A. Third Quarter 2010 Financial Review, 2011-2015 CIP, 2011 Utility Fund Operating BudgetsBuilding Inspections BACKGROUND
Phone: 952.227.1180
Fax: 952227.1190
On Monday evening, staff will review three separate topics; all of which are related
Engineering to or will help with continued discussion of 2011 budget items.
Phone: 952.227.1160
Fax: 952.227.1170 Third Quarter Financial Review
Finance
Through September of this year, there are no expenditure line items that are over
Phone: 952.227.1140
Fax: 952.227,1110
budget or unexpected to this point. The only expenditure line item staff anticipates
CITY OF
MEMORANDUM
Park & Recreation
CHMEMSEN
TO:
Mayor and City Council
i
7700 Market Boulevard
FROM:
Greg Sticha, Finance Director
GS
PO Box 147
Chanhassen, MN 55317
DATE:
October 25, 2010
0
Administration
SUBJ:
Third Quarter 2010 financial review, 2011 -2015 CIP, 2011 Utility
Phone: 952.227.1100
for the firefighter pension for 2010.
Fund Operating Budgets
Fax: 952,227.1110
Also included in your packet is the quarterly analysis of our investments thus far
Fax: 952.227.1110
through the year. The average yield at cost for the portfolio as of September 30,
Building Inspections BACKGROUND
Phone: 952.227.1180
Fax: 952227.1190
On Monday evening, staff will review three separate topics; all of which are related
Engineering to or will help with continued discussion of 2011 budget items.
Phone: 952.227.1160
Fax: 952.227.1170 Third Quarter Financial Review
Finance
Through September of this year, there are no expenditure line items that are over
Phone: 952.227.1140
Fax: 952.227,1110
budget or unexpected to this point. The only expenditure line item staff anticipates
to be over budget is the required contribution for the volunteer firefighter pension.
Park & Recreation
We will discuss this in more detail at Monday's meeting.
Phone: 952.227.1120
Fax: 952.227.1110
On the revenue side, all line items are on par with budget with the exception of
permit revenue, which is almost 95% collected as of the end of September. Based
Recreation Center
on historical trends and an analysis of what permits we are anticipating collecting
Phone: 952.227.1400 Coulter Boulevard
Pho
for developments the rest of the year, the permit revenue line item could finish the
Fax: 952.227.1404
year with a surplus of anywhere between $30,000 to $90,000. The potential surplus
in building permit revenue for 2010 could be used to offset the required contribution
Planning &
for the firefighter pension for 2010.
Natural Resources
Phone: 952.227.1130
Also included in your packet is the quarterly analysis of our investments thus far
Fax: 952.227.1110
through the year. The average yield at cost for the portfolio as of September 30,
Public Works
2010 is 1.82% which is a very attractive rate of return in the current environment.
1591 Park Road
There are a number of other indicators and information about the portfolio included
Phone: 952.227.1300
in the summary, and I will be happy to answer any of your questions at the meeting.
Fax: 952.227.1310
2011— 2015 CIP
Senior Center
Phone: 952227.1125
Fax: 952.227.1110
Our Capital Improvement Program is a five -year projection of the amount of money
the city will need to maintain our existing capital assets and add improvements or
Web Site
system expansions when necessary. It is incumbent on the city council and staff to
www.ci.chanhassen.mn.us
exercise prudent stewardship over these capital assets. This plan will fully fund our
capital needs while maintaining existing services.
Chanhassen is a Community for Life - Providing for Today and Planning for Tomorrow
Mayor & City Council
October 25, 2010
Page 2
- Capital Replacement Equipment Fund
The city currently levies $824,000 per year for the Capital Replacement Fund (400)
to finance capital equipment purchases. In 2011, these purchases are estimated to
be $899,034. This amount is slightly higher than the amount levied on an annual
basis. In the previous 2 years (2008 & 2009), staff has under -spent CIP dollars by
approximately $170,000.
The equipment purchases for the public works building were originally planned to
be paid from the capital replacement equipment fund in the amount of $500,000.
The costs for constructing the building came in about $500,000 under budget, so the
equipment needed for the building was purchased using the remaining bond
proceeds. Therefore, the $500,000 planned to be spent on equipment for the public
works building with capital replacement equipment fund dollars will now be
available for another purpose.
Staff's intention is to use some of the previous year's unspent dollars ($75,000 of
the $170,000) to cover a portion of the 2011 CIP purchases and to use the unspent
public works building CIP dollars ($500,000) to help fund the equipment costs for
the satellite fire station in 2012.
- Other Major Capital Improvements (after 2011)
Fire Station No. 3 (MB -009) is now slated for 2012 with $1 million in equipment
and a $2 million building. Its construction is also dependant on the sale of the old
public works building, the proceeds of which will be used to offset the total cost.
This project will be reviewed by staff on an annual basis to determine the
appropriate timing of the construction of the building.
Lyman Boulevard Phase II (ST -003) improvements are scheduled in 2013, for a
total cost of $8.8 million. Other agencies and development in that area will fund
$6.6 million of this amount, with the remaining portion for utility costs related to the
project and $1.7 million in MSA construction dollars..
Lyman Boulevard Phase III (ST -003) improvements are scheduled in 2015, for a
total cost of $8.4 million. Other agencies will fund $6.9 million of this amount,
with the remaining portion of the project funded by $1.5 million in MSA
construction dollars.
Improvements to TH 5 from TH 41 to Victoria (ST -025) are scheduled for 2012 in
the amount of $9.0 million, $8.8 million of which is funded by contributions from
other agencies and the remaining $200,000 to come from the park dedication fund
and the street pavement management fund.
The 2010 MUSA sanitary lift station costing $1.9 million (SS -020) is now being
estimated to take place in 2013, and is dependent on development in that area.
Mayor & City Council
October 25, 2010
Page 3
The high zone elevated storage tank (W -042) at an anticipated cost of $1.9 million
is estimated for construction in 2012.
- Other Major Capital Improvements (In 2011)
Listed below are the purchases greater than $250,000 scheduled for 2011, and the
funding source:
Project
Annual St Improve Proj (ST -012)
TH 101 Corridor Presery Plan (ST -017)
TH 101/PleasantV iew/Trail Imp(ST027)
Hwy 41 Ped Trail Underpass
Pioneer Pass Park Acq (PK &T -078)
West 78"' St (ST -012)
Funding Source Amount
Revolve Assess Fund
$1.2 million
Other Agncy /St Pave Mgmt
$1.0 million
Other Agncy/Various
$765,000
Park Ded Fund
$400,000
Park Ded Fund
$290,000
Street Pavement Mgmt
$300,000
Staff will be happy to review any of these projects or any of the other projects
presented in the 2011 -2015 CIP on Monday.
Utility Fund Operating Budgets
Included in this packet are the utility fund operating budgets proposed for 2011.
Staff will be walking through each fund's budget with the attached PowerPoint.
The total operating budget proposed for the water fund for 2011 is $1,424,000,
$2,163,300 for the sanitary sewer fund, and $502,800 for the storm water fund.
Each of these operating budgets helps in preparation of the utility rate study that we
will be reviewing at the next meeting in November.
RECOMMENDATION
No action is required at this meeting. The 2011 -2015 CIP will be discussed and
adopted at the December 13`" city council meeting along with the general fund
budget and city tax levy for 2011. The utility fund operating budgets will be used in
compiling the utility rate study, which will be reviewed at our next work session
meeting in November.
ATTACHMENTS
1. Revenue & Expenditure Reports as of 9 -30 -10
2. Investment Portfolio Analysis as of 9 -30 -10
3. 2011 -2015 CIP Summary Pages
4. 2011 -2015 CIP Detail Sheets
5. 2011 Utility Fund Budgets
6.2011 Utility Fund Budget PowerPoint
General Ledger
Revenue - Budget vs Actual
Period 01 - 09
Fiscal Year 2010 - 2010
Licenses
3203
Dog Kennel
2010
2010
2010
2010
Account
Description
Budget
Actual
$ Uncollected
% Uncollected
General Property
Tax
500.00
650.00
(150.00)
(30.00)
3010
Current Property Tax
7,380,000.00
3,562,172.50
3,817,827.50
51.73
3002
Allowance for Delinquent Taxes
(270,000.00)
-
(270,000.00)
100.00
3011
Delinquent Property Tax
100,000.00
97,820.91
2,179.09
2.18
3041
Homestead & Ag Credit
-
-
-
-
3090
Other Property Taxes
7,500.00
4,455.00
3,045.00
40.60
3500
Local Government Aid
-
-
-
-
3331
Total General Property Tax
$ 7,210,000.00 $
3,659,993.41
$ 3,550,006.59
49.24%
Licenses
3203
Dog Kennel
800.00
538.07
261.93
32.74
3205
Dog or Cat
6,000.00
7,842.50
(1,842.50)
(30.71)
3213
Solicitor
500.00
650.00
(150.00)
(30.00)
3226
Liquor On /Off Sale
84,000.00
95,543.94
(11,543.94)
(13.74)
3230
Rental Housing Licenses
30,000.00
8,050.00
21,950.00
73.17
3284
Rubbish
5,000.00
1,500.00
3,500.00
70.00
3309
Total Licenses
$ 126,300.00 $
114,124.51 $
12,175.49
9.64%
Permits
3301
Building
350,000.00
328,032.25
21,967.75
6.28
3302
Plan Check
175,000.00
160,112.41
14,887.59
8.51
3305
Heating & A/C
60,000.00
63,488.49
(3,488.49)
(5.81)
3306
Plumbing
50,000.00
46,399.47
3,600.53
7.20
3307
Trenching
15,000.00
16,561.86
(1,561.86)
(10.41)
3308
Gun
1,000.00
820.00
180.00
18.00
3309
Sprinkler
14,000.00
7,586.89
6,413.11
45.81
3311
Sign
7,500.00
4,455.00
3,045.00
40.60
3320
Stable
300.00
210.00
90.00
30.00
3331
Firework's Application Fee
-
225.00
(225.00)
-
3390
Misc Permits
2,000.00
1,905.00
95.00
4.75
Total Permits
$ 674,800.00 $
629,796.37 $
45,003.63
6.67%
Fines & Penalties
3140
S/A Penalties & Interest
-
-
-
-
3401
Traffic & Ordinance Violation
125,000.00
55,426.28
69,573.72
55.66
3402
Vehicle Lockouts
2,500.00
1,200.00
1,300.00
52.00
3404
Dog /Cat Impound
6,000.00
3,345.09
2,654.91
44.25
3405
Other Fines & Penalties
-
-
-
-
Total Fines & Penalties
$ 133,500.00 $
59,971.37 $
73,528.63
55.08%
Intergovernmental Revenue
3503 School District Reimbursement
45,000.00
- 45,000.00
100.00
3509 Other Shared Taxes
160,000.00
9,733.50 150,266.50
93.92
3510 Grants -State
80,000.00
- 80,000.00
100.00
Total Intergovernmental Revenue
$ 285,000.00 $
9,733.50 $ 275,266.50
96.58%
Page 1 of 2
General Ledger
Revenue - Budget vs Actual
Period 01 - 09
Fiscal Year 2010 - 2010
Account Description
Charges for Current Services
3601
Sale of Documents
3602
Use & Variance Permits
3603
Rezoning Fees
3604
Assessment Searches
3605
Plat Recording Fees
3607
Election Filing Fees
3613
Misc - General Government
3614
Admin Charge -2% Const
3615
Admin Charge -5% Street Re -Const
3617
Engineering General
3619
Investment Management Fee
3629
Misc - Public Safety
3630
Recreation Program Fees
3631
Recreation Center
3633
Park Equipment Rental
3634
Park Facility Usage Fee
3635
Watercraft Rental
3636
Self- Supporting Programs
3637
Senior Programs
3638
Food Concessions
3639
Misc -Park & Rec
3641
Youth Sport Donation
3642
Recreation Sports
3649
Misc - Public Works
3651
Merchandise Sales
3670
Internment Fee
46,190.70
Total Current Services
Other Revenue
3801
Interest Earnings
3802
Equipment Rental & Sale
3803
Building Rental
3804
Land Sale
3807
Donations
3808
Ins Recoveries & Reimbursements
3816
SAC Retainer
3818
Sur -Tax Retainer
3820
Misc Other Revenue
3829
Interest/Penalties-Other
3901
Contributed Assets
3903
Refunds /Reimbursements
3910
Misc Revenue
3980
Cash Over /Short
(30.00)
Total Other Revenue
Grand Total
2010
Budget
2010 2010
Actual $ Uncollected
1,000.00
3,013.81
(2,013.81)
22,000.00
3,830.00
18,170.00
2,000.00
-
2,000.00
500.00
165.00
335.00
7,000.00
1,050.00
5,950.00
-
20.00
(20.00)
5,000.00
2,404.41
2,595.59
25,000.00
20,274.00
4,726.00
108,000.00
-
108,000.00
-
30.00
(30.00)
75,000.00
-
75,000.00
6,000.00
11,364.89
(5,364.89)
40,000.00
32,405.54
7,594.46
221,000.00
152,933.58
68,066.42
300.00
149.70
150.30
14,000.00
11,080.14
2,919.86
4,500.00
5,466.78
(966.78)
98,000.00
51,809.30
46,190.70
28,000.00
26,433.33
1,566.67
12,000.00
9,542.10
2,457.90
1,000.00
1,164.57
(164.57)
31,000.00
24,502.10
6,497.90
5,000.00
900.00
4,100.00
1,500.00
1,820.97
(320.97)
-
50.00
(50.00)
$ 707,800.00 T - 360,410.22
$
347,389.78
2010
% Uncollected
(201.38)
82.59
100.00
67.00
85.00
51.91
18.90
100.00
100.00
(89.41)
18.99
(20.09)
50.10
20.86
(21.48)
47.13
5.60
20.48
(16.46)
20.96
82.00
(21.40)
49.08%
200,000.00
-
200,000.00
100.00
140,000.00
133,899.41
6,100.59
4.36
4,000.00
4,070.00
(70.00)
(1.75)
-
4,400.00
(4,400.00)
-
20,500.00
34,185.00
(13,685.00)
(66.76)
5,000.00
-
5,000.00
100.00
5,000.00
1,324.00
3,676.00
73.52
1,000.00
378.61
621.39
62.14
1,000.00
240.00
760.00
76.00
500.00
-
500.00
100.00
43,000.00
104,701.16
(61,701.16)
(143.49)
-
2.00
(2.00)
-
$ 420,000.00
$ 283,200.18
$ 136,799.82
32.57%
$ 9,557,400.00
$ 5,117,229.56
$ 4,440,170.44
46.46%
Page 2 of 2
General Ledger
Expense - Budget vs Actual
Period 01 - 09
Fiscal Year 2010 - 2010
2010
2010
2010
2010
Description
Budget
Actual
Dollars Unspent
% Unspent
City Council
109,300.00
80,136.89
29,163.11
26.68
Administration
461,200.00
322,991.44
138,208.56
29.97
Finance
277,300.00
209,669.65
67,630.35
24.39
Legal
148,000.00
92,066.94
55,933.06
37.79
Property Assessment
110,000.00
7,733.44
102,266.56
92.97
Management Information Systems
247,800.00
170,670.13
77,129.87
31.13
City Hall Maintenance
419,500.00
459,622.01
(40,122.01)
-9.56
Elections
27,900.00
15,571.88
12,328.12
44.19
Library Building
137,200.00
80,630.76
56,569.24
41.23
General Government
$
1,938,200.00
$
1,439,093.14
$
499,106.86
25.75%
Police /Carver Co Contract
1,631,200.00
835,464.07
795,735.93
48.78
Fire Prevention & Admin
648,100.00
360,191.73
287,908.27
44.42
Code Enforcement
606,000.00
431,351.71
174,648.29
28.82
Animal Control
74,700.00
51,946.41
22,753.59
30.46
Law Enforcement
$
2,960,000.00
$
1,678,953.92
$
1,281,046.08
43.28%
Engineering
563,200.00
396,379.68
166,820.32
29.62
Street Maintenance
818,500.00
543,113.21
275,386.79
33.65
Street Lighting & Signals
348,400.00
237,240.82
111,159.18
31.91
City Garage
527,200.00
330,716.20
196,483.80
37.27
Public Works
$
2,257,300.00
$
1,507,449.91
$
749,850.09
33.22%
Planning Commission
4,200.00
2,422.11
1,777.89
42.33
Planning Administration
408,900.00
278,217.83
130,682.17
31.96
Senior Facility Commission
32,700.00
20,124.31
12,575.69
38.46
Community Development
$
445,800.00
$
300,764.25
$
145,035.75
32.53%
Park Commission
2,200.00
1,336.08
863.92
39.27
Park Administration
150,400.00
92,410.19
57,989.81
38.56
Recreation Center
346,300.00
206,788.40
139,511.60
40.29
Lake Ann Park
68,300.00
23,856.38
44,443.62
65.07
Park Maintenance
884,600.00
655,788.94
228,811.06
25.87
Senior Citizens Center
69,100.00
47,731.50
21,368.50
30.92
Recreation Programs
283,500.00
224,764.45
58,735.55
20.72
Self- Supporting Programs
83,300.00
51,960.26
31,339.74
37.62
Recreation Sports
18,400.00
18,116.57
283.43
1.54
Park & Recreation
$
1,906,100.00
$
1,322,752.77
$
583,347.23
30.60%
Transfer for Roads
$
50,000.00
$
-
$
50,000.00
100.00%
Grand Total
$
9,557,400.00
$
6,249,013.99
$
3,308,386.01
34.62%
Fixed Income Sales
Portfolio Analytics
Analysis for:
CITY OF CHANHASSEN
Presented by:
J. CURTIS
September 30, 2010
This account summary was prepared by Wells Fargo Securities Portfolio Analytic Services and is not a substitute for your monthly statement or trade confirmation. Prices
and yields are current as of the date of this summary and are subject to change and availability; past performance is no guarantee of future results. Municipal leases are
shown at their par value. Any rating provided for a municipal lease investment is a rating associated with the lessee, and does not constitute a rating of the lease
investment itself.
Wells Fargo Securities is the trade name for certain capital markets and investment banking services of Wells Fargo & Company and its subsidiaries, including Wells
Fargo Securities, LLC, a member of NYSE, FINRA and SIPC, Wells Fargo Institutional Securities, LLC, a member of FINRA and SIPC, and Wells Fargo Bank, National
Association. Wells Fargo Securities, LLC carries and provides clearing services for Wells Fargo Institutional Securities, LLC customer accounts.
Investments: NOT FDIC Insured • May Lose Value • No Bank Guarantee
PORTFOLIO SUMMARY REPORT
CITY OF CHANHASSEN
Total Par Value($000):
$20,742
Avg. Market Yield:
0.71
Total Market Value($000)(w /accrued):
$21,183
Avg. Book Yield:
1.82
Total Market Value($000)(w /o accrd):
$21,069
Avg. Coupon:
2.21
Unrealized G/L ($000):
$228
Avg. Price:
101.58
3 Month Cash Flow Projection ($000):
$474
Number of Bonds:
33
Annual Income($000):
$379
Avg. Effective Duration:
1.34
Avg. S &P Rating:
AGY
Avg. Convexity:
-0.05
Avg. Moody's Rating:
AGY
Avg. Life (Years):
1.30
Current Yield Curve
1 4.00
2.00
0.00
6 1 Year 2 Year 3 Year 5 Year 7 Year 10 20 30
Month Year Year Year
Sector Distribution
58.10
30.43
Ratings Distribution
30.43
58.1
8.99
2.48
■ AGY ■ Aa -- N R ■ N/A
2
AW
DISTRIBUTION CHARTS
CITY OF CHANHASSEN
Agency Distribution
FFCB, 4.93
FHLMC, 19.41 0 FHLB, 24.27
FNMA, 9.49
Call Distribution
Priced to Call,
16.70%
NC /Not Priced To
Call, 83.30%
Municipal State Distribution
Duration Distribution
60
10
5o
8.99
40
9
O
8
--
7
O
a
20
O
10
0
6
<0.00 0.00-0.99 1.00-2.99 3.00-3.99 4.00-5.99 6.00 - 7.99 8.00+
O
LL
5
�
i
4
0
3
2
1
ANN=
MN
WI
Duration Distribution
60
5o
40
O
J
O
U. 30
0:
O
a
20
10
0
<0.00 0.00-0.99 1.00-2.99 3.00-3.99 4.00-5.99 6.00 - 7.99 8.00+
PORTFOLIO HISTORY
$45,000
$40,000
$35,000
CITY OF CHANHASSEN
$25,000
$20,000
$15,000
$10,000
r '
'All averages market weighted
3
$0
° o, ob
Q m
a c C} q e o. c 4 u
to Q Q S N f G
Date
Total Par
Unrealized
Effective
Avg. Life
Market
Benchmark
Avg. Book
Avg.
Avg.
Value($000)
GIL($000)
Duration
Convexity
Yrs
YTW
Tsy Yld
Yield
Coupon
Price
Avg. Rating
#Issues
Sep-10 $20,742
$228
1.34
-0.05
1.30
0.71 116
1.77
2.21
101.58
AGY
33
Jun -10 $24,387
234
0.79
-0.01
0.77
0.69
2.52
3.09
101.71
AGY
42
Apr -10 $21,083
233
0.62
0.00
0.64
0.34
2.54
3.23
101.681
AGY
41
Apr -10 $21,083
233
0.62
0.00
0.64
0.34
2.54
3.23
101.681
AGY
41
Mar -10 $24,083
282
0.98
-0.19
1.16
0.86
2.59
3.23
101.791
AGY
44
Jan -10 $33,510
320
0.85
-0.07
1.07
1.03
2.79
3.26
101.507
AGY
79
Sep-09 $28,573
557
0.72
0.01
0.74
0.76
3.32
3.85
102,528
NIA
78
Jun -09 $35,177
638
0.80
-0.01
0.81
1.07
3.05
3.48
102.381
NIA
88
Mar -09 $36,027
621
1.00
0.00
1.03
1.78
3.27
3.68
102.377
NIA
97
Dec -08 $42,745
762
1.07
403
1.08
1.70
3.12
3.54
102.441
AGY
107
Portfolio Par Value($000)
$45,000
$40,000
$35,000
$30,000
$25,000
$20,000
$15,000
$10,000
$5,000
.
3
$0
° o, ob
Q m
a c C} q e o. c 4 u
to Q Q S N f G
4
INVESTMENT SECTOR REPORT
CITY OF CHANHASSEN
Sector
Par
$000 Cusip
Issuer
MDY
Ratin
S &P
Rating
Coupon
%
Maturity
Call
Date
Worst
Date
Mkt
Price
Mkt Val
% Port
YTW
Book
Yid
Eff
Dur
Conv
Gain /Loss
5000
1,000 3128X4QK
FEDERAL HOME LN MTG CORP
AGY
AGY
5.000
10/18/10
N/A
10/18/10
100.22
1,025
4.84
0.64
2.95
0.05
0.00
1.18
1,000 3133XDTA
FEDERAL HOME LN BKS
AGY
AGY
4.750
12/10/10
N/A
12/10/10
100.88
1,023
4.83
0.24
3.84
0.19
0.00
7.10
1,000 313384BB
FHLB DISC NT
AGY
AGY
0.000
01/26/11
N/A
01/26/11
99.95
999
4.72
0.16
0.19
0.32
0.00
0.12
500 313588CG
FNMA DISC NT
AGY
AGY
0.000
02124/11
N/A
02/24/11
99.94
500
2.36
0.15
0.16
0.40
0.00
0.03
500 313396EV
FHLMC DISC NT
AGY
AGY
0.000
04/26/11
N/A
04/26/11
99.90
499
2.36
0.18
0.20
0.57
0.00
0.08
500 313588FZ
FNMA DISC NT
AGY
AGY
0.000
05/24/11
N/A
05/24/11
99.88
499
2.36
0.19
0.19
0.65
0.00
0.02
1,000 3133XBYA
FEDERAL HOME LN BKS
AGY
AGY
4.250
06/10/11
N/A
06/10/11
102.59
1,039
4.90
0.50
3.79
0.68
0.00
22.86
1,500 3128X75G
FEDERAL HOME LN MTG CORP
AGY
AGY
3.250
12/09/11
12/09/10
12/09/10
100.53
1,523
7.19
0.46
2.49
0.19
0.00
5.91
1,000 3137EAAR
FEDERAL HOME LN MTG CORP
AGY
AGY
4.750
03/05/12
N/A
03/05/12
106.16
1,065
5.03
0.43
3.25
1.39
0.01
40.79
950 31331XG3
FEDERAL FARM CR BKS CONS
AGY
AGY
5.450
06/21/12
N/A
06/21/12
108.41
1,044
4.93
0.55
4.52
1.65
0.02
65.43
1,000 3133XSP9
FEDERAL HOME LOAN BANKS
AGY
AGY
3.125
12/13/13
N/A
12/13/13
106.78
1,077
5.08
0.97
1.81
3.04
0.06
27.09
1,000 3136FM3R
FEDERAL NATL MTG ASSN
AGY
AGY
1.750
08/18/14
08/18/11
08/18/11
100.97
1,012
4.78
0.65
1.70
1.74
-0.70
9.25
1,000 313370KG
FEDERAL HOME LOAN BANKS
AGY
AGY
1.000
08/25/15
08/25/11
08/25/11
100.13
1,002
4.73
0.86
1.00
1.78
-0.67
1.25
AGY 11,950
99.94
AGY
AGY
2.902
0.20
0.48
0.00
102.20
12,308
58.10
0.50
2.25
1.01
-0.10
181.10
5
550
51043PAA
LAKE PARK - AUDUBON MINN INDP
NR
AAA
2.000
02/01/14
N/A
02/01/14
101.35
560
2.64
1.58
2.00
3.21
0.06
7.44
1,300
51043PAB
LAKE PARK- AUDUBON MINN INDP
NR
AAA
2.750
02/01/15
N/A
02/01/15
102.87
1,344
6.35
2.05
2.75
4.06
0.10
37.35
510
951427X4
WEST BEND WIS TAXABLE G O R
Aa2
NR
2.875
03/01/16
N/A
03/01/16
102.97
525
2.48
2.26
2.19
5.01
0.14
-1.86
MUNI
2,360
Aa2
AAA
2.602
102.54
2,429
11.47
1.99
2.45
4.07
0.10
42.93
2,616
CHAN0004
M &144647075
N/A
N/A
0.001
10/07/10
N/A
10/07/10
100.00
2,616
12.35
0.00
0.00
0.02
0.00
0.00
365
CHAN0001
4M FUND MMF
N/A
N/A
0.070
10107/10
N/A
10/07/10
100.00
365
1.72
0.07
0.07
0.02
0.00
0.00
528
WFMM01
WF ADV GOVT MM
N/A
N/A
0.009
10/07/10
N/A
10/07/10
100.00
528
2.49
0.01
0.01
0.02
0.00
0.00
MM
3,509
N/A
N/A
0.027
100.000
3,509
16.56
0.03
0.03
0.02
0.00
3.78
99
759187AS
REGIONS BK BIRMINGHAM ALA
N/A
N/A
1.500
01/31/11
N/A
01/31/11
100.42
99
0.47
0.24
1.51
0.34
0.00
0.42
98
9393792N
WASHINGTON MUT BK HENDERSON
N/A
N/A
4.000
01/31/11
N/A
01/31/11
101.25
100
0.47
0.24
4.00
0.34
0.00
1.22
98
95989QAL
WESTERNBANK P R
N/A
N/A
4.000
01/31/11
N/A
01/31/11
101.25
100
0.47
0.24
4.00
0.34
0.00
1.22
249
686184RU
ORIENTAL B &T HATO REY PR
N/A
N/A
0.150
03/22/11
N/A
03/22/11
99.92
249
1.17
0.33
0.15
0.47
0.00
-0.21
249
628825HZ
NCB SVGS BK FSB HILLSBORO OH
N/A
N/A
0.200
03/24/11
N/A
03/24/11
99.94
249
1.17
0.34
0.20
0.48
0.00
-0.16
245
86175TAJ
STONEBRIDGE BK EXTON PA
N/A
N/A
1.250
06/09/11
N/A
06/09/11
100.53
247
1.17
0.49
1.25
0.69
0.00
1.29
245
05568PUE
BMW BK NORTH AMER UTAH
N/A
N/A
1.700
12/12/11
N/A
12/12/11
100.00
246
1.16
1.70
1.70
1.18
0.01
0.00
170
060243CW
BANGOR SVGS BK ME
N/A
N/A
2.200
12/10/12
N/A
12/10/12
100.00
171
0.81
2.20
2.20
2.12
0.03
0.00
245
02580VF4
AMERICAN EXPRESS BK FSB UTAH
N/A
N/A
2.350
12/10/12
N/A
12/10/12
100.00
247
1.17
2.35
2.35
2.11
0.03
0.00
245
02586T4Z
AMERICAN EXPRESS CENTURION B
N/A
N/A
2.350
12/10/12
N/A
12/10/12
100.00
247
1.17
2.35
2.35
2.11
0.03
0.00
245
87164DAC
SYNOVUS BK COLUMBUS GA
N/A
N/A
1.450
02/25/14
N/A
02/25/14
100.00
245
1.16
1.45
1.45
3.31
0.06
0.00
245
36159SRA
GE MONEY BK DRAPER UTAH
N/A
N/A
1.900
08/20/14
N/A
08/20/14
100.00
246
1.16
1.90
1.90
3.72
0.08
0.00
245
14042E3R
CAPITAL ONE NATL ASSN VA
N/A
N/A
1.750
08/25/14
N/A
08/25/14
100.00
245
1.16
1.75
1.75
3.75
0.08
0.00
245
140420MY
CAPITAL ONE BK USA NATL ASSN
N/A
N/A
1.750
08/25/14
N/A
08/25/14
100.00
245
1.16
1.75
1.75
3.75
0.08
0.00
CD
2,923
N/A
N/A
0.774
100.24
2,936
13.87
1.24
1.90
1.76
0.03
0.27
Total:
20,742
AGY
AGY
2.208
1.71
101.58
21,183
100.00
0.71
1.82
1.33
-0.04
227.81
5
CALLABLE /PUTTABLE HOLDINGS REPORT
CITY OF CHANHASSEN
Par YTW Bk I Eff Prc
Ide ntifier Issuer Coupon Maturity Value Date I Price YTW Yid Dur Cony Fla
3128X75G FEDERAL HOME LN MTG CORP 3.250 12/09/11 1,500,000 12/09/10 100.53 0.46 2.49 0.19 0.00 Priced to Call
3136FM3R FEDERAL NATL MTG ASSN 1.750 08/18/14 1,000,000 08/18/11 100.97 0.65 1.70 1.74 -0.70 Priced to Call
313370KG FEDERAL HOME LOAN BANKS 1.000 08/25/15 1,000,000 08/25/11 100.13 0.86 1.00 1.78 -0.67 Priced to Call
2.179 3.01 3,500,000 100.54 0.63 1.84 1.08 -0.39
6
PORTFOLIO SIMULATION - MARKET
CITY OF CHANHASSEN
----- - - - - -- Returns( %) ----- - - - - -- Avg Eff Mkt Value $ Mkt Value % Mkt Value
Yield Change (bp) Total Income Price Life Dur Convexity 1 [$000] Chan I Change
-300
3.283
0.329
2.955
1.01
0.987
0.017
12,297
$594,172
5.219%
-250
2.791
0.337
2.454
1.00
0.974
0.017
12,191
$489,854
4.312%
-200
2.307
0.346
1.961
0.99
0.962
0.017
12,087
$387,371
3.423%
-150
1.832
0.355
1.477
0.98
0.950
0.016
11,984
$286,682
2.541%
-100
1.365
0.364
1.001
0.97
0.938
0.016
11,883
$187,749
1.677%
-50
0.906
0.373
0.533
0.96
0.927
0.016
11,784
$90,507
0.830%
0
0.478
0.407
0.072
0.95
0.915
0.017
11,687
$0
0.000%
50
0.087
0.480
-0.394
0.95
0.922
0.013
11,588
- $82,982
- 0.847%
100
-0.357
0.554
-0.912
1.17
1.035
-0.037
11,478
- $177,082
- 1.788%
150
-0.843
0.628
-1.471
1.16
1.076
0.027
11,360
- $279,884
- 2.798%
200
-1.336
0.702
-2.038
1.20
1.124
0.038
11,240
- $384,291
- 3.825%
250
-1.827
0.776
-2.603
1.23
1.122
0.064
11,120
- $488,335
- 4.852%
300
-2.311
0.849
-3.161
1.22
1.148
0.017
11,002
- $590,988
-5.861%
Horizon Months 6
Reinvestment Rate 0.194
Base Currency US
$ Mkt Value Change
$800,000
$600,000
$400,000
$200,000
$0
- $200,000 -300 -2 -200 -1 -100 - 150 200 250 300
- $400,000
- $600,000
- $800,000
7
MONTHLY STATIC CASH FLOW CALENDAR
CITY OF CHANHASSEN
Run Off
Date Total Int CF Maturity CF Call CF Put CF Sink CF Total Princ CF Total Cashflow YTW Run Off Bk Yld
Aug -10 0 0 0 0 0 0 0 0.63 2.63
Sep -10 74,125 2,000,000 1,000,000 0 0 3,000,000 3,074,125 0.00 3.35
Oct -10 25,000 1,000,000 0 0 0 1,000,000 1,025,000 0.46 2.95
Nov -10 0 0 0 0 0 0 0 0.00 0.00
Dec -10 110,887 1,000,000 1,500,000 0 0 2,500,000 2,610,887 0.34 3.03
Jan -11 0 0 0 0 0 0 0 0.00 0.00
Feb -11 0 0 0 0 0 0 0 0.00 0.00
Mar -11 23,750 0 0 0 0 0 23,750 0.00 0.00
Apr -11 0 0 0 0 0 0 0 0.00 0.00
May -11 0 0 0 0 0 0 0 0.00 0.00
Jun -11 62,762 1,000,000 0 0 0 1,000,000 1,062,762 0.50 3.79
Jul -11 0 0 0 0 0 0 0 0.00 0.00
Aug -11 0 0 0 0 0 0 0 0.00 0.00
Sep -11 23,750 0 0 0 0 0 23,750 0.00 0.00
Oct -11 0 0 0 0 0 0 0 0.00 0.00
Nov -11 0 0 0 0 0 0 0 0.00 0.00
Dec -11 41,512 0 0 0 0 0 41,512 0.00 0.00
Jan -12 0 0 0 0 0 0 0 0.00 0.00
Feb -12 0 0 0 0 0 0 0 0.00 0.00
Mar -12 23,750 1,000,000 0 0 0 1,000,000 1,023,750 0.25 3.25
Apr -12 0 0 0 0 0 0 0 0.00 0.00
May -12 0 0 0 0 0 0 0 0.00 0.00
Jun -12 41,512 950,000 0 0 0 950,000 991,512 0.39 4.52
Jul -12 0 0 0 0 0 0 0 0.00 0.00
Aug -12 0 0 0 0 0 0 0 0.00 0.00
YEAR 1 +2 427,048 6,950,000 2,500,000 0 0 9,450,000 9,877,048
YEAR 31,250 0 0 0 0 0 31,250
YEAR 13,454,748 8,950,000 2,540,469 0 0 11,450,000 11,939,550
YEAR 5 0 5 201,954 202,105 0 0 4
33,,151(010,000 - --
3 _0.000 ,
1500,000 - - -
9000,000
500,000 LL -
71000,000 - - -
U
500,000
0 -
09/ 1010 / 1011 /1012/10 01 / 11 02 /1103/1104/11 05/ 1106/ 11 07 /1108/ 1109/11 10 /11 11 / 11 12/ 1101 / 1202 / 1203 /12 04/12 05/12 06 /1207/12 08/12
Total int CF CASH FLOW TYPE
8
PORTFOLIO ALERTS REPORT
CITY OF CHANHASSEN
Called Bonds /Announcements /Pre- Refundings
Identifier
Issuer
Coupon
Maturity
Currcy
Sector /State
Call Date
Call Price
I
Portfolio
Par Value (000)
Mkt Value ($000)
% of Port
Prc Date
I
CALLED:
3128X9T9
FEDERAL HOME LN MTG CORF
1.000
12/22/11
USD
AGY -AGY
09/22/10
100
15114523
10
10
6.05
08/31/10
3128X9ZM
FEDERAL HOME LN MTG CORF
1.250
06/01/12
USD
AGY -AGY
09/01/10
100
15114523
8
8
4.54
08/31/10
31331JRF
FEDERAL FARM CR BKS CONS
1.250
09/14/12
USD
AGY -AGY
09/14/10
100
15114523
4
4
2.11
08/31/10
31331JRV
FEDERAL FARM CR BKS CONS
0.960
03/16/12
USD
AGY -AGY
09/16/10
100
15114523
4
4
2.11
08/31/10
31331JSB
FEDERAL FARM CR BKS CONS
1.340
12117/12
USD
AGY -AGY
09/17/10
100
15114523
4
4
2.11
08/31110
31331JSG
FEDERAL FARM CR BKS CONS
1.090
06/15/12
USD
AGY -AGY
09/15/10
100
15114523
4
4
2.11
08/31/10
31331JTG
FEDERAL FARM CR BKS CONS
0.870
03/28/12
USD
AGY -AGY
09/28/10
100
15114523
15
15
9.05
08/31/10
3133XXE8
FEDERAL HOME LOAN BANKS
1.150
03/22/12
USD
AGY -AGY
09/22/10
100
15114523
5
5
3.03
08/31/10
3136FHEP
FEDERAL NATL MTG ASSN
2.000
03123/12
USD
AGY -AGY
09/23/10
100
15114523
10
10
6.08
08/31/10
ANNOUNCED
CALL:
31398AK7
FEDERAL NATL MTG ASSN
1.600
10/01/12
USD
AGY -AGY
10/01/10
100
15114523
5
5
3.03
08/31/10
' WATCHLIST: UPG /POS = Possible Upgrade; DNG /NEG Possible Downgrade; UNC /DEV /EVO = Uncertain (Possible Upgrade or Downgrade)
Report Shows rating changes, called bonds, call announcements and pre - refundings occurring since 08/31/2010.
9
City of Chanhassen, MN
Capital Improvement Program
2011 thm 2015
DEPARTMENT SUMMARY
Department
2011 2012 2013 2014 2015 Total
Major Equipment
Municipal Buildings
Park & Trail Improvements
Planning
Sanitary Sewer Improvements
Street Improvements
Surface Water Management
Water System Improvements
983,465
1,713,795
660,300
1,195,855
1,498,116
6,051,531
90,000
2,000,000
405,000
2,495,000
1,080,000
1,350,000
635,000
590,000
210,000
3,865,000
75,000
75,000
290,000
425,000
2,040,000
415,000
115,000
3,285,000
3,650,000
11,029,000
19,850,000
1,400,000
10,000,000
45,929,000
240,000
650,000
395,000
770,000
345,000
2,400,000
340,00
2,7 10,000
1, 520,000
3,350,000
820,000
8,740,000
TOTAL 6,673,465
19,877,795
28,505,300
7,795,855
12,988,118
72,840,531
City of Chanhassen, MN
Capital Improvement Program
2011 dnu 2015
Department
PROJECTS BY DEPARTMENT
Project# Priority 2011 2012 2013 2014 2015 Total
Major Equipment
Fire Dept.: SCBA Equipment
EQ -004
n/a
5,000
5,000
5,000
5,000
7,000
27,000
PPE: Turnout(Helmets
EQ -010
n/a
15,000
20,000
20,000
20,000
75,000
Computer/Network Equipment Purchases/Upgrades
EQ -013
n/a
85,500
94,350
91,850
104,100
85,156
460,956
Telecommunication Purchases/Upgrades
EQ -014
n/a
10,500
5,500
5,500
5,500
5,500
32,500
Community Dev.: Light Duty Trucks
EQ -015
n/a
29,000
30,000
30,000
89,000
Dump /Plow Truck Replacements/Additions
EQ -016
n/a
399,800
120,000
206,000
209,000
216,000
1,150,800
Line Striper
EQ -025
n/a
9,000
9,000
Audio/Visual Equipment
EQ -026
n/a
10,000
10,000
10,000
10,000
10,000
50,000
Light Duty Trucks: Public Works
EQ -029
n/a
73,000
73,000
Utility Bobcat Snow Accessories
EQ -031
n/a
7,000
7,000
Software Purchases
EQ -048
n/a
78,690
80,695
77,700
79,205
80,210
396,500
Computerized Records Retention System
EQ -049
n/a
8,000
16,000
6,500
14,800
16,000
61,300
Fire Vehicles
EQ -054
n/a
40,000
40,000
170,000
195,000
445,000
Aerial Photography for City GIS Datasets
EQ -055
n/a
7,250
250
7,250
250
7,250
22,250
Light Duty Trucks: Utilities
EQ -062
n/a
85,000
55,000
58,000
34,000
232,000
Engineering Vehicles
EQ -065
n/a
25,000
25,000
Storage Area Network (SAN)
EQ -081
n/a
25,000
25,000
50,000
Office Furniture
EQ -084
n/a
5,000
5,000
5,000
5,000
5,000
25,000
Equipment for New Fire Station
EQ -086
n/a
1,000,000
1,000,000
Excavator
EQ -091
n/a
100,000
100,000
Fire Pager Replacement
EQ -092
n/a
12,000
12,000
Thermal Cameras
EQ -093
n/a
15,000
15,000
30,000
Portable Radios
EQ -094
n/a
8,000
8,000
16,000
Skid loader - Parks
EQ -095
n/a
43,000
43,000
Skid loader Tracks - Parks
EQ -096
n/a
7,500
7,500
Portable Generator - Utility Department
EQ -097
n/a
17,000
17,000
Loader Mounted Snow Blower
EQ -098
n/a
141,000
141,000
Sweeper - Parks
EQ -099
n/a
33,000
33,000
Light Duty Trucks - Parks
EQ -100
n/a
65,000
40,000
105,000
Skid loader - Utility Department
EQ -101
n/a
48,000
48,000
Light Weight Vehicle - Park
EQ -103
n/a
22,000
22,000
Mower Replacement - Park
EQ -104
n/a
90,000
95,000
64,000
249,000
Skid loader - Street Department
EQ -105
n/a
40,000
40,000
Tractor Replacement - Park
EQ -106
n/a
30,000
30,000
Springbrook Version 7 Software Upgrade
EQ -108
n/a
25,725
25,725
Bucket Truck Refurbish
EQ -109
n/a
30,000
30,000
Vactor /Sewer Jetting Truck
EQ -110
n/a
425,000
425,000
Paint Striper
EQ -111
n/a
19,000
19,000
Hydro Seeder
EQ-112
n/a
5,000
5,000
Refurbish Engine 12 (#212)
EQ -113
n/a
15,000
15,000
Refurbish Engine 11 (#211)
EQ -114
n/a
15,000
15,000
Brush Chipper
EQ -115
n/a
56,000
56,000
Watermain Break Supply Van
EQ -116
n/a
20,000
20,000
Berti Rear Mount Mower
EQ -117
n/a
10,000
10,000
Street Sweeper
EQ -118
n/a
281,000
281,000
Department
Project#
Priority
2011
2012
2013
2014
2015
Total
Elliptical Machine Replacement - Fire Station #1
EQ -119
n/a
5,000
5,000
Website Improvements
EQ -120
n/a
20,000
20,000
Major Equipment Total
983,465
1,713,795
660,300
1,195,855
1,498,116
6,051,531
Municipal Buildings
Fire Station 3
MB -009
n/a
2,000,000
2,000,000
City Hall Remodel
MB -010
n/a
125,000
125,000
City Hall North Parking Lot
MB -014
n/a
280,000
280,000
Engineering Copy Area Renovation
MB -015
n/a
10,000
10,000
City Hall Parking Lot Expansion
MB -016
n/a
70,000
70,000
Fire Station 1 Repainting and Carpeting
MB -017
n/a
10,000
10,000
Municipal Buildings Total
90,000
2,000,000
405,000
2,495,000
Park & Trail Improvements
Picnic TableslPark Benches
PK &T -042
n/a
10,000
10,000
10,000
10,000
10,000
50,000
Trees
PK &T -043
We
25,000
25,000
25,000
25,000
25,000
125,000
Hwy 41 Pedestrian Underpass/Trail Grant Match
PK &T -069
n/a
400,000
400,000
Tennis Courts
PK &T -072
n/a
125,000
75,000
200,000
Pioneer Pass Park Acquisition
PK &T -078
n/a
290,000
290,000
Recreation Center Fitness Equipment
PK &T -079
n/a
10,000
10,000
20,000
Bluff Creek Drive Gap Trail
PK &T -083
n/a
390,000
390,000
Disc Golf Course Construction
PK &T -085
n/a
20,000
20,000
Skate Park Ramp Replacement & Asphalt Resurfacing
PK &T -093
n/a
110,000
110,000
Pedestrian Trail to Arboretum
PK &T -098
n/a
250,000
250,000
Chanhassen Native Preserve Trail, Final Phase
PK &T -099
n/a
90,000
90,000
Lyman Boulevard North Park Acquisition
PK &T -101
n/a
175,000
175,000
TH5 Pedestrian Underpass at Minnewashta
PK &T -108
n/a
1,000,000
1,000,000
Pioneer Pass Neighborhood Park Development
PK &T -109
n/a
350,000
350,000
Hwy 41 Trail Extension/Stairway
PK &T -110
n/a
250,000
250,000
City Hall Landscaping
PK &T -111
n/a
75,000
75,000
Bandimere Park Tree Replacement
PK &T -112
n/a
60,000
60,000
Herman Field Park Half Court Basketball
PK &T -113
n/a
10,000
10,000
Park & Trail Improvements Total
1,080,000
1,350,000
635,000
590,000
210,000
3,865,000
Planning
County Rd 61 (old 212) Corridor Study
PL -002
n/a
75,000
75,000
Planning Total
75,000
75,000
Sanitary Sewer Improvements
Inflow and Infiltration Abatement
SS -012
n/a
200,000
75,000
75,000
75,000
75,000
500,000
Sanitary Sewer Replacement
SS -014
n/a
300,000
300,000
600,000
Sanitary Lift Station Rehabilitation Program
SS -017
n/a
90,000
50,000
65,000
40,000
40,000
285,000
2010 MUSA Sanitary Lift Station
SS -020
n/a
1,900,000
1,900,000
Sanitary Sewer Improvements Total
290,000
425,000
2,040,000
415,000
115,000
3,285,000
Street Improvements
West 78th St Streetlights
ST -001
n/a
300,000
300,000
Lyman Boulevard Improvements
ST -003
n/a
8,850,000
8,400,000
17,250,000
Annual Street Improvement Program
ST -012
n/a
1,500,000
1,700,000
1,200,000
1,100,000
1,000,000
6,500,000
TH 101 Corridor Preservation Planning
ST -017
n/a
1,000,000
1,000,000
Department Project# Priority 2011 2012 2013 2014 2015 Total
Pavement Management
ST-018
n/a
300,000
300,000
300,000
300,000
300,000
1,500,000
TH5 Improvements - TH41 to Downtown Victoria
ST -025
n/a
9,029,000
9,029,000
TH 101 /Pleasant View Rd Intersection & Trail Imp
ST -027
n/a
765,000
765,000
TH 101 Improvements - Lyman Blvd to Pioneer Trail
ST -028
n/a
9,500,000
9,500,000
Repaint TH 5 Signals
ST -029
n/a
85,000
85,000
Street Improvements Total
3,650,000
11,029,000
19,850,000
1,400,000
10,000,000
45,929,000
Surface Water Management
Property Acquisition
SWMP -014
n/a
75,000
75,000
75,000
75,000
75,000
375,000
Street Improvement Projects - Storm Water Mgmt
SWMP -019
n/a
400,000
400,000
800,000
Bluff Cr. Nat. Resources Mgmt Plan Implementation
SWMP -024
n/a
125,000
125,000
125,000
125,000
125,000
625,000
Lake Minnewashta Outlet
SWMP -026
n/a
30,000
30,000
Landings Court Storm Water Pond Imp
SWMP -029
n/a
70,000
70,000
Stormwater Pond Improvements
SWMP -032
n/a
25,000
35,000
25,000
35,000
40,000
160,000
LID Implementation Project
SWMP -035
n/a
15,000
15,000
15,000
15,000
15,000
75,000
Well 13 Parking Lot
SWMP -037
n/a
90,000
90,000
Cranes Vineyard Creek
SWMP -039
n/a
55,000
55,000
Bluff Creek Drive Drainage Improvement Project
SWMP -042
n/a
120,000
120,000
Surface Water Management Total
240,000
650,000
395,000
770,000
345,000
2,400,000
Water System Improvements
Repainting: West 76th St. Water Tower
W -015
n/a
110,000
110,000
Arboretum Water Main
W -020
n/a
220,000
220,000
Watermain Replacement
W -024
n/a
700,000
700,000
1,400,000
Pressure Reducing Station
W -027
n/a
65,000
65,000
75,000
205,000
Well Rehabilitation Program
W -032
n/a
45,000
45,000
45,000
50,000
50,000
235,000
Repaint Lake Lucy Water Stand Pipe
W -041
n/a
550,000
550,000
High Zone Elevated Storage Tank
W -042
n/a
1,900,000
1,900,000
Low Zone 1 million gallon Elevated Storage Tank
W -046
n/a
2,600,000
2,600,000
Well #15 Improvements
W -048
n/a
1,400,000
1,400,000
High Zone High Service Pump
W -050
n/a
120,000
120,000
Water System Improvements Total
340,000
2,710,000
1,520,000
3,350,000
820,000
8,740,000
GRAND TOTAL
6,673,465
19,877,795
25,505,300
7,795,855
12,988,116
72,840,531
City of Chanhassen, MN
Capital Improvement Program
2011 thi u 2015
FUNDING SOURCE SUMMARY
Source 2011 2012 2013 2014 2015 Total
Arterial Collector Dvlpmnt Fee
100,000
100,000
Assessment/Revolving Assess Fund
1,200,000
1,700,000
1,200,000
1,100,000
1,000,000
6,200,000
Cable TV Fund
30,000
10,000
10,000
10,000
10,000
70,000
Capital Replacement Fund
899,034
1,403,795
710,300
1,284,855
1,063,116
5,361,100
GO Bonds
2,500,000
2,500,000
MSA
1,700,000
1,800,000
3,500,000
Other Agency Contribution
1,535,000
9,814,000
15,915,000
105,000
6,985,000
34,354,000
Park Dedication Fund
1,090,000
235,000
635,000
515,000
210,000
2,685,000
Sewer Utility Fund
389,073
452,500
2,222,500
449,000
440,000
3,953,073
Street Pavement Management
655,000
220,000
100,000
100,000
100,000
1,175,000
Surface Water Utility Fund
236,285
585,000
460,000
665,000
260,000
2,206,285
Tax Levy
200,000
200,000
200,000
200,000
200,000
1,000,000
Water Utility Fund
439,073
2,757,500
2,252,500
3,367,000
920,000
9,736,073
GRAND TOTAL
6,673,485
19,877,795
25,505,300
7,795,855
12,988,118
72,840,531
City of Chanhassen, MN
Capital Improvement Program
2011 anu 2015
PROJECTS BY FUNDING SOURCE
Source Project# Priority 2011 2012 2013 2014 2015 Total
Art erial Collector Dvlpmnt Fee
Lyman Boulevard Improvements
ST -003
n/a
5,000
5,000
100,000
5,000
7,000
100,000
Arterial Collector Dvlpmnt Fee Total
EQ -010
n/a
15,000
100,000
20,000
20,000
100,000
Assessment/Revolving Assess Fund
EQ -013
n/a
85,500
94,350
91,850
104,100
85,156
460,956
Annual Street Improvement Program
ST -012
n/a
1,200,000
1,700,000
1,200,000
1,100,000
1,000,000
6,200,000
Assessment/Revolving Assess Fund Total
EQ -015
n/a
1,200,000
1,700,000
1,200,000
1,100,000
1,000,000
6,200,000
Cable TV Fund
EQ -016
n/a
399,800
120,000
206,000
209,000
216,000
1,150,800
AudioNisual Equipment
EQ -026
n/a
10,000
10,000
10,000
10,000
10,000
50,000
Website Improvements
EQ -120
n/a
20,000
73,000
20,000
Cable TV Fund Total
EQ -048
n/a
30,000
10,000
10,000
10,000
10,000
70,000
Capital Renlacement Fund
Fire Dept.: SCBA Equipment
EQ -004
n/a
5,000
5,000
5,000
5,000
7,000
27,000
PPE: Turnout/Helmets
EQ -010
n/a
15,000
20,000
20,000
20,000
75,000
Computer/Network Equipment Purchases/Upgrades
EQ -013
n/a
85,500
94,350
91,850
104,100
85,156
460,956
Telecommunication Purchases/Upgrades
EQ -014
n/a
10,500
5,500
5,500
5,500
5,500
32,500
Community Dev.: Light Duty Trucks
EQ -015
n/a
29,000
30,000
30,000
89,000
Dump /Plow Truck Replacements/Additions
EQ -016
n/a
399,800
120,000
206,000
209,000
216,000
1,150,800
Line Striper
EQ -025
n/a
9,000
9,000
Light Duty Trucks: Public Works
EQ -029
n/a
73,000
73,000
Software Purchases
EQ -048
n/a
78,690
80,695
77,700
79,205
80,210
396,500
Computerized Records Retention System
EQ -049
n/a
8,000
16,000
6,500
14,800
16,000
61,300
Fire Vehicles
EQ -054
n/a
40,000
40,000
170,000
195,000
445,000
Aerial Photography for City GIS Datasets
EQ -055
n/a
7,250
250
7,250
250
7,250
22,250
Engineering Vehicles
EQ -065
n/a
25,000
25,000
Storage Area Network (SAN)
EQ -081
n/a
25,000
25,000
50,000
Office Furniture
EQ -084
n/a
5,000
5,000
5,000
5,000
5,000
25,000
Equipment for New Fire Station
EQ -086
n/a
500,000
500,000
Excavator
EQ -091
n/a
10,000
10,000
Fire Pager Replacement
EQ -092
n/a
12,000
12,000
Thermal Cameras
EQ -093
n/a
15,000
15,000
30,000
Portable Radios
EQ -094
n/a
8,000
8,000
16,000
Skid loader- Parks
EQ -095
n/a
43,000
43,000
Skid loader Tracks - Parks
EQ -096
n/a
7,500
7,500
Loader Mounted Snow Blower
EQ -098
n/a
141,000
141,000
Sweeper - Parks
EQ -099
n/a
33,000
33,000
Light Duty Trucks - Parks
EQ -100
n/a
65,000
40,000
105,000
Light Weight Vehicle - Park
EQ -103
n/a
22,000
22,000
Source Project# Priority 2011 2012 2013 2014 2015 Total
Mower Replacement - Park
EQ -104
n/a
90,000
95,000 64,000
249,000
Skid loader - Street Department
EQ -105
n/a
40,000
40,000
Tractor Replacement - Park
EQ -106
n/a
30,000
30,000
Springbrook Version 7 Software Upgrade
EQ -108
n/a
19,294
19,294
Bucket Truck Refurbish
EQ -109
n/a
30,000
30,000
Paint Striper
EQ -111
n/a
19,000
19,000
Hydro Seeder
EQ -112
n/a
5,000
5,000
Refurbish Engine 12 (#212)
EQ -113
n/a
15,000
15,000
Refurbish Engine 11 (#211)
EQ -114
n/a
15,000
15,000
Brush Chipper
EQ -115
n/a
56,000
56,000
Berti Rear Mount Mower
EQ-117
n/a
10,000
10,000
Street Sweeper
EQ -118
n/a
281,000
281,000
Elliptical Machine Replacement - Fire Station #1
EQ -119
n/a
5,000
5,000
City Hall Remodel
MB -010
n/a
125,000
125,000
Engineering Copy Area Renovation
MB-015
n/a
10,000
10,000
City Hall Parking Lot Expansion
MB -016
n/a
70,000
70,000
Fire Station 1 Repainting and Carpeting
MB -017
n/a
10,000
10,000
Tennis Courts
PK &T -072
n/a
125,000
75,000
200,000
Recreation Center Fitness Equipment
PK &T -079
n/a
10,000
10,000
20,000
Skate Park Ramp Replacement & Asphalt Resurfacing
PK &T -093
n/a
110,000
110,000
City Hall Landscaping
PK &T -111
n/a
75,000
75,000
Bandimere Park Tree Replacement
PK &T -112
n/a
30,000
30,000
County Rd 61 (old 212) Corridor Study
PL -002
n/a
75,000
75,000
Capital Replacement Fund Total
899,034
1,403,795
710,300
1,284,855 1,063,116
5,361,100
GO Bonds
Equipment for New Fire Station
EQ -086
n/a
500,000
500,000
Fire Station 3
MB -009
n/a
2,000,000
2,000,000
GO Bonds Total
2,500,000
2,500,000
MSA
West 78th St Streetlights
ST -001
n/a
300,000
300,000
Lyman Boulevard Improvements
ST -003
n/a
1,700,000
1,500,000
3,200,000
MSA Total
1,700,000
1,800,000
3
Other Agency Contribution
City Hall North Parking Lot
MB -014
n/a
140,000
140,000
TH5 Pedestrian Underpass at MinnevVashta
PK &T -108
n/a
920,000
920,000
Lyman Boulevard Improvements
ST -003
n/a
6,500,000
6,900,000
13,400,000
TH 101 Corridor Preservation Planning
ST -017
n/a
920,000
920,000
TH5 Improvements - TH41 to Downtown Victoria
ST -025
n/a
8,829,000
8,829,000
TH 101 /Pleasant View Rd Intersection & Trail Imp
ST -027
n/a
560,000
560,000
TH 101 Improvements - Lyman Blvd to Pioneer Trail
ST -028
n/a
9,200,000
9,200,000
Bluff Cr. Nat. Resources Mgmt Plan Implementation
SWMP -024
n/a
50,000
50,000
50,000
50,000 50,000
250,000
Stormwater Pond Improvements
SWMP -032
n/a
10,000
10,000
20,000
LID Implementation Project
SWMP -035
n/a
5,000
5,000
5,000
5,000 5,000
25,000
Well 13 Parking Lot
SWMP -037
n/a
30,000
30,000
Cranes Vineyard Creek
SWMP -039
n/a
20,000
20,000
Bluff Creek Drive Drainage Improvement Project
SWMP -042
n/a
40,000
40,000
Source Prqject# Priority 2011 2012 2013 2014 2015 Total
Other Agency Contribution Total
1,535,000
9,814,000
15,915,000
105,000 6,985,000
34,354,000
Park Dedication Fund
Picnic Tables/ParkBenches
PK &T -042
n/a
10,000
10,000
10,000
10,000 10,000
50,000
Trees
PK &T -043
n/a
25,000
25,000
25,000
25,000 25,000
125,000
Hwy 41 Pedestrian Underpass/Trail Grant Match
PK &T -069
n/a
400,000
400,000
Pioneer Pass Park Acquisition
PK &T -078
n/a
290,000
290,000
Bluff Creek Drive Gap Trail
PK &T -083
n/a
390,000
390,000
Disc Golf Course Construction
PK &T -085
n/a
20,000
20,000
Pedestrian Trail to Arboretum
PK &T -098
n/a
250,000
250,000
Chanhassen Native Preserve Trail, Final Phase
PK &T -099
n/a
90,000
90,000
Lyman Boulevard North Park Acquisition
PK &T -101
n/a
175,000
175,000
TH5 Pedestrian Underpass at Minnewashta
PK &T -108
n/a
80,000
80,000
Pioneer Pass Neighborhood Park Development
PK &T -109
n/a
350,000
350,000
Hwy 41 Trail Extension/Stairway
PK &T -110
n/a
250,000
250,000
Bandimere Park Tree Replacement
PK &T -112
n/a
30,000
30,000
Herman Field Park Half Court Basketball
PK &T -113
n/a
10,000
10,000
TH5 Improvements - TH41 to Downtown Victoria
ST -025
n/a
80,000
80,000
TH 101 /Pleasant View Rd Intersection & Trail Imp
ST -027
n/a
95,000
95,000
Park Dedication Fund Total
1,090,000
235,000
635,000
515,000 210,000
2,685,000
Sewer Utility Fund
Utility Bobcat Snow Accessories
EQ -031
n/a
3,500
3,500
Light Duty Trucks: Utilities
EQ -062
n/a
42,500
27,500
29,000
17,000
116,000
Excavator
EQ -091
n/a
30,000
30,000
Portable Generator - Utility Department
EQ -097
n/a
17,000
17,000
Skid loader- Utility Department
EQ -101
n/a
24,000
24,000
Springbrook Version 7 Software Upgrade
EQ -108
n/a
2,573
2,573
Vactor /Sewer Jetting Truck
EQ -110
n/a
325,000
325,000
Inflow and Infiltration Abatement
SS -012
n/a
200,000
75,000
75,000
75,000 75,000
500,000
Sanitary Sewer Replacement
SS -014
We
300,000
300,000
600,000
Sanitary Lift Station Rehabilitation Program
SS -017
n/a
90,000
50,000
65,000
40,000 40,000
285,000
2010 MUSA Sanitary Lift Station
SS -020
n/a
1,900,000
1,900,000
Lyman Boulevard Improvements
ST -003
n/a
150,000
150,000
Sewer Utility Fund Total
389,073
452,500
2,222,500
449,000 440,000
3,953,073
Street Pavement Mana ement
Annual Street Improvement Program
ST -012
n/a
300,000
300,000
TH 101 Corridor Preservation Planning
ST -017
n/a
80,000
80,000
Pavement Management
ST -018
n/a
100,000
100,000
100,000
100,000 100,000
500,000
TH5 Improvements - TH41 to Downtown Victoria
ST -025
n/a
120,000
120,000
TH 101 /Pleasant View Rd Intersection & Trail Imp
ST -027
n/a
90,000
90,000
Repaint TH 5 Signals
ST -029
n/a
85,000
85,000
Street Pavement Management Total
655,000
220,000
100,000
100,000 100,000
1,175,000
Surface Water Utility Fund
Excavator
EQ -091
n/a
30,000
30,000
Springbrook Version 7 Software Upgrade
EQ -108
n/a
1,285
1,285
City Hall North Parking Lot
MB -014
n/a
140,000
140,000
Source Project# Priority 2011 2012 2013 2014 2015 Total
TH 101 /Pleasant View Rd Intersection & Trail Imp
ST -027
Property Acquisition
SWMP -014
Street Improvement Projects - Storm Water Mgmt
SWMP -019
Bluff Cr. Nat. Resources Mgmt Plan Implementation
SWMP -024
Lake Minnewashta Outlet
SWMP -026
Landings Court Storm Water Pond Imp
SWMP -029
Stormwater Pond Improvements
SWMP -032
LID Implementation Project
SWMP -035
Well 13 Parking Lot
SWMP -037
Cranes Vineyard Creek
SWMP -039
Bluff Creek Drive Drainage Improvement Project
SWMP -042
Surface Water Utility Fund Total
Tax Le
Pavement Management ST -018
Tax Levy Total
Water Utility Fund
Utility Bobcat Snow Accessories
EQ -031
Light Duty Trucks: Utilities
EQ -062
Excavator
EQ -091
Skid loader - Utility Department
EQ -101
Springbrook Version 7 Software Upgrade
EQ -108
Vactor /Sewer Jetting Truck
EQ -110
Watermain Break Supply Van
EQ -116
Lyman Boulevard Improvements
ST -003
TH 101 Improvements - Lyman Blvd to Pioneer Trail
ST -028
Repainting: West 76th St. Water Tower
W -015
Arboretum Water Main
W -020
Watermain Replacement
W -024
Pressure Reducing Station
W -027
Well Rehabilitation Program
W -032
Repaint Lake Lucy Water Stand Pipe
W -041
High Zone Elevated Storage Tank
W -042
Low Zone 1 million gallon Elevated Storage Tank
W -046
Well #15 Improvements
W -048
High Zone High Service Pump
W -050
Water Utility Fund Total
n/a
20,000
20,000
n/a
75,000
75,000
75,000
75,000
75,000
375,000
n/a
400,000
400,000
800,000
n/a
75,000
75,000
75,000
75,000
75,000
375,000
n/a
30,000
30,000
n/a
70,000
70,000
n/a
25,000
25,000
25,000
25,000
40,000
140,000
n/a
10,000
10,000
10,000
10,000
10,000
50,000
n/a
60,000
60,000
n/a
35,000
35,000
n/a
80,000
80,000
236,285
585,000
460,000
665,000
260,000
2,206,285
n/a 200,000 200,000 200,000 200,000 200,000 1,000,000
200,000 200,000 200,000 200,000 200,000 1,000,000
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
3,500
116,000
30,000
24,000
2,573
100,000
20,000
400,000
300,000
110,000
220,000
1,400,000
205,000
235,000
550,000
1,900,000
2,600,000
1,400,000
120,000
3,500
42,500 27,500 29,000 17,000
30,000
24,000
2,573
100,000
20,000
400,000
300,000
110,000
220,000
700,000 700,000
65,000 65,000 75,000
45,000 45,000 45,000 50,000 50,000
550,000
1,900,000
2,600,000
1,400,000
120,000
439,073 2,757,500 2,252,500 3,367,000 920,000 9,736,073
GRAND TOTAL 6,673,465 19,877,795 25,505,300 7,795,855 12,988,116 72,840,531
Capital Improvement Program 2011 thru 2015 Department Major Equipment
City of Chanhassen, MN Contact Richard Rice
Project # EQ -004
Project Name Fire Dept.: SCBA Equipment
Account #1 400 - 41154705
Account #2
Account #3
Account #4
Description Total Project Cost: $117,000
Phis program is to provide additional and/or replacement SCBA air bottles, SCBA face masks, and upgrades to SCBA air packs as needed.
Justification
Firefighting is a very rigorous and demanding activity that is performed in an environment of extremes. The high temperatures and other hostile
;nvironmental conditions can quickly shorten the service life of SCBA equipment. The periodic replacement and/or additions to SCBA equipment
s required to maintain current quantities through replacement of damaged or destroyed equipment and to equip new firefighters.
Prior Expenditures
90,000 Equipment
Total
Total 5,000 5,000 5,000 5,000 7,000 27,000
Prior Funding Sources
2011
2012
2013
2014
2015
Total
90,000 Capital Replacement Fund
5,000
5,000
5,000
5,000
7,000
27,000
Total Total
5,000
5,000
5,000
5,000
7,000
27,000
2011 2012
5,000 5,000
2013 2014
5,000 5,000
Type
Equipment
Useful Life
20 years
Category
Fire
Priority
n/a
2015 Total
7,000 27,000
Budget Impact/Other
there should be no operational impact from this purchase. The current maintenance budget will accommodate for this addition.
Capital Improvement Program 2011 rhru 2015
City of Chanhassen, MN
Project # EQ -010
Project Name PP E: Turnout/Helmets
Account #1 400 -4105 -4705
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life 5 -7 years
Category Fire
Priority n/a
Description I Total Project Cost: $135,000
teplacement of 3 -5 sets of turnout gear per year as a result of damage received from firefighting activities. The City will also provide new
nembers with new turnout gear after they complete their probationary period. Funding for turnout gear in 2012 will be funded out of the Station 3
equipment fund.
Justification I
ITurnout gear lasts approximately 5 -7 years on average.
Prior Expenditures 2011 2012 2013 2014 2015 Total
60,000 Maintenance 15,000 20,000 20,000 20,000 75,000
Total Total 15,000 20,000 20,000 20,000 75,000
Prior Funding Sources
2011 2012
2013
2014
2015
Total
F - 6 - 0 — ,00 - 0 1 Capital Replacement Fund
15,000
20,000
20,000
20,000
75,000
Total Total
15,000
20,000
20,000
20,000
75,000
Budget Impact/Other I
There should be no operational impact from this purchase. The current maintenance budget will accommodate for this addition.
Capital Improvement Program 2011 thru 2015 Department Major Equipment
City of Chanhassen, MN Contact Richard Rice
Project # EQ -013 Type Equipment
Useful Life 3 -8 years
Project Name Computer/Network Equipment Purchases/Upgrades
Category Administration
Account #1 400 - 4126 -4703 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $765,206
the purchase of replacement user and network computer, printer, peripherals, and networking hardware. The replacement schedule was
d in 1999 and is subject to modification by the MIS Coordinator with the approval of the City Manager and department heads.
Justification
-ting and purchasing computer equipment through this project allows the City greater flexibility to direct equipment to where it is needed the
rather than in individual budgets. The replacement schedule was developed by the MIS Coordinator in 1999 and approved by the 1999
it appointed IT task force. Expenditures in the 2011 budget requests are for the replacement of one domain controller, 2 network switches, 2
rk servers, 4 workstations, 11 desktop PC's and 4 notebook PC's. Some equipment will be traded in. Other replaced equipment will be
ed if possible for use by other users or will be sold on the public surplus auction site.
Prior Expenditures 2011 2012 2013 2014 2015 Total
F - 304 - , - 25 - 0 1 Office Equipment 85,500 94,350 91,850 104,100 85,156 460,956
Total Total 85,500 94,350 91,850 104,100 85,156 460,956
Prior Funding Sources
2011
2012
2013
2014
2015
Total
304,250 Capital Replacement Fund
Total Total
85,500
85,500
94,350
94,350
91,850
91,850
104,100
104,100
85,156
85,156
460,956
460,956
Budget Impact/Other
items purchased for this account come with a 3 year warranty. Repairs to items are done by MIS staff after the warranty period expires. Spare
or outside repairs are funded out of 101- 1160 -4530 (Repair & Maintenance - Equipment) or 101- 1160 -4300 (Consulting).
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -014
Project Name Telecommunication Purchases/Upgrades
Account #1 400 - 4101 -4703
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life 10 years
Category Administration
Priority n/a
Total Project Cost: $88,700
project funds the expansion and upgrades to the City telephone systems, excluding cellular equipment and services which remains an
, idual department budget item. The current City telephone system is an Intertel Axxess PBX which provides phone service for City Hall,
is Works, the Recreation Center, Fire Station 1, and the Water Treatment Plant. This system is being replaced in 2011.
Justification
k central PBX system simplifies the management of phone services and allows for the integration of phone services with other City applications
uch as unified messaging and fax services. The current system was installed in 1999 and upgraded in 2006. The majority of the handsets are from
he original order. The system has an estimated service life of 10 years and was scheduled to be replaced in 2010, but was delayed due to budget
ssues. The system will be replaced in 2011 with 2010 funds. The system will utilize the majority of the existing handsets. Some older non
*mpatible IP handsets will be replaced when the system is replaced. Additional IP handsets will be ordered as replacements for existing digital
)hones in City Hall in years 2 - 4. New IP phone in year 5 will be for projected Fire Station 3.
Prior Expenditures 2011 2012 2013 2014 2015 Total
F - 5 - 6, - 20 - 0 1 Office Equipment 10,500 5,500 5,500 5,500 5,500 32,500
Total Total 10,500 5,500 5,500 5,500 5,500 32,500
Prior Funding Sources
2011
2012
2013
2014
2015
Total
56,200 Capital Replacement Fund
Total Total
10,500
10,500
5,500
5,500
5,500
5,500
5,500
5,500
5,500
5,500
32,500
32,500
Budget Impact/Other
k new maintenance agreement was established with Integra Telecom following the expiration of the 5 year warranty from Intertel. The MIS
)perating budget includes annual maintenance charges for this service. A new system will have some warranty period.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -015
Project Name Community Dev.: Light Duty Trucks
Account #1 400 - 4107 -4704
Account #2
Account #3
Account #4
Department Major Equipment
Contact Kate Aanenson
Type Vehicles
Useful Life Unassigned
Category Community Development
Priority n/a
D Total Project Cost: $173,000
These purchases are consistent with the Vehicle Replacement Schedule. Replacement units are generally purchased early in the year to
accommodate the time frames established by Hennepin County and the State of Minnesota Cooperative Purchasing Program.
12 - #609 1999 Ford Ranger Pickup
13 - #603 2001 Ford Ranger Pickup
14 - #604 2002 Ford Ranger Pickup
Justification
These vehicles are used to provide building inspection services throughout the community. The average replacement age is over 10 years.
Prior Expenditures 2011 2012 2013 2014 2015 Total
F Vehicles 29,000 30,000 30,000 89,000
Total Total 29,000 30,000 30,000 89,000
Prior Funding Sources 2011
2012
2013
2014 2015
Total
84,000 Capital Replacement Fund
29,000
30,000
30,000
89,000
Total. Total
29,000
30,000
30,000
89,000
Budget Impact/Other
these purchases will include a limited warranty and will reduce the annual maintenance and repair costs as compared to the vehicles replaced.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -016
Project Name Dump/Plow Truck Replacements /Additions
Account #1 400 -4108 -4704 Account #3
Account #2 Account #4
Description
Department Major Equipment
Contact Paul Oehme
Type Vehicles
Useful Life Unassigned
Category Street Equipment
Priority n/a
Total Project Cost: $1,150,800
-se purchases are required to maintain a reliable truck fleet. Costs include truck chassis, dump box, hydraulic system, snow wing, snow plow
I sander. Truck chassis costs are higher due to new federal mandated anti -lock braking requirements effective since 2000. These vehicles are
- chased using either the Hennepin County or State of MN cooperative bid systems. Orders for truck chassis are typically required to be placed
to one year in advance of delivery.
placement schedule is as follows:
11 - #117 1994 Ford L8000 Dump/Plow Truck
11 - #118 1994 Ford L8000 Dump/Plow Truck
12 - #115 1991 Ford F800 Dump/Plow Truck (would also replace truck #302)
13 - #120 1995 Ford LS8006 Dump/Plow Truck
14 - #121 1995 Ford LS8000 Dump/Plow Truck
15 - #122 1996 Ford LS8000 DumD/Plow Truck
Justification
These vehicles are used to provide a variety of maintenance services throughout the community including winter response for plowing and hauling
know. The average replacement age is 18.5 years. Winter emergency service necessitates these vehicles be reliable and dependable. Growth in the
:ommunity creates additional work for these trucks. These vehicle purchases are consistent with the Vehicle Replacement Schedule and are
)urchased through MnDot State contracts..
Expenditures 2011 2012 2013 2014 2015 Total
Vehicles 399,8 120,000 206,000 209,000 216,000 1,150,800
Total 399,800 120,000 206,000 209,000 216,000 1,150,800
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 399,800 120,000 206,000 209,000 216,000 1,150,800
Total 399,800 120,000 206,000 209,000 216,000 1,150,800
Budget Impact/Other
These purchases will include a limited warranty and will reduce the annual maintenance and repair costs as compared to the vehicles replaced.
Capital Improvement Program 2011 chat 2015
City of Chanhassen, MN
Project # EQ -025
Project Name Line Str
Account #1 400 - 0000 -4705
Account #2
Account #3
Account #4
Description
'rovides for the replacement of an existing line - striping machine.
12 - 1994 Graco GM5000 Line Striper 5 hp
Department Major Equipment
Contact Paul Oehme
Type Equipment
Useful Life Unassigned
Category Street Equipment
Priority n/a
Total Project Cost: $9,000
Justification
This machine is used to paint pavement markings and stripe lanes on roads. This purchase will ensure timely and reliable pavement marking
operations. The purchase is consistent with the Equipment Replacement Schedule.
Expenditur
2011 2012 2013 201 2015 Total
Equipment 9,000 9,000
Total 9,000 9,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 9,000 9,000
Total 9,000 9,000
purchase will include a limited warranty.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -026
Project dame AudioNisual Equipment
Account #1 210 - 0000 -4705
Account #2
Account #3
Account #4
Description
'rovides for the systematic maintenance and upgrading of audio /visual equipment.
Department Major Equipment
Contact Laurie Hokkanen
Type Equipment
Useful Life Unassigned
Category Administration
Priority n/a
Total Project Cost: $80,000
Justification
The original AN equipment was purchased in 1989, with the upgrades in 1994 and 2008.
Prior Expenditures
2011
2012
2013
2014
2015
Total
30, Maintenance
10,000
10,000
10,000
10,000
10,000
50,000
Total
Total 10,000
10,000
10,000
10,000
10,000
50,000
Prior
30,000
Total
Funding Sources 2011 2012 2013 2014 2015 Total
Cable N Fund 10,000 10,000 10,000 10,000 10,000 50,000
Total 10,000 10,000 10,000 10,000 10,000 50,000
Budget Impact/Other
This purchase will include a limited warranty. In 2008, a major remodeling including cameras, display screens, AN control systems, and Ch 8
management was undertaken. Future upgrades include expanding access to programming to those without access to cable, and continued
enhancement of the live and broadcast experience.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, NIN
Project # EQ -029
Project Name Light Duty Trucks: Public Works
Account #1 400 -4120 -4704
Account #2
Total
Department Major Equipment
Contact Paul Oehme
Type Vehicles
Useful Life Unassigned
Category Street Equipment
Priority n/a
Description Total Project Cost: $106,000
?rovides for scheduled replacement of light duty trucks in the street and garage departments. Replacement units are generally purchased early in
he year in order to accommodate the time frames established by Hennepin County and the State of MN Cooperative Purchasing Program.
13 - #110 1996 Chevrolet 3/4 ton 4x4 ($35,000)
13 - #125 1999 Dodge 3/4 ton 4x4 with plow ($38,000)
Justification
These vehicles are used for a variety of services throughout the community. The average replacement age is 13 years. These purchases are
consistent with the Vehicle Replacement Program.
Prior Expenditures
33,000 Vehicles
Total
Total 73,000 73,000
Prior Funding Sources 2011 2012 2013 2014 2015 Total
r Capital Replacement Fund 73,000 73,000
Total Total 73,000 73,000
Account #3
Account #4
2011 2012 2013 2014 2015
73,000
73,000
purchases will include a limited warranty and will reduce annual maintenance and repair costs as compared to the vehicles replaced.
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Major Equipment
Contact Paul Oehme
Project # EQ -031
Project Name Utility Bobcat Snow Accessories
Account #1 700 - 7025 -4705 Account #3
Account #2 701 - 7025 -4705 Account #4
Description
[fie snow blower attachment is nearing its useful life and needs replacement.
!013 - 2007 Loftness Snow Blower
Type Improvement
Useful Life 10 -15 years
Category Utilities
Priority n/a
Total Project Cost: $7,000
Justification
This equipment is necessary for cleaning snow from water and sewer locations.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 7,000 7,000
Total 7,000 7,000
Funding Sources 2011 2012 2013 2014 2015 Total
Sewer Utility Fund 3,500 3,500
Water Utility Fund 3,500 3,500
Total
7,000
7,000
Budget Impact/Other
Capital Improvement Program 2011 rhru 2015
City of Chanhassen, MN
Project # EQ -048
Project Name Software Purchases
Account #1 400 - 4117 -4703
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life 3 -6 years
Category Administration
Priority n/a
Total Project Cost: $535,900
.is project funds the purchase of software for all City departments that is not associated with a specific, individual project. Most annual software
?port and license renewal fees are funded out of account 101 -1160 -4300. Some reoccurring software costs have been moved to this account in
10.
Justification
The major portion of funds requested for this project are for Microsoft software purchases. In 2007, the City joined the Microsoft Office
Enterprise Agreement for the State of Minnesota. Microsoft Office is the standard desktop software application for all City users. Participating in
the state agreement allows the City to spread the cost of the product over a period of six years in which there are no additional fees for product
upgrades. Additional Microsoft Server licenses are proposed to update existing Windows Server 2000 and 2003 licenses. Some reoccurring
software costs have been moved to this account in 2010. The City is anticipating purchasing mapping software under an ESRI enterprise software
agreement with Carver County, which allows for use of all vendor mapping software applications. It is anticipated that all cities in Carver County
will participate in the agreement.
Prior Expenditures 2011 2012 2013 2014 2015 Total
139,400 Office Equipment 78,690 80,695 77,700 79,205 80,210 396,500
Total Total 78,690 80,695 77,700 79,205 80,210 396,500
Prior Funding Sources
2011
2012
2013
2014
2015
Total
F --- 139 - , - 40 - 0 1 Capital Replacement Fund
78,690
80,695
77,700
79,205
80,210
396,500
Total Total
78,690
80,695
77,700
79,205
80,210
396,500
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -049
Project Name Computerized Records Retention System
Account #1 400 -4124 -4703
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life 3 -5 Years
Category Administration
Priority n/a
Description Total Project Cost: $107,800
This project originally funded the purchase of an electronic records retention system in 2002. Laserfiche was the vendor chosen for the project.
This project is now used to fund its expansion and the replacement costs for associated scanning equipment, which have an useful life expectancy
of 3 to 5 years. Additional software modules are proposed for later years to allow for managing retention policy compliance.
Justification
this system allows for quick and simultaneous retrieval of documents from any computer on the City network. Both physical document storage
.pace and the occurrence of lost or misfiled documents will be significantly reduced. In addition, documents specified for public access can be
easily made available to residents and constituents from any internet capable computer. Small workgroup scanners in the fire and public works
lepartments will be replaced in the 2011 budget cycle. An additional bar code license is being added for scanning building and finance documents
itilizing bar codes for identification.
Prior Expenditures
2011
2012
2013
2014
2015
Total
46,500 Office Equipment
8,000
16,000
6,500
14,800
16,000
61,300
Total
Total 8,000
16,000
6,500
14,800
16,000
61,300
Prior Funding Sources
2011
2012
2013
2014
2015
Total
F -- 4 - 6, - 50 - 0 1 Capital Replacement Fund
8,000
16,000
6,500
14,800
16,000
61,300
Total Total
8 1 000
16,000
6,500
14,800
16,000
61,300
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -054
Project Name Fire Vehicles
Account #1 400 - 4135 -4704
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Vehicles
Useful Life 10 -15 years
Category Fire
Priority n/a
Description I Total Project Cost: $638,000
[his item allows for the replacement of existing equipment. Vehicles are purchased off either the Hennepin County or State of Minnesota
:ooperative bid. Orders are typically required to be placed up to one (1) year in advance of delivery.
Justification
As vehicles age they become less reliable and require more costly maintenance. Vehicles proposed for replacement in this budget are:
2011 - 1995 Chevrolet Astro Van (207)
2012 - 1988 Chevrolet Third Chiefs vehicle (203)
2014 - 2004 Dodge Durango (20 1)
2014 - 1999 Ford F350 Rescue (218)
2015 - 2004 Dodge Durango (202)
2015 - 1990 Chevrolet Heaw Rescue (216)
Prior Expenditures 2011
2012 2013 2014 2015 Total
F -- 19 - 3,0 - 00 - 1 Vehicles 40,000 40,000 170,000 195,000 445,000
Total Total 40,000 40,000 170,000 195,000 445,000
Prior Funding Sources
2011
2012 2013
2014
2015
Total
193,000 Capital Replacement Fund
40,000
40,000
170,000
195,000
445,000
Total Total
40,000
40,000
170,000
195,000
445,000
include a limited warranty and will reduce the annual maintenance and repair costs.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -055
Project Name Aerial Photography for City GIS Datasets
Account #1 400 - 0000 -4752 Account #3
Account #2 Account #4
Description
Department Major Equipment
Contact Richard Rice
Type Improvement
Useful Life 2 -3 years
Category Administration
Priority n/a
Total Project Cost: $79,250
project funds the aerial photography for the integration with the City's existing GIS datasets. This project is heavily dependent upon the
eration of the Carver County GIS department. An initial joint aerial flyover for high resolution orthographic imagery data was conducted in
12005 and was scheduled to be re -flown every two years. Due to budgetary issues, Carver County is not scheduled to do another flyover until
12011 and will return to a two year schedule if their budget allows.
Justification
City Planners, Engineers and Utility staff use this data in conjunction with other GIS datasets to help resolve geographical issues with residents and
contractors without repeated site visits. It is used in nearly every scheduled staff meeting and has proven useful to the Sheriffs Office and fire
department when conducting area searches. In 2008, Carver County chose a new vendor (Pictometry), which added a three dimensional view to
mapping data. The Pictometry solution provides the ability for staff to view each side of buildings and includes a toolset which allows for accurate
measurement of areas and lines. The vendor data however was not able to be used for updating the Planometric data currently used by City
departments. A separate flyover, delayed by Carver County in 2010, is proposed for 2011 to collect data for this purpose.
Prior Expenditures 2011 2012 2013 2014 2015 Total
— 57 — ,00 - 0 1 Maintenance 7,250 250 7,250 250 7,250 22,250
Total Total 7,250 250 7,250 250 7,250 22,250
Prior
Funding Sources
2011
2012
2013
2014
2015
Total
57,000
Capital Replacement Fund
7,250
250
7,250
250
7,250
22,250
Total
Total
7,250
250
7,250
250
7,250
22,250
Bu dget I mpact / Other
Jo operational impact is expected.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -062
Project Name Light Duty Trucks: Utilities
Account #1 700 - 7025 -4704 Account #3
Account #2 701- 7025 -4704 Account #4
Description
Chis allows for replacement of existing vehicles in the Water and Sewer department.
2011 - #302 1999 Ford F -450 3/4 ton pickup
2012 - #317 1997 Chevrolet 3/4 ton pickup
2013 - #320 2003 Chevrolet 3/4 ton pickup
2013 - #316 1997 Chevrolet 3/4 ton pickup
2014 - #3012002 Chevrolet 3/4 ton DickuD
Department
Major Equipment
Contact
PaulOehme
Type
Vehicles
Useful Life
Unassigned
Category
Utilities
Priority
n/a
Total Project Cost: $296,000
I Justification I
This replaces pickups in accordance with the vehicle replacement plan.
Prior Expenditures
64,000 Vehicles
Total
Total 85,000 55,000 58,000 34,000 232,000
Prior
Funding Sources
2011
2012
2013
2014 2015
Total
64,000
Sewer Utility Fund
42,500
27,500
29,000
17,000
116,000
Total
Water Utility Fund
42,500
27,500
29,000
17,000
116,000
Total 85,000
55,000
58,000
34,000
232,000
Total
2011 2012
85,000 55,000
2013 2014 2015
58,000 34,
232,000
Budget Impact/Other
Capital Improvement Program 2011 rhru 2015
City of Chanhassen, MN
Project # EQ -065
Project Name Engineering Vehicles
Account #1 400 - 0000 -4704
Account #2
Account #3
Account #4
Description Total Project Cost: $60,000
[ he Crown Victoria was purchased in 1993 and is used for general transportation for City Hall employees and site inspections.
Justification
This replacement is in accordance with the vehicle replacement plan.
Prior Expenditures
35,000 Vehicles
Total
Total 25,000 25,000
Prior Funding Sources 2011 2012 2013 2014 2015 Total
35,000 Capital Replacement Fund 25,000 25,000
Total Total 25,000 25,000
2011 2012 2013 2014 2015 Total
25,000
Department Major Equipment
Contact Paul Oehme
Type Vehicles
Useful Life Unassigned
Category Street Equipment
Priority n/a
25,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -081
Project Name Storage Area Network (SAN)
Account #1 400 - 4126 -4703 Account #3
Account #2 Account #4
Description
Department Major Equipment
Contact Richard Rice
Type Improvement
Useful Life 5 -7 years
Category Administration
Priority n/a
Total Project Cost: $136,600
project funds the purchase of a storage area network (SAN), which will gradually replace all internal disk drives in existing network servers.
storage area network is a central storage device made up of individual storage modules, and managed from a single console. The SAN allows
storage to be modified as storage needs change, without any downtime for users. New network servers will not be ordered with internal
tge. Existing network servers are being migrated to a virtualized environment which will utilize the SAN for all data storage needs.
Justification
The need for digital storage space for City documentation and applications is growing at a rate of approximately 50OGB per year. Existing storage
space became difficult to manage on individual network servers. Internal storage utilization is inefficient, and requires system downtime to
reconfigure. SAN storage allows for real time reconfiguration as well as the ability to make real time copies for redundancy and for daytime
backup processes. The initial SAN array was purchased in 2008, a second unit in 2009, and a replication SAN in 2010. Currently all units reside
in City Hall, however the third replication SAN will be moved to the public works building after it receives fiber connectivity. An additional SAN
array is projected for 2012 to accommodate growth. The initial SAN is projected to reach the end of its serviceable life in 2014 and is scheduled to
be replaced. As each unit is added, the overall performance of the SAN as a whole is aTeatly increased.
Prior Exp e n d i tures 2011
2012 2013
2014 2015
Total
F --- 8 - 6 — ,60 - 0 - 1 Equipment
25,000
25,000
50,000
Total Total
25,000
25,000
50,000
Prior Funding Sources 2011
2012 2013
2014 2015
Total
86,600 Capital Replacement Fund
Total Total
25,000
25,000
25,000
25,000
50,000
50,000
Budget Impact/Other
support is included for the first year. Software support for the following years would be funded out of 101- 1160 -4300. The hardware
is covered under a three year, next day warranty. Hardware repairs would be done by MIS staff' using a spare kit and replenished by the
Spare parts required after the warranty expiration would be funded out of 101 -1160 -4530.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -084
Project Name Office Furniture
Account #1 400 - 0000 -4703 Account #3
Account #2 Account #4
Description
'rovide for office furniture and chair replacements.
Department
Major Equipment
Contact
Laurie Hokkanen
Type
Unassigned
Useful Life
Total
Category
Administration
Priority
n/a
Total Project Cost: $40,000
Justification
This item will allow items to be replaced as they wear out or needs change.
Prior Expenditures
15,000 Office Equipment
Total
2011 2012
5,000 5,000
2013 2014
5,0 00 5,000
2015 Total
5,000 25,000
Total 5,000 5,000 5,000 5,000 5,000 25,000
Prior
Funding Sources
2011
2012
2013
2014
2015
Total
1 - 5, - 00 - 0 1
capital Replacement Fund
5,000
5,000
5,000
5,000
5,000
25,000
Total
Total
5,000
5,000
5,000
5,000
5,000
25,000
Capital Improvement Program 2011 thru 2015 Department Major Equipment
City of Chanhassen, MN Contact Richard Rice
ject # EQ -086 Type Equipment
Useful Life 20 years
ject Name Equipment for New Fire Station Category Fire
Account #1 Account #3 Priority n/a
Account #2 Account #4
scription Total Project Cost: $1,000,000
project funds new equipment for a new satellite fire station scheduled to be constructed in 2012.
Justification
Response times from the other two fire stations will be unacceptable for the new commercial and residential development that will surround the
212 corridor.
purchases will include a limited warranty and will reduce the annual maintenance and repair costs.
Expenditures 2011
2012 2013
2014 2015 Total
Equipment
1,000,000
1,000,000
Total
Funding Sources 2011
1,000,000
2012 2013
1,000,000
2014 2015 Total
Capital Replacement Fund
GO Bonds
500,000
500,000
500,000
500,000
Total
1,000,000
1,000,000
purchases will include a limited warranty and will reduce the annual maintenance and repair costs.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -091
Project Name Excavator
Account #1 400 - 00004705
Account #2 700 - 7025 -4705
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 100,000 100,000
Department Major Equipment
Contact Paul Oehme
Type Equipment
Useful Life
Category Public Works
Priority n/a
D esc rip tion Total Project Cost: $100,000
this is for the replacement of the City's rubber tire backhoe with a used track excavator. The City's backhoe is a 1989 model that is 21 years old.
Justification
Currently the City is renting an excavator or hiring a contractor to complete excavation projects. These projects include watermain breaks, sewer
pipe repairs and storm sewer pipe improvements. The City's backhoe is not large enough and does not have the necessary features to complete
these tasks. The pay back for purchasing an excavator is estimated at 2 years.
Account #3 701 - 7025 -4705
Account #4 720 - 7025 -4705
Total 100,000 100,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 10,000 10,000
Sewer Utility Fund 30,000 30,000
Surface Water Utility Fund 30,000 30,000
Water Utility Fund 30,000 30,000
Total 100,000 100,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -092
Project Name Fire Pager Replacement
Account #1 4004127 -4705
Account #2
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 12,000 12,000
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life 7 -10 years
Category Fire
Priority n/a
Description Total Project Cost: $12,000
n 2013, the FCC will be making changes to the fire paging frequencies. A consequence of these changes is that older model pagers will become
noperable. The fire department expects that approximately 30 fire pagers will have to be replaced in 2013.
Justification
Each member of the fire department must have a pager in order to respond to calls.
Account #3
Account #4
Total 12,000 12,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 12,000 12,000
Total 12,000 12,000
Budget Impact/Other
Fhere should be no operational impact from this purchase. The current maintenance budget will accommodate for this addition.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -093
Project dame Thermal Cameras
Account #1 400 - 4127 -4705
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life 7 -10 years
Category Fire
Priority n/a
Description Total Project Cost: $30,000
Thermal cameras are critical tools necessary for rescue operations at fire scenes. They are also a vital part of firefighter safety during interior fire
uppression actions.
Justification
Two thermal cameras are 7 -10 years old and should be replaced. These cameras have outdated technology, require frequent repairs and are
becoming unreliable.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 15,000 15,000 30,000
Total 15,000 15,000 30,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 15,000 15,000 30,000
Total 15,000 15,000 30,000
Budget Impact/Other
Chere should be no operational impact from this purchase. The current maintenance budget will accommodate for this addition.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -094
Project Name P ortable Radios
Department
Major Equipment
Contact
Richard Rice
Type
Equipment
Useful Life
7 -10 years
Category
Fire
Account #1 400 -4122 -4705 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $16,000
[be fire department utilizes 800 MHz radios to communicate at fire and rescue scenes. The radios also allow for communication with other
urrounding departments, Carver County Sheriff deputies and various other agencies at the local, state and federal levels.
Justification
To achieve optimum firefighter safety there must be one radio for each firefighter on first due engines. Currently, there are two front line engines
that only have 2 radios which must be shared by 4 firefighters. We need to add two radios each to E11 and E21
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 8,000 8,000 16,000
Total 8,000 8,000 16,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 8,000 8,000 16,000
Total 8,000 8,000 16,000
;et Impact/Other
should be no operational impact from this purchase. The current maintenance budget will accommodate for this addition.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -095
Project Name Skid loader - Parks
Account #1 400 - 4119 -4705 Account #3
Account #2 Account #4
Department Major Equipment
Contact Todd Hoffman
Type Equipment
Useful Life
Category Park
Priority n/a
Total Project Cost: $43,000
2002 753H Bobcat ( #413)
Justification
This piece of equipment is used extensively by the park department for construction projects.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 43,000 43,000
Total 43,000 43,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 43,000 43,000
Total 43,000 43,000
Capital Improvement Program 2011 rhru 2015
City of Chanhassen, MN
Project # EQ -096
Project Name Skid loader Tracks - Parks
Account #1 400 - 4119 -4705 Account #3
Account #2 Account #4
Description
teplacement of rubber tracks for skid loader.
Department
Major Equipment
Contact
Todd Hoffman
Type
Equipment
Useful Life
Category
Park
Priority
n/a
Total Project Cost: $15,000
Justification
Approximately every three years these tracks have to be replaced because of wear.
Prior Expenditures
F --- 7, - 50 - 0 1 Equipment
Total
2011 2012
Total
Prior Funding Sources 2011 2012 2013 2014 2015 Total
7,500 Capital Replacement Fund 7,500 7,500
Total Total 7,500 7,500
2013 2014 2015
7,500
7,500
Total
7,500
7,500
Budget Impact/Other
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015 Department Major Equipment
Contact Paul Oehme
E ect # EQ -097
ect ]name Portable Generator - Utility Department
Account #1 701 - 7025 -4705
Account #2
Description
1984 7.5 khw Generator ( #310)
Type Equipment
Useful Life
Category Utilities
Account #3 Priority n/a
Account #4
Total Project Cost: $17,000
Justification
This generator is used for generation of power for lift stations when power is interrupted. The City maintains 31 lift stations and most of the lift
stations do not have onsite standby generation. Generators for lift stations need to be in good working order when needed.
Impact/Other
Expenditures 2011 2012 2013
2014 2015
Total
Equipment
17,000
17,000
Total
Funding Sources 2011 2012 2013
17,000
2014 2015
17,000
Total
Sewer Utility Fund
17,000
17,000
Total
17,000
17,000
Impact/Other
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Major Equipment
Contact Paul Oehme
F ect # EQ -098
ect Name Loader Mounted Snow Blower
Account #1 400 - 0000 -4705
Account #2
Description
1989 Loader Mounted Snow BI
Type Equipment
Useful Life
Category Public Works
Account #3 Priority n/a
Account #4
Total Project Cost: $141,000
Justification
This snow blower is used by the street and park departments for removal of snow primarily in the downtown and library parking lot. For large
snow events or when snow piles up, snow needs to be removed from the downtown because of lack of storage space.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 141,000 141,000
Total 141,000 141,000
Funding Sources 2011 2 012 2013 2014 2015 Total
Capital Replacement Fund 141,000 141,000
Total 141,000 141,000
Budget Impact/Other
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Major Equipment
Contact Todd Hoffman
Project # EQ -099
Project Name Sweeper - Parks
Account #1 400 - 0000 -4705
Account #2
Description
1999 Tenant Sweeper (#470)
Type Equipment
Useful Life
Category Park
Account #3 Priority n/a
Account #4
Total Project Cost: $33,000
Justification
This piece of equipment is used by the park department to sweep downtown sidewalks, trails, tennis courts and play areas. The sweeper is used in
areas where the larger sweeper can not be used.
Expenditures 2011
2012 2013 2014 2015
Total
Equipment
33,000
33,000
Total
Funding Sources 2011
33,000
2012 2013 2014 2015
33,000
Total
Capital Replacement Fund
33,000
33,000
Total
33,000
33,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -100
Project Name Light Duty Trucks - Parks
Department
Major Equipment
Contact
Todd Hoffman
Type
Vehicles
Useful Life
Category
Park
Account #1 400 - 4120 -4704 Account #3 Priority n/a
Account #2 Account #4
Description I Total Project Cost: $105,000
1995 Chevrolet 3/4 ton pickup with plow ( #414)
1995 Chevrolet 3/4 ton pickup with plow ( #415)
2002 Chevrolet 3/4 ton pickup with plow (#422)
Justification
Expenditures 2011 2012 2013 2014 2015 Total
Vehicles 65,000 40,000 105,000
Total 65,000 40,000 105,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 65,000 40,000 105,000
Total 65,000 40,000 105,000
Budget Impact/Other
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -101
Project Name Skid loader -Utility Department
Account #1 700 - 7025 -4705
Account #2 701 - 7025 -4705
Description
1997 863H Bobcat Skid loader ( #318)
Department
Major Equipment
Contact
Paul Oehme
Type
Equipment
Useful Life
Category
Utilities
Account #3 Priority n/a
Account #4
Total Project Cost: $48,000
Justification
this piece of equipment is used by the utility department for water main breaks and other utility construction projects. It will be 14 years old when
t is replaced.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 48,000 48,000
Total 48,000 48,000
Funding Sources 2011 2012 2013 2014 2015 Total
Sewer Utility Fund 24,000 24,000
Water Utility Fund 24,000 24,000
Total 48,000 48,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -103
Project name Light Weight Vehicle - Park
Account #1 400 - 00004704 Account #3
Account #2 Account #4
Description
1997 Toro 3300 Workman ( #475)
Department Major Equipment
Contact Todd Hoffman
Type Vehicles
Useful Life
Category Park
Priority n/a
Total Project Cost: $22,000
Justification
This vehicle is used for ballfield maintenance and park projects. It will be 17 years old when it is replaced.
Expenditures 2011 2012 2013 2014 2015 Total
Vehicles 22,000 22,000
Total 22,000 22,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 22,000 22,000
Total 22,000 22,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -104
Project name Mower Replacement - Park
Account #1 400 - 00004705 Account #3
Account #2 Account #4
Description
?012 - 1998 Toro 560D (#452)
?014 - 2000 Toro 580D (#453)
?015 - 1996 Toro 325D ( #465)
?015 - 1998 Toro 325D ( #466)
Department Major Equipment
Contact Todd Hoffman
Type Equipment
Useful Life
Category Park
Priority n/a
Total Project Cost: $249,000
Justification
The City currently has 4 high - production grounds mowers. Each machine is used daily during the growing season and needs to be in good
working condition.
Expenditures 2011 2012 2013
2014
2015
Total
Equipment 90,000
95,000
64,000
249,000
Total 90,000
95,000
64,000
249,000
Funding Sources 2011 2012 2013
2014
2015
Total
Capital Replacement Fund 90,000
95,000
64,000
249,000
Total 90,000
95,000
64,000
249,000
Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -105
Project Name Skid loader - Street Department
Account #1 400 - 0000 -4705 Account #3
Account #2 Account #4
Description
?000 863H Bobcat ( #149)
Department Major Equipment
Contact Paul Oehme
Type Equipment
Useful Life
Category Street Equipment
Priority n/a
Total Project Cost: $40,000
Justification
This piece of equipment is used extensively by the street department for construction projects.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 40,000 40,000
Total 40,000 40,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 40,000 40,000
Total 40,000 40,000
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Major Equipment
Contact Todd Hoffman
Project # EQ -106
Pr °ject name Tractor Replacement - Park
30,000
Account #1 400 - 0000 -4705 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $30,000
These tractors are used for field maintenance at park facilities.
2014 - 1997 John Deere 455 ( #468)
2014 - 1999 John Deere 455 ( #469)
Justification
These tractors are used for maintenance and upkeep of baseball fields. The tractors will be 15 and 17 years old before they are replaced.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 30,000 30,000
Total
Type Equipment
Useful Life
Category Park
30,000
Funding Sources 2011 2012 2013 2 014 2015 Total
Capital Replacement Fund 30,000 30,000
Total 30,000 30,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -108
Project Name Springbrook Version 7 Software Upgrade
Account #1 400 - 00004707
Account #2 700 - 7025 -4707
Account #3 701 - 7025 -4707
Account #4 720 - 7025 -4707
Department Major Equipment
Contact Greg Sticha
Type Equipment
Useful Life
Category Finance
Priority n/a
Description Total Project Cost: $25,725
In order to provide enhanced customer and employee services, we are requesting an upgrade to our financial, payroll, human resources and utility
billing software to the newest version.
Justification
This upgrade will allow for a more customer friendly on -line utility billing interface, as well as an upgrade to the payroll and human resources
module that will allow for online time entry and employee human resource services.
Expenditures
2011 2012 2013 2014 2015
T otal
Equipment 25,725 25,725
Total 25,725 25,725
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund
19,294
t9,P94
Sewer Utility Fund
2,573
2,573
Surface Water Utility Fund
1,285
1,285
Water Utility Fund
2,573
2,573
Total
25,725
25,725
Budget Impact/Other
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -109
Project Name B ucket Truck Refurbish
Account #1
Account #2
Account #3
Account #4
Department Major Equipment
Contact Paul Oehme
Type Equipment
Useful Life
Category Street Equipment
Priority n/a
Description Total Project Cost: $30,000
Zefurbish the bucket truck subframe under the bed of the truck. This frame supports the pedestal for the broom. This truck was purchased in 1996
and is not scheduled to be replaced for another 10 years.
Justification
the bed of the truck is rusted and will not pass the annual safety inspection.
Expenditures
2011 2012 2013 2014 2015 Total
Equipment 30,000 30,000
Total 30,000 30,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 30,000 30,000
Total 30,000 30,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -110
Project Name Vactor /Sewer Jetting Truck
Account #1 701 - 7025 -4704
Account #2 700 - 7025 -4704
Account #3
Account #4
Department Major Equipment
Contact Paul Oehme
Type Equipment
Useful Life
Category Utilities
Priority n/a
Description Total Project Cost: $425,000
Phis truck was purchased by the City in 2000 and will be 15 years old when it will be replaced. This truck is used mainly by the utility department
.or sewer jetting, emergency sewer back -ups, watermain breaks and delicate excavations around utilities. This truck has to be reliable and in good
working condition because of the projects and emergency calls it is used for.
Justification
To have the truck as reliable as possible with minimal downtime.
Expenditures
2011 2012 2013 2014 2015 Total
Equipment 425,000 425,000
Total 425,000 425,000
Funding Sources 2011 2012 2013 2014 2015 Total
Sewer Utility Fund 325,000 325,000
Water Utility Fund 100,000 100,000
Total 425,000 425,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -111
Project ]name P aint Striper
Account #1
Account #2
Account #3
Account #4
Description
teplace existing riding paint striper used for painting athletic fields.
Department Major Equipment
Contact Todd Hoffman
Type Equipment
Useful Life
Category Park
Priority n/a
Total Project Cost: $19,000
Justification
The City stripes 15 ballfields and 20 soccer fields, going through 50 fifty gallons of paint a week.
Expenditures
2011 2012 2013 2014 2015 Total
Equipment 19,000 19,000
Total 19,000 19,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 19,000 19,000
Total 19,000 19,000
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Major Equipment
Contact Todd Hoffman
Project # EQ -112
Project Name Hydro Seeder
Type Equipment
Useful Life
Category Park
Account #1 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $5,000
Fhe hydro seeder is used for smaller areas of reseeding and mulching all in one operation.
Justification
Will be used by all departments on smaller lawn restoration projects. It speeds up grass growth and helps stop erosion problems.
Expenditures . 2011 2012 2013 2014 2015 Total
Equipment 5,000 5,000
Total 5,000 5,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 5,000 5,000
Total 5,000 5,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -113
Project Name Refurbish Engine 12 ( #212)
Account #1
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Equipment
Useful Life
Category Fire
Priority n/a
Total Project Cost: $15,000
repair and replace deteriorated body panels and interior components of engine 12.
Justification
Firetruck refurbishment will extend the service life of the unit and delay the need to replace the truck.
Exp e n d i tures 2011 2012 2013 2014 2015 Total
Maintenance 15,000 15,000
Total 15,000 15,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 15,000 15,000
Total 15,000 15,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -114
Project Name Refurbish Engine 11 ( #211)
Account #1
Account #2
Account #3
Account #4
Department Major Equipment
Contact Richard Rice
Type Maintenance
Useful Life
Category Fire
Priority n/a
Description I Total Project Cost: $15,000
Paint, repair and replace deteriorated body panels and interior components of engine 11.
Justification
Firetruck refurbishment will extend the service IN of the unit and delay the need to replace the truck.
Expenditures 2011 2012 2013 2014 2015 Total
Maintenance 15,000 15,000
Total 15,000 15,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Repl acement Fund 15,000 15,000
Total 15,000 15,000
Capital Improvement Program 2011 chru 2015 Department Major Equipment
lvl
City of Chanhassen, Contact Paul Oehme
Project # EQ -115 Type Equipment
Useful Life
Project Name Brush Chipper Category Street Equipment
Account #1 400 - 0000 -4705 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $56,000
This item is to replace the brush and tree limb chipper. This unit will be 16 years old when it is replaced. This unit is used heavily year round by
all the public works departments and needs to be in good working condition.
Justification
To keep equipment in good repair. This purchase is consistent with the vehicle replacement program.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 56,000 56,000
Total 56,000 56,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 56,000 56,000
Total 56,000 56,000
Budget bWact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -116
Project Name Watermain Break Supply Van
Department
Major Equipment
Contact
Paul Oehme
Type
Vehicles
Useful Life
Category
Utilities
Account #1 700 - 7025 -4704 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $20,000
rbis item is to replace the 1973 watermain break supply van. This van is used to transport parts, generator and temporary utility lights to the job
>ite. The van is starting to show signs of needing major repairs and it is advisable to replace the van before major repairs are needed. The
•eplacement for this van will be a used van.
Justification
To avoid costly maintenance and repairs and to keep equipment in good repair.
Expenditures 2011 2012 2013 2014 2015 Total
Vehicles 20,000 20,000
Total 20,000 20,000
Funding Sources 2011 2012 2013 2014 2015 Total
Water Utility Fund 20,000 20,000
Total 20,000 20,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -117
Project Name Berti Rear Mount Mower
Account #1 400 - 0000 -4705 Account #3
Account #2 Account #4
cription
purchase is required to maintain a reliable piece of equipment of mowing.
Department Major Equipment
Contact Todd Hoffman
Type Equipment
Useful Life
Category Park
Priority n/a
Total Project Cost: $10,000
Justification
This tractor mounted attachment was purchased in 2006 and is used to mow the 500 acre park system, which features 5 community parks, 22
neighborhood parks and 55 miles of trails and sidewalks. Mowing is done in the parks and along the trails and sidewalks which is hard on
equipment. Growth in the park system creates additional work for this mower. This equipment purchase is consistent with the equipment
replacement schedule.
Expenditures 2011 2012 2013
2014 2015
Total
Equipment
10,000
10,000
Total
Funding Sources 2011 2012 2013
10,000
2014 2015
10,000
Total
Capital Replacement Fund
10,000
10,000
Total
10,000
10,000
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # EQ -118
Project Name Street Sweeper
Account #1 400 - 0000 -4705
Account #2
Account #3
Account #4
Description
[his purchase is required to maintain a reliable piece of equipment for street sweeping.
136 Elgin Eagle Street Sweeper
Department Major Equipment
Contact Paul Oehme
Type Equipment
Useful Life
Category Street Equipment
Priority n/a
Total Project Cost: $281,000
Justification
[his piece of equipment was purchased in 2003 and provides street sweeping for the 108 miles of local streets within the City of Chanhassen. The
treet department sweeps all the streets at least once a year starting as soon as weather permits in the spring. This piece of equipment is also used
pring through fall to maintain safe streets void of debris that accumulates from storms, construction and general use. Street sweeping is also part
)f the City's MS4 permit requirement. This equipment purchase is consistent with the equipment replacement schedule.
Expenditures 2011 2012 2013 2014 2015 Total
Equipment 281,000 281,000
Total 281,000 281,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 281,000 281,000
Total 281,000 281,000
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Major Equipment
Contact Laurie Hokkanen
Project # EQ -119
Project name Elliptical Machine Replacement - Fire Station #1
Account #1 400 - 4127 -4705 Account #3
Account #2 Account #4
wription
current elliptical machine has reached the end of it's useful life.
Type Equipment
Useful Life
Category Fire
Priority n/a
Total Project Cost: $5,000
Justification
The City will pay 50% and the Fire Relief will pay 50 %.
Budget Impact/Other
'To operational impact from this purchase.
Expenditures
2011 2012
2013 2014 2015 Total
Equipment
5,000
5,000
Total
Funding Sources
5,000
2011 2012
5,000
2013 2014 2015 Total
Capital Replacement Fund
5,000
5,000
Total
5,000
5,000
Budget Impact/Other
'To operational impact from this purchase.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # EQ -120
Project Name Website Improvements
Account #1 210 - 0000 -4706
Account #2
Account #3
Account #4
Department Major Equipment
Contact Laurie Hokkanen
Type Improvement
Useful Life
Category Administration
Priority n/a
Description I Total Project Cost: $20,000
the City website was last updated in 2002. The site receives over 3 million hits per year. City staff recommends improvements to make it more
zser friendly and add additional information.
Justification
The website is used extensively by citizens, businesses and staff.
Expenditures 2011 2012 2013 2014 2015 Total
Planning /Design 20,000 20,000
Total 20,000 20,000
Funding Sources 2011 2012 2013 2014 2015 Total
Cable N Fund 20,000 20,000
Total 20,000 20,000
Capital Improvement Program 2011 thru 2015 Department Municipal Buildings
City of Chanhassen, MN Contact Richard Rice
2,000,000
Account #1 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $2,000,000
This is for the proposed third fire station to be built in the southern area of the city which is currently being developed.
Justification
Response time from the other two stations will be unacceptable for the new commercial and residential development that will surround the 212
Expenditures 2011 2012 2013 2014 2015 Total
Construction 2,000,000 2,000,000
Total
Type Improvement
Useful Life 30 Years
Category Fire
2,000,000
Funding Sources 2011 2012 2013 2014 20 15 Total
GO Bonds 2,0 00,000 2, 000,000
Total 2,000,000 2,000,000
Budget Impact/Other
There will need to be additional hiring for firefighters to staff the third station.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # MB -010
Project Name City Hall Remodel
Account #1 400-4142 -
Account #2
Account #3
Account #4
Department Municipal Buildings
Contact Laurie Hokkanen
Type Improvement
Useful Life
Category Administration
Priority n/a
Total Project Cost: $125,000
and refurbish areas of City Hall that need paint, carpet or storage areas added.
Justification I
Certain areas of City Hall will be in need of some small repair and maintenance needs in 2013.
Expenditures 2011 2012 2013 2014 2015 Total
Maintenance 125,000 125,000
Total 125,000 125,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 125,000 125,000
Total 125,000 125,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # MB -014
Project Name City Hall North Parking Lot
Account #1
Account #2
Account #3
Account #4
Department Municipal Buildings
Contact Paul Oehme
Type Improvement
Useful Life
Category Streets /Highways
Priority n/a
)n Total Project Cost: $280,000
of a 70 stall permeable blacktop parking lot on the north side of City Hall. The Other Agency Contribution will be from the Watershed
Justification
Needed to relieve parking congestion at City Hall.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 280,000 280,000
Total 280,000 280,000
Funding Sources 2011 2012 2013 2014 2015 Total
Other Agency Contribution 140,000 140,000
Surface Water Utility Fund 140,000 140,000
Total 280,000 280,000
Impact/Other
Capital Improvement Program 2011 thru 2015
C of Chanhassen, MN
Project # MB -015
Project name Engineering Copy Area Renovation
Account #1
Account #2
Account #3
Account #4
Department Municipal Buildings
Contact Paul Oehme
Type Improvement
Useful Life
Category Engineering
Priority n/a
Description I Total Project Cost: $10,000
the copy area in the engineering department is used by all the departments at City Hall for making copies and plotting large prints or displays.
this area used to have work stations for summer help, but is now used by the printers. The summer help have to use the engineering conference
•oom as a work station. This is not as productive and makes the engineering conference room unavailable for meetings. The improvements
Manned are to remove the bathrooms in the engineering office area and convert them into a copy and printer room. This area would also be
ttilized for storage of hanging files such as plans and plats.
Just
Will allow for a more efficient work space.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 10,000 10,000
Total 10,000 10,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replace Fund 10,000 10,000
Total 10,000 10,000
Budget Impact/Other
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Municipal Buildings
Contact Paul Oehme
Project # MB -016 Type Improvement
Useful Life
Project Name City Hall Parking Lot Expansion Category Engineering
Account #1 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $70,000
Expansion of the lower east parking lot at City Hall adding ten new spaces.
Justification I
Additional parking capacity is needed for City Hall, senior center, library and park.
Expenditures
2011 2012
2013 2014 2015 Total
Construction
70,000
70,000
Total
Funding Sources
70,000
2011 2012
70,000
2013 2014 2015 Total
Capital Replacement Fund
70,000
70,000
Total
70,000
70,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # MB -017
Project Name Fire Station 1 Repainting and Carpeting
Account #1 Account #3
Account #2 Account #4
Description
tepaint the interior and replace the carpeting in Fire Station 1.
Department
Municipal Buildings
Contact
Richard Rice
Type
Improvement
Useful Life
Category
Fire
Priority
n/a
Total Project Cost: $10,000
Justification
The paint and carpet are approximately 8 - 10 years old and are very worn and deteriorated. The building is open to the public and is used as a
polling place. The appearance of the worn carpet and paint presents a poor image to the public.
Expenditures 2011 2012 2013 2014 2015 Total
Maintenance 10,000 10,000
Total 10,000 10,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 10,000 10,000
Total 10,000 10,000
Budget Impact/Other
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015 Department Park & Trail Improvements
Contact Todd Hoffman
Project # PK &T -042
Project Name Picnic Tables/Park Benches
Account #1 410- 000 -4705
Account #2
D
'urchase of picnic tables and park benches.
Type Improvement
Useful Life 30 Years
Category Park
Account #3 Priority n/a
Account #4
Total Project Cost: $76,000
Justification
New tables and benches are needed annually to replace old stock and meet new needs.
Prior
Expenditures
2011
2012
2013
2014
2015
Total
F --- 26,000 1
Equipment
10,000
10,000
10,000
10,000
10,000
50,000
Total
Prior
Total
Funding Sources
10,000
2011
10,000
2012
10,000
2013
10,000
2014
10,000
2015
50,000
Total
26,000
Total.
Park Dedication Fund
Total
10,000
10,000
10,000
10,000
10,000
10,000
10,000
10,000
10,000
10,000
50,000
50,000
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -043
Project Name Trees
Account #1 410 - 0000 -4701
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life 50 Years
Category Park
Priority n/a
Descrip Total Project Cost: $175,000
Annual tree planting program. This program is proposed to be accelerated to mitigate the affects of Emerald Ash Borer.
Justification
Parklands and other City properties experience tree loss annually, due to storm damage, disease, stress, etc.
Prior Expenditures
2011
2012
2013
2014
2015
Total
Future
F - 4 - 0 — ,00 - 0 1 Land Improvement
25,000
25,000
25,000
25,000
25,000
125,000
10,000
Total
Total 25,000
25,000
25,000
25,000
25,000
125,000
Total
Prior
40,000
Total
Funding Sources 2011 2012 2013 2014 2015 Total Future
Park Dedication Fund 25,000 25,000 25,000 25,000 25,000 125,000 10,000
Total 25,000 25,000 25,000 25,000 25,000 125,000 Total
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -069
Project Name H 41 Pedestrian Underpass /Trail Grant Match
Account #1 410- 0000 -4706
Account #2
rian underpass to Minnewashta Regional Park is a highly sought after improvement. The project also completes a one mile section of trail
to State Highway 41 identified in the City's Comprehensive Plan.
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life 50 Years
Category Park
Priority n/a
Description Total Project Cost: $400,000
�arver County has applied for a federal grant to provide these improvements. The City originally supported the application by pledging a
;125,000 matching contribution. However, project engineering and increased project costs have resulted in the City share of the budget to be re-
!stimated at $400,000.
Justification
Expenditures 2011 2012 2013 2014 2015 Total
Construction 400,000 400,000
Account #3
Account #4
Total 400,000 400,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedication Fund 400,000 400,000
Total 400,000 400,000
and operations costs. Will need to be included in the pavement management program.
Capital Improvement Program 2011 rhru 2015
City of Chanhassen, MN
Project # PK &T -072
Project Name 'Tennis Courts
Account #1 400 - 0000 -4706
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life 25 years
Category Park
Priority n/a
Description Total Project Cost: $200,000
to -build two courts at the Chanhassen Recreation Center, patch and resurface remainder of courts.
Justification
have deliberately limited the number of courts constructed within our system to lower overall maintenance costs associated with tennis courts.
courts we do offer are kept in playable condition through patching and resurfacing on a six to ten year cycle.
Expen ditures 2011 2012 2013 2014 2015 Total
Maintenance 125,000 75,000 200,000
Total 125,000 75,000 200,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement F u n d 125,000 75,000 200,000
Total 125,000 75,000 200,000
Budget
and operations costs.
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015 Department Park & Trail Improvements
Contact Todd Hoffman
Project # PK &T -078
Project dame Pioneer Pass Park Acquisition
Account #1 Account #3
Account #2 Account #4
Description
kcquisition of a neighborhood park in the 2005 MUSA area.
Type Improvement
Useful Life 50 Years
Category Park
Priority n/a
Total Project Cost: $290,000
Justification
This acquisition satisfies a significant void in the City's comprehensive park plan. It will serve neighborhood park needs for over 500 homes
located within 1 /2 mile of its' location.
and operations costs.
Expenditures
2011 2012
2013 2014 2015 Total
Land Acquisition
290,000
290,000
Total
Funding Sources
290,000
2011 2012
290,000
2013 2014 2015 Total
Park Dedication Fund
290,000
290,000
Total
290,000
290,000
and operations costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -079
Project Name Recreation Center Fitness Equipment
Account #1 400 - 4145 -4705
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Equipment
Useful Life
Category Park
Priority n/a
Total Project Cost: $50,000
of new fitness room equipment for the Recreation Center over a five year period.
Justification
The fitness room equipment has not been replaced since the opening of the Recreation Center in 1995. The equipment is now 14 years old with
many pieces nearing or past their useful life expectancy.
Prior Expenditures
2011
2012 2013
2014 2015 Total
30,000 Equipment
10,000
10,000
20,000
Total
Total 10,000
10,000
20,000
Prior Funding Sources
2011
2012 2013
2014 2015 Total
30,000 Capital Replacement Fund
10,000
10,000
20,000
Total Total
10,000
10,000
20,000
Budget
costs will be reduced.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # PK &T -083
Project Name B luff Creek Drive Gap Trail
Account #1 410- 0000 -4710
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type
Improvement
Useful Life
30 Years
Category
Park
Priority
n/a
Description Total Project Cost: $390,000
construction of a 10 foot wide pedestrian trail along the east side of Bluff Creek Drive from south of Pioneer Trail to the Minnesota Valley LRT
.Tail head.
Justification
The Highway 212 improvement project included a pedestrian trail along the first 2,000 feet of Bluff Creek Drive. The resulting trail "gap"
represents a missing link in the City s trail system. Bluff Creek Drive is a difficult stretch of road to negotiate as a pedestrian in the absence of a
Expenditures
2011 2012 2013 2014 2015 Total
Construction 390,000 390,000
Total 390,000 390,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedication Fund 390,000 390,000
Total 390,000 390,000
Budget Impact/Other
Maintenance and operations costs. Will need to be included in the pavement management program.
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015 Department Park & Trail Improvements
Contact Todd Hoffman
Project # PK &T -085
Project Name Disc Golf Course Construction
Account #1 410 - 0000 -4705 Account #3
Account #2 Account #4
Description
:onstruction of a nine hole disc golf course in Bandimere Park.
Type Equipment
Useful Life 30 Years
Category Park
Priority n/a
Total Project Cost: $20,000
Justification
Disc golf is a very popular activity with many teenage and adult participants.
Budget Impact/Other
\nnual maintenance costs of $50041,000.
Expenditures
2011 2012
2013 2014 2015 Total
Equipment
20,000
20,000
Total
Funding Sources
20,000
2011 2012
20,000
2013 2014 2015 Total
Park Dedication Fund
20,000
20,000
Total
20,000
20,000
Budget Impact/Other
\nnual maintenance costs of $50041,000.
Capital Improvement Program 2011 thru 2015 Department Park & Trail Improvements
City of Chanhassen, MN Contact Todd Hoffman
Project # PK &T -093 Type Equipment
Useful Life 10 -15 years
Project Name Skate Park Ramp Replacement & Asphalt Resurfacing Category Park
Account #1 400 - 0000 -4705 Account #3 Priority n/a
Account #2 Account #4
Description I Total Project Cost: $110,000
Replacement of the original skate park equipment with new equipment. The original equipment at the park was purchased in 1999, 2000 and
2003. The asphalt surface in both the skate park and hockey rink is in need of repair.
Justification
The skate park is one of the most highly visited recreation areas in the City. The existing equipment has deteriorated to a level that makes repairs
challenging.
Budget Impact/Other
Expenditures 2011
2012 2013
2014 2015 Total
Maintenance
Equipment
55,000
55,000
55,000
55,000
Total
Funding Sources 2011
110,000
2012 2013
110,000
2014 2015 Total
Capital Replacement Fund
110,000
110,000
Total
110,000
110,000
Budget Impact/Other
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # PK &T -098
Project name P edestrian Trail to Arboretum
Account #1 410 - 0000 -4710
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life
Category Park
Priority n/a
Description Total Project Cost: $250,000
ten foot wide bituminous pedestrian trail located on the south side of State Highway 5, from Century Boulevard to the Minnesota Landscape
krboretum entry road. The total project cost will exceed $250,000, requiring additional funding partners /sources to be identified for the project.
Justification
Completing a pedestrian/bicycle trail route to the Arboretum has been a long range goal for the City. The Arboretum will continue the trail from
their entrance into the property.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 250,000 250,000
Total 250,000 250,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedication Fund 250,000 250,000
Total 250,000 250,000
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # PK &T -099
Project Name Chanhassen Native Preserve Trail, Final Phase
Department
Park & Trail Improvements
Contact
Todd Hoffman
Type
Improvement
Useful Life
Category
Park
Account #1 410 - 0000 -4710 Account #3 Priority n/a
Account #2 Account #4
Description I Total Project Cost: $90,000
900 foot section of eight foot wide bituminous trail, located at the perimeter of Lot 2, Block 1 Arboretum Business Park 7th Addition.
Justification
This section of trail is the final phase of a two mile trail loop around the Chanhassen Native Preserve. The trail project was initiated in 1995.
Expenditures ,
2011 2012 2013 2014 2 015 Total
Construction 90,000 90,000
Total 90,000 90,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedication Fund 90,000 90,000
Total 90,000 90,000
Impact/Other
nce and operation costs. Will need to be included in the pavement management program.
Capital Improvement Program 2011 thru 2015 Department Park & Trail Improvements
City of Chanhassen, NW Contact Todd Hoffman
Project # PK &T -101 Type Improvement
Useful Life
Project Name Lyman Boulevard North Park Acquisition Category Park
Account #1 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $175,000
kcquisition and initial development of a neighborhood park in the area north of Lyman Boulevard, south of Highway 212, east of Quinn Road and
west of the Chanhassen/Eden Prairie border.
Justification
This acquisition satisfies a void in the City's Comprehensive Park Plan. This park will serve approximately 400 homes located within a 1/2 mile
neighborhood park service area.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 175,000 175,000
Total 175,000 175,000
Funding Sourc 2011 2012 2013 2014 2015 Total
Park Dedication F und 175,000 175,000
Total 175,000 175,000
Budget Impact/Other
Capital Improvement rovement Program 2011 thru 2015
Department Park &Trail Improvements
City of Chanhassen, MN Contact Todd Hoffman
Project # PK &T -108 Type Improvement
Useful Life
Project Name TH5 Pedestrian Underpass at Minnewashta Category Park
Account #1 410 - 0000 -4706 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $1,000,000
If the City is successful in securing federal funds, this project will be included in MNDOT's resurfacing project for TH5 scheduled for 2012. The
project includes the installation of a box culvert under TH5 from Minnewashta Parkway to the Landscape Arboretum. This project is consistent
with the Landscape Arboretum's comprehensive plan and the City's trail master plan.
Justification
I To increase safety to pedestrians wanting to access the Landscape Arboretum.
B Impac
daintenance and operation costs.
Expenditures 2011
2012 2013
2014 2015 Total
Construction
1,000,000
1,000,000
Total
Funding Sources 2011
1,000,000
2012 2013
1,000,000
2014 2015 Total
Other Agency Contribution
Park Dedication Fund
920,000
80,000
920,000
80,000
Total
1,000,000
1,000,000
B Impac
daintenance and operation costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -109
Project Name P ioneer Pass Neighborhood Park Development
Account #1
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life
Category Park
Priority n/a
Description Total Project Cost: $350,000
construction of an 8.7 acre neighborhood park in southern Chanhassen. This property is being acquired through a combination of dedication and
.ee purchase as a component of the Pioneer Pass housing development.
Justification
This new park is being acquired and developed to fulfill the neighborhood park needs of a large portion of the 2005 MUSA area. This is the first
new neighborhood park acquisition in the past 15 years.
Expenditures 2011
Constructio
2012 2013 2014 2015 Total
350,000 350,000
Total 350,000 350,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedication Fund 350,000 350,000
Total 350,000 350,000
.t h
operation and maintenance costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -110
Project Name H 41 Trail Extension/Stairway
Account #1
Account #2
Expenditures 2011 2012 2013 2014 2015 Total
Construction 250,000 250,000
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life
Category Park
Priority n/a
Des Total Project Cost: $250,000
:xtension of the Highway 41 trail from Minnetonka Middle School West to the intersection of Highway 7 and Highway 41 and construction of a
>edestrian stairway connecting to Highover Drive.
Justification
The current trail project being undertaken by Carver County in cooperation with the City terminates at Minnetonka Middle School West.
Extending the trail to Highway 7 will allow for a signalized at grade pedestrian crossing.
Account #3
Account #4
Total 250,000 250,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedi Fund 250,000 250,000
Total 250,000 250,000
need to be included in the pavement management program.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -111
Project Name City Hall Landscaping
Account #1 400 - 0000 -4706
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life
Category Park
Priority n/a
D Total Project Cost: $75,000
Jpdating the landscaping around the perimeter of City Hall to blend with City Center Park and the library. Addition of exterior furniture to match
bmiture in City Center Park.
Justification
The landscaping around City Hall is 30 years old and in need of updating.
Expenditures 2011 2012 2013 2014 2015 Total
Maintenance 75,000 75,000
Total 75,000 75,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replac Fund 75,000 75,000
Total 75,000 75,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -112
Project Name Bandimere Park Tree Replacement
Account #1
Account #2
Account #3
Account #4
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life
Category Park
Priority n/a
Description Total Project Cost: $60,000
3andimere park was opened in 2000. Dozens of the trees originally planted have perished due to stress or disease. Also, half of the planting
)riginally scheduled was not completed.
Justification
The presence of healthy shade trees in community parks ensures that visitors can seek relief from the sun.
Expenditures 2011 2012 2013 2014 2015 Total
Maintenance 60,000 60,000
Total 60,000 60,000
Funding Sources 2011 2012 2013 2014 2015 Total
Capital Replacement Fund 30,000 30,000
Park Dedic Fund 30,000 30,000
Total 60,000 60,000
Impact/Other
nce and trimming.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # PK &T -113
Project Name H erman Field Park Half Court Basketball
Account #1
Account #2
Expenditures 2011 2012 2013 2014 2015 Total
C onstruction 10,000 10,000
Description
'. onstruction of a 50' by 50' asphalt half court basketball area with single hoop.
Department Park & Trail Improvements
Contact Todd Hoffman
Type Improvement
Useful Life
Category Park
Priority n/a
Total Project Cost: $10,000
Justification
The park currently lacks amenities for teenagers.
Account #3
Account #4
Total 10,000 10,000
Funding Sources 2011 2012 2013 2014 2015 Total
Park Dedication Fund 10,000 10,000
Total 10,000 10,000
Budget Impact/Other
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015
Department Planning
Contact Kate Aanenson
Project # PL -002
Project Name County Rd 61 (old 212) Corridor Study
Type Improvement
Useful Life 10 -15 years
Category Planning
Account #1 Account #3 Priority n/a
Account #2 Account #4
Descri ption Total Project Cost: $75,000
- orridor design along new County Road 61 and old State Highway 212.
Justification
The specific corridor study is an extension of the comprehensive plan identifying necessary improvements and developing configurements for
parcels along the right of way.
Expenditures 2011 2012 2013 2014 2015 Total
Planning /Design . 75,000 75,000
Total
Funding Sources
75,000
75,000
20 2012 2013 2014 2015 Total
Capital Replacement Fund 75,000 75,000
Total 75,000 75,000
corridor study will identify development potential and specific infrastructure improvements needed for development.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SS -012
Project Name Inflow and Infiltration Abatement
Account #1 701- 7024 -4751 Account #3
Account #2 Account #4
Department Sanitary Sewer Improvements
Contact Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
Utilities
Priority
n/a
Description Total Project Cost: $900,000
[his annual project includes televising, repairs and rehabilitation of existing sanitary sewer. The program also detects and eliminates points of
entry of ground water and surface water into the City sanitary sewer system. Projects have been identified from the 2006 Inflow and Infiltration
teport. The projects were reviewed by Metropolitan Council and approved in lieu of surcharge fees.
I Justification I
City staff has identified numerous older sewer lines that are in need of repair. The City of Chanhassen pays the Metropolitan Council for sewage
treatment. Those payments are based on the amount of flow generated by the City of Chanhassen. Surface water and ground water that makes its
way into the system either through breaks, displaced joints, manhole covers, or private connections to the system increase the amount charged to
the City for sewage disposal and increasing the load on the City's lift stations. Also, MCES would place a surcharge on the annual charge if the
City was not actively trying to reduce the inflow and infiltration problem.
Prior
400,000
Total
Expenditures
2011 2012 2013 2014 2015 Total
Maintenance 200,000 75,000 75,000 75,000 75,000 500,000
Total 200,000 75,000 75,000 75,000 75,000 500,000
Prior Funding So
2011
2012
2013
2014
2015
Total
F -- 4 - 00 — ,00 - 0 1 Sewer Utility Fund
200,000
75,000
75,000
75,000
75,000
500,000
Total
Total 200,000
75,000
75,000
75,000
75,000
500,000
Budget Impact/Other
the efforts may decrease operational costs, MCES fees and emergency call outs. It is also the City's intent to use connection charges to help fund
or those costs. It is the City's belief that as new customers come on line those connection fees should help fund future infiltration problems.
Capital Improvement Program 2011 thru 2015 Department Sanitary Sewer Improvements
City of Chanhassen, MN Contact Paul Oehme
oject # SS -014 Type Improvement
Useful Life Unassigned
oject Name Sanitary Sewer Replacement Category Utilities
Account #1 701 - 7025 -4751 Account #3 Priority n/a
Account #2 Account #4
-scription Total Project Cost: $850,000
placement or rehabilitation of existing sanitary sewer lines in conjunction with the reconstruction of the City street.
Justification
The City considers the condition of the existing utilities in the process to select streets for rehabilitation in an effort to realize cost savings by
consolidating these projects.
Prior Expenditures
250,000 Construction
Total
Prior Funding Sources
2 0 Sewer Utility Fund
Total
2011 2012 2013 2014 2015 Total
300,000
Total 300,000 300,000 600,000
2011 2012 2013 2014 2015 Total
300,000
600,000
300,000 300,000 600,000
Total 300,000 300,000 600,000
iget impamwmer
project will decrease maintenance costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SS -017
Project Name Sanitary Lift Station Rehabilitation Program
Department
Sanitary Sewer Improvements
Contact
Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
Utilities
Account #1 701 - 7025 -4751 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $585,000
the sanitary lift station rehabilitation program is designed to minimize sewer backups and emergency calls due to failed lift station equipment. The
"ity currently maintains 31 lift stations. Many of these lift stations are high service pumps and need frequent servicing. The program will service
>r replace pumps, pipe gallery, and electrical components as needed. The proposed lift stations scheduled for improvements over the next 5 years
u as follows:
2011 - #10 and #11
2012 - # 16 and #21
2013 - #1, #22 and #25
2014 - #23
2015 - #17
Justification
Reduce emergency calls and potential sewer backups.
Prior Expenditures
F - 300 — ,0 - 0 - 0 1 Maintenance
Total
Prior Funding Sources
300,000 Sewer Utility Fund
Total
20 11 2012 2013 2014 2015 Total
90,000 50,000 65,000 40,000 40,000 285,000
Total 90,000 50,000 65,000 40,000 40,000 285,000
2011 2012 2013 2014 2015 Total
90,000 50,000 65,000 40,000 40,000 285,000
Total 90,000 50,000 65,000 40,000 40,000 285,000
Impact/Other
Capital Improvement Program 2011 thru 2015 Department Sanitary Sewer Improvements
City of Chanhassen, MN Contact Paul Oehme
Project # SS -020 Type Improvement
Useful Life
Project Name 2010 MUSA Sanitary Lift Station Category Utilities
Account #1 701- 7025 -4702 Account #3 Priority n/a
Account #2 Account #4
Description I Total Project Cost: $1,900,000
This lift station will be located on Powers Boulevard south of TH 212 to service the future 2010 MUSA and will also be used by future MUSAs
The project needs to be constructed before this area starts to develop and is contingent on when that happens.
Justification
2eyuired for future development of the 2010 MUSA. The cost for this improvement will be assessed to future MUSA areas using connection fees.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 1,900,000 1,900,000
Total 1,900,000 1,900,000
Funding Sources 2011 2012 20 2014 2015 Total
Sewer Utility Fund 1,900,000 1,900,000
Total 1,900,000 1,900,000
Capital Improvement Program 2011 thru 2015 Department Street Improvements
City of Chanhassen, MN Contact Paul Oehme
Project # ST -001 Type Improvement
Useful Life Unassigned
Project Name
West 78th St Streetlights
Category Streets /Highways
Account #1 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $300,000
Install street lights on West 78th Street from the western edge of Lake Ann Park to Century Blvd. Street lights already exist on the section of West
78th Street east of this section of road.
Justification
Visibility will be improved with the installation of street lights.
Expenditures . 2011 2012 2013 2014 2015 Total
Equipment 300,000 300,000
Total 300,000 300,000
Funding Sources 2011 2012 2013 2014 2015 Total
MSA 300,000 300,000
Total 300,000 300,000
iget Impact/Other
project will increase maintenance and electrical usage costs.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # ST -003
Project Name Lyman Boulevard Improvements
Account #1
Account #2
Account #3
Account #4
Department Street Improvements
Contact Paul Oehme
Type Improvement
Useful Life Unassigned
Category Streets /Highways
Priority n/a
Description I Total Project Cost: $17,250,000
The City will need to participate in the reconstruction of Lyman Boulevard between Powers Boulevard and TH 41 based on the master funding
agreement plan for the corridor. The corridor is proposed to be widened and urbanized to accommodate increased traffic volume from TH 212,
new developments in the area and the new Chanhassen High School. Improvements include roadway widening, storm sewer, trail, sanitary sewer
and trunk watermain improvements.
Phase II - 2013 - Improvements are from Audubon south to Powers Blvd
Phase III - 2015 - Improvements are from Galpin Blvd to TH 41
I Justification
I To improve safety and mobility along the corridor.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 8,850,000 8,400,000 17,250,000
Total 8,850,000 8,400,000 17,250,000
Funding Sources 2011
2012 2013 2014
2015 Total
Arterial Collector Dvlpmnt Fee
100,000
100,000
MSA
1,700,000
1,500,000 3,200,000
Other Agency Contribution
6,500,000
6,900,000 13,400,000
Sewer Utility Fund
150,000
150,000
Water Utility Fund
400,000
400,000
Total 8,850,000 8,400,000 17,250,000
[get Impact/Other
project will increase maintenance costs in relation to the increase in City utilities and trails constructed with the project.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # ST -012
Project dame Annual Street Improvement Program
Account #1 601 - xxxx -4751 Account #3
Account #2 Account #4
Department Street Improvements
Contact PaulOehme
Type
Improvement
Useful Life
Unassigned
Category
Streets/Highways
Priority
n/a
Description I Total Project Cost: $9,700,000
knnual project to rehabilitate and reconstruct streets in the City. Current 5 -year plan shows the following neighborhood areas:
tesidential 2011 - Timberwood Drive neighborhood, Saratoga, Santa Vera, Chippewa, Picha and Kerber (S of W 78th), Target lane and W 78th
Street (Powers Blvd to Market Blvd)
2012 - Greenbriar, Fir Tree, Elm Tree, Dogwood, Shore Drive and Maplewood Circle (Reconstruction)
2013 - Greenwood Shores and West 78th Street (Powers to Market)
2014 - Dartmouth Drive and Cypress Drive
2015 - Carver Beach area (south and west of Carver Beach Road)
I Justification
The City uses a Pavement Management System to monitor the condition of the City streets. While proper preventative maintenance extends the
life of the street and is cost effective, a street will eventually deteriorate to a point that further maintenance is no longer cost effective.
Rehabilitation projects extend the life of the street. In cases with utility or poor sub grade needs to be replaced or where streets have deteriorated
to a point where rehabilitation will no longer be practical reconstruction of the street is necessary. A feasibility study is written to consider the
merits of the project and scope of work.
Prior Expenditures
2011
2012
2013
2014
2015
Total
3,200,000 Construction
1,500,000
1,700,000
1,200,000
1,100,000
1,000,000
6,500,000
Total
Total 1,500,000
1,700,000
1,200,000
1,100,000
1,000,000
6,500,000
Prior
Funding Sources
2011
2012 2013 2014 2015 Total
3,200,000
Assessment/Revolving Assess
1,200,000
1,700,000 1,200,000 1,100,000 1,000,000 6,200,000
Total
Street Pavement Management
300,000
300,000
Total
1,500,000
1,700,000 1,200,000 1,100,000 1,000,000 6,500,000
Budget Impact/Other
this project may decrease maintenance costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # ST -017
Project Name TH 101 Corridor Preservation Planning
Account #1
Account #2
Total
Department Street Improvements
Contact Paul Oehme
Type Improvement
Useful Life Unassigned
Category Streets/Highways
Priority n/a
Total Project Cost: $1,180,000
preliminary design, environmental scoping study was completed in 2007. A study to complete the environmental assessment review and
-liminary design from Pioneer Trail to Scott county is proposed for 2011 if other funds become available. No construction funding for
provements have been identified at this time.
Justification
I To improve safety and mobility along the corridor and plan for future growth.
Prior Expenditures
1 8-0 — 10 0 Planning /Design
Total
Total 1,000,000 1,000,000
Prior
Funding Sources
2011 2012 2013
2014 2015 Total
F -7 1 - 80 — ,00 - 01
Other Agency Contribution
920,000
920,000
Total
Street Pavement Management
80,000
80,000
Total
1,000,000
1,000,000
Account #3
Account #4
2011 2012 2013 2014 2015
1,000,000
1,000,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, NIN
Project # ST -018
Project ]Name P avement Management
Account #1 420 - 0000 -4751
Account #2
Account #3
Account #4
Department Street Improvements
Contact Paul Oehme
Type Maintenance
Useful Life 7 -10 years
Category Streets /Highways
Priority n/a
Des Total Project Cost: $2,165,000
[his project will provide maintenance such as crack sealing, seal - coating and pothole patching for City streets. The projects will be determined
umually based on the pavement condition index as generated by the pavement management program.
I Justification
This will provide a centralized funding mechanism that will help reduce the effect on General Fund operating expenditures.
Prior Expenditures
F -- 6 - 65 — ,00 - 0 1 Maintenance
Total
Total 300,000 300,000 300,000 300,000 300,000 1,500,000
Prior
Funding Sources
2011
2012
2013
2014
2015
Total
F -- 6 - 65 — ,00 - 0 - 1
Street Pavement Management
100,000
100,000
100,000
100,000
100,000
500,000
Total
Tax Levy
200,000
200,000
200,000
200,000
200,000
1,000,000
Total
300,000
300,000
300,000
300,000
300,000
1,500,000
2011 2012 2013 2014 2015 Total
300,000 300,000 300,000 300,000 300,000 1,500,000
Budget Impact/Other
these improvements will cost effectively prolong the life of the street so major improvements such as reconstruction projects can be delayed.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # ST -025
Project Name TH5 Improvements - TH41 to Downtown Victoria
Account #1
Account #2
Account #3
Account #4
Department Street Improvements
Contact Paul Oehme
Type Improvement
Useful Life
Category Streets /Highways
Priority n/a
Description I Total Project Cost: $9,029,000
vINDOT is planning to resurface and make improvements to TH5 west of TH41 in 2011. These improvements include resurfacing, shoulder
mprovements, turn lane improvements and intersection improvements at Minnewashta Parkway. The City will be responsible for a small portion
>f the project as it relates to local access and trail and underpass improvements. The City applied for federal funding for trail and underpass
mprovements along with safety improvements at Minnewashta Parkway. The trail underpass local share is estimated at $275,000. It is anticipated
he Landscape Arboretum, City of Victoria and Carver County Parks will help pay for the local share.
Justification
To improve safety and mobility along the corridor.
Expenditures
2011 2012 2013 2014 2015 Total
Construction 9,029,000 9,029,000
Total 9,029,000 9,029,000
Funding Sources 2011 2012 2013 2014 2015 Total
Other Agency Contribution 8,829,000 8,829,000
Park Dedication Fund 80,000 80,000
Street Pavement Management 120,000 120,000
Total 9,029,000 9,029,000
Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # ST -027
Project name TH 101/Pleasant View Rd Intersection & Trail Imp
Account #1
Account #2
Account #3
Account #4
Department Street Improvements
Contact Paul Oehme
Type Improvement
Useful Life
Category Streets /Highways
Priority n/a
Description I Total Project Cost: $765,000
[be City has applied for state funds to make improvements to the intersection of TH 101 and Pleasant View Road. These improvements include
urn lanes, shoulder, drainage and trail improvements. The project would widen the intersection so left turn lanes can be constructed and curb and
,utter on TH 101 would be constructed where necessary. A 10' wide bituminous trail would be constructed on the west side of TH 101 from
'leasant View Road to Town Line Drive. A trail would also be constructed on the north side of Pleasant View Road to connect to an existing trail
Justification
To improve safety, access and mobility in the project area.
Expenditures
2011 2012 2013 2014 2015 Total
Construction 765,000 765,000
Total 765,000 765,000
Funding Sources
2011 2012
2013 2014 2015 Total
Other Agency Contribution
560,000
560,000
Park Dedication Fund
95,000
95,000
Street Pavement Management
90,000
90,000
Surface Water Utility Fund
20,000
20,000
Total
765,000
765,000
B udget Impact/Other
?uture maintenance of trail.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # ST -028
Project Name TH 101 Improvements - Lyman Blvd to Pioneer Trail
Account #1 700 -7025-
Account #2
Account #3
Account #4
Department Street Improvements
Contact Paul Oehme
Type Improvement
Useful Life
Category Streets /Highways
Priority n/a
Description I Total Project Cost: $9,500,000
Phis project is proposed to make improvements on TH 101 from Lyman Blvd to Pioneer Trail. The improvements are proposed to improve safety
and mobility along the corridor. The project is consistent with the 2007 101 corridor scoping study. Federal funds are proposed to be used to pay
br most of the improvements and other state funds are anticipated to pay for the remaining construction costs. The City will need to pay for
Mension of watermain consistent with the 2030 comprehensive plan.
Justification I
To improve safety and mobility on TH 101. The project also plans for growth of the community south of Lyman Blvd.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 9,500,000 9,500,000
Total 9,500,000 9,500,000
Funding Sources 2011 2012 2013 2014 2015 Total
Other Agency Contribution 9,200,000 9,200,000
Water Utility Fund 300,000 300,000
Total 9,500,000 9,500,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # ST -029
Project Name Repaint TH 5 Signals
Account #1
Account #2
Account #3
Account #4
Department Street Improvements
Contact Paul Oehme
Type Maintenance
Useful Life
Category Streets/Highways
Priority n/a
Description I Total Project Cost: $85,000
Ibis project would repaint the signals along TH 5 which are severely rusted. The maintenance agreement the City has with MNDOT and Carver
'ounty states the City is responsible for the minor maintenance of the signals, which includes painting. If these signals are left to rust much
urther, replacement may be warranted which would cost the City more. Seven signals are planned to be repainted on TH 5 from Century Blvd to
Dakota Ave.
Justification
To avoid total replacement due to lack of maintenance and for aesthetic appeal.
Expenditures 2011 2012 2013 2014 2015 Total
Maintenance 85,000 85,000
Total 85,000 85,000
Funding Sources 2011 2012 2013 2014 2015 Total
Street Pavement Manage 85,000 85,000
Total 85,000 85,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SWMP -014
Project Name Property Acquisition
2011 2012 2013 2014
Account #1 720 - 7025 -4701 Account #3 Priority n/a
Account #2 Account #4
Description I Total Project Cost: $650,000
The City will acquire property in accordance with its Comprehensive and Surface Water Management Plans.
I Justification
(Properties within the City must be acquired in order to achieve the goals set forth in the Comprehensive and Surface Water Management Plans.
Prior Expenditures
275,000 Land Acquisition
Total
Total 75,000 75,000 75,000 75,000 75,000 375,000
Prior
Funding Sources
2011
2012
2013
2014
2015
Total
275,000
Surface Water Utility Fund
75,000
75,000
75,000
75,000
75,000
375,000
Total
Total
75,000
75,000
75,000
75,000
75,000
375,000
Department
Surface Water Management
Contact
Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
SWMP
2015 Total
75,000 75,000 75,000 75,000 75,000 375,000
Budget Im
�itywide. No map.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SWMP -019
Project Name Street Improvement Projects -Storm Water Mgmt
Account #1 720 - 70254751
Account #2
Department Surface Water Management
Contact Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
SWMP
Priority
n/a
Description Total Project Cost: $1,250,000
kn annual amount set aside for storm water management infrastructure construction or expansion associated with street improvement projects
mdertaken by the engineering and public works departments.
Justification
Street improvement projects frequently require construction or expansion of storm water management infrastructure in order to comply with
federal, state and local regulations, as well as protecting existing and proposed development adjacent to the projects.
Prior Expenditures
450,000 Construction
Total
Total 400,000 400,000 800,000
Prior Funding Sources 2011
2012 2013
2014 2015
Total
F_W,75 Surface Water Utility Fund
400,000
400,000
800,000
Total Total
400,000
400,000
800,000
Account #3
Account #4
2011 2012 2013
400,000
2014 2015 Total
400,000 800,000
Budget Impact/Other
nventory, inspection and maintenance of new infrastructure will be required. Citywide. No map
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SWMP -024
Project Name B luff Cr. Nat. Resources Mgmt Plan Implementation
Account #1 720 - 7025 -4751 Account #3
Account #2 Account #4
Description
Department Surface Water Management
Contact Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
SWMP
Priority
n/a
Total Project Cost: $925,000
action and restoration as recommended in the Bluff Creek Natural Resource Management Plan. It is unknown how much funding the Riley -
.ory-Bluff Creek Watershed District will contribute to this project. Upon completion of Bluff Creek TMDL, the City will be eligible for
Water Legacy Act Funds. Will assist in achieving compliance with NPDES Phase II MS4 Permit.
Justification
Prior
300,000
Total
ttion of recommendations in 1996 Bluff Creek Natural Resource Management Plan in cooperation with the Riley- Purgatory-Bluff
District. These projects will improve habitat and aesthetics in the Bluff Creek Watershed.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 125,000 125,000 125,000 125,000 125,000 625,000
Total 125,000 125,000 125,000 125,000 125,000 625,000
Prior
Funding Sources
2011
2012
2013
2014
2015
Total
3 - 0 - 0, - 00 - 01
Other Agency Contribution
50,000
50,000
50,000
50,000
50,000
250,000
Total
Surface Water Utility Fund
75,000
75,000
75,000
75,000
75,000
375,000
Total
125,000
125,000
125,000
125,000
125,000
625,000
dget Irnpact/Other
restored areas will require regular maintenance to sustain the native plant communities.
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015 Department Surface Water Management
Contact PaulOehme
Project # SWMP -026
Project name Lake Minnewashta Outlet
Account #1 720 - 7025 -4751- Account #3
Account #2 Account #4
cription
Il a permanent outlet structure at the outlet for Lake Minnewashta.
Type Improvement
Useful Life
Category SWMP
Priority n/a
Total Project Cost: $30,000
Justification
The current outlet is sand and is therefore easily altered. Alterations to the outlet can cause the entire lake to drain down to the outlet elevation.
Expenditures 2011
2012 2013 2014
2015 Total
Construction
30,000
30,000
Total
Funding Sources 2011
30,000
2012 2013 2014
30,000
2015 Total
Surface Water Utility Fund
30,000
30,000
Total
30,000
30,000
Budget Impact/Other
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # SWMP -029
Project ]name Landings Court Storm Water Pond Imp
Account #1 720 - 7025 -4751
Account #2
Expenditures 2011 2012 2013 2014 2015 Total
Construction 70,000 70,000
Department Surface Water Management
Contact Paul Oehme
Type Improvement
Useful Life
Category SWMP
Priority n/a
Des Total Project Cost: $70,000
[his project addresses storm water quantity issues entering Lake Minnewashta. This project was discussed with the City Council during the
3oulder Cove development application. The improvements include ponding and additional storm water piping to the lake.
Justification
To help address erosion and reduce storm water discharge rates into Lake Minnewashta.
Account #3
Account #4
Total 70,000 70,000
Funding Sources 2011 2012 2013 2014 2015 Total
Surface Water Utility Fund 70,000 70,000
Total 70,000 70,000
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # SWMP -032
Project Name Stormwater Pond Improvements
Account #1 720 - 70254751 Account #3
Account #2 Account #4
Description
Department Surface Water Management
Contact Paul Oehme
Type Improvement
Useful Life
Category SWMP
Priority n/a
Total Project Cost: $245,000
This project will provide inspection and cleaning if required of all City stormwater ponds on a rotating four (4) year schedule, to identify any
management needs and perform needed repairs and improvements. This may include sediment removal, placement of blanket, rip -rap or other
erosion control BMP's, vegetation management and assessment, repair and replacement of inlet and outlet structures.
Justification
are over 170 stormwater ponds in the City of Chanhassen, all requiring regular maintenance to assure they function to National Urban
f Program recommendations. This measure has also been identified in Chanhassen's National Pollution Discharge Elimination Municipal
tte Storm Sewer System permit.
Prior Expenditures 2011 2012 2013 2014 2015 Total
85,000 Construction 25,000 35,000 25,000 35,000 40,000 160,000
Total Total 25,000 35,000 25,000 35,000 40,000 160,000
Prior
Funding Sources 2011
2012 2013
2014
2015 Total
85,000
Other Agency Contribution
10,000
10,000
20,000
Total
Surface Water Utility Fund 25,000
25,000 25,000
25,000
40,000 140,000
Total 25,000
35,000 25,000
35,000
40,000 160,000
will require an input of other public works staff hours.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SWMP -035
Project Name LID Implementation Project
Account #1 720 - 7025 -4751 Account #3
Account #2 Account #4
Department Surface Water Management
Contact Paul Oehme
Type Improvement
Useful Life
Category SWMP
Priority n/a
Total Project Cost: $107,500
is project will work with residents within the City of Chanhassen who are willing to construct alternative stormwater best management practices
their property and assist them with the design and construction of these features.
Justification I
Water Resources staff have been approached by several Chanhassen residents and neighborhood groups interested in incorporating these features
into their landscaping plans and looking for guidance and assistance with the design and construction. By identifying and assisting residents with
the design and implementation of alternative stormwater treatment features, the City will be able to address water quality and quantity issues in
fully developed areas where regional ponding is not a practical option. This project will also meet requirements of the City's NPDES permit and
nondegradation plan as well as meeting issues identified in the Second Generation Surface Water Management Plan.
Prior
32,500
Total
Expenditures 2011 2012 2013 2014 2015 Total
Construction 15,000 15,000 15,000 15,000 15,000 75,000
Total 15,000 15,000 15,000 15,000 15,000 75,000
Prior
Funding Sources
2011
2012
2013
2014
2015
Total
F --- 32 - ,50 - 01
Other Agency Contribution
5,000
5,000
5,000
5,000
5,000
25,000
Total
Surface Water Utility Fund
10,000
10,000
10,000
10,000
10,000
50,000
Total 15,000 15,000 15,000 15,000 15,000 75,000
Budget Impact/Other
v4ay require additional notices, mailings and web page communications.
Capital Improvement Program 2011 rhru 2015
City of Chanhassen, MN
Project # SWMP -037
Project Name W ell 13 Parking Lot
Account #1 720 - 7025 -4751
Account #2
Account #3
Account #4
Department Surface Water Management
Contact Paul Oehme
Type Improvement
Useful Life
Category SWMP
Priority n/a
Total Project Cost: $90,000
project would install a pervious pavement parking lot at Well 13 in Chanhassen Estates Park. Other low impact development features may be
porated into the design as well depending upon feasibility of the features.
Justification
Parks and Recreation has noted that there is no available parking within the park nor are there sidewalks to allow for pedestrian access to the park.
This project will meet the requirements of the National Pollution Discharge Elimination System permit, the nondegradation plan and serve as a
demonstration for the practicality of pervious pavement in a parking lot application.
Expenditures
2011 20 12 2013 2014 2015 Total
Construction 90,000 90,000
Total 90,000 90,000
Funding Sources 2011 2012 2013 2014 2015 Total
Other Agency Contribution 30,000 30,000
Surface Water Utility Fund 60,000 60,000
Total 90,000 90,000
i
Budget Impact/Other
Ibis project may require different deicing techniques in the winter months and will need biannual sweepings.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SWMP -039
Project Name Cranes Vineyard Creek
Account #1 720 - 70254751
Account #2
Account #3
Account #4
Department Surface Water Management
Contact Paul Oehme
Type Improvement
Useful Life
Category SWMP
Priority n/a
Description Total Project Cost: $55,000
[his project will stabilize the remaining 750 feet of Cranes Vineyard Creek (aka Curry Farm Creek) and stabilize the delta that has formed at the
)utlet into Christmas Lake.
Justification
Previously a large portion of the Creek was stabilized with utility repair work. The final 750 feet was not addressed at that time due to conflicts
with area landowners. City staff has been in dialogue with the landowners and it appears a compromise may be attainable. This project is
identified in the Second Generation Surface Water Management Plan and will meet the mitigation requirements of the Nondegradation Plan.
Expenditures
Construction
2011 2012 2013 2014 2015 Total
55,000 55,000
Total
55,000
55,000
Funding Sources 2011 2012 2013 2014 2015 Total
Other Agency Contribution 20,000 20,000
Surface Water Utility Fund 35,000 35,000
Total 55,000 55,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # SWMP -042
Project Name Bluff Creek Drive Drainage Improvement Project
Account #1 720 - 7025 -4300
Account #2 720 - 7025 -4706
Account #3
Account #4
Department Surface Water Management
Contact Paul Oehme
Type Improvement
Useful Life
Category SWMP
Priority n/a
Total Project Cost: $140,000
project proposes to work cooperatively with the Parks Department to identify possible stormwater treatment best management practices and
porate them into the design and construction of the trail. This is likely to include ponding within the right -of -way ditches, the installation of
ional storm sewer pipe and structures and possibly the utilization of pervious pavement sections in part of the trial.
Justification
Bluff Creek Drive is a steep road with minimal storm sewer infrastructure and no stormwater treatment. As a result of these conditions, numerous
gullies have developed on private property which are threatening these properties as well as Seminary Fen. Five of the six watershed areas
tributary to Bluff Creek Drive are identified in the Surface Water Management Plan as needing additional ponding and treatment.
Prior Expenditures 2011 2012 2013 2014 2015 Total
20,000 Construction 120,000 120,000
Total Total 120,000 120,000
Prior
Funding Sources 2011
2012 2013 2014 2015
Total
F -- 2 - 0, - 00 - 01
Other Agency Contribution
40,000
40,000
Total.
Surface Water Utility Fund
80,000
80,000
Total
120,000
120,000
B udget Impact/Other
['he BMP's constructed will need long -term maintenance. The cost of the trail may be distributed among two separate funding mechanisms.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # W -015
Project Name Repainting: West 76th St. Water Tower
Account #1 700 - 7025 -4751
Account #2
Account #3
Account #4
Department Water System Improvements
Contact Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
Utilities
Priority
n/a
Description I Total Project Cost: $110,000
Provides for the recoating of the exterior surfaces of the W. 76th St. Water Tower. The water tower is currently not used for water storage because
of the hydraulic changes that were made when the Lake Lucy Road/Powers Boulevard tower was built. The tower is only used as a cell tower. A
feasibility study should be drafted evaluating if it is more cost effective to paint the tower or remove the tower. If the tower is removed, a cell
tower would be needed at the same location or in close proximity.
Justification
This type of infrastructure requires periodic repainting to protect the metal structure so more costly repairs can be avoided. The tower was last
painted approximately 20 years ago.
Expenditures
2011 2012 2013 2014 2015 Total
Construction 110,000 110,000
Total 110,000 110,000
Funding Sources 2011 2012 2013 2014 2015 Total
Water Utility Fund 110,000 110,0
Total 110,000 110,000
Budget Impact/Other
Chis project does not increase operational costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # W -020
Project Name Arboretum Water Main
Account #1 700 - 7025 -4751
Account #2
of a missing piece of water main to provide better looping and system reliability between the Arboretum Water Tower and W 78th
Department Water System Improvements
Contact Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
Utilities
Priority
n/a
Total Project Cost: $220,000
Street.
Justification
Completing this section of water main will complete a missing loop in the system providing improved water quality and pressure as well as
increasing operational reliability. This project was identified in the 2003 Master Water Study.
Expenditures
Account #3
Account #4
2011 2012 2013 2014 201 Total
Construction 220,000 220,000
Total 220,000 220,000
Funding Sources 2011 2012 2013 2014 2015 Total
Water Utility F u n d 220,000 220,000
Total 220,000 220,000
Budget hnpact/Other
rhis project will increase maintenance costs.
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # W -024
Project Name W atermain Replacement
Account #1 700 - 7025 -4751 Account #3
Account #2 Account #4
Description
of existing water main lines in coordination with the reconstruction of the City street.
Department Water System Improvements
Contact Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
Utilities
. Priority
n/a
Total Project Cost: $2,200,000
Justification I
The City considers the condition of the existing utilities in the process to select streets for rehabilitation in an effort to realize cost savings by
consolidating these projects and also to avoid potential cuts in recently improved streets. If significant repairs are necessary to the existing water
main, replacement may be the most cost effective option. Given the highly corrosive soils in the City, water main replacement is an ongoing
project in the City.
Prior
800,000
Total
Expenditures 2011 2012 2013 2014 2015 Total
Construction 700,000 700,000 1,400,000
Total 700,000 700,000 1,400,000
Prior Funding Sources 2011
2012 2013
2014 2015
Total
F -- 800 — ,00 - 0 1 Water Utility Fund
700,000
700,000
1,400,000
Total Total
700,000
700,000
1,400,000
Budget Impact/Other
rhese projects will decrease maintenance costs.
Capital Improvement Program 2011 thru 2015 Department Water System p y Improvements
City of Chanhassen, MN Contact Paul Oehme
Project # W -027 Type Improvement
Useful Life Unassigned
Project Name
Pressure Reducing Station Category Utilities
Account #1 700 - 7025 -4751 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $205,000
Construction of a pressure reducing valve station in the 2005 MUSA area by Pioneer Trail is programmed for 2011 if the development along
Pioneer Trail is constructed. Two pressure reducing stations are programmed for the 2010 MUSA area in 2012 and 2013 if the area is developed
Justification
I Identified in the 2010 Comprehensive Water Supply Plan. Needed to control watermain pressure due to elevation changes for future development
Budge I I
Ibis project will increase maintenance costs.
Expenditures
2011
2012
2013 2014
2015 Total
Construction
65,000
65,000
75,000
205,000
Funding Sources
Total 65,000
2011
65,000
2012
75,000
2013 2014
205,000
2015 Total
Water Utility Fund
65,000
65,000
75,000
205,000
Total 65,000
65,000
75,000
205,000
Budge I I
Ibis project will increase maintenance costs.
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # W -032
Project Name W ell Rehabilitation Program
Department
Water System Improvements
Contact
Paul Oehme
Type
Improvement
Useful Life
Unassigned
Category
Utilities
Account #1 700 - 7025 -4530 Account #3 Priority n/a
Account #2 Account #4
Description I Total Project Cost: $325,000
This program annually inspects and performs regular maintenance of the City's wells. Well pumps are recommended to be serviced every 8 years.
It is recommended that the following pumps and motors be pulled and inspected for wear:
2011 - Well #9
2012 - Well #5 (Abandon)
2013 - Well #10
2014 - Well #11
2015 - Well #12
Justification
Performing regular maintenance will extend the life of well components, reduce emergency calls and have a more reliable water supply system.
Prior Expenditures
7 -96— ,55 -5 1 Maintenance
Total
Prior Funding Sources
905500 Water Utility Fund
Total
2011 2012 2013
45,000 45,000 4500
2014 2015 Total
50,000 50,000 235,000
Total 45,000 45,000 45,000 50,000 50,000 235,000
2011 2012 2013 2014 2015 Total
45,000 45,000 45,000 50,000 50,000 235,000
Total 45,000 45,000 45,000 50,000 50,000 235,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # W -041
Project Name Repaint Lake Lucy Water Stand Pipe
Account #1 700 - 70254751 Account #3
Account #2 Account #4
Description
[his project will repaint the interior and exterior surfaces of the Lake Lucy stand pipe.
Department
Water System Improvements
Contact
Paul Oehme
Type
Improvement
Useful Life
Category
Utilities
Priority
n/a
Total Project Cost: $550,000
Justification
Steel tanks require recoating to protect the metal to prevent more costly repairs. An inspection report will be drafted prior to construction
justifying the work.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 550,000 550,000
Total 550,000 550,000
Funding Sources 2011 2012 2013 2014 2015 Total
Water Utility Fund 550,000 550,000
Total 550,000 550,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015
City of Chanhassen, MN
Project # W -042
Project Name H igh Zone Elevated Storage Tank
Account #1 700 - 7025 -4751
Account #2
Expenditures 2011 2012 2013 2014 2015 Total
Construction 1,90 0,000 1,900,000
Department Water System Improvements
Contact Paul Oehme
Type Improvement
Useful Life
Category Utilities
Priority n/a
Description —1 Total Project Cost: $1,900,000
3ased on current and projected system demands, the high zone should have additional storage capacity. The 2008 water comprehensive plan
recommends a total of 750,000 gallons for storage. Currently, the high zone only has 200,000 gallons of storage. The location of the tank has not
(et been determined, but a few locations were identified in the 2008 comprehensive plan. A tank siting study should be completed to identify the
)est location.
Justification
I To meet current and future water demands for the high zone area and to meet recommended fire flow storage requirements.
Water Utility Fund 1,900,000 1,900,000
Total 1,900,000 1,900,000
Account #3
Account #4
Total 1,900,000 1,900,000
Funding Sources 2011 2012 2013 2014 2015 Total
Budget Impact/Other
Capital Improvement Program 2011 Mru 2015
City of Chanhassen, MN
Project # W -046
Project name Low Zone 1 million gallon Elevated Storage Tank
Account #1 700 - 7025 -4751
Account #2
Account #3
Account #4
Department Water System Improvements
Contact Paul Oehme
Type Improvement
Useful Life
Category Utilities
Priority n/a
Description I Total Project Cost: $2,600,000
Phis tank is needed to meet the peak day irrigation demand and potential emergency demand for the growth of the community. It is needed in the
ow zone pressure area to service the growth area south of Lyman Boulevard. The location for the tank has not been determined, but a few
ocations are feasible or identified in the 2008 water comprehensive plan. This tank is dependent on development. Staff plans to evaluate the need
br this tank annually and adjust the construction date accordingly.
I Justification I
I To meet peak irrigation demand and emergency water demand for the growing community as identified in the 2008 water comprehensive plan.
Expenditures 2011 2012 2013 2014 2015 Total
Construction 2,600,000 2,600,000
Total 2,600,000 2,600,000
Funding Sources 2011 2012 2013 2014 2015 Total
Water Utility Fund 2,600,000 2,600,000
Total 2,600,000 2,600,000
Capital Improvement Program
City of Chanhassen, MN
2011 thru 2015 Department Water System Improvements
Contact Paul Oehme
Project # W -048
Project Name Well #15 Improvements
Type Improvement
Useful Life
Category Utilities
Account #1 700 - 7025 -4751, Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $1,400,000
Phis well is proposed to meet the water needs of the growing community.
Justification
I To meet the growing water needs of the City planned for in the 2008 water comprehensive plan.
Budget Impact/Other
Expenditures 2011
2012 2013 2014
2015 Total
Construction
1,400,000
1,400,000
Total
Funding Sources 2011
1,400,000
2012 2013 2014
1,400,000
2015 Total
Water Utility Fund
1,400,000
1,400,000
Total
1,400,000
1,400,000
Budget Impact/Other
Capital Improvement Program 2011 thru 2015 Department Water System Improvements
1v1
City of Chanhassen, Contact Paul Oehme
Project # W -050 Type Improvement
Useful Life
Project Name High Zone High Service Pump Category Utilities
Account #1 700 - 7025 -4751 Account #3 Priority n/a
Account #2 Account #4
Description Total Project Cost: $120,000
[his project would allow water in the low zone pressure area to be pumped up to the high zone water pressure area.
Justification I
['his project is proposed due to the development growth in the high zone water pressure area. The west water treatment plant will be designed to
Lllow water to be pumped to either the high or low zone area. However, construction of the west water treatment plant is not planned until 2016 at
he earliest. The high service pump will allow treated water into the high zone during the winter months, so potentially 100% of the City could
lave treated water a portion of the year.
Expenditures
2011 2012
2013 2014 2015 Total
Construction
120,000
120,000
Funding Sources
Total 120,000
2011 2012
120,000
2013 2014 2015 Total
Water Utility Fund
120,000
120,000
Total 120,000
120,000
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
700 Water Enterprise Fund Operations
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
REVENUE
2,500,000
CHARGES FOR CURRENT SERVICES
3661
Water Usage
3662
Utility Penalties
3664
Sale of Meters & Parts
3666
Bulk Water Sales
3806
Hook Up Fees
*
TOTAL CURRENT SERVICES
OTHER REVENUE
3801 Interest Earnings
3903 Refunds /Reimbursements
* TOTAL OTHER REVENUE
** TOTAL REVENUE
2,584,114
2,500,000
2,550,000
2.0%
70,370
65,000
65,000
0.0%
31,976
50,000
30,000
(40.0 %)
2,710
-
5,000
100.0%
824,212
500,000
600,000
20.0%
3,513,382
3,115,000
3,250,000
4.3%
62,407
300,000
80,000
(73.3 %)
744
50,000
5,000
(90.0 %)
63,151
350,000
85,000
(75.7 %)
3,576,532
3,465,000
3,335,000
(3.8 %)
REVENUE OVER/(UNDER) EXPENDITURES 2,166,766 2,142,600 1,911,000
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
Water Operations
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC /(DEC)
4010
Salaries & Wages -Reg
358,611
345,000
362,000
4.9%
4011
Overtime -Reg
17,473
25,000
20,000
(20.0 %)
4012
Stand -By Pay
6,408
7,000
7,000
0.0%
4020
Salaries & Wages -Temp
15,170
15,000
16,000
6.7%
4021
Overtime -Temp
119
-
-
0.0%
4030
Contributions - Retirement
53,879
52,000
55,000
5.8%
4040
Contributions - Insurance
48,693
52,000
52,000
0.0%
4050
Workers Compensation
30,456
27,000
32,500
20.4%
4060
Unemployment
3,266
-
-
0.0%
TOTAL PERSONAL SERVICES
534,075
523,000
544,500
4.1%
4120
Supplies- Equipment
9,921
10,000
10,000
0.0%
4130
Supplies- Program
18
100
100
0.0%
4140
Supplies - Vehicles
2,731
6,000
5,000
(16.7 %)
4150
Maintenance Materials
21,348
20,000
20,000
0.0%
4160
Chemicals
117,080
110,000
120,000
9.1%
4170
Motor Fuels & Lubricants
10,329
22,000
15,000
(31.8 %)
4210
Books & Periodicals
67
200
200
0.0%
4240
Uniforms & Clothing
1,876
1,800
2,100
16.7%
4250
Merchandise for Resale
56,768
60,000
100,000
66.7%
4260
Small Tools. & Equipment
2,830
2,800
2,800
0.0%
TOTAL MATERIALS & SUPPLIES
222,966
232,900
275,200
18.2%
4300
Fees, Services
18,141
38,000
30,000
(21.1 %)
4301
Auditing
6,000
6,000
6,000
0.0%
4310
Telephone
8,989
15,000
10,000
(33.3 %)
4320
Utilities
235,557
230,000
238,000
3.5%
4330
Postage
8,389
7,000
6,500
(7.1%)
4340
Printing & Publishing
1,619
4,000
2,000
(50.0 %)
4350
Cleaning & Waste Removal
123
600
300
(50.0 %)
4360
Subscriptions & Memberships
576
400
500
25.0%
4370
Travel & Training
2,493
3,000
3,500
16.7%
4410
Rental- Equipment
1,406
1,500
1,500
0.0%
4440
License & Registration
132
300
300
0.0%
4483
Insurance - General Liability
13,000
13,000
13,000
0.0%
4509
Remit to Other Agencies
78,884
60,000
80,000
33.3%
4510
Repair & Maintenance - Building
5,677
6,000
6,000
0.0%
4520
Repair & Maintenance - Vehicles
241
1,000
1,000
0.0%
4530
Repair & Maintenance -Equip
47,468
20,000
35,000
75.0%
4550
Repair & Maintenance -Water
86,607
75,000
80,000
6.7%
4552
Emergency Repairs -Water
136,572
80,000
90,000
12.5%
4701
Land & Improvements
163
-
-
0.0%
4807
Property Tax Expense
-
5,000
-
(100.0 %)
4933
Sales Tax
689
700
700
0.0%
TOTAL CONTRACTUAL SERVICES
652,725
566,500
604,300
6.7%
**
TOTAL WATER OPERATIONS
1,409,766
1,322,400
1,424,000
7.7%
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
701 Sewer Enterprise Fund Operations
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
REVENUE
CHARGES
3660
3662
3806
3811
FOR CURRENT SERVICES
Sewer Customers
Utility Penalties
Hook -up Fees
Sewer Surcharge
TOTAL CURRENT SERVICES
OTHER REVENUE
3801 Interest Earnings
3903 Refunds /Reimbursements
TOTAL OTHER REVENUE
** TOTAL REVENUE
2,304,128
2,300,000
2,350,000
2.2%
61,458
50,000
60,000
20.0%
308,587
225,000
210,000
(6.7 %)
12,525
25,000
15,000
(40.0 %)
2,686,698
2,600,000
2,635,000
1.3%
28,810 75,000 50,000
1,774 1,000 1,000
30,584 76,000 51,000
2,717,283 2,676,000 2,686,000
(33.3 %)
0.4%
REVENUE OVER/(UNDER) EXPENDITURES 661,118 678,900 522,700
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
Sewer Operations
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC /(DEC)
4010
Salaries & Wages -Reg
234,143
235,000
238,000
1.3%
4011
Overtime -Reg
8,209
10,000
10,000
0.0%
4012
Stand -By Pay
6,408
6,500
6,500
0.0%
4020
Salaries & Wages -Temp
14,245
16,000
16,000
0.0%
4021
Overtime -Temp
158
-
-
0.0%
4030
Contributions - Retirement
35,617
37,000
38,000
2.7%
4040
Contributions - Insurance
30,313
32,000
32,000
0.0%
4050
Workers Compensation
2,889
4,000
4,000
0.0%
4060
Unemployment
3,266
-
-
0.0%
*
TOTAL PERSONAL SERVICES
335,248
340,500
344,500
1.2%
4120
Supplies- Equipment
9,490
6,800
7,500
10.3%
4130
Supplies- Program
116
-
-
0.0%
4140
Supplies- Vehicles
968
1,000
1,000
0.0%
4150
Maintenance Materials
11,035
4,000
8,000
100.0%
4160
Chemicals
612
3,000
3,000
0.0%
4170
Motor Fuels & Lubricants
8,961
20,000
15,000
(25.0 %)
4210
Books & Periodicals
20
200
200
0.0%
4240
Uniforms & Clothing
1,694
2,000
2,000
0.0%
4260
Small Tools & Equipment
2,923
2,800
2,800
0.0%
*
TOTAL MATERIALS & SUPPLIES
35,819
39,800
39,500
(0.8 %)
4300
Fees, Services
11,987
30,000
25,000
(16.7 %)
4301
Auditing
6,000
6,000
6,000
0.0%
4310
Telephone
6,656
7,000
7,000
0.0%
4320
Utilities
74,076
70,000
78,000
11.4%
4330
Postage
5,911
7,000
7,000
0.0%
4340
Printing & Publishing
1,619
2,000
1,800
(10.0 %)
4350
Cleaning & Waste Removal
-
200
200
0.0%
4360
Subscriptions & Memberships
400
400
400
0.0%
4370
Travel & Training
3,392
3,000
3,200
6.7%
4410
Rental- Equipment
-
1,500
500
(66.7 %)
4440
License & Registration
48
200
200
0.0%
4483
Insurance - General Liability
13,000
13,000
13,000
0.0%
4509
Remit to Other Agencies
1,311,819
1,370,000
1,520,000
10.9%
4510
Repair & Maintenance - Building
4,458
3,500
4,000
14.3%
4520
Repair & Maintenance - Vehicles
227
1,000
1,000
0.0%
4530
Repair & Maintenance -Equip
13,251
12,000
12,000
0.0%
4551
Repair & Maintenance -Sewer
73,278
75,000
75,000
0.0%
4553
Emergency Repairs
158,297
15,000
25,000
66.7%
4701
Land & Improvements
163
-
-
0.0%
4933
Sales Tax
517
-
-
0.0%
*
TOTAL CONTRACTUAL SERVICES
1,685,097
1,616,800
1,779,300
10.1%
**
TOTAL SEWER OPERATIONS
2,056,164
1,997,100
2,163,300
8.3%
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
720 Surface Water Management Fund
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
REVENUE
470,000
PERMITS
10.6%
3328
Wetland Alteration
14,000
TOTAL PERMITS
CHARGES FOR CURRENT SERVICES
3660
Sewer Customers
3662
Utility Penalties
3806
Connection Charges
(13.2 %)
TOTAL CURRENT SERVICES
OTHER REVENUE
3801
Interest Earnings
3903
Refunds and Reimbursements
TOTAL OTHER REVENUE
"
TOTAL REVENUE
REVENUE OVER/(UNDER) EXPENDITURES
226 1,000 300 (70.0 %)
226 1,000 300 (70.0 %)
500,576
470,000
520,000
10.6%
12,185
10,000
14,000
40.0%
24,965
250,000
100,000
(60.0 %)
537,726
730,000
634,000
(13.2 %)
23,444 150,000
70 -
23,514 150,000
561,466 881,000
270,204 474,800
60,000 (60.0 %)
- 0.0%
60,000 (60.0 %)
694,300 (21.2 %)
309,000
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
surrace water management Tuna
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
4010
Salaries & Wages -Reg
123,527
126,200
129,200
2.4%
4020
Salaries & Wages -Temp
-
10,000
8,000
(20.0 %)
4030
Contributions - Retirement
16,968
18,200
18,200
0.0%
4040
Contributions - Insurance
18,166
19,000
21,000
10.5%
4050
Workers Compensation
326
900
500
(44.4 %)
*
TOTAL PERSONAL SERVICES
158,986
174,300
176,900
1.5%
4120
Supplies- Equipment
939
5,000
2,000
(60.0 %)
4130
Supplies- Program
5,857
5,000
7,500
50.0%
4150
Maintenance Materials
13,481
25,000
10,000
(60.0 %)
4210
Books and Periodicals
-
100
100
0.0%
4240
Uniforms & Clothing
-
100
100
0.0%
*
TOTAL MATERIALS & SUPPLIES
20,277
35,200
19,700
(44.0 %)
4300
Fees, Services
99,379
175,000
175,000
0.0%
4301
Auditing
8,000
8,000
8,000
0.0%
4310
Telephone and Communications
491
600
600
0.0%
4340
Printing & Publishing
25
1,000
100
(90.0 %)
4360
Subscriptions & Memberships
1,060
1,800
1,200
(33.3 %)
4370
Travel & Training
1,427
4,500
2,000
(55.6 %)
4380
Mileage
-
300
300
0.0%
4410
Rental- Equipment
-
4,000
-
(100.0 %)
4483
Insurance - General Liability
1,500
1,500
1,500
0.0%
4933
Sales Tax
117
-
-
*
TOTAL CONTRACTUAL SERVICES
111,998
196,700
188,700
(4.1 %)
** TOTAL EXPENDITURES 291,262 406,200 385,300 (5.1%)
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
720 Surface Water Management Fund
7201 Recycling
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
REVENUE
INTERGOVERNMENTAL REVENUE
3520 Grants - County
4,270
1,500
4,000
166.7%
TOTAL INTERGOVERNMENTAL REV
4,270
1,500
4,000
166.7%
CHARGES FOR CURRENT SERVICES
3650 Sale of Recyclables
12
-
-
0.0%
TOTAL CURRENT SERVICES
12
-
-
0.0%
TOTAL REVENUE
4,282
1,500
4,000
166.7%
REVENUE OVER/(UNDER) EXPENDITURES
(33,902)
(50,800)
(36,900)
CITY OF CHANHASSEN
2011 BUDGET
720 Surface Water Management Fund
7201 Recycling
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
4010
Salaries & Wages -Reg
21,926
21,800
22,300
2.3%
4030
Contributions - Retirement
2,990
3,200
3,200
0.0%
4040
Contributions - Insurance
4,804
4,900
5,100
4.1%
4050
Workers Compensation
67
200
100
(50.0 %)
"
TOTAL PERSONAL SERVICES
29,787
30,100
30,700
2.0%
4130
Supplies- Program
1,467
4,500
2,000
(55.6 %)
4210
Books and Periodicals
-
100
100
0.0%
4260
Small Tools.& Equipment
-
100
100
0.0%
TOTAL MATERIALS & SUPPLIES
1,467
4,700
2,200
(53.2 %)
4300
Fees, Services
5,416
15,000
6,000
(60.0 %)
4340
Printing & Publishing
1,340
1,700
1,700
0.0%
4350
Cleaning and Waste Removal
-
500
-
(100.0 %)
4360
Subscriptions & Memberships
174
200
200
0.0%
4370
Travel & Training
-
100
100
0.0%
TOTAL CONTRACTUAL SERVICES
6,929
17,500
8,000
(54.3 %)
** TOTAL RECYCLING 38,184 52,300 40,900 (21.8%
CITY OF CHANHASSEN
2011 BUDGET
ENTERPRISE FUNDS
720 Environmental Protection
7202 Reforestation
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
REVENUE
INTERGOVERNMENTAL REVENUE
3533 Grants -Other
TOTAL INTERGOVERNMENTAL REV
CHARGES FOR CURRENT SERVICES
3640 Community Garden Plot Rental
3650 Sale of Recyclables
3903 Refunds and Reimbursements
TOTAL CURRENT SERVICES
** TOTAL REVENUE
REVENUE OVER/(UNDER) EXPENDITURES
0.0%
0.0%
1,855 1,500 1,800 20.0%
2,044 1,500 2,000 33.3%
3,824 - - 0.0%
7,723 3,000 3,800 26.7%
7,723 3,000 3,800 26.7%
(61,594) (77,200) (72,800)
CITY OF CHANHASSEN
2011 BUDGET
720 Surface Water Management Fund
7202 Reforestation
2010 to
2009 2010 2011 2011
ACCOUNT DESCRIPTION ACTUAL BUDGET BUDGET % INC/(DEC)
4010
Salaries & Wages -Reg
4030
Contributions - Retirement
4040
Contributions- Insurance
4050
Workers Compensation
4,804
TOTAL PERSONAL SERVICES
4130
Supplies- Program
67
TOTAL MATERIALS & SUPPLIES
4300
Fees, Services
4320
Utilities /Com.munity Garden
4340
Printing & Publishing
4360
Subscriptions & Memberships
4370
Travel & Training
4933
Sales Tax
5,000
TOTAL CONTRACTUAL SERVICES
21,926
21,800
22,300
2.3%
2,990
3,200
3,200
0.0%
4,804
4,900
5,100
4.1%
67
200
100
(50.0 %)
29,786
30,100
30,700
2.0%
4,752
6,000
5,000
(16.7 %)
4,752
6,000
5,000
(16.7 %)
32,470
40,000
38,000
(5.0 %)
1,554
1,900
1,600
(15.8 %)
-
1,100
500
(54.5 %)
207
100
200
100.0%
485
1,000
600
(40.0 %)
61
-
-
0.0%
34,778
44,100
40,900
(7.3 %)
** TOTAL REFORESTATION 69,317 80,200 76,600 (4.5 %)
"To provide a safe, reliable efficient and
cost effective water operation system to
meet the needs of the residents and
business now and into the future."
Services Provided /Outcomes
Water Operations, 700
Staff: 8 Employees
Major Expenditures
Chemicals for water operations
Utility to run operations
Major Responsibilities include:
Meet potable water production demands, treatment of water and operate
distribution system efficiently.
Repair watermain breaks.
Routine maintenance of system.
Annual Hydrant Flushing operation.
Utility Locates for City owned infrastructure — approx. 3,400 annually
Confirm water meets MDH requirements.
Test between 1,300 to 1,400 water samples annually
Water Operations - 700
Personal
Service
e ce
2010 $523,000 $232,900 $566,500 $1,322,400
Percent 4.1%
Change
18.2%
6.7%
7.7%
Significant Changes:
• Decrease in overtime pay & increase in workers Comp.
• Decrease in fuel for utility vehicles and increase in merchandise for resale
• Decrease in fees for services and phones and increase in other agencies permit
fees and watermain breaks budget.
$275,200 $604,300 $1,424,000
Sewer Operations 701
"To provide an efficient, well maintained
and cost effective sewer collection system
system to meet the needs of a growing
Community. "
Services Provided /Outcomes
Sewer Operations, 701
• Staff: 8Employees —Same as Water Operations Staff
Significant contracts
Met Council Sewer Treatment - $1,520,000
Utility cost to run operations — $78,000
Major Responsibilities Include:
Annual sewer Jetting /Cleaning Operations
Ongoing maintenance and inspection of 31 lift stations
Implementation of I &I reduction plan
Emergency Sewer Repairs
Sewer Operations - 701
2010
Percent
Change
$340
1.2%
• :11
$1,616,800
10.1%
$1,997,100
Significant Changes:
• Decrease in motor fuel
• Decrease in Fees for service
• Increase in Metropolitan Council payment (10.9 %)
8.3%
2011 $344,500 $39,500 $1,779,300 $2,163,300
to
Surface " ater anagement 720
Also Includes Recycling &Reforestation
"Dedicated to maintaining and improving surface water
quality and the protection of property through the
maintenance and expansion of the storm water drainage
and treatment system in a cost effective manner while
assuring compliance with EPA rules for Phase II MS4s."
Services Provided /Outcomes
Surface Water Management, Recycling Reforestation 720
• Staff: 3 Employees including Forester
• Major Responsibilities
O & M of existing storm water infrastructure and expansion as needed.
Design and implantation of projects to improve water quality.
Assure City compliance with Federal, State and local water quality rules.
Address resident drainage, flooding, erosion, etc concerns.
Inspect all active construction sites for compliance with NPDES permits.
Review development/building plans for proper surface water management and
compliance with City Code.
Performance of diseased tree inspections, site inspections for compliance with
landscape plans, manages escrow funds.
Administer Wetland Conservation Act.
Community outreach and education initiatives.
Administer Recycling program
Waterwise Program
Administer Reforestation program including buckthorn removal & boulevard tree
program
Surface Water — 720
Personal Total
Service Su pplies Services • . -
2011 $238,300 $26,900 $237,600 $502,800
2010 $234,500 $45,900 $258,300 $538,700
Percent 1.62% -58.61% -8.71% -7.14%
Change
Significant Changes:
•Reduction in Maintenance Materials, Supplies and Equipment and
Travel & Training