Loading...
corrChanhassen Public Library Progress Meeting #22 Meeting Held: Nov. 14, 2002 Page 2 OLD BUSINESS (Cont'd.): ITEM 1.12 Larson Electric is awaiting response for their R_FI requesting clarification for the parking ramp lighting configuration. Larson Electric stated that shop drawings for light fixtures will be submitted shortly. This will allow MS&R to review Larson's concern about conflict with the structural components for best lighting results as well as clearance issues in the parking structure. The light fixture shop drawing submittal has not been received. K-A will inquire as to the status. The lighting package submittal was received from Larson Electric on Oct. 30, 2002 and forwarded to the Architect. 7.3 7.4 The Owner is contemplating installation of a retail coffee shop within the library and was advised that under floor piping required for this installation will be needed by Sept. 1, 2002. Melissa Brechon and Barry Petit attended a planning meeting with the "Friends of the Library" group pr/or to the progress meeting held this morning. More information to follow. Mechanical and electrical rough-ins, if any, in masonry walls above grade that may be affected by the proposed retail coffee shop, should be provided to the contractor immediately as these walls are being constructed. The coffee shop proposal concept will be submitted and reviewed at the City Council meeting to be held on Oct. 14, 2002. The City indicated that the coffee shop proposal would not be presented to the City Council until after their budget process is completed. K-A indicated this should not have any impact on the construction activities. K-A stated that under floor rough-in work will commence at the south side of the building at the end of November. Rough-in work will continue to the north as soon as the structural steel erection will permit. Rough-in activities in the vicinity of the retail coffee shop will commence approximately the first week in December. Therefore all below slab activities including the toilet room "flipping" design documents should be received by Nov. 25, 2002. The depth of frost prior to enclosure will dictate the extent of trenching required for under floor rough- in work. Steve Torell stated that all remaining smoke/fire dampers may be deleted from the project. Per the code, these elements are not necessary. Steve will speak with the mechanical engineer in this regard. Barry Petit will verify with Steve Torell if he has had conversation with the mechanical engineer regarding the dampers. Barry Petit indicated that Steve Torell has talked to the mechanical engineer and is of the opinion that no smoke or fire dampers are needed on the project. Smoke detectors however, are required. A proposal request will be issued by MS&R to formally delete the smoke and fire dampers xvhich were previously added to the scope of work and subsequently struck from the returned CO #1. A proposal request is forthcoming from MS&R that will document final status of the smoke and fire dampers. Steve Torell spoke to Sebesta Bloomberg & Assoc. on Wed., Oct. 9 regarding the smoke and fire dampers and detectors. Proposal Request No. 6 was issued on Oct. 3, 2002. Larson Electric will subrrdt their electrical cost impact for PR #6 today or Fr/. This will allow K-A to submit their response to PR #6 in total. Larson Electric was advised by the Fire Marshall that the building does not require a fire alarm system for an A3 Building Classification. The current contract documents however include a fire alarm system which is reflected in the recent shop drawing submittal by Larson Electric. The necessity of the system will require review by the electrical engineer and the City. Steve Torell has emailed data to Sebesta Bloomberg & Assoc. in this regard. K-A subrmtted their response to PR #6 on Oct. 29, 2002. MS&R stated that the revised fire alarm system scope will be forthcoming in a future proposal that is currently being drafted. Steve Torell requested to review the forthcoming PR prior to issuance to review scope. It was suggested that Steve contact MS&R directly. ACTION BY MS&R MS&R MS&R DATE REQ'D Chanhassen Public Libra~ Progress Meeting #22 Meeting HeM: Nov. 14, 2002 Page 3 OLD BUSINESS (Cont'd.): ITEM 13.1 K-A expressed potential concern for frost getting under the interior column pads which are currently shallow in case the building is not enclosed prior to freezing weather. Bill Cox indicated that he would request a budget estimate from the excavator and concrete subcontractors to drop the footings to frost elevation. K-A presented a cost proposal in the amount of approximately $10,000.00 to lower all interior column pad footings to frost elevation. Another alternate is being reviewed to include rigid insulation installed at the edges of the interior column pads extending out approximately 2-3 ft. which will prevent frost from infiltrating under the concrete structure. MS&R will advise if this alternative method is acceptable. The rigid insulation system to protect the interior column pad footings from frost has been approved. A band of 2" rigid insulation shall be placed around the perimeter of the column pad footing 2'. The top of the insulation shall be recessed to accept sand cover which will hold the insulation in place. Clarification: In lieu of spending $10,000.00 to drop the interior column pads as previously stated, consensus of those present including Crosstown Masonry, K-A, and the Architect, agreed that based on previous experience and the performance of rigid insulation as an alternative method of concrete pad protection, this method is a viable alternative. This method is also based on a short-term measure until temporary or permanent enclosure with heating is in place. Further discussion has resuked in the decision to lower the interior column pads within the library building. This is necessitated -due to the delay in building enclosure which would exceed any temporary protection from frost infiltration. A drawing will be issued by the structural engineer indicating the pertinent information required. MS&R indicated that a construction change document will be issued for the lowering of the interior column pads and adding concrete piers. 16.2 K-A requested clarification of an earlier comment made by GME regarding additional sand cushion under the slab on grade at the exterior chiller location. K-A will review this item with GME. The current contract documents stipulate a 4' sand cushion at the chiller pad. We understand that a letter is forthcoming from GME regarding the potential additional sand cushion at the north entrance entry slab. K-A placed 4' of sand cushion at the north entrance entry slab. 16.6 A meeting will be held with the City and Architect regarding locks and security. Steve Torell requested to be involved in the meeting that will be held to discuss locks and security. A meeting has been scheduled to discuss locks and security following today's Progress meeting. A memo is forthcoming regarding the results of the locks and security meeting held two weeks ago. 17.1 K-A suggested that it may be appropriate to relocate the gas line that services City Hall which runs from Kerber Blvd. easterly along the north side of the vacated Coulter Blvd. then running north to the south side of City Hall due to the shallowness of the gas line installation as well as running under the new circle drive. If the existing gas line runs continuous to Market Blvd., the existing line could possibly be vacated at the area of concern. The City indicated they would contact the gas company to review the options. The City has attempted to reach the gas company for potential relocation however, has not been successful in reaching them. Dan Remer with the City Engineering dept. will continue to make attempts to contact the gas company. The City indicated that the gas line discussed will remain where it is currently located, but will continue to lobby to have it relocated. If it is determined that it is not possible or feasible to relocate the gas line, K-A will require to have the gas line disconnected while the excavation and paving activities occur. Currently, the gas line falls within the paving profile depth at some segments. A temporary gas line will be required to avoid potential damage to the existing gas line during these construction activities. K-A met with the gas utility company and was advised that they would not relocate the existing gas line. They indicated they would work with K-A and their excavator to monitor the depth of excavation cuts for installation of the base for bituminous pavement. They will react to existing conditions at the time the excavation activities occur. ACTION BY MS&R Info. MS&R Info. DATE REQ'D Chanhassen Public Library Progress Meeting #22 Meeting Held: Nov. 14, 2002 Page 4 OLD BUSINESS (Cont'd.): ITEM 18.3 K-A requested that a CCD be issued to include the damp proofing at the foundation walls of the parking ramp structure not originally included in the scope of work but now required due to the moisture content of the soil. A CCD will be issued to incorporate the damp proofing required at the parking ramp foundation walls. Crosstown Masonry will review a flashing detail with MS&R at the ramp. 18.4 K-A stated that temporary enclosures will be required prior to installation of all final exterior building systems. Attempts will be made to minimize the extent of the temporary enclosures as job progress permits. Cost for temporary enclosures will be borne by the Owner as stated in the contract agreement. Some temporary heat and enclosures may be required for exterior concrete, masonry and stone activities not originally anticipated. Crosstown Masonry, based on the original construction schedule, figured all of their work being completed prior to Nov. 1. 19.2 Temporary power requirements including location will be discussed between Larson Electric and K-A for more significant Subcontractor usage. Mike Oelrich indicated it may take between 8-13 weeks for Excel Energy to deliver the permanent transformer. Larson Electric will review the power capacity of the existing temporary office building and utilize for temporary electric power. Temporary power will be provided from the existing construction office building that has a 400 amp service. 19.3 The City indicated that the driveway approach at the parking lot entrance should meet City rrfinimum requirements. K-A will coordinate efforts to pour the concrete curb and gutter and approach at the existing east parking lot to allow sufficient time for curing prior to usage. The concrete approach to the existing parking lot off Market Blvd. will be poured today and the City will advise potential users not to use the parking lot until next Tues. allowing for curing time. 19.4 Electrical heating mats for snowmelt at the parking ramp stairs will require two weeks delivery. A rough slab will be poured initially as a working surface to receive the heating mats. The treads and risers are formed and poured with the mats in a separate activity. K-A indicated that the pouring of the initial rough slab at the parking ramp stair will be poured next week. Electrical mats for snowmelt should be available shortly thereafter. 20.1 Exterior electrical outlets for (8) vehicles north of the new parking structure will be required by the City. Current scope will be reviewed. All conduit required for exterior electrical vehicle outlets and lighting should be finalized prior to placement of bituminous paving at the surface parking lot north of the parking structure. 20.4 MS&R indicated that additional detailing and design will be required for the metal railings at the parking ramp structure commensurate with the original architectural documents. 21.1 The Owner suggested installation of temporary orange fencing at the parking ramp entrance lower level to prevent utilization of this space during construction activities. Temporary orange fencing has replaced the temporary construction cyclone fence north of the upper level-parking ramp. ACTION BY MS&R Info. Larson Info. Info. MS&R Minnetonka Iron Info. DATE REQ'D Chanhassen Public Library Progress Meeting #22 Meeting Held: Nov. 14, 2002 Page 5 NEW BUSINESS: ITEM 22.1 Teresa Burgess indicated their engineering department will be closed next Thurs. and Fri. for a MPWA Conference. 22.2 K-A indicated they would order an additional portable toilet and provide heaters for this and the City provided portable toilet unit. 22.3 The City indicated it would not be necessary to place the wearing bituminous surface at the parking lot north of the parking structure. Teresa Burgess indicated that when building City roads, the City usually waits one year after the base course has been placed prior to applying the final wearing surface. 22.4 Some existing concrete sidewalk segments will be poured which were cracked due to the installation of the site utility ~vork at the area north of the parking structure. The new sidewalk that is located between the existing City Hall building and the new parking structure will not be poured until next Spring. ACTION BY Info. Info. Info. K-A/Info. DATE REQ'D The next Progress Meeting will be Thursday, November 21~ ~ 9:00 a.m. at the Kraus-Anderson jobsite office. All present are asked to attend. Chanhassen Public Library Progress Meeting #21 Meeting Held: Nov. 7, 2002 Page 2 OLD BUSINESS: ITEM 1.11 Although the bldg. permit has been issued, the bldg. inspection dept. still needs to address some issues that Steve Torell itemized in his e-mail to Barry Petit on June 4, 2002. MS&R gave Steve Torell a letter addressing issues No. 1 - 24. Response to the remaining items will be forthcoming. Steve Torell's letter dated August 6, 2002 was distributed at the progress meeting wherein he addresses his original March 20, 2002 plan review letter and MS&R's response to that letter which was given to Steve at last week's progress meeting. MS&R will review Steve's comments and will respond to open issues accordingly. MS&R distributed their letter dated August 21, 2002 to Justin Miller who will forward it to Steve Torell, which is a response to the City's plan review letter addressing open issues. There are still some issues, which cannot be addressed due to potential modifications recently initiated. These will be addressed when the final scope has been established. Barry Petit indicated that the energy calculation for the building envelope is perhaps the most significant outstanding item yet to be submitted to Steve Torell. Barry Petit presented requested information to Justin Miller at the meeting which will be forwarded to Steve Torell. Steve Torell stated the following items are still outstanding: 1. ASI l& 3 2. PR4&5 3. The signature page to the Specification and Addenda 1 & 2. MS&R provided additional information and documents to the City. Although not present at the meeting, Steve Torell stopped by prior to the meeting and indicated that he has not seen Items 1-4 yet as well as the structural engineer signed CCD #6. Steve Torell received ASI #1, (ASI #3 is non-ex/stent), PR #4 & 5 and CCD #6. Steve Torell will assemble a current list of outstanding documents and forward to MS&R. 1.12 Larson Electric is awaiting response for their RFI requesting clarification for the parking ramp lighting configuration. Larson Electric stated that shop drawings for light fixtures will be submitted shortly. This will allow MS&R to review Larson's concern about conflict with the structural components for best lighting results as well as clearance issues in the parking structure. The light fixture shop drawing submittal has not been received. K-A will inquire as to the status. The lighting package submittal was received from Larson Electric on Oct. 30, 2002 and forwarded to the Architect. 7.3 The Owner is contemplating installation of a retail coffee shop within the library and was advised that under floor piping required for this installation will be needed by Sept. 1, 2002. Melissa Brechon and Barry Petit attended a planning meeting with the "Friends of the Library" group prior to the progress meeting held this morning. More information to follow. Mechanical and electrical rough-ins, if any, in masonry walls above grade that may be affected by the proposed retail coffee shop, should be provided to the contractor immediately as these walls are being constructed. The coffee shop proposal concept will be submitted and reviewed at the City Council meeting to be held on Oct. 14, 2002. The City indicated that the coffee shop proposal would not be presented to the City Council until after their budget process is completed. K-A indicated this should not have any impact on the construction activities. K-A stated that under floor rough-in work will commence at the south side of the building at the end of November. Rough-in work will continue to the north as soon as the structural steel erection will permit, Rough-in activities in the vicinity of the retail coffee shop will commence approximately the first week in December. Therefore all below slab activities including the toilet room "flipping" design documents should be received by Nov. 25, 2002. ACTION BY City Info. Ii, fo. DATE REQ'D Chanhassen Public Libra~v Progress Meeting #21 Meeting Held: Nov. 7, 2002 Page 3 OLD BUSINESS (Cont'd.): ITEM 7.4 Steve Torell stated that all remaining smoke/fire dampers may be deleted from the project. Per the code, these elements are not necessary. Steve will speak w/th the mechanical engineer in this regard. Barry Petit will verify with Steve Torell if he has had conversation with the mechanical engineer regarding the dampers. Barry Petit indicated that Steve Torell has talked to the mechanical engineer and is of the opinion that no smoke or fire dampers are needed on the project. Smoke detectors however, are required. A proposal request will be issued by MS&R to formally delete the smoke and fire dampers which were previously added to the scope of work and subsequently struck from the returned CO #1. A proposal request is forthcoming from MS&R that will document final status of the smoke and fire dampers. Steve Torell spoke to Sebesta Bloomberg & Assoc. on Wed., Oct. 9 regarding the smoke and fire dampers and detectors. Proposal Request No. 6 was issued on Oct. 3, 2002. Larson Electric will submit their electrical cost impact for PR #6 today or Fri. This will allow K-A to submit their response to PR #6 in total. Larson Electric was advised by the Fire Marshall that the building does not require a fire alarm system for an A3 Building Classification. The current contract documents however include a fire alarm system which is reflected in the recent shop drawing submittal by Larson Electric. The necessity of the system will require review by the electrical engineer and the City. Steve Torell has emailed data to Sebesta Bloomberg & Assoc. in this regard. K-A submitted their response to PR #6 on Oct. 29, 2002. MS&R stated that the revised fire alarm system scope will be forthcoming in a future proposal that is currently being drafted. Steve Torell requested to review the forthcoming PR prior to issuance to review scope. It was suggested that Steve contact MS&R directly. 13.1 K-A expressed potential concern for frost getting under the interior column pads which are currently shallow in case the building is not enclosed prior to freezing weather. Bill Cox indicated that he would request a budget estimate from the excavator and concrete subcontractors to drop the footings to frost elevation. K-A presented a cost proposal in the amount of approximately $10,000.00 to lower all interior column pad footings to frost elevation. Another alternate is being reviewed to include rigid insulation installed at the edges of the interior column pads extending out approximately 2-3 ft. which will prevent frost from infiltrating under the concrete structure. MS&R will advise if this alternative method is acceptable. The rigid insulation system to protect the interior column pad footings from frost has been approved. A band of 2" rigid insulation shall be placed around the perimeter of the column pad footing 2'. The top of the insulation shall be recessed to accept sand cover which will hold the insulation in place. Clarification: In lieu of spending $10,000.00 to drop the interior column pads as previously stated, consensus of those present including Crosstown Masonry, K-A, and the Architect, agreed that based on previous experience and the performance of rigid insulation as an alternative method of concrete pad protection, this method is a viable alternative. This method is also based on a short-term measure until temporary or permanent enclosure with heating is in place. Further discussion has resulted in the decision to lower the interior column pads within the library building. This is necessitated due to the delay in building enclosure which would exceed any temporary protection from frost infiltration. A drawing will be issued by the structural engineer indicating the pertinent information required. MS&R indicated that a construction change document will be issued for the lowering of the interior column pads and adding concrete piers. 16.2 K-A requested clarification of an earlier comment made by GME regarding additional sand cushion under the slab on grade at the exterior chiller location. K-A will review this item with GME. The current contract documents stipulate a 4' sand cushion at the chiller pad. We understand that a letter is forthcoming from GME regarding the potential additional sand cushion at the north entrance entry slab. ACTION BY City MS&R GME DATE REQ'D Chanhassen Public Library Progress Meeting #2.I Meeting Held: Nov. 7, 2002 Page 4 OLD BUSINESS (Cont'd.): ITEM 16.6 18.3 18.4 19.2 19.3 19.4 17.1 A meeting will be held with the City and Architect regarding locks and security. Steve Torell requested to be involved in the meeting which will be held to discuss locks and security. A meeting has been scheduled to discuss locks and security following today's Progress meeting. A memo is forthcoming regarding the results of the locks and security meeting held two weeks ago. K-A suggested that it may be appropriate to relocate the gas line that services City Hall which runs from Kerber Blvd. easterly along the north side of the vacated Coulter Blvd. then running north to the south side of City Hall due to the shallowness of the gas line installation as well as running under the new circle drive. If the existing gas line runs continuous to Market Blvd., the existing line could possibly be vacated at the area of concern. The City indicated they would contact the gas company to review the options. The City has attempted to reach the gas company for potential relocation however, has not been successful in reaching them. Dan Remer with the City Engineenng dept. will continue to make attempts to contact the gas company. The City indicated that the gas line discussed will remain where it is currently located, but will continue to lobby to have it relocated. If it is determined that it is not possible or feasible to relocate the gas line, K-A will require to have the gas line disconnected while the excavation and paving activities occur. Currently, the gas line falls within the paving profile depth at some segrnents. A temporary gas line will be required to avoid potential damage to the existing gas line during these construction activities. K-A requested that a CCD be issued to include the damp proofing at the foundation walls of the parking ramp structure not originally included in the scope of work but now required due to the moisture content of the soil. A CCD will be issued to incorporate the damp proofing required at the parking ramp foundation walls. Crosstown Masonry will review a flashing detail with MS&R at the ramp. K-A stated that temporary enclosures will be required prior to installation of all final exterior building .systems. Attempts will be made to minimize the extent of the temporary enclosures as job progress permits. Cost for temporary enclosures will be borne by the Owner as stated in the contract agreement. Some temporary heat and enclosures may be required for exterior concrete, masonry and stone activities not originally anticipated. Crosstown Masonry, based on the original construction schedule, figured all of their work being completed prior to Nov. 1. Temporary power requirements including location will be discussed between Larson Electric and K-A for more significant Subcontractor usage. Mike Oelrich indicated it may take between 8-13 weeks for Excel Energy to deliver the permanent transformer. Larson Electric will review the power capacity of the existing temporary office building and utilize for temporary electric power. The City indicated that the driveway approach at the parking lot entrance should meet City minimum requirements. K-A will coordinate efforts to pour the concrete curb and gutter and approach at the existing east parking lot to allow sufficient time for curing prior to usage. Electrical heating mats for snowmelt at the parking ramp stairs will require two weeks delivery. A rough slab will be poured initially as a working surface to receive the heating mats. The treads and risers are formed and poured with the mats in a separate activity. K-A indicated that the pouring of the initial rough slab at the parking ramp stair will be poured next week. Electrical mats for snowmelt should be available shortly thereafter. ACTION BY MS&R City MS&R/ Crosstown Larson Info. Info. DATE REQ'D Chanhassen Public Library Progress Meeting #21 Meeting Held: Nov. 7, 2002 Page 5 OLD BUSINESS (Cont'd.): ITEM 20.1 Exterior electrical outlets for (8) vehicles north of the new parking structure will be required by the City. Current scope will be reviewed. All conduit required for exterior electrical vehicle outlets and lighting should be finalized prior to placement of bituminous paving at the surface parking lot north of the parking structure. 20.3 K-A indicated that a meeting was held on Oct. 29, 2002 with KMH Erectors, who will be erecting the structural steel for the library, to review the new OSHA erection requirements prior to the commencement of their work. Sequencing of work, designation of a stag/ng area, and site access and proper roadways also were reviewed. K-A will receive general information from MBJ for anchor bolt repair if required. These designations and documents will be delineated on drawings and posted in the construction office for reference purposes. K-A will also advise KMH that all concrete and masonry to receive structural steel members have met the designated strengths. Those in attendance were as follows: Tim Geyen, KMH Erectors Jim Packard, K-A · Harold Fournier, K-A · Bill Cox, K-A It was also determined that once the erection process which will commence from the south and work to the north reaches Grid 3.5, the exterior wall steel stud framing can commence on the south side. 20.4 MS&R indicated that additional detailing and design will be required for the metal railings at the parking ramp structure commensurate with the original architectural documents. ACTION BY MS&R Minnetonka Iron DATE REQ'D NEW BUSINESS. ITEM 21.1 The Owner suggested installation of temporary orange fencing at the parking ramp entrance lower level to prevent utilization of this space during construction activities. ACTION BY K-A DATE REQ'D The next Progress Meeting will be Thursday. x_~November 1~0 a.m. at the Kraus-Anderson jobsite office. All present are asked to attend. Chanhassen Public Library Progress Meeting #20 Meeting Held: Oct. 31, 2002 Page 2 OLD BUSINESS: ITEM 1.11 Although the bldg. permit has been issued, the bldg. inspection dept. still needs to address some issues that Steve Torell itemized in his e-mail to Barry Petit on June 4, 2002. MS&R gave Steve Torell a letter addressing issues No. 1 - 24. Response to the remaining items will be forthcoming. Steve Torell's letter dated August 6, 2002 was distributed at the progress meeting wherein he addresses his original March 20, 2002 plan review letter and MS&R's response to that letter which was given to Steve at last week's progress meeting. MS&R will review Steve's comments and will respond to open issues accordingly. MS&R distributed their letter dated August 21, 2002 to Justin Miller who will for~vard it to Steve Torell, which is a response to the City's plan review letter addressing open issues. There are still some issues, which cannot be addressed due to potential modifications recently initiated. These will be addressed when the final scope has been established. Barry Petit indicated that the energy calculation for the building envelope is perhaps the most significant outstanding item yet to be submitted to Steve Torell. Barry Petit presented requested information to Justin Miller at the meeting which ;vill be forwarded to Steve Torell. Steve Torell stated the following items are still outstanding: 1. ASI l& 3 2. PR4&5 3. The signature page to the Specification and Addenda 1 & 2. MS&R provided additional information and documents to the City. Although not present at the meeting, Steve Torell stopped by prior to the meeting and indicated that he has not seen Items 1-4 yet as well as the structural engineer signed CCD #6. Steve Torell received ASI #1, (ASI #3 is non-existent), PR #4 & 5 and CCD #6. 1.12 Larson Electric is awaiting response for their RFI requesting clarification for the parking ramp lighting configuration. Larson Electric stated that shop drawings for light fixtures will be submitted shortly. This will allow MS&R to review Larson's concern about conflict with the structural components for best lighting results as well as clearance issues in the parking structure. The light fixture shop drawing submittal has not been received. K-A will inquire as to the status. 7.3 The Owner is contemplating installation of a retail coffee shop within the library and was advised that under floor piping required for this installation will be needed by Sept. 1, 2002. Melissa Brechon and Barry Petit attended a planning meeting with the "Friends of the Library" group prior to the progress meeting held this morning. More information to follow. Mechanical and electrical rough-ins, if any, in masonry walls above grade that may be affected by the proposed retail coffee shop, should be provided to the contractor immediately as these walls are being constructed. The coffee shop proposal concept will be submitted and re,Aexved at the City Council meeting to be held on Oct. 14, 2002. The City indicated that the coffee shop proposal would not be presented to the City Council until after their budget process is completed. K-A indicated this should not have any impact on the construction activities. ACTION BY MS&R Larson/ K-A Info. DATE REQ'D Chanhassen Public Library Progress Meeting #20 Meeting Held: Oct. 31, 2002 Page 3 OLD BUSINESS (Cont'd.): ITEM 7.4 Steve Torell stated that alt remaining smoke/fire dampers may be deleted from the project. Per the code, these elements are not necessary. Steve will speak with the mechanical engineer in this regard. Barry Petit will verify with Steve Torell if he has had conversation with the mechanical engineer regarding the dampers. Barry Petit indicated that Steve Torell has talked to the mechanical engineer and is of the opinion that no smoke or fire dampers are needed on the project. Smoke detectors however, are required. A proposal request will be issued by MS&R to formally delete the smoke and fire dampers which were previously added to the scope of work and subsequently struck from the returned CO #1. A proposal request is forthcoming from MS&R that will document final status of the smoke and fire dampers. Steve Torell spoke to Sebesta Bloomberg & Assoc. on Wed., Oct. 9 regarding the smoke and fire dampers and detectors. Proposal Request No. 6 was issued on Oct. 3, 2002. Larson Electric will submit their electrical cost impact for PR #6 today or Fri. This will allow K-A to submit their response to PR #6 in total. Larson Electric was advised by the Fire Marshall that the building does not require a fire alarm system for an A3 Building Classification. The current contract documents however include a fire alarm system which is reflected in the recent shop drawing submittal by Larson Electric. The necessity of the system will require review by the electhcat engineer and the City. Steve Torell has emailed data to Sebesta Bloomberg & Assoc. in this regard. K-A submitted their response to PR #6 on Oct. 29, 2002. MS&R stated that the revised fire alarm system scope will be forthcoming in a future proposal that is currently being drafted. ACTION BY MS&R DATE REQ'D 13.1 K-A expressed potential concern for frost getting under the interior column pads which are currently shallow in case the building is not enclosed prior to freezing weather. Bill Cox indicated that he would request a budget estimate from the excavator and concrete subcontractors to drop the footings to frost elevation. K-A presented a cost proposal in the amount of approximately $10,000.00 to lower all interior column pad footings to frost elevation. Another alternate is being reviewed to include rigid insulation installed at the edges of the interior column pads extending out approximately 2-3 ft. which will prevent frost from infiltrating under the concrete structure. MS&R will advise if this alternative method is acceptable. The rigid insulation system to protect the interior column pad footings from frost has been approved. A band of 2" rigid insulation shall be placed around the perimeter of the column pad footing 2'. The top of the insulation shall be recessed to accept sand cover which will hold the insulation in place. Clarification: In lieu of spending $10,000.00 to drop the interior column pads as previously stated, consensus of those present including Crosstown Masonry, K-A, and the Architect, agreed that based on previous experience and the performance of rigid insulation as an alternative method of concrete pad protection, this method is a viable alternative. This method is also based on a short-term measure until temporary or permanent enclosure with heating is in place. Further discussion has resulted in the decision to lower the interior column pads within the library building. This is necessitated due to the delay in building enclosure which would exceed any temporary protection from frost infiltration. A drawing will be issued by the structural engineer indicating the pertinent information required. MS&R indicated that a construction change document will be issued for the lowering of the interior column pads and adding concrete piers. MS&R 16.2 K-A requested clarification of an earlier comment made by GME regarding additional sand cushion under the slab on grade at the exterior chiller location. K-A will review this item with GME. The current contract documents stipulate a 4' sand cushion at the chiller pad. We understand that a letter is forthcoming from GME regarding the potential additional sand cushion at the north entrance entry slab. GME Chanhassen Public Librwy Progress Meeting #20 Meeting Held: Oct. 31, 2002 Page 4 OLD BUSINESS (Cont'd.): ITEM 16.3 K-A indicated that when the backfilling activity starts at the north ramp wall, vehicle parking will be limited to allow truck access and equipment activity until the wall has been backfilled. K-A will coordinate in advance this activity with the City. The City has requested a minimum of one week's notification for parking restrictions north of the new parking ramp structure to coordinate with their employees. The City also requested that no activity occur in this area on Nov. 5 which is election day. Backfilling activities at the ramp will commence on Mon. 10/21/02 and will take approximately three days to complete weather permitting. The Owner agreed to provide access for truck activity at the upper part of the new parking ramp area. The Owner has requested that pre-cast installation at the ramp not be scheduled for Tues. 11/05/02 which is election day. Any activities occurring north of the parking structure affecting the parking area should be scheduled a minimum of two days in advance with the City. K-A will continue to coordinate the backfilling activities with the Owner at the parking structure. 16.6 17.1 18.2 18.3 18.4 19.1 A meeting will be held with the City and Architect regarding locks and security. Steve Torell requested to be involved in the meeting which will be held to discuss locks and security. A meeting has been scheduled to discuss locks and security following today's Progress meeting. A memo is forthcoming regarding the results of the locks and security meeting held two weeks ago. K-A suggested that it may be appropriate to relocate the gas line that services City Hall which runs from Kerber Blvd. easterly along the north side of the vacated Coulter Blvd. then running north to the south side of City Hall due to the shallowness of the gas line installation as well as running under the new circle drive. If the existing gas line runs continuous to Market Blvd., the existing line could possibly be vacated at the area of concern. The City indicated they would contact the aas company to review the options. The City has attempted to reach the gas company for potential relocation however, has not been successful in reaching them. Dan Remer with the City Engineering dept. will continue to make attempts to contact the gas company. The City indicated that the gas line discussed will remain where it is currently located, but will continue to lobby to have it relocated. If it is determined that it is not possible or feasible to relocate the gas line, K-A will require to have the gas line disconnected while the excavation and paving activities occur. Currently, the gas line falls within the paving profile depth at some segments. A temporary gas line will be required to avoid potential damage to the existing gas line during these construction activities. The City indicated that mechanical and electaical rough-ins minimally should be installed to support the proposed coffee shop equipment if the fully developed proposal has not been approved by the time that the other contractual rough-ins have commenced. Further discussion of this item will occur at a special council meeting which will be held on 11/07/02. A specific date for the special council meeting has not been determined at this time. K-A requested that a CCD be issued to include the damp proofing at the foundation ,,vails of the parking ramp structure not originally included in the scope of work but now required due to the moisture content of the soil. A CCD will be issued to incorporate the damp proofing required at the parking ramp foundation walls. Crosstown Masonry will review a flashing detail with MS&R at the ramp. K-A stated that temporary enclosures will be required prior to installation of all final exterior building systems. Attempts will be made to minimize the extent of the temporary enclosures as job progress permits. Cost for temporary enclosures will be borne by the Owner as stated in the contract agreement. Some temporary heat and enclosures may be required for exterior concrete, masonry and stone activities not originally anticipated. Crosstown Masonry, based on the original construction schedule, figured all of their work being completed prior to Nov. 1. Larson Electric will review rough-in requirements for the power and lights at the parking structure in preparation for the placement of pre-cast members. ACTION DATE BY REQ'D Info./ K-A MS&R City Info. MS&R/ Crosstown Info. Larson/ K-A Chanhassen _Public Library Progress Meeting #20 Meeting Held: Oct. 31, 2002 Page 5 OLD BUSINESS (Cont'd.): ITEM 19.2 19.3 Temporary power requirements including location will be discussed between Larson Electric and K-A for more significant Subcontractor usage. The City indicated that the driveway approach at the parking lot entrance should meet City minimum requirements. K-A will coordinate efforts to pour the concrete curb and gutter and approach at the existing east parking lot to allow sufficient time for curing prior to usage. 19.4 Electrical heating mats for snowmelt at the parking ramp stairs will require two weeks delivery. A rough slab will be poured initially as a working surface to receive the heating mats. The treads and risers are formed and poured with the mats in a separate activity. ACTION BY Larson/ K-A DATE REQ'D NEW BUSINESS: ITEM 20.1 20.2 Exterior electrical outlets for (8) vehicles north of the new parking structure will be required by the City. Current scope will be reviewed. Justin Miller indicated that funding has been approved for the acquisition of books for the new library. 20.3 K-A indicated that a meeting was held on Oct. 29, 2002 with KMH Erectors, who will be erecting the structural steel for the library, to review the new OSHA erection requirements prior to the commencement of their work. Sequencing of work, designation of a staging area, and site access and proper roadways also ~vere reviewed. K-A will receive general information from MBJ for anchor bolt repair if required. These designations and documents will be delineated on drawings and posted in the construction office for reference purposes. K-A will also advise KMH that all concrete and masonry to receive structural steel members have met the designated strengths. Those in attendance were as follows: · Tim Geyen, KMH Erectors Jim Packard, K-A · Harold Fournier, K-A Bill Cox, K-A It was also determined that once the erection process which will commence from the south and work to the north reaches Grid 3.5, the exterior wall steel stud framing can commence on the south side. 20.4 MS&R indicated that additional detailing and design will be required for the metal railings at the parking ramp structure commensurate with the original architectural documents. ACTION BY MS&R Info. Info. Minnetonka Iron DATE REQ'D The next Progress Meeting will be Thursday:._November 7, ~ 9:00 a.m. at the Kraus-Anderson iobsite office. All present are asked to attend. NOV 0. ? 2002 C]TY' OF C'HANHA$SEN O. CITY OF CHANHASSEN CITY REPORTS Office of County Sheriff ~ Carver County Government Ccnrer. ~ Justice Cemer . ER 600 East Fourth Street Chaska, Minnesota 55318-2190 Bud O!son, Sheriff Emergency: 911 S..enffAdm:,n: (9>2; 36!-i212 Admin. Fax: ('952) 36 t- 1229 Dispatch: (952) 361-1231 (Non-Emergency) Listed below is a descriPtion of each of the different classification of calls for service which the Carver County Sheriff's Office received and ~rocessed for your area. Criminal Assault Burglary Drug Violation Homicide Traffic/Alcohol Misc. Criminal Property Damage Robbery Sex Crime Theft Theft Related Vehicle Theft Non-Criminal Disturb Peace/Privacy Misc. Non Criminal Lock out Alarm Domestic Missing Persons/Runaway Animal Medical House/Business Check Assist other Agency Fire Call Prowler Mental Health Civil Process Transport Warrant Service Boat and Water Snowmobile Gun Permit/Acquire Gun Permit/Ca, .'-Cy ~'ock Post Office Suspicious Activity Open door Auto Accd-Prop Damage Auto Accd-Injury Auto Accd-Fatal Traffic Special Traffic Altercation between pa~ies where actual physical harm occurred Breaking into a residence or business Ail drug violations, possession of, sale of, manufacture of or under the influence of. Taking of a persons life Traffic stops or accidents involving a driver under the influence Minor offenses which include order of protection violations, warrant service, threats- and harassment, tobacco violations? All damage to property includh3, g vandalism-and trespassing on property Taking of property in the presence of another with use of force Rape, sexual abuse, indecent exposure and pornography Taking of property' Credit card fraud, issuance of bad checks, counterfeiting, theft by swindle Theft of a motor vehicle Noise, harassing phone calls, Citizen assists,~ lost and found property, general law enforcement questions, civil matters, delivery of council, packets, juvenile disciplinary problems etc. Unlock doors of automobiles, residences or businesses for owners Checking on an alarm at a'private residence or business. Verbal argument between parties Juvenile runaways or missing persons Animal bites, stray animals Assist persons with medical issues, natural cause deaths Check on houses or businesses when owners are away fi.om property, Assist other law enforcement offices; state patrol or government departments Fires and assist fire departments Person on property who does not belong Suicides, 72 hr holds for mental health issues. Service of civil papers, assist with civil stand by Situations Transport persons for various reasons- Service a warrant for Carver County and other counties Ail incidents involving boats or lakes All incidents involving sno.wmobile Issuance of a permit to purchase a handgun Issuance of a permit to carry a handgun Deputies lock post o~ce buildings Suspicious persons, acts or vehicIes - Locating an open door to a business Auto accident when onlY property damage occurred Auto accident when injUry, and property damage occurred Auto accident in which a fatality occurred All traffic stops and calls, stalled vehicles, debris on the roadway Radar wagon, special traffic details Affirmative A ctionfEqual.Opportuni~.. Employer Printed on 10% Post-Consumer Recycled Paper CARVER COUNTY SHERIFF'S OFFICE AREA REPORT FOR CITY OF CHANHASSEN CALLS FOR SERVICE FOR MONTH OF OCTOBER 2002 2002 2001 2001 MONTHLY YTD MONTHLY YTD CRIMINAL Assault 2 39 2 40 Burglaw, 3 33 0 36 Drug Violation 2 18 1 25 . Homcide 0 0 0 0' Traffic/Alcohol 14 133 14 137 Misc. Criminal 12 183 22 217 property Damage 45 265 21 287 Robbery 2 2 1 .. 5 Sex Crime 0 5 2 .. 12 ,.. Theft 38 344 49 376 Theft/Related 5 27 3 25 Vehicle Theft 1 23 2 22 . , TOTAL CRIMINAL 124 1072 117 1182 , , NON-CRIMINAL Disturb Peace/Privacy 48 411 43 424. Misc/Non criminal 59 583 55 647 .. Lock out 16 289 58 526 Alarm 72 730 80 781 Domestic 10 79 11 122 Missing Person/Runaw. ays 4 53 8 66 Child Abuse/Neglect 2 14 0 45 Motorist Assist '- 27 315 20 287 Animal 32 311 41 346 Medical 37 365 37 387 House/Business Check 4 27 2 25 Assist other A.g.ency 11 91 3 63 Fire Call 28 197 26 224 ~rowler 6 19 2 10 Mental Health 6 30 1 35 ., .. Civil Process 2 6 0 2 Transport 0 10 0 5 Warrant Service 1 21 5 41 Boat & Water 0 95 0 51 Snowmobile 0 26 0 20 Gun Permit/Acquire 12 71 19 102 ., Gun Permit/Carry 0 1 1 4 Lock Post Office 0 0 0 0 Suspicious 'Activity 71 734 110 744 . Open Door 0 24 1 21 Auto Accd- Prop Dam 36 424 28 424 , , Auto Accd - Injury 3 58.. 6 84 ... Fatal Auto Accd 0 2 0 1 ., Traffic 215 2273 179 2209 Special Traffic "' 23 91 8 51 ..... TOTAL NON-CRIM 725 7350 744 7747 . ITOTAL REPORTED 849 I 8422 I 861 I 8929 ILl ~_' I-- Z 0 n,' 0 C~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0'0 0 0 0 0 0 0 0 0 0 C~ 0 0 0 ' 0 0 oo '~- oo 0 0 CD '~- kO OX 0", 0 0 0 0 ~ t'"- kO t"'- 0 ~ 0.4 0 ¢q 0 0 0 0 0 0 · '~ 0 0 0 C~ 0 C) 0 0 0 0 0 0 0 C~ C~ 0 0 0 0 0 CHANHAS SEN FIRE DEPARTMENT FIRE/RESCUE WEEK OF NOVEMBER 4- NOVEMBER 10, 2002 mon Mon Mort Tues Thurs Fri Fri Fri Sat Sat Sun Nov 4 Nov 4 Nov 4 Nov 5 Nov 7 Nov 8 Nov 8 Nov 8 Nov 9 Nov 9 Nov 10 3:51 PM 7:42 PM 7:50 PM 6:22 AM 1:28 PM 9:58 AM 1:59 PM 8:12PM 6:21 PM 9:19 PM 9:22 AM Hwy 101 & Hwy 212 Lake Drive East Market Boulevard Hallgren Court Pond Promenade Meadowlark Lane Navajo .Drive Chan View Fawn Hill Road Essex Road Cheyenne Trail Car accident with injuries Smell of smoke in building Medical - possible heart attack Medical- difficulty breathing Fire alarm- false alarm, no frre Gas line break Carbon Monoxide alarm Medical - difficulty breathing Medical - head injury- Medical - difficulty breathing Medical - head injury Mon Mon Tues Tues Tues Tues Weds Weds Weds Weds Weds Thurs Thurs Sun Sun Sun Sun Oct 28 Oct 28 Oct 29 Oct 29 Oct 29 Oct 29 Oct 30 Oct 30 Oct 30 Oct 30 Oct 30 Oct 31 Oct 31 Nov 3 Nov 3 Nov 3 Nov 3 10:51 AM 9:13 PM 10:35 AM 12:55 PM 2:05 PM 8:09 PM 9:01 AM 12:38 PM 2:05 PM 3:17 PM 8:05 PM 8:37 PM 9:37 PM 12:42 AM 8:42 AM 7:55 PM 10:11 PM CHANHAS SEN FIRE DEPARTMENT FIRE/RESCUE WEEK OF OCTOBER 28 -NOVEMBER 3, 2002 Lake Drive East Horseshoe Cut-ce Hesse Farm Road Bluebonnet Boulevard Hazeltine Boulevard Chan View Shasta Circle West West 7.8~h Street Pontiac Circle Hwy 101 & Hwy 212 White Oak Lane Edina Fire Department Edina Fire Department Fox Curve Utica Lane Hwy 101 & Vogelsbut-g Tr Trapline Lane Fire alarm-false ala. m~, no fn:e Carbon Monoxide alarm Fire alarrn- false alarm, no fire Carbon Monoxide alarm Medical - asthma attack Medical - trouble breathing Medical-person fell from roof Medical- seizures Medical- possible heart Car fire, unfounded Medical - trouble breathing Mutual aid- engine standby Mutual aid- ladder standby Medical- cancelled enroute Recreation fn:e Car accident-cancelled, no injuries Medical - unlmown problem CHANHASSEN FIRE DEPARTMENT FIRE/RESCUE WEEK OF OCTOBER 21 - OCTOBER 27, 2002 Mon Mort Tues Tues Weds Weds Thurs Thurs Fri Fri Sat Sun Sun Oct Oct Oct Oct Oct Oct Oct Oct Oct Oct Oct Oct Oct 21 9:36 AM 21 3:09 PM 22 3:30 PM 22 8:40 PM 23 8:42 AM 23 10:45 PM 24 1:25 PM 24 2:55 PM 25 6:37 AM 25 5:46 PM 26 5:40 PM 27 12:18 AM 27 2:38 AM Audubon Road Highway 5 & Galpin Blvd West 78* Street Pontiac Circle West 78th Street Buttercup Court Preakness Lane Park Road & Powers Blvd West 78th Street Highway I 01 Flying Cloud Drive West 96'~' Su'eet We,qt 79th Street Fire alarm-false alarm, no fu'e Car accident- cancelled,, no injuries Medical - person fell Medical - possible heart attack Smell of gas Oven fire Medical- difficulty breathing Car accident - minor injuries Medical - crushed finger Smell of natural gas Medical - person fell, cancelled Medical - unknown problem Car accident- no injuries