEREFORE, BE IT RESOLVED by the Chanhassen City Council:
1. The mayor and clerk are hereby authorized and directed to enter into a contract with
contractors in the name of the City of Chanhassen for the Public Works Maintenance
Facility Project No. 08-03 according to recommendations in RJM Construction's letter of
recommendation.
2. RJM Construction is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids and quotes, except that the deposits of the successful bidder
and the next lowest bidder shall be retained until a contract has been signed.
Passed and adopted by the Chanhassen City Council this 13th day of April, 2009.
ATTEST:
44 J:l...JJ54
Todd Gerhardt, City Manager
YES
Furlong
Ernst
Litsey
McDonald
Tjornhom
NO
ABSENT
~
CONSTRUCTION
CORPORATE OFFICE
HWY.7 CORPORATE CWTF.R
700:) W. LAKE ~.l.
SUITE 400
ST. LOUIS PAflK. MN 55426
PHONE 952'837'(1600
FAX 952.832 9600
SATELLITE OFFICES
PLAZA VII
MINNEAPOLIS, MN
NOIHHLAND EXECUTIVE
orFlCE crNTCFl
BLOOMI:-J(,TON, r"~N
NOFlMANDALE.LAI(E
OfTleE PAf~I\
8LOOt.\INGTOI~. IMI
April 08, 2009
Mr. Todd Gerhardt
City of Chanhassen
7700 Market Boulevard
Chanhassen, MN 55317
Re: City ofChanhassen Public Works Facility
Recommendations for A ward of Contracts
Dear Mr. Gerhardt,
On March 19, 2009 public bids were received for the sixteen (16) advertised public bid categories.
Subsequently on March 23 the City Council awarded the contracts for Bid Categories that
included Precast Wall Panels, Precast Floor Plank, Structural Steel Materials, Building Concrete
and Masonry.
RJM Construction has now reviewed and qualified all remaining public bid categories. Based on
the results of these reviews we recommend to the City Council that they award the following
contracts. The values of these awards include Alternates 6 and 10.
Bid Category 5B - Structural Steel/JoistslDecking/Mlsc. Steel- Erection
Linco, Inc. Contract Amount: $ 132,500
12786 60111 Street NE
St. Michael, MN 55376
Bid Category 6A - CarpentrylFinish CarpentrylMillworkIDoorslFrameslHardware
Frerichs Construction Company Contract Amount: $ 197,600
3600 Labore Road
St. Paul, MN 55110
Bid Category 7 A - Roofing/SheetmetallAccessories
Palmer West Construction Company, Inc. Contract Amount:
14595 James Road
Rogers, MN 55374
$ 489,600
Bid Category 8A - Aluminum Entrances and Storefronts
Brin Northwestern Contract Amount:
144 Glenwood Avenue North
Minneapolis, MN 55405
$ 135,700
Bid Category 9A - Gypsum Board Systems
RTL Construction Contract Amount:
4000 Valley Industrial Blvd. South
Shakopee, MM 55379
$ 82,469
Bid Category 9B - Painting
Steinbrecher Painting
1408 71h Street North
Princeton, MN 55371
Contract Amount:
$ 99,300
Bid Category ttA - Vehicle Maintenance Equipment
Pump and Meter Contract Amount:
11303 Excelsior Blvd
Hopkins, MN 55343
$ 239,541
~
CONSTRUCTION
CORPORATE OFFICE
HWY,7 CORPOI1AH CENIDI
1003 \'/, LAKE ST,
SUITE 400
ST. LOUIS P/l..f~K, MN S542tj
PHONE 952'837-0600
FAX 952'fl32-9bOO
SATELLITE OF'F'ICES
PLAZA VII
MINNEAPOLIS, WJ
NORTHLAND EXECUTIVE
OFFICE CENTER
BLOOMINGTON, MN
NORMANDALE LAKr.
OfTICf: PARII
BLOOMINGTor~, MN
Bid Category 11 B - Fuel Island
Griggs Construction
530 Shoreview Park Road
Shoreview, MN 55]26
Contract Amount:
$ 137,000
Bid Category 1SA - Plumbing and Piping Systems
Minnetonka Plumbing Contract Amount:
520 River Street South
Delano, MN 55328
$ 696,000
Bid Category 15B - HV AC and Control Systems
General Sheetmetal Contract Amount:
2330 Louisiana Avenue North
Minneapolis, MN 55427
$ 4]2,500
Bid Category 16A - Electrical
Dynamic Electric
2800 ] 51 Avenue NW
Faribault, MN 55021
Contract Amount:
$ 551,490
The lowest bid contractors for Bid Categories 5B and I1A were not recommended for award.
AME Steel Erectors submitted the lowest bid for Bid Category 5B Steel Erection; however they
did not acknowledge receipt of Addenda 3 and 4. Their bid was subsequently rejected as
Addendum 3 presented changes to the bid scope of work. Aero Materials submitted the lowest bid
for Bid Category IIA Vehicle Maintenance Equipment; however it was determined that the bid
submitted was for the incorrect scope of work. Aero Materials has subsequently requested to have
their bid rescinded.
In addition to the public bids received RJM has also solicited several quoted scopes of work on
behalf of the City of Chanhassen. After a thorough scope review of all quotes received RJM
recommends the following contracts. The values of these awards also include Alternates 6 and 10.
Building Earthwork
Olson Construction Co., Inc.
6970 Inwood Road
Cologne, MN 55322
Contract Amount:
$ 82,640
Site Concrete
Capital Concrete
I7682I21s'Avenue
Kimball, MM 55353
Contract Amount:
$ 44,861
Precast Bin Storage Dividing Walls
Hanson Silo Company
] 1587 County Road 8 SE
Lake Lillian, MN 56253
Contract Amount:
$ 17,435
Interior Fences and Gates
Century Fence Company
PO Box 277
Forest Lake, MN 55025
Contract Amount:
$ 2,000
Retaining Walls
Structures Hardscapes
PO Box 711
Wayzata, MN 55391
Contract Amount:
$ 24,232
~
CONSTRUCTION
CORPORATE OFFICE
HVIY.7 COf,PORAiE CENTER
7003 W. LAKE ST.
SUITE 400
ST. LOUlS PN~I<, MN 55426
PHONE 952-837-81;00
fAX 952'832-9600
SATELLITE OFFICES
PLAZA VII
MINNEAPOliS. MN
NORTHLAND EXECUTIVL
OFnCE CENfLR
III OOMINGTON, MN
flORMANDALL L.Al\L
orneE P^,~K
BI.OOMINGTON, MN
Site Utilities
St. Paul Utilities and Excavating
190 Ryan Lane
Little Canada, MN 55117
Contract Amount:
$ 88,800
Overhead Sectional Doors
API Garage Door Store
2330 900 West Division Street
Waite Park, MN 56387
Contract Amount:
$ 88,700
Overhead Coiling Doors
Twin City Garage Door Company
5601 Boone Avenue North
New Hope, MN 55428
Contract Amount:
$ 16,166
Acoustical Ceilings
Twin City Acoustics, Inc.
2655 Cheshire Lane North
Plymouth, MN 55447
Contract Amount:
$ 7,805
Interior and Exterior Signage
Leroy Signs
6325 Welcome Avenue, North
Brooklyn Park, MN 55429
Contract Amount:
$ 9,357
Overhead Crane Systems
Aero Material Handling
103 Pleasant Street
Anoka, MN 55303
Contract Amount:
$ 51,740
Window Blinds
Prairie Edge
1609 West County Road 42, Suite 146
Burnsville, MN 55306
Contract Amount:
$ 1,795
Fire Sprinkler Systems
Service Fire Protection
211 Xenium Lane South
Minnetonka, MN 55305
Contract Amount:
$ 82,540
Presently RJM Construction is continuing to review the remaining quote categories for flooring
materials. The recommendations for the award of these quotes will be presented at the next City
Council meeting.
If you should have any questions, please feel free to contact me.
~?~
Brian G. Recker
Vice President
~
CONSTRUCTION
CORPORATE OFFICE
HWY. 7 CORPORA TE CUlTm
7003 \'1. LAKE ST.
SUITE 400
ST. LOUIS PAIlK, MN 55426
PHONE 952'837-8600
VAX 952'832-9600
SATELLITE OFFICES
Pl.AZA VII
MINNEAPOLIS, MN
NOHTHLAIIO EXECUTIVE
OFFICE CE:NTER
81.00MIN0TO:-I. MN
NORMANDALE l..Al<t
onlCE PAHK
BU)0I.1INGTON, MN
Chanhassen Public Works
Bid Summary
AprilS,2009
DESCRIPTION
Contractor
Public Bids Awarded March 23 2009
Cate orv 3A - Buildlna Concrete and 4A Masonrv Combined
Cate orv 3B . Precast Structural Concrete Walls
Cate orv 3C . Precast Plank
Cate orv 5A - Structural SteeIfJoists/Decklng/Misc. Steel Material
Davco Concrete
Fabcon
Molin
Thurnbeck
Public Bids Recommended for Award
Cate orv 5B - Structural SteelfJolsts/Deckina/Misc. Steel Erection linco
Cate orv 6A - Caro.lFinish Caro.lMillworkiDoors, Frame, Hrdwr/Misc. Spec Frerichs Construction
Cate 0 7 A . RoofinalSheetmetaVAccessories Palmer West
Cate 0 6A . Aluminum Entrances/Storefronts Brin Northwestern
Cate 0 9A. Gypsum Board Systems RTL Construction
Cate 9B . Palntin!l Steinbrecher Painting
CateQo 11A . Vehicle Maintenance Eauloment Pumo and Meter
Cateao" 11 B . Fuel Island Griaas Construction
Cateaorv 15A. Plumbing and Plpina Systems Minnetonka Plumbina
Cateaorv 15B - HVAC and Control Systems General Sheetmetal
Cate!lorv 16A. Electrical I Dvnamic Electric
Quotes Recommended for Award
Eerthwork
Site Concrete
Precast Bunker Divider Walls
Fences & Gates
Modular Retainina Walls
Site Utilities
Sectional Overhead Doors
Overhead COiling Doors
Acoustic Ceilinas
Slanaae
Overhead Crane Svstems
Window Treatment
Fire Protection
Olson Construction
Capital Concrete
Hanson Silo Company
Century Fence
Structures Hardscapes
SI. Paul Utilities and Excavatin
API Garaae Door Store
Twin Cltv Garaae Door Co.
Twin Citv Acoustics
Lerov Sians
Aero Material Handling
Prairie's Edge. Inc.
Service Fire Protection
Quotes Under Review
Tile
CaroeUResllient
Resinous Coatings
Pendina
Pendina
Pendina
Mise BudaetslAllowances
Earthwork. Site
Asphalt Pavina 1T0 Be Bid at Later Datel
Salt Structure
Landscaoe & Irriaation
Appliances
Commercial Vacuum System
Proiect Allowance
Proiect Allowance
Proiect Allowance
Proiect Allowance
Proiect Allowance
Proiect Allowance
Alternates Recommended for Award
A1temate 6. TPO rOOfing at all areas. $54,490
Alternate 10 . Provide six (6) skyliahts - $22 627
General Conditions
Tamo Heatina Equipment
Survey
General Liabilitv Insurance
Final Cleanlna
Blueprints
RJM Construction
RJM Construction
RJM Construction
RJM Construction
RJM Construction
RJM Construction
Subtotal Construction Cost
Continaency
Construction Management Fee
Total Construction Budget
Base
Estimate
$994,200
$692 605
$116,337
$400,863
$132,500
$197,600
$489 600
$135,700
$82,469
$99 300
$239,541
$137.000
$696 000
$412500
$551 490
$82 640
$44,861
$17 435
$2,000
$24,232
$88 800
$88,700
$16166
$7,805
$9,357
$51,740
$1 795
$82,540
$40 830
$5 670
$27,960
$75,000
$300 000
$110,000
$20.000
$12.000
$12.000
Included above
Included above
$260 600
$25 000
$20 000
$68.583
$18500
$35.000
$6 926 919
$346 346
$160,012
$7.433.277
.
~ Chanhassen Public Works
Bid Summary
April 8, 2009
CONSTRUCTION
Owner Costs
Soil Correction $310,000
Testina & Soeciallnsoections $25,000
Buildina Permit $54,276
SAC - 16 Units $32 000
Builders Risk Insurance $8 000
Furniture $60 000
Fiber Optic $50 000
Subtotal $539.276
Daslan Fees
Arch., Mech./Elec. Deskln Fees $429,485
Subtotal $429,485
Totaf Project Budget $8,402,038
rOrlalnalPro~ctBuaaet I 1 $8.800,0001
rTotaf Project Budget Sawngs I $397,962
Alternates. Not Recommended for Award
Alternate 1 - VCT in lieu of Resinous Flooring ($20,614)
Alternate 2 - Modular block retaining walls in lieu of "Recon" unit concrete ($9,537)
Alternate 3 - Exclude painting precast concrete walls at Vehicle Storage ($8,692)
Alternate 4 - Exclude painting of metal deck and joists at Vehicle Storage ($26,935)
Alternate 5 - Provide motorized gate and chain link fence at site entrance $10,731
Alternate 7 - Provide standard grey concrete finish at west elevation ($18,156)
Alternate 8 . Provide 2" thick overhead doors in lieu of 3" thick doors ($11,268)
Alternate 9 - Provide eighteen (18) smoke hatches $72,258
CORPORATE OfFICE
HI'IV. 7 CORPORATE CfNTUi
7003 'N. LAilE ST.
SUITE 400
ST. LOUIS 0,\1111, W; 55426
PHONE 952-837-!l600
FAX 952-B32.9600
SATELLITE OFFICES
PLAZA VII
MINN[I\POLlS, IAN
NORTHLAND ExeCUTIVE
OFFICE CEtHER
llLOOMINGlCl!J, MN
NORM!dW"LC LA;([
OFncc P!\l~I(
BLOOMING [ON. MN
Chanhassen Public Works
Bid Summary by Trade
March 19, 2009
~
CONSTRUCTION
Bid Category
5B - Structural SteeI/Joists/DeckinglMisc. Steel Erection
Company Base Bid Bid Addenda Alt #10 Total Contract
Security 4
6 Skylights
AME Construction $108,800.00 y 2 $720.00 $109.520.00
Linco $131,300.00 y 4 $1,200.00 $132.500.00
KMH Erectors $133,735.00 y 4 $600.00 $134;335.00
Hiah Five Erectors $154.500.00 y 4 $1 200.00 $155,700.00
Red Cedar $159,000.00 y 4 $720.00 $159,720.00
Danny's $198,189.00 y 4 $3,600.00 $201,789.00
Patriot Erection $239,597.00 y 4 $936.00 $240,533.00
Chanhassen Public Works
Bid Summary by Trade
March 19; 2009
~
CONSTRUCTION
Bid Category
6A - CarpJFinish CarpJMillworklDoors, Frames;
HrdwrlSpecialties
Company Base Bid Bid Addenda AIt#10 Total Contract
Security 4
6 Skylights
Freirichs $197,600.00 y 4 $197,600.00
Kellinqton $204,500.00 y 4 $1,800.00 $206,300.00
Crossroads $212,900.00 y 4 $212,900.00
Georae F. Cook $215,300.00 y 4 $215,300.00
Tekton $223.000.00 y 4 $223,000.00
Gladstone $230,094.00 y 4 $230,094.00
Maanev $249,500.00 y 4 $1 800.00 $251,300.00
Prestiae Builders $262,000.00 y 4 $4,800.00 $266,800.00
J. Eiden Construction $265,437.00 y 4 $1,960.00 $267,397.00
$0.00
Combined Bid - Bid Category 3A Concrete I 4A Masonry 16A Carpentry
$1,479,800.00
$1,800.00
$1,481,600.00
Chanhassen Public Works
Bid Summary by Trade
March 19,2009
~
CONSTRUCTION
Bid Category
7A - RoofinglSheetmetal/Accessories
Company Base Bid Bid Addenda Alt#6 Alt #10 Total Contract
Security 4
TPO Roofing
all areas 6 skylights
Palmer West $415,325.00 y 4 $54,490.00 $19,785.00 $489,600.00
HerzOQ $428,750.00 y 4 $38 450.00 $23,400.00 $490,600.00
Gemini $423,707.00 y 4 $50,195.00 $20,653.00 $494,555.00
John A. Dalsln $433,752.00 y 4 $46 242.00 $17,429.00 $497,423.00
SGO RoofinQ $476,042.00 y 4 $38,119.00 $4,767.00 $518,928.00
Lake Area $422,254.00 y 4 $81,838.00 $18,942.00 $523,034.00
Roof Tech $417,525.00 y 4 $87,591.00 $18,615.00 $523,731.00
Central Roofina $486,137.00 y 4 $22,012.00 $20,396.00 $528,545.00
Schweikert $448,725.00 y 4 $94 085.00 $16,550.00 $559,360.00
Peterson Bros $518,586.00 y 4 $27,364.00 $27,638.00 $573,588.00
Benard L Dalsin $512,000.00 y 4 $43,000.00 $21,000.00 $576,000.00
Sentra Sota $455,700.00 y 4 $114,500.00 $16,900.00 $587,100.00
Daleo Roofing $469,850.00 y 4 $98,980.00 $29,500.00 $598330.00
SPS Infrastructure $455,807.00 y 4 $59,346.00 $515,153.00
Chanhassen Public Works
Bid Summary by Trade
March 19,2009
~
CONSTRUCTION
Bid Category
8A - Aluminum Entrances/Storefronts
Company Base Bid Bid Addenda Total Contract
Security 4
Brin Contract $135,700.00 y 4 $135,700.00
Capital Citv $136,519.00 y 4 $136,519.00
Northern Glass Glazinq $139,599.00 y 4 $139,599.00
All Metro Glass $158514.00 y 4 $158,514.00
Empire House $171,177.00 y 4 $171,177.00
Chanhassen Public Works
Bid Summary by Trade
March 19, 2009
~
CONSTRUCTION
Bid Category
9A - Gypsum Board Systems
Company Base Bid Bid Addenda Total Contract
Security 4
RTL Construction $82,469.00 y 4 $82,469.00
M. Reinhart $90,000.00 y 4 $90,000.00
Custom Drvwall $96,600.00 y 4 $96,600.00
Mulcahv $96.975.00 y 4 . $96.975.00
Olvmoic $98.750.00 y 4 $98,750.00
Imperial Drywall $99,600.00 y 4 $99,600.00
AE Conrad $99,700.00 y 4 $99,700.00
W.Zintl $107,250.00 y 4 $107,250.00
Minuti Oole $117,550.00 y 4 $117,550.00
Chanhassen Public Works
Bid Summary by Trade
March 19,2009
~
CONSTRUCTION
Bid Category
9B - Painting
Company Base Bid Bid Addenda AIt#10 Total Contract
Security 4
6 Skylights
Steinbrecher $99,300.00 Y 4 $99,300.00
Swanson Younadale $102,760.00 Y 4 $102,760.00
Geo's Paint $103,487.00 Y 4 $900.00 $104,387.00
Franzen $105,486.00 Y 4 $1,800.00 $107286.00
Rainbow $107,760.00 Y 4 $107,760.00
Sunrise $115,400.00 Y 4 $115,400.00
Dan Treb $124,780.00 Y 4 $124,780.00
Decor Tee $127,750.00 Y 4 $127,750.00
.
Chanhassen Public Works ~
Bid Summary by Trade
March 19, 2009
CONSTRUCTION
Bid Category 11 A - Vehicle Maintenance Equipment
Company Base Bid Bid Addenda Total Contract
Security 4
Aero Materials $51,739.00 y 3 $51 739.00
Pump and Meter $239,541.00 y 4 $239 541.00
Westside Eauipment $241,500.00 y 4 $241,500.00
Chanhassen Public Works
Bid Summary by Trade
March 19,2009
~
CONSTRUCTION
Bid Category
11 B . Fuel Island
Company Base Bid Bid Addenda Total Contract
Security 4
Griaas Construction $137,000.00 y 4 $137,000.00
Pumo and Meter $138,036.00 y 4 $138,036.00
Mineesota Petroleum $146,742.00 y 4 $146,742.00
Zahl Petroleum $149,436.00 y 4 $149,436.00
Q'Oav EauiDment $189,500.00 y 4 $189 500.00
Chanhassen Public Works
Bid Summary by Trade
March 19, 2009
~
CONSTRUCTION
Bid Category
15A - Plumbing and Piping Systems
Company Base Bid Bid Addenda Total Contract
Security 4
Minnetonka Plumbina $696,000.00 y 4 $696.000.00
Horwitz $816,800.00 y 4 $816,800.00
Sun Mechanical $825,000.00 y 4 $825,000.00
Master Mechanical $838.000.00 y 4 $838,000.00
EI-Jav Plumbino $857,000.00 y 4 $857,000.00
MD Mechanical $865.000.00 y 4 $865,000.00
Wenzel $900.700.00 y 4 $900,700.00
Pearson $975,000.00 y 4 $975,000.00
US Mechanical $1,063,311.00 y 4 $1,063,311.00
McQuillan Brothers $1,092,000.00 y 3 $1.092,000.00
Combined Bid - Bid Categories 15A Plumbing and 15B HVAC
I Pearson
1$1 ,420,000.00
y
4
$1.420,000.00
Chanhassen Public Works
Bid Summary by Trade
March 19,2009
~
CONSTRUCTION
Bid Category
15B - HV AC and Control Systems
Company Base Bid Bid Addenda Total Contract
Security 4
General Sheet Metal $412,500.00 y 4 $412.500.00
Environ Con $413300.00 y 4 $413.300.00
Master Mechanical $422,000.00 y 4 $422,000.00
Sentra Sota $436,100.00 y 4 $436,100.00
Northern Air $454,400.00 y 4 $454,400.00
Chappel Central $460,000.00 y 4 $460,000.00
Thelen Heatina $484,000.00 y 4 $484000.00
Pearson $502,000.00 y 4 $502,000.00
Tek Mechanical $464,787.00 y 4 $464,787.00
Combined Bid. Bid Categories 15A Plumbing and 15B HVAC
Pearson
$1,466,000.00
4
$1,466,000.00
Chanhassen Publlc Works
Bid Summary by Trade
March 19, 2009
~
CONSTRUCTION
Bid Category
16A - Electrical
Company Base Bid Bid Addenda Total Contract
Security 4
Dvnamic Electric $551,490.00 y 4 $551,490.00
Manor Electric $556480.00 y 4 $556,480.00
Electrical Production $566,000.00 y 4 $566,000.00
C&S Electric $596,000.00 y 4 $596,000.00
OlvmpiaTech $629,375.00 y 4 $629,375.00
Phasor Electric $647,000.00 y 4 $647000.00
Medina Electric $647,076.00 y 4 $647,076.00
Ace Electric $649,436.00 y 4 $649436.00
Bloominoton Electric $652,000.00 y 4 $652,000.00
Kilmer Electric $659060.00 y 4 $659060.00
Eoan Companies $759,930.00 y 4 $759,930.00
Electrical Resource $854,301.00 y 4 $854,301.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Earthwork
Company Base Bid Addenda Total Contract
4
Olson Construction $82.640.00 3 $82,640.00
Minaer Construction $90,400.00 3 $90,400.00
Nord Excavatina $109,525.00 3 $109525.00
Kusske Construction $112,475.00 3 $112,475.00
PAC - Late bid 3-30-09 $113,400.00 4 $113,400.00
Northwest Asphalt $119120.00 4 $119,120.00
Minnesota Dirt Works $119,498.00 3 $119,498.00
Dennis Fehn Excavatina $128.800.00 2 $128 800.00
Imoerial Developers $132,124.00 3 $132,124.00
Nven Excavatina $162,617.00 4 $162,617.00
Concrete Science $178,552.00 $178,552.00
Frattalone Companies $192,000.00 3 $192.000.00
Ramsev Excavatina $194,642.00 3 $194,642.00
Julian Johnson Construction $233,150.00 4 $233.150.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Site Concrete
Company Base Bid Addenda Total Contract
4
Capital Concrete $44,861.00 3 $44,861.00
MN State Curb & Gutter $46,000.00 2 $46,000.00
Curb Masters, Inc. $48.071.00 4 $48,071.00
C.R. Fischer $48,535.00 3 $48,535.00
North Country Concrete $51,787.00 3 $51,787.00
Chanhassen Public Works ~
Bid Summary by Trade
April 8, 2009 CONSTRUCTION
Quote Category Bunker Walls
Company Base Bid Addenda Total Contract
4
Hanson Silo Comoanv $17,435.00 $17,435.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Fences and Gates
Company Base Bid Addenda Total Contract
4
Century Fence $2,000.00 2 $2.000.00
Anchor Fence $2,250.00 3 $2,250.00
Midwest Fence $2,396.00 $2,396.00
Town and Country $2.465.00 2 $2.465.00
Action Fence $3,985.00 $3,985.00
Keller Fence $4,200.00 4 $4200.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Modular Retaining Walls
Company Base Bid Addenda Total Contract
4
Structures Hardscaoes $24,232 3 $24,232
Hardscape Construction $24,645 $24,645
Advanced Wall $25,064 $25,064
WW Services $25,607 $25,607
Sunram Construction $25,994 $25,994
TMS Construction $28,830 $28,830
Desianina Nature $31,815 $31,815
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Site Utilties
Company Base Bid Addenda Total Contract
4
St. Paul Utilities & Excavatina $88.800.00 3 $88.800.00
Olson Construction $93.790.00 3 $93,790.00
Nova-Frost $93.800.00 3 $93.800.00
Kusske $95,545.00 3 $95545.00
Julian Johnson $96.750.00 4 $96.750.00
Sia Cat Excavatina $100.527.50 $100.527.50
Parrott Contractina $103,930.00 3 $103,930.00
Nyen Excavating $104500.00 4 $104.500.00
United Water and Sewer $106545.00 3 $106.545.00
Minaer Construction $108.275.00 3 $108.275.00
Frattalone Comoanies $115.000.00 $115,000.00
Valley-Rich $125,470.00 3 $125,470.00
.
Chanhassen Public Works ~
Bid Summary by Trade
AprilS,2009 CONSTRUCTION
Quote Category Overhead Sectional Doors
Company Base Bid Addenda Total Contract
4
API Garaae Door $88,700.00 4 $88,700.00
Twin City Garaae Door $98,515.00 4 $98,515.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Overhead Coiling Doors
Company Base Bid Addenda Total Contract
4
Twin City Garaae Door $16,166.00 4 $16,166.00
API Garaae Door $18,500.00 4 $18,500.00
Hufcor MN, LLC $18776.00 $18,776.00
Overhead Door Co. of the Northland $19,999.00 2 $19,999.00
Industrial Door Company $23,218.00 3 $23,218.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Acoustic Ceilings
Company Base Bid Addenda Total Contract
4
TeA $7,805.00 4 $7,805.00
Acoustics Associates $7,990.00 3 $7,990.00
Minnesota Acoustics $8,460.00 3 $8,460.00
Kirk $8,460.00 3 $8,460.00
Jannina's Acoustics $8,590.00 3 $8,590.00
Metro Acoustics $9.120,00 3 $9 120.00
Sonus $11.320.00 3 $11.320.00
.
Chanhassen Public Works ~
Bid Summary by Trade
April 8, 2009 CONSTRUCTION
Quote Category Signage
Company Base Bid Addenda Total Contract
4
Lerov Sians $9,357.00 3 $9,357.00
Designer Sign Svstems $9,400.00 3 $9,400.00
SiQncrafters $9,704.00 3 $9,704.00
,
I
.
Chanhassen Public Works ~
Bid Summary by Trade
April 8, 2009 CONSTRUCTION
Quote Category Overhead Crane Systems
Company Base Bid Addenda Total Contract
4
Aero Material HandlinQ $51,740.00 3 $51,740.00
J & B Eauipment Company $58,895.00 2 $58,895.00
Superior Crane Corporation $63,672.00 2 $63,672.00
I
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Window Treatment
Company Base Bid Addenda Total Contract
4
Prairie Edae $1,795.00 3 $1.795.00
Midwest Blinds $1,915.00 3 $1 915.00
Officesource $1.950.00 4 $1 950.00
Uniaue $2,327.00 $2,327.00
Custom Expressions $2.361.00 $2,361.00
HomeValu Interiors $4.565.00 $4.565.00
Multiole Conceot Interiors $13,950.00 4 $13.950.00
Chanhassen Public Works
Bid Summary by Trade
April 8, 2009
~
CONSTRUCTION
Quote Category
Fire Protection
Company Base Bid Addenda Total Contract
4
Service Fire Protection $82,540.00 4 $82.540.00
Ahern Fire Protection $86,250.00 3 $86,250.00
General Sorinkler $91,000.00 4 $91,000.00
Summit Fire Protection $96,500.00 3 . $96.500.00
Brothers Fire Protection $97,900.00 4 $97,900.00
Olsen Fire $98,760.00 $98.760.00
Viklna Automatic Sorinkler $107,920.00 3 $107,920.00
Shield Fire Protection $130,000.00 $130,000.00
e
OERTEL ARCHITECTS
1795 SAINT CLAIR AVENUE, SAINT PAUL, MN 55105
TEL: 651/696-5186
FAX: 651/696-5188
March 23,2009
Mr. Paul Oehme, Public Works Director
City of Chanhassen
7700 Market Boulevard
Chanhassen, MN 55317
RE: Public Works Department Project
Dear Paul,
Per your request, the following are my comments on the alternates that are being considered for
the project:
Alternate #1, VCT flooring in lieu of resinous flooring: Although the cost of$21,341.00 may
seem like a lot of money, the longevity, quality, low-maintenance and general appearance of the
this epoxy type material is far superior than the VCT flooring. I spent a fair amount of time on
this item, partially due to your interest, and I would strongly recommend the City maintain the
original base bid resinous floor in the office area.
Alternate #2, modular block walls in lieu of Recon units: I do not have a strong feeling either
way, and this was more in the civil related work.
Alternate #3, exclude painting at the interior concrete walls: The cost/credit of$8,527.00 is a
modest amount, and the painting (or lack thereof) will not greatly change the project. This would
be a good item to add if the monies are available (mild recommendation).
Alternate #4, painting the deck, joists and steel at the ceiling: This is one painting item that I
believe will make a difference. In combination with the skylights, this work will noticeably
improve the daylighting and general appearance. I have been in buildings, during construction,
when the skylights are installed and the painting yet to be performed. There is quite a difference
in light quality after the ceiling has been painted. Thus the recommendation to maintain base
bid.
Alternate #5, motorized gate and fence: This is pretty much your call, as it is mostly an
operational issue.
Alternate #6, TPO roofmg in lieu ofEPDM roofing: $55,667.00 is a considerable amount of
money, but the upgrade may be worth it. The black (rubber) EPDM roof is ballasted and is
essentially glued together, while the white TPO roof is essentially heat-welded. With the TPO
product, one can always see the roof (making inspection and repairs easier) while accessing a
~
ballasted roof is problematic. This alternate mostly involves method of construction, as opposed
to the actual materials used or color (since only a portion of the building is air conditioned). On
the other hand, the warranties differ, 20 years for the TPO roof and 10 years for the EPDM roof.
As a side issue, it would also be a good thing to have all the membrane used on the building to be
the same. Right now, with the base bid, different products are at different locations. If the cost
difference were less, this would be an easier recommendation for upgrade to the work.
Otherwise, this is a mild recommendation to accept the Alternate TPO roof at all locations.
~-_.-.
Alternate #7, grey concrete at the west elevation: As the architect, I believe that it is
fundamentally wrong to have three side of the building attractive and unified, with one side
essentially uninteresting, colorless and inconsistent with the rest of the building design and
materials. I do not consider the $18,156.00 a lot of money for this, especially considering this is
a permanent decision. Consequently, I would strongly recommend staying with the base bid.
Alternate #8, 2" thick versus 3" thick overhead doors: If the door openings were narrower and
shorter, I might suggest taking the credit and obtaining the 2" doors. In the case of this project,
with over-sized doors, I believe that staffwill appreciate the better performance and structural
integrity of the 3" doors. Therefore this is a recommendation to stay with the base bid 3" doors.
Alternate #9, smoke hatches: This alternate is no longer applicable.
Alternate #10, skylights (actually, alternates 10 and 11 are for skylights): I concur with the
proposed direction of city staff and construction manager in selecting twelve skylights for the
vehicle storage area.
Please contact me with any other questions you may have.
Sincerely,
OErj;
Jeffrey L. Oertel, AIA, CCS, President
2
CONSTRUCTION
-I
:r:
-
~
vtz
QC)
fZ4
:c
. [I1q
,en
..~
:::c
c
n
-I
c
:::c
,."
CORPORATE omCE
HWY.7CORPORATECENTER
7003 W. LAKE ST.
SUITE 400
ST. LOUIS PARK, MN 55426
PI:IONE 952-837-8600
FAX 952-832-9600
SATELUTE omCES
. PLAZA VII
MINNEAPOLIS, MN
NORTHLAND EXECUTIVE
OFFICE CENTER.,.
BLOOMINGTON, MN
,,!ORMANDALE LAKE
OFFICE PARK.
BLOOMINGTON, MN
March 25, 2009
Mr. Scott Vickerman
A.M.E. Construction Corp.
P.o. Box 388
Wayzata, MN 55391
Re: Chanhassen Public Works Facility
Submitted Bid - Bid Category 5B
Dear Mr.Vickerman,
On March 19, 2009 the City of Chanhassen received a sealed bid from A.M.E.
Construction Corporation (AME) for the work of Bid Category 5B for the structural and
miscellaneous steel erection.
In review of the bid form submitted, and publicly announced during the reading of the
bids, AME noted acknowledgement of only two (2) of the four (4) bid addenda issued.
Upon review of the addenda not acknowledged it has been concluded that Addendum 3
provided. for material changes to the work scope of Bid Category 5B.
Based on these circumstances the bid provided by:AME has been rejected as incomplete
.AlDd the award will be made to the next lowest qualified bidder. This action has been
reviewed and conferred with the City of Chanhassen and the City's attorney.
On behalf of the City of Chanhassen we thank you for your bid. If you should have any
questions, please feel free to contact me at 952-837-8636.
Sincerely,
Brian Recker
Vice President
RJM Construction
Cc:
Paul Oehme, City of Chanhassen
Jeff Oertel, Oertel Architects