1c. Lake Susan Hills West 9th: Approve Quote for Sanitary Sewer Repairs
CITY OF
CHANHASSEN
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317
Administration
Phone: 952,227,1100
Fax: 952,227.1110
Building Inspections
Phone: 952,227,1180
Fax: 952,227,1190
Engineering
Phone: 952,227.1160
Fax: 952,227.1170
Finance
Phone: 952,227,1140
Fax: 952,227,1110
Park & Recreation
Phone: 952,227,1120
Fax: 952,227.1110
Recreation Center
2310 Coulter Boulevard
Phone: 952,227,1400
Fax: 952,227.1404
Planning &
Natural Resources
Phone: 952,227.1130
Fax: 952,227,1110
Public Works
1591 Park Road
Phone: 952,227.1300
Fax: 952,227,1310
Senior Center
Phone: 952,227.1125
Fax: 952,227.1110
Web Site
www.ci.chanhassen.mn.us
.1~
MEMORANDUM
TO:
FROM:
DATE:
September 28, 2009
a~
SUBJ:
Lake Susan Hills West 9th Addition, Project No 93-5-1:
Approve Quote for Sanitary Sewer Repairs
PROPOSED MOTION
"The City Council approves a quote in the amount of $39,400.00 with Parrott
Contracting, Inc. for work to be performed on the Lake Susan Hills West 9th
Addition Sanitary Sewer Repairs."
City Council approval requires a simple majority vote of the City Council
present.
BACKGROUND
During the course of the annual sewer cleaning operations, the Utility Department
discovered a full pipe sag in the gravity sewer located in the street at 820 Lake
Susan Hills Drive. Staff discussed this issue with the residents at this location and
the sewer system apparently has been surcharging back into the lateral service
pipe. Staff has had problems with this sewer pipe before. In 2005 this section of
pipe was repaired and relayed. This fix involved placing aggregate bedding
underneath the pipe for additional foundation support. After finding out about the
sag this time, staff enlisted the services of a soils engineering firm to take soil
borings and recommend a fix. The soil borings show there is swamp deposited
organic silt material approximately of 22 to 34 feet below the pavement. The
organic soil is believed to be consolidating which is causing the pipe and a
manhole to settle.
RECOMMENDATIONS FOR IMPROVEMENTS
The City has several options it can consider. First, the City can do nothing. This
option would need to include having the Utility department jet and clean the pipe
monthly to reduce the likelihood of sewer backups. This, however, is not a good
long-term fix because eventually, if the sewer keeps settling, sewer backups will
occur. This option will also tax the Utility department and would not be feasible
during winter months. The second option is to add additional aggregate
foundation under the sewer pipe and manhole similar to what was done in 2005.
The cost for this option would be approximately $25,000. This option is not
Chanhassen is a Community for Life - Providing for Today and Planning for Tomorrow
Todd Gerhardt
Lake Susan Hills West 9th Addition
Sanitary Sewer Repairs
September 28, 2009
Page 2
recommended as a long-term solution because it has been proven to be a
temporary fix.
The third option is to remove the organic, compressible soils that are causing the
problem. This option is not cost effective and would severely impact the residents
during construction.
Due to site confinement and excavation depth, the soils engineer has
recommended the installation of helical piling supports for the 160' of settled
sewer pipe and manhole. Piling-supported, rigid pipe and structures will maintain
positive slope on the pipe while allowing for any future settlement of the
surrounding soils. This piling support technique has been used successfully on
other City projects. City staff cannot complete this type of work and would need
to hire a contractor who has expertise in this type of construction.
PROJECT LOGISTICS
To reduce out of pocket costs, City forces will be used as much as possible. The
City will purchase directly the materials needed for the project to avoid contractor
material markups. City forces will also truck aggregate material for the project
and bypass pump the sewer during construction. It is planned that the contractor
will install the City-purchased helical piling and rigid sanitary sewer. The
contractor will backfill and reconstruct the street to the gravel base level. City
forces will pave the bituminous street section and complete the restoration.
QUOTES
A request for quotes was submitted to four contractors on September 10, 2009.
Three quotes were received. The quotes received are as follows:
Kusske Construction Com an
Min er Construction, Inc.
Parrott Contractin , Inc.
$66,450.00
$48,760.00
$39,400.00
The fourth contractor was not able to submit a bid.
Parrott Contracting submitted the low bid. This contractor has worked on several
projects for the City in the past. Their work has been acceptable. The project
should start October 5, 2009 with substantial completion by October 14, 2009.
Bids were wide spread and can be attributed to work load of the contractors, time
line when the work needs to be completed, and comfort level on completing the
work.
g:\eng\projects\k-o\lshw.9th\2009 sanitary sewer repairs\award contract 092809.doc
Todd Gerhardt
Lake Susan Hills West 9th Addition
Sanitary Sewer Repairs
September 28, 2009
Page 3
The cost for the City furnished materials and restoration is estimated at
$46,600.00. The estimated cost of the sewer fix is $86,000.00 with the contractor
furnished work, city purchased materials and restoration.
This project was not budgeted for in 2009 since the problem was not identified.
Staff is requesting the funds for the work be taken out of the sanitary sewer fund
account.
Attachments: 1. Repair Area Map
2. Soils Report
c: Kevin Crooks, Utility Superintendent
g:\eng\projects\k-o\lshw.9th\2009 sanitary sewer repairs\award contract 092809.doc
Geotechnical Evaluation Report
Proposed Manhole Repair
Manhole Structure and Sanitary Sewer Repair
Near 823 Lake Susan Hills Drive
Chanhassen, Minnesota
Prepared for
City of Chanhassen
Professional Certification:
I hereby certify that this plan, specification, or report
was prepared by me or under my direct supervision
and that I am a duly Licensed Professional Engineer
under the laws of the State of Minnesota.
~ \\,llltl""I/
\',db /
:7!: ,\ \-\v.' l. 1(/1-'> //.(
-..-..' 00:.....,' "":.\~ 'l
~ ).~. '0 ~
shua L. Kirk, PE ~;' (.q,ISED.... ~
- . Llw'~"~ '_
Project Engineer :: : rROFESSI~NAL: ::
License Number: 45005 ENGINEeR ,: :::
... . . "("...
August 28, 2009 ~tP~" 45005 ..t;~
",'.,n', .'~~
",,~7l'." ......~-.......
,,/ I$' ....H..:.\~V,...
1'1 OF Mh" ",
1111111\\\\\\
Project Bl-09-03401
Braun Intertec Corpor13tion
BRAUN
INTERTEC
Braun Inlertec Corporation
1100 1 Hampshire Avenue S
Minneapolis, MN 55438
Phone: 952.995.2000
Fax: 952.995.2020
Web: broullintertec.com
August 28, 2009
Project BL-09-03401
Mr. Kevin Crooks
City of Chanhassen
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317-8363
Re: Geotechnical Evaluation
Manhole Structure and Sanitary Sewer Repair
Near 823 Lake Susan Hills Drive
Chanhassen, Minnesota
Dear Mr. Crooks:
We are pleased to present this Geotechnical Evaluation Report for the proposed repair of the manhole
structure and associated sanitary sewer pipes near 823 Lake Susan Hills Drive. A summary of our results,
and a summary of our recommendations in light ofthe geotechnical issues influencing design and
construction, is presented below. More detailed information and recommendations follow.
Summary of Results
Based on information provided by you, it is our understanding the existing sanitarY sewer lines entering
and exiting the manhole structure are not properly flowing, and are likely the result of ongoing soil
consolidation issues. This manhole has previously settled and been repaired, and is again experiencing
settlement. Based on discussions with you, the manhole structure is approximately 11 feet deep.
One boring to a nominal depth of 40 feet was completed on Lake Susan Hills Drive, approximately 5 feet
from the manhole structure.
The boring encountered sandy lean clay fill to a depth of about 22 feet, where organic silts were
encountered to a depth of about 34 feet. Beneath the organic soils, alluvial lean clay was encountered to
a depth of 39 feet, where glacial till sandy lean clay was encountered to the boring termination depth.
Groundwater was initially encountered during drilling at a depth of 11 feet beneath the surface. This
may represent a perched condition as the boring was being completed, water was observed at a depth of
25 feet with 39 1/2 feet of auger in the ground. We anticipate the static groundwater level will be near
that of the organic soils, however long term monitoring would be necessary to confirm this.
Groundwater monitoring was not included in our scope of services. Seasonal and annual fluctuations in
the groundwater level should be anticipated.
o Providing engineering and environmental solutions since 1957
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 2
Summary of Recommendations
It appears that the organic silt soils are the main cause of the past and current settlement of the manhole
structure. These soils are generally weak, and prone to settlement over time. We anticipate that these
soils will continue to consolidate and settle over time.
Due to the depth of the soils and the confined area for construction, it is our opinion that the manhole
and associated pipes should be supported using helical anchors. Please read the attached report for
more detailed results and recommendations.
Remarks
Thank you for making Braun Intertec your geotechni~al consultant for this project. If you have questions
about this report, or if there are other services that we can provide in support of our work to date, please
call Josh Kirk at 952.995.2222 or Ray Huber at 952.995.2260.
Sincerely,
BRAUN INTERTEC CORPORATION
~
qa L Kirk, PE
h~~~ct Engineer
~t
Associate-Senior Engineer
Geo Report-Lake Susan Hills Manhole Repair
BRAUN
INTERTEC
I
Table of Contents
Description
Page
A.
Introductio I) ................................. ........... ..... ............... ....................................... .............................. 1
A.l. Project Description ..... ............... ....... ......... ................ .... ......... ......... ............... ............... ..... 1
A.2. Purpose......... ........... ...................... ....... ...... ........................................... ........... .................. 1
A.3. Background Information and Reference Documents......................................................... 1
A.4. Site Conditions........ ......... ......... ..... ......... ........................ .............. ......... ............................. 1
A.S. Scope of Services...... ......... ........ ................. .................... ................ ................ .................... 1
Results.. ............ ................... .................... .............. ....... ............ ...................... ............... ................... 2
B.l. Exploration Logs.. ................ ......... ............ .................. .......... ................................... ........ .... 2
B.1.a. Log of Boring Sheets .............................................................................................. 2
B.l.b. Geologic 0 rigins......... ......... ........ ................................. ....... ............... ..... ............... 2
B.2. G eologi c Profile.... ....... .......... ...... ....... ..... ............................................. ........... ..... ............... 3
B.2.a. Geologic Materia Is ........... ..... ........... .................. ... ........... ..... ............. .................... 3
B .2.b. Groundwater .............. ........... ...................... ........................... ............. .................. 3
6.3. Laboratory Test Results ........ .......... ................................... ......... ......... ...... ..... ....~ ....... ........ 4
Basis for Recommendations . ..........:~.................. .................. .......... ......... .................... ............ ........ 4
C.l. Design Deta i Is ....... ..... ........... ..... ....... ..... ......... .............................. ....... ........... .................... 4
C.2. Design Considerations ............... ..................... ......... ....... ............ .................. ...........:.. ........ 4
C.3. Construction Considerations ....... ..... ....... ....... ............................ .................. ...................... 5
Recommendations............ ..... ............ .......... ...... ............ ......... ..................... ................ ................;... 6
D.l. Helical Anchor Foundation System ............................................ ......................................... 6
D.2. Soil Parameters... ..... .............. ........ ........... ..................... ..... .... .......... ............ ...... ................ 7
D.3. Pave ments ......... ...................... ............. ........ ...................................... ...... ....... ............... .... 7
D.3.a. Utility Trench Backfill............... ................. ............................ ....... .......................... 7
D.3.b. Subgrade Proof-Ro II............ ..... .......... ....... ........ ................. ..... ......... ...................... 7
0.3.c. Design Sections.... ................ ...... ...................... ............... ................. ................ ...... 7
0.3.d. Materials and Compaction .................................................................................... 8
D.4. Construction Quality Control..... ..... ............ ....... .......... ................ ................ .............. ......... 8
D.4.a. Excavation Observations ............ .......... ...... ....... ....... ............. ;... ....... .............. ....... 8
D.4.b. Helica l'Anchor Observations. ........................ .... .......... .................. ................. ....... 8
D.4.c. . Materia Is Testing ..................... ............... ....................... ....... ........... ............. ......... 8
D.4.d. Pavement Subgrade Proof-RoiL......... ................. .......... ....... ........... .......... ............. 8
D.4.e. Cold Weather Precautions. ................. ....................... ........ ..................... ....... ........ 9
Proced ures...................................... ..... ......... ...... ..... .............................~. ....... ....... ......... ............ ...... 9
E.l. Penetration Test Borings .......... ..... ..... ........................ ........... ........... ......... ............ ............. 9
E.2. Material Classification and Testing......... ....... ...... ................. ......... ....... ..................... ......... 9
E.2.a. Visual and Manual Classification ...........................................................................9
E.2.b. La boratory Testing ............. ....... ............. .......................... .............. ........................ 9
E.3. Groundwater Measurements ......................... ...... .............. ............ ...................... ..... ........ 10
B.
C.
D.
E.
Table of Contents (continued)
Description
Page
F. Qua lifications........... ......... ............................ ............ ...................... .............. ................................. 10
F.1. Variations in Subsurface Conditions ................................................................................. 10
F.1.a. Material Strata...... ..... ......... ............ ................. ....... ....... ..... ........................ ......... 10
F.1.b. Groundwater Levels............................ ....... ...... ....... ....... ..... ........... ............. ......... 10
F.2. Continuity of Professional Responsibility .........................................................................11 .
F .2.a. Pia n Review... ............... ............. ... ....... ............. ....... ......... .................................... 11
F.2.b. Construction ObserVations and Testing ..............................................................11
F .3. Use of Report.... ...................... ....... ....... ...... .................. ................ .................... ................. 11
F .4. Sta ndard of Ca re ... .................. .............. ..... ................ ................... ........................... ......... 11
Appendix
Log of Boring Sheet
Descriptive Terminology
BRAUN
INTERTEC
A. Introduction
A.l. Project Description
This Geotechnical Evaluation Report addresses the proposed repair to the manhole structure and
sanitary sewer pipes that are experiencing settlement near 823 Lake Susan Hills Drive in Chanhassen,
Minnesota. The key design, construction or performance component of this project is the presence of
swamp deposited soils at depth beneath the manhole and its effect on the long term performance of the
structure and associated pipes.
A.2. Purpose
The purpose of this geotechnical evaluation is to evaluate the cause of the apparent manhole settlement
and to present recommendations for repair of the structure.
A.3. Background Information and Reference Documents
To facilitate our evaluation, we reviewed the following information:
· A discussion with Kevin Crooks regarding the current state of the structure and issues from
the past regarding settlement.
· Geologic atlas showing the expected soil types in this area.
A.4. Site Conditions
The manhole structure in question is in Lake Susan Hills Drive, near the house located at 823 lake Susan
Hills Drive. The street is part of an existing residential neighborhood. The neighborhood is fully.
developed, with a bituminous road surface and curb and gutter in place. The Lake Susan Hills West Park
borders the eastern portion ofthe development, and appears to consist mainly of wetland areas.
A.S. Scope of Services
Our scope of services for this project was originally submitted as a Proposal for Geotechnical Evaluation
dated August 5, 2009. We received authorization to proceed from you on August 11, 2009. Tasks
performed in accordance with our authorized scope of services included:
· Performing a reconnaissance of the site.
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 2
.
Staking and coordinating the clearing the area of underground utilities.
.
Performing 1 penetration test boring to a nominal depth of 40 feet below grade.
.
Performing laboratory moisture content and organic content tests on selected penetration
test samples.
.
Preparing this report containing a summary of the geologic materials encountered, results of
laboratory tests, and recommendations for methods to support the existing structures.
Our scope of services was performed under the terms of our General Conditions, dated June 15, 2006
B. Results
B.l. Exploration logs
B.l.a. Log of Boring Sheets
Log of Boring sheets for our penetration test boring is included in the Appendix. The log identifies and
describes the geologic materials that were penetrated, and present the results of penetration resistance
tests performed within them, laboratory tests performed on penetration test samples retrieved from
them, and groundwater measurements.
Strata boundaries were inferred from changes in the penetration test samples and the auger cuttings.
Because sampling was not performed continuously, the strata boundary depths are only approximate.
The boundary depths likely vary away from the boring locations, and the boundaries themselves may
also occur as gradual rather than abrupt transitions.
B.l.b. Geologic Origins
Geologic origins assigned to the materials shown on the logs and referenced within this report were
based on: (l) a review of the background information and reference documents cited above, (2) visual
classification of the various geologic material samples retrieved during the course of our subsurface
exploration, (3) penetration resistance (4) laboratory test results, and (5) available common knowledge
of the geologic processes and environments that have impacted the site and surrounding area in the
past.
BRAUN
I NTE RTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 3
B.2. Geologic Profile
B.2.a. Geologic Materials
The general geologic profile at the boring location consists of (proceeding down from the ground surface)
a pavement section, fill, organic silts, and alluvial and glacially deposited clays to the boring termination
depth.
The existing pavement section consisted of 6 inches of bituminous pavement over 12 inches of aggregate
base. The aggregate base layer can become contaminated with the underlying subgrade soils over time
and it can be difficult to determine the actual thickness. As a result, aggregate base thicknesses should
be considered approximate.
Beneath the pavement section, fill soils consisting of sandy lean clay were encountered to a depth 21
feet beneath the surface. The penetration resistance of the fill soils ranged from 4 to 12 blows per foot
(BPF).
Organic silt was encountered beneath the fill to a depth of 34 feet beneath the surface. The organic silt
contained occasional layers of fibers and contained shells throughout. The penetration resistances
encountered in the swamp deposit soils ranged from Weight of Hammer (0) to 7 BPF.
Alluvial lean clay was encountered beneath the organic soils. The lean clay contained silt and silty sand
lenses throughout. The penetration resistance in the lean clay was 5 BPF, indicating a rather soft
consistency.
. Glacially deposited sandy lean clay was encountered at a depth of 39 feet and extended tothe
termination depth of the boring. The sandy lean clay contained trace amounts of gravel. The
penetration resistance in the sandy lean clay was 7 BPF, indicating a medium consistency.
B.2.b. Groundwater
Groundwater was initially encountered during drilling at a depth of about 11 feet beneath the surface,
and again at a depth of 25 feet with 391/2 feet of auger in the ground. The groundwater encountered at
11 feet was likely a perched condition within the fill. We anticipate the static groundwater level will be
near that of the organic soils, however long term monitoring would be necessary to confirm this.
Groundwater monitoring was not included in our scope of services. Seasonal and annual fluctuations in
the groundwater level should be anticipated.
BRAUN
I NTE RTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 4
B.3. laboratory Test Results
The moisture content of the selected samples was determined to vary from approximately 17 to 85
percent, indicating that the material was near or above of its probable optimum moisture content.
Several of the samples were selected from the swamp deposited soils, and had elevated moisture
contents (above 50 percent). This is due to the presence of organic matter.
Our organic content tests indicated that the swamp deposited soils contained 4 to 11 percent organic
material by weight, indicating the soils were considered slightly organic to moderately organic.
C. Basis for Recommendations
C.l. Design Details
Based on conversations with the project team, we understand that the manhole will remain in its present
location, and will be raised to re-establish its design invert elevation. Similarly, the sanitary sewer pipes
that have been affected by the settlement of the manhole, will also be raised to their design elevations.
C.2. Design Considerations
It appears that the organic silt soils are the main cause of the past and current settlement of the manhole
structure and adjacent pipes. These soils are generally weak, and prone to settlement over time. We
anticipate that these soils will continue to consolidate and settle over time.
Due to the depth of the soils and the confined area for construction, it is our opinion that the manhole
and associated pipes should be supported using helical anchors. This is based on the following
considerations:
· The swamp deposited organic silt was encountered approximately 22 feet beneath the
surface, extending to about 34 feet. An excavate/ backfill approach including the removal of
all of the organic soils beneath the structure is not feasible due to the confined work area
and presence of existing utility lines and homes.
BRAUN
INTERTEC
City of Chanhassen
Project Bl-09-03401
August 28, 2009
Page 5
· Sheet piling or driven piles are also likely not feasible due to the confined work space, and
the possible presence organic soils in surrounding areas that may become unstable from
vibrations. The vibrations generated from sheet piling or driven piles will also be highly
intrusive to the neighboring homeowners.
· If a partial correction of the organic soils beneath the structure is considered, there is a
minor risk of continued settlement due to the continued consolidation of the organic soils.
This risk should be assumed by the owner, and may result in periodic maintenance of the
pipe.
C.3. Construction Considerations
From a construction perspective, the project team should also be aware that:
.
The helical anchors will need to extend through the organic soils and alluvial clays into the
glacial till soils.
.
We recommend encasing the helical anchor shafts in grout. The grout will provide additional
stiffness for lateral support of the a nchor, and reduce the corrosion potential of the anchor
shaft due to the presence of organic soils.
.
The sanitary sewer pipes extending away from the manhole will also need to be supported
by helical anchors. The weight of the soil on top of the pipe should also be considered when
designing helical anchor capacity.
.
If the haunch supporting the pipe is larger than the diameter of the pipe, the soil mass above
the exposed portions of the support structure should also be considered during helical
. anchor design.
.
It is our understanding that the sanitary sewer pipe will be welded to the haunch. By welding
the two pieces together, the potential for pipe corrosion is introduced. Steps to prevent
corrosion of the pipes should be implemented.
.
It appears that there are several other underground utilities present beneath the roadways.
Careful consideration should be taken if portions of the roadway are excavated, as this may
disturb the soils supporting the existing utilities.
BR.AUN
INTERTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 6
D. Recommendations
Based on conversations with the design team, it appears that a system of helical anchors will be designed
to extend into the native glacial till soils to support the manhole structure and associated pipes. The
following sections provide recommendations regarding the design and construction of the helical
anchors and the reconstruction of the roadway. It is our understanding that final design of the helical
anchors will be conducted by a specialty contractor that will also install the anchors.
0.1. Helical Anchor Foundation System
Helical anchors appear to be the most suitable approach to support the manhole structure. The
installation ofthe anchors can be performed in relatively confined areas and will not produce excess
vibrations that could disturb or destabilize any organic soils that may be present in the surrounding area,
and will be less intrusive to neighboring homeowners.
Based on the results of the boring, it appears that about 10 feet of fill and 10 feet of organic soils are
present beneath the manhole, with an additional 5 feet of rather soft alluvial clays. These soils will need
to be penetrated by the helical anchors and embedded into the glacial till soils to attain the desired
capacity. The final design of the helical anchor system will be conducted by others; however, based on
the results from the boring, we anticipate the anchors will extend to a depth of at least 50 feet. The
specialty contractor doing the installation should calculate the final design length, capacity and number,
size and spacing of the helical anchors.
A number of helical anchors will likely be placed beneath the manhole structure and at prescribed
distances along the pipe alignment to support the weight of the pipe and the overlying fill soils. A
structural slab or grade beam may also be constructed beneath the manhole to support it. Haunches will
likely be constructed at the top of the anchors to act as a cradle for the pipe. We understand the pipe
will be welded to the haunch.
We recommend using a rigid sanitary sewer pipe with flexible connections to reduce the risk of pipe
cracking or shearing of the pipe at the transition between the a nchor supported pipe and the ground
supported pipe.
BRAUN
INTERTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 7
Organic soils can also be corrosive to the helical anchor shafts, as such, we recommend the shafts be
encased in grout during installation. The grout will also provide increased lateral stiffness to the anchors.
Additionally, if the pipe is welded to the haunch, the corrosion potential that the location of the weld has
been increased. We recommend the necessary corrosion protection measures be taken.
0.2. Soil Parameters
The soils present above the pipe will likely consist of the existing sandy lean clay fill encountered by the
boring. The soil mass will act on the pipe and should be accounted for in the design of the helical
anchors. We have assumed a wet density of 125 pounds per cubic foot (PCF) for the soil, with a friction
angle of 26 degrees. The volume of soil supported by the pipe was assumed to extend up and away from
the pipe at a 1:1 angle, or a 45 degree angle from vertical. Based on these parameters, we anticipate the
pipe will carry a weight of approximately 15 kips (15,000 pounds) per linear foot of pipe.
0.3. Pavements
D.3.a. Utility Trench Backfill
After the installation of the helical anchors to support the manhole structure and pipes, we recommend
compacting the soils in the utility trench to re-establish roadway subgrade elevations. We recommend
spreading backfill and fill. in loose lifts of approximately 8 to 12 inches and the compacting the backfill to
at least 95 percent of the standard Proctor density to within 3 feet of the subgrade elevations, and to 100
percent in the upper 3 feet of the subgrade. The moisture content ofthe fill should be maintained
between 1 percentage point below to 3 percentage points above the soils optimum moisture content.
The existing fill soils encountered by the borings appear suitable for re-use as engineered filt.
D.3.b. Subgrade Proof-Roll
After the installation of the helical anchors, backfilling of the utility trench, and prior to placing aggregate
base material, we recommend proof-rolling the pavement subgrade to determine if the subgrade
materials are loose, soft or weak, and in need of further stabilization, compaction or subexcavation and
recompaction or replacement. A second proof-roll should be performed after the aggregate base
material is in place, and prior to placing bituminous pavement.
D.3.c. Design Sections
We recommend placing a pavement section similar to that in the surrounding street. Based on the result
of our boring, it appears that the existing pavement section consists of approximately 6 inches of
bituminous pavement and 12 inches of aggregate base.
BRAUN
INTERTEC
City of Chanhassen
Project BL-D9-03401
August 28, 2009
Page 8
D.3.d. Materials and Compaction
We recommend specifying crushed aggregate base meeting the requirements of Minnesota Department
ofTransportation (Mn/DOT) Specification 3138 for Class 5. We recommend that the bituminous wear
and base courses meet the requirements of Specifications 2360.
We recommend that the aggregate base be compacted to a minin;um of 100 percent of its maximum
standard Proctor dry density. We recommend that the bituminous pavement be compacted to at least 92
percent ofthe maximum theoretical density.
0.4. Construction Quality Control
O.4.a. Excavation Observations
We recommend having a geotechnical engineer observe all excavations related to subgrade preparation.
The purpose of the observations is to evaluate the competence ofthe geologic materials exposed in the
excavations in areas that will be ground supported.
D.4.b. Helical Anchor Observations
We recommend a geotechnical engineer or engineering technician observe the insta lIation of the helical
anchors. The installation documentation should include the type of pier, the depth, the gauge pressure
and the torque that is achieved during installation.
0.4.c. Materials Testing
We recommend density tests be taken on the soils placed for the utility trench backfill to determine if
the compaction efforts meet the minimum project specifications.
We also recommend slump, air content and strength tests of Portland cement concrete during curb and
gutter replacement.
0.4.d. Pavement Subgrade Proof.RolI
We recommend that proof-rolling of the pavement subgrades be observed by a geotechnical engineer to
determine if the results of the procedure meet project specifications, or delineate the extent of
additional pavement subgrade preparation work.
BR.AUN
INTERTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 9
DA.e. Cold Weather Precautions
If construction is anticipated during cold weather, all snow and ice should be removed from the
excavations prior to placing fill. No fill should be placed on frozen subgrades. No frozen soils should be
used as fill.
Concrete delivered to the site should meet the temperature requirements of ASTM C 94. Concrete
should not be placed on frozen subgrades. Concrete should be protected from freezing until the
necessary strength is attained. Frost should not be permitted to penetrate below footings.
E. Procedures
E.l. Penetration Test Borings
The penetration test boring was drilled with a truck-mounted core and auger drill equipped with hollow-.
stem auger on August 21,2009. The boring was performed in accordance with A5TM D 1586.
Penetration test samples were taken at 2 l/2-or 5-foot intervals. Actual sample intervals and
corresponding depths are shown on the boring logs.
E.2. Material Classification and Testing
f.2.a. Visual and Manual Classification
The geologic materials encountered were visually and manually classified in accordance with ASTM Test
Method D 2488. A chart explaining the classification system is attached. Samples were sealed in jars or
bags and returned to our facility for review and storage.
E.2.b. Laboratory Testing
The results of the laboratory tests peiformed on geologic material samples are noted on or follow the
appropriate attached exploration logs. The tests were performed in accordance with ASTM or AASHTO
procedures.
BRAUN
I NTE RTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 10
E.3. Groundwater Measurements
The drillers checked for groundwater as the penetration test borings were advanced, and again after
auger withdrawal. The boreholes were then backfilled or allowed to remain open for an extended period
of observation as noted on the boring logs.
F. Qualifications
F.l. Variations in Subsurface Conditions
F.l.a. Material Strata
Our evaluation, analyses and recommendations were developed from a limited amount of site and
subsurface information. It is not standard engineering practice to retrieve material samples from
exploration locations continuously with depth, and therefore strata boundaries and thicknesses must be
inferred to some extent. Strata boundaries may also be gradual transitions, and can be expected to vary
in depth, elevation and thickness away from the exploration locations.
Variations in subsurface conditions present between exploration locations may not be revealed until
additional exploration work is completed, or construction commences. If any such variations are
revealed, our recommendations should be re-evaluated. Such variations could increase construction
costs, and a contingency should be provided to accommodate them.
F.l.b. Groundwater Levels
Groundwater measurements were made under the conditions reported herein and shown on the
exploration logs, and interpreted in the text of this report. It should be noted that the observation period
was relatively short, and groundwater can be expected to fluctuate in response to rainfall, flooding,
irrigation, seasonal freezing and thawing, surface drainage modifications and other seasonal and annual
factors.
BRAUN
INTERTEC
City of Chanhassen
Project BL-09-03401
August 28, 2009
Page 11
F.2. Continuity of Professional Responsibility
F.2.a. Plan Review
This report is based on a limited amount of information, and a number of assumptions were necessary to
help us develop our recommendations. It is recommended that our firm review the geotechnical aspects
of the designs and specifications, and evaluate whether the design is as expected, if any design changes
have affected the validity of our recommendations, and if our recommendations have been correctly
interpreted and implemented in the designs and specifications.
F.2.b. Construction Observations and Testing
It is recommended that we be retained to perform observations and tests during construction. This will
'allow correlation of the subsurface conditions encountered during construction with those encountered
by the borings, and provide continuity of professional responsibility.
F.3. Use of Report
This report is for the exclusive use of the parties to which it has been addressed. Without written
approval, we assume no responsibility to other parties regarding this report. Our evaluation, analyses
and recommendations may not be appropriate for other parties or projects.
FA. Standard of Care
In performing its services, Braun lntertec used that degree of care and skill ordinarily exercised under
similar circumstances by reputable members of its profession currently practicing in the same locality. No
warranty, express or implied, is made.
BRAUN
INTERTEC
Appendix
BRAUNSM
INTERTEC
Braun Project BL-09-03401
GEOTECHNICAL EVALUATION
Sanitary Sewer Investigation
823 lake Susan Hills Drive
Chanhassen, Minnesota
DRilLER: C, Powers I METHOD: 3 1/4" HSA, Autohammer
Depth
feet ASTM
0.0 Symbol
PAV
- 1.5
FILL
~
c_
o
fii
'>-
Q)
.Q
.0
ro-
15
c_
.Q
ro
c_
e{'
'9
)(
al-
-
.e
1l-
.c
VI
~-
o
(5
c
'E
--
al
t-
CIl
>-
~
G-
t/)
al
Cl
CIl-
CIl
!:9_
888
21.0
OH
.....
0-
.:.i
...
g)-
c0-
N
c0-
b
\!)
gi-
I
..
=>
q:-
'"
cO
Q. -
l!)
rl
~
'" -
o
l!)
z_
a:
o
cO
::J-
l!)
9
B L -09-03401
BORING:
LOG OF BORING
ST-1
LOCATION: Lake Susan Hills Drive, in front of
823 lake Susan Hills Drive
DATE:
Description of Materials
(ASTM 02488 or D2487)
6 inches of Bituminous over 12 inches of Aggregate Base.
-
Fill: Sandy Lean Clay, with a trace of Gravel, with occasional _
Poorly Graded Sand lenses, brown, wet.
-
-
ORGANIC SILT, with traces of fibers, with shells, black and dark
brown to 27 feet, then brown and gray, wet. _
(Swamp Deposit)
-
Braun Intertec Corporation
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
8/20/09
I SCALE:
BPF WL mc qp
% tsf
4
5
4
5 17
:sz.
12
10
11
8
23
3
.!.
3 85
7
51
1"=4'
Tests or Notes
An open triangle in
the water level
(WL) column
indicates the depth
at which
groundwater was
observed while
drilling. A solid
triangle indicates
the groundwater
level in the bOring
on the date
indicated.
Groundwater'
levels fluctuate.
oc = 11%
oc = 4%
5T-1 page 1 of 2
BRAUNIM
INTERTEC
Braun Project BL-09-03401
GEOTECHNICAL EVALUATION
Sanitary Sewer Investigation
823 lake Susan Hills Drive
Chanhassen, Minnesota
DRILLER: C. Powers METHOD: 31/4" HSA, Autohammer
LOG OF BORING
BORING: ST-1 (cont.)
LOCATION: Lake Susan Hills Drive, in front of
823 Lake Susan Hills Drive
DATE:
8/20/09
SCALE:
1" =4'
Depth Description of Materials
feet ASTM BPF WL me qp Tests or Notes
32.0 Symbol (ASTM 02488 or D2487) % tsf
ORGANIC SILT, with traces of fibers, with shells, black and dark
brown to 27 feet, then brown and gray, wet. 0
34.0 (Swamp Deposit) (continued)
CL LEAN CLAY, with frequent Silt and Silty Sand lenses, gray, wet,
rather soft.
(Alluvium) 5 1/2
fJl
.~-
~ 39.0
~ CL
.a
ro-
'0
c 41.0
.9
1il
t:_
.JS!
'C
'-'-
Vi
a
o
Q)-
Q)
en
....
c-
,:.;
...
8_
......
00
~
...
c
~
. cd _
~I
:::>
;2-
00
~
a._
~
,..;
o
;;l;-
<>
C>
2_
C2
o
'"
.... -
o
\!l
9
BL-09-03401
SANDY LEAN CLAY, with a trace of Gravel, gray, wet, medium.
(Glacial Till)
7
1 1/4
END OF BORING.
Water observed at 11 feet with 11 1/2 feet of hollow-stem auger
in the ground.
Water observed at 25 feet with 39 1/2 feet of hollow-stem auger
in the ground.
Boring immediately backfilled with bentonite grout.
Braun Intertec Corporation
ST-1 page 2 of 2
BRAUN
INTERTEC
Descriptive Terminology of Soil
::8
~!~rJgl!~~
Standard 0 2487 . 00
Classification of Soils for Engineering Purposes
{Unified Soil Classification System}
Particle Size Identification
Boulders ..................,.....,...... over 12"
Cobbles ..,...,......,..,..............3"to 12"
Gravel
Coarse ............................ 314" to 3'
Fine ................................. NO.4 to 3/4"
Sand
Coarse ............................ NO.4 to No, 10
Medium ........................,.. No. 10 to No. 40
Fine ................................. No. 40 to No. 200
Silt ..........................,..,......... -< No. 200, PI< 4 or
below "A" line
Clay .......................,.....,.......-< No. 200, PI ~ 4 and
on or above "A" line
Criteria for Assigning Group Symbols and Soils Classification
Group Names Using Laboratory Tests · Group
Symbol Group Name b
c: Gravels Clean Gravels Cu a: 4 and 1 $. Co $. 3 c GW Well-graded graveld
'" 0 More than 50% of 5% or less fines e
=-0 Cu -< 4 andlor 1 > Co> 3 c GP Poorly graded gravel"
o (t) coarse fraction
t/J .S Q)
a11.'l~ retained on Gravels with Fines Fines classify as ML or MH GM Silty gravel" ,~
c:~'" NO.4 sieve More than 12% fines' Fines classify as CL or CH GC Clayey gravel d19
'E ~g Sands Clean Sands Cu:2 6 and 1 :5. Co :5. 3 c SW Well-graded sand h
",,,, ('oj
~~o 50% or more of 6% or less fines I Cu < 6 andlor 1 > Cc::' 3 c SP Poorly graded sand h
...<:Z coarse fraction
"'~ Fines classify as ML or MH Silty sand I 9 t,
o~ passes Sands with Fines SM
()O
E No.4 sieve More than 12% I Fines classify as CL or CH SC Clayey sand' p.
., Inorganic PI > 7 and plots on or above "A" line I CL Lean clav' i m
(/):5 Silts and Clays PI -< 4 or plots below" A" linel ML
:0::-0 Silt" m
0'" '" Liquid limit
(l)fIl:> Liquid limit - oven dried OL Organic clay k 'm"
'" ., less the n 50 Organic 0.75
"D co .- -< OL Organic silt' I m 0
.,c.'" Liquid limit - not dried
.5 ~8 PI plOIS on or aoove "A' line CH Fat clav k I "'
"'ON Inorganic
l;,E . Silts and clays PI plots below "A' line MH Elastic silt k ' m
. ~ 0 Liquid limit
~oZ
u:~ 50 or more Organic Uquid limit - oven dried <: 0.75 OH Organic clay k , m p
'" Liquid limit - not dried OH Organic silt' , m .
Highly Organic Soils Primarily organic matter, dark in color and organic odor PT Peat
a, Basedonthe malerial passing the 3-in{i5mm)sieve,
b. If field sample contained cobbles or boulders. or both, add -with cobbles or boulders or both- to group name.
c, Cu: D;oID" Co:~
010 X D60
d, If soli contains~15% sand, add 'with sand' to group name.
e. Gravelswilh 5 to 12% fines require dual symbols:
GW.GM well-graded gravel with silt
GW-GC well-graded gravel with clay
GP.GM pooriy graded gravel with sill
GP-GC poony graded gravel w~h clay
f If fines classify as CL-ML, use dual symbol GC-GM or SC-SM.
g. Iff,nes...-e organic. add "with organic fines' togroup name.
h, If soil contains ~ 15% gravel. add "with gravel' to group name,
Sands with 5to 12% rifles require dual symbols:
SW-SM well-graded sand wilh silt
SW-SC well-graded sand with clay
SP..SM poorly graded sand with sin
Sp.SC poorly graded sand with clay
j. If Alterberg limits plol in hatct1ed area. soil is a CL.ML. silty clay,
k If soil contains 10 1029% plus No. 200, add 'with saner or 'wilh gravel" whichever is predominant
I. ~ soil contains ;;o3O"k plus No, 200, predominanlly sand, add 'sandy'togroup name.
m, ~ wil contains~ 30% plus No. 200 predominantly gravel, add'graveDf to gruup name.
n. PI ~ 4 and plolS on or above 'N line,
o. PI < 4 or plOIS below "A' line.
p, PI plots on or above "A' line.
q, PI plots below "A" fine.
60
50
-
~ 40
X
(Il
"0
1: 30
.r:-
't)
; 20
III
III
0::
00
WD
MC
LL
PL
PI
P200
10
7 .
4
o
0,
30
90
10 16 20
40
50
80
100
60
70
Dry density, pel
Wet density, pcf
Natural moisture content, %
Liqiuid limit, %
Plastic limit, %
Plasticity index, %
% passing 200 sieve
Liquid Limit (LL}
Laboratory Tests
OC Organic content, %
S Percent of saturation, %
SG Specific gravity
C Cohesion, psf
o Angle of internal friction
qu Unconfined compressive strength. pst
qp Pocket penetrometer strength, tsf
Relative Density of
Cohesion less Soils
Very loose ................................ 0 to 4 BPF
Loose ....................................... 5 to 10 BPF
Medium dense ......................... 11 to 30 BPF
Dense .......".."......................... 311050 BPF
Very dense ............................... over 50 BPF
Consistency of Cohesive Soils
Very soft ................................... 0 to 1 8PF
Soft ....................................... 2to:l BPF
Rathersott ............."................ 4to 5 BPF
Medium .....".............."......"..." 6 to 8 8PF
Rather stiff ............................... 9 to 12 BPF
Stiff ....................................... 13 to 16 BPF
Very stiff ................................... 17to 30 BPF
Hard ..............m...................... over 30 8PF
Drifling Notes
Standard penetration test borings were advanced by 31/4" or 61/4"
10 hollow.stem augers unless noted otherwise, Jetting water was used
to clean out auger prior to sampl.ing only where indicated on logs.
Standard penetration test borings are designated by the prefix "ST'
(Split Tuoe). AU samples were taken with the standard 2" 00 split-tube
sa mpler, except where noted.
Power auger borings were advanced by 4" or 6" diameter continuous-
flight, solid-stem augers. Soil classifications and strata depths were in-
ferred from disturbed samples augered to the surface and are, therefore,
somewhat approximate. Power auger borings are designated by the
prefix "6,"
Hand auger borings were advanced manually with a 1 1/2" or 3 1/4"
diameter auger and were limited to the depth from which the auger could
be manually withdrawn. Hand auger borings are indicated by the prefix
"H,"
110
BPF:. Numbers indicate blows per foot recorded in standard penetration
test. also known as "N" value, The sampler was set 6" into undisturbed
soil below the hollow-stem auger. Driving resistances were then counted
for second and third 6" increments and added to get 6PF. Where they
differed significantly. they are reported in the following form: 2/12 for the
second and third 6" increments, respectively.
WH: WH indicates the sampler penetrated soil under weight of hammer
and rods alone; driving not required.
WR: WR indicates the sampler penetrated soH under weight of rods
alone; hammer weight and driving not required,
TW indicates thin.walled (undisturbed) tube sample.
Note: All tests were run in general accordance with applicable ASTM
standards.
Re. 7107