1g. Lake Lucy Road: Change Order No. 1.CITY OF 1-� CHANHASSEN 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317 (612) 937 -1900 • FAX (612) 937 -5739 MEMORANDUM TO: Don Ashworth, City Manager FROM: Charles Folch, Director of Public Works I / DATE: April 4, 1997 l � Action by City Administr. Endorsed Modified Rejected Date--- Date Submitted to Commission Date submitted to Council q-fit :7 — SUBJ: Approve Change Order No. 1 for Lake Lucy Road - Project No. 92 -12 The City Council officially ordered the Lake Lucy Road Improvement Project back in June, 1994. The project consisted of the construction of Lake Lucy Road from Trunk Highway 41 to 1,500 feet east to an urban roadway section with bituminous surfacing, concrete curb and gutter, storm sewer, sanitary sewer and watermain. The construction contract for this improvement project was awarded in October, 1994 to Northdale Contracting in the amount of $530,154.17. The actual construction of the project began in the late spring of 1995 and was substantially completed by that fall. The only work that remained (except for minor punchlist work) was the paving of the final bituminous wearing course which was placed in 1996. The assessment roll for this improvement project was formally adopted by the City Council on October 9, 1995. Based on the above project history synopsis, one might wonder why the project contract has not yet been finaled out. The answer lies due in part to a number of circumstances such as a change in key project staff personnel with the engineering consulting firm at the end of the project, a project subcontractor who went out of business prior to completing his punchlist work, and general delay time between the general contractor and the engineering consultant in coordinating completing final contract documents. In the past two months, there has been a significant effort put forth between the consultant engineer and the general contractor to complete the necessary contract documents and paperwork. This effort has resulted in the one, only and final contract change order which is attached to this report. The consultant engineer has provided a very brief explanation of each specific change order item. A large portion ($15,610 or 28 %) of the overall change order amount resulted from increasing the length for the right turn lane, acceleration lane, and bypass lane constructed along Trunk Highway 41 at the Lake Lucy Road Intersection. These were MnDOT plan review requirements (which Don Ashworth April 4, 1997 Page 2 became known after the contract bid) and were a requirements of the MnDOT access permit connection to Trunk Highway 41. Another major increase ($13,187 or 24 %) was the result of soil correction work. Other changes include quantity underestimates and /or typos in the plans or bid form proposal ($8,026 or 14.5%), watermain changes to facilitate new Well No. 7 ($5,836 or. 10.5 %) which was not known about in 1995, an extra set of utility services to Outlot C, Brenden Pond ($3,922 or 7 %) (cost was assessed) and extra quantity work such as sodding, retaining walls, etc. to accommodate adjacent property owners. In total, the change order amounts to $55,264.54. Since the project was substantially completed by the fall of 1995 when the assessment hearing was held, these extra work items and corresponding cost increase in contract amount was known about and taken into account on the assessment roll. In addition, the revised contract amount, with this approved change order and corresponding overall project cost, will still be approximately 5% below the original bonding amount for the project. What this means is that even though change order is occurring well after the fact, the numbers were taken into account with the assessment roll and no additional bond funding is required. With the approval of this change order and the contractor completing a few remaining punch list items, the contract documents can be finaled. It is therefore recommended that the City Council approve Change Order No. 1 in the $55,264.54 for the Lake Lucy Road Improvement Project No. 92 -12 yielding a revised contract amount of $585,418.71. Jms Attachment: 1. Location map. 2. Change Order No. 1. \bfs1 \vo12\en&har1esNcc\1ake lucy road co no. Ldoc /•[,'� / DANIEL CLARK N 89'01'05" W O q � i� AN JEROME CARLSON d C d i N 56.55, o w 10 17 BLOCK ONE 2 7 1 \ \ \ 5 \ I SAM k NANCY MANCINI) , 1 S 89'01'05" E 270.40' 0 60 70 S OUTLOT B " 6 Z U w TOTAL CURVE DATA i n Q 9426'40' O M R = 410.00' T 443.10• 00 L . 675.83' / 4 \ T6 1 137.56' 18 IIJ 19 e JJJ O PC TO PLAT LINE PLAT LINE TO PT - L - � 15'28}1 p . N 89'32'21' w ' " N / JB'SB'09' R 410..' R _ 32'11'4 00' R 41000 7 _ 1J f a R= 110.00' �.9 T= 55.71' T} }7.79' / y N Q T 120.27' \ L 110.74' L. 565.09' I O 3 L = 233.97' �� \ / '� _ p i / x90 J` 1 / F' O O O w �� 5 Wa 4 3 P` s9 ' CK� ON c m/ Q r r 3 P° >� 0 9 ss N •I r r moo, v 5 \ TOTAL CU DATA L L = 43'09 *09 1 .14. JEROME CARLSON \ L(UCY r r .. R 4 14' L = 308.80' PC TO CENTERLINE CENTERUNE TO PT OUTLOT C , 0 = 17'41'46' 0 - 25'2728- R 3.82' ' R 410.00' T 6 }.82' T = 52.61' OUTLOT D L = 12663' L - 182.17' — _ — — — 2.10' 604.57 S 01'03'05 E 1068.97' u.a 7 ti S 0712'49' W S 89'32'24" E _ _ _ _ -• - '- - r 6w1n fine of ine NW 114 01 the SW 1/4 .1 Sec. 3, Twp. 1166 Rnge, 23 JEROME CARLSON tNC1NrrR ctnunuuaN " 00.40 R(N:]NS 5.11 6[PI,94 N'II IIAM R. ENGCLNARDI ASSOC. INC. n LAKE LUCY ROAD CONSUL 'INC ENGINEER$ 110) u.)[11x1C bO EC . -K •EE —11 1111[ ulW) O1ESe.. uiNN[SOIr. ]SITE / � -- ROADWAY o. K nt0 N0L ALIGNMENT DATA S, A. R NO. 194 -101 -07 Sheet No, 5 Of 19 Sheets ., THU 14:39 FAX 612 937 9152 CITY CHAN --- - - -_ -- 10002 f CITY OF CHANHASSEN CHANGE ORDER NO. 1 CHANGE ORDER DATE APRIL 4,1997 SHEET 1 OF 4 Quantity( PROJECT NO. Increase Amount Decrease Amount 194 - 101 - 07 CONTRACTOR NORTHDALE CONSTRUCTION CO. INC. PROJECT NAME UTILITY AND STRE ET i ADDRESS 14450 NORTHDALE BLV TYPE OF WORK ROGERS MN. UTILITY AND STREET IMPROVEMENTS ORIGINAL CONTRACT AMOUNT $530,154.17 Spec. No. Item No. Item of Work Unit Original± Previous Change Quantit Quantity( Unit Price Increase Amount Decrease Amount APRIL 4 1997 SEE ATTACHED SHEETS Not I of rPACA nr nP_nrBaSe to Date $ 55. 264. 54 Totals 55,264. Due to this change, the contract time: C a: is increased /decreased by n/a working days. is increased /decreased by _IlZa calendar days. ❑ b: is not changed. o c: may be revised if the work affects /affected the controlling operation nChl1RARA=K!nr -h lA++nnh orirli+innal chootc if nanaaaarv) Cnr L/'1IIMI %J in w— — - -- - - - - -- -- - - - SEE ATTACHED SHEETS CO SIGNAT Et , w DATE APRIL 4, 1997 C DATE APRIL 4, 1997 S TOR IGNATURE DATE APRIL 4 1997 ENGELHARDT & ASSOCIATES CHANGE ORDER # 1 ITEM # DESCRIPTION UNIT PRICE QUANTITY TOTAL COST 1 CLASS 5100% CRUSHED $8.01 1646.38 $13,187.50 REASON: CLASS 5 AGGREGATE USED TO STABILIZE ROADWAY SODDING USED ON TOP OF THE FROM STATION 0+00 TO 9 +75 2 CLASS 5 SHOULDERING $11.50 49 $563.50 REASON: CHANGE TO COMPLY WITH MNDOT PERMIT 3 BITUMINOUS BASE $22.85 189.96 $4,340.59 REASON: CHANGE TO COMPLY WITH MNDOT PERMIT $794.88 4 BITUMINOUS BINDER $22.85 42.95 $981.41 REASON: CHANGE TO COMPLY WITH MNDOT PERMIT 5 BITUMINOUS WEAR $27.35 153.63 $4,201.78 REASON: CHANGE TO COMPLY WITH MNDOT PERMIT 6 3" BITUMINOUS DRIVEWAY $11.00 91 $1,001.00 REASON: EXTRA DRIVEWAY NEEDED TO BE RE- $2,112.25 PLACED DUE TO THE LOCATION OF THE TYPO - GRAPHICIAL ERROR ON THE EXISTING WATERMAIN ON T.H. 41 7 RETAINING WALL $13.26 77 $1,021.02 REASON: LENGTHING OF WALL DUE TO PROTECT THE EXISTING SLOPE 6" SERVICE PIPE $9.50 8 SODDING $1.70 725 $1,232.50 REASON: SODDING USED ON TOP OF THE RETAINING WALL TO PREVENT EROSION 9 EXTRA DEPTH MANHOLE $72.00 11.04 $794.88 REASON: FIELD CHANGE DUE TO ELEVATION OF THE EXISTING M.W.C.C. MANHOLE 10 OUTSIDE DROP $85.00 24.85 $2,112.25 REASON: TYPO - GRAPHICIAL ERROR ON THE ORIGINAL BID FORM 11 6" SERVICE PIPE $9.50 71 $674.50 REASON: DEVELOPER REQUEST TO SERVE A LOT__.. NOT IN THE ORIGINAL PLAN - OUTLOT C 12 12" BUTTERFLY VALVE $755.00 1 $755.00 REASON: EXTRA VALVE TO NEW PUMP HOUSE 13 6'° GATE VALVE $400.00 REASON: FOR ADDED HYDRANT ALONG T.H. 41 FOR FUTURE DEVELOPMENT TO DIMINISH EXISTING RESIDENT INCONVIENCE 14 HYDRANT $1,340.00 REASON: CHANGE TO COMPLY WITH MNDOT PERMIT 15 FITTINGS $1.39 REASON: FIELD COUNT VS. ESTIMATED QUANTITY 16 CASING PIPE $90.00 REASON: EXTRA LENGTH DUE TO RELOCATION OF CROSSING TO SAVE TREES ON THE WEST SIDE OF T.H. 41 AT LAKE LUCY RD. 17 1" COPPER PIPE $9.50 REASON: DEVELOPER REQUEST TO SERVE A LOT NOT IN THE ORIGINAL PLAN - OUTLOT C 18 15" R.C.P. STORM SEWER $23.75 REASON: ACTUAL INSTALLATION - SHEET 15 VS. ORIGINAL BID FORM 19 3 CABLE GUARD RAIL $18.00 REASON: CHANGE TO COMPLY WITH MNDOT PERMIT 20 4" SOLID YELLOW DOUBLE LINE $0.35 REASON: CHANGE IN CITY DETAIL FOR STRIPING LAYOUT AFTER THE BID WAS LET 21 12" D.I.P. WATERMAIN $24.55 REASON: FIELD MEASURE VS. ESTIMATED QUANTITY NOTE: 45' TO NEW PUMP HOUSE 22 EXTRA SERVICE TO OUTLOT C $2,799.32 REASON: EXTRA SERVICE REQUEST BY DEVELOPER EXTRA COST DUE TO THE NEED TO HOOK - UP TO THE EXISTING SEWER MAIN THAT WAS 25' DEEP 23 HYDRANT EXTENSIONS $375.00 REASON: EXTENSION NEEDED ON 1ST HYDRANT ON T.H. 41 DUE TO DEPTH OF THE WATERMAIN 24 LOCATE EXISTING WATERMAIN $1,535.00 REASON: EXTRA TIME SPENT SEARCHING FOR THE EXISTING WATERMAIN 2 $800.00 1 $1,340.00 1820 $2,529.80 7 $630.00 42 $399.00 30 $712.50 306.8 $5,522.40 2136 $747.60 207 $5,081.85 1 $2,799.32 1 $375.00 1 $1,535.00 r 'r :ASON : FIELD MEASURE VS. ESTIMATED QUANTITY TOTAL $55,264.54 25 SEEDING W/ 4" TOPSOIL $900.00 0.8 $720.00 SON: FIELD MEASURE VS. ESTIMATED QUANTITY 26 MULCH $185.00 1.6 $296.00 ASON : FIELD MEASURE VS. ESTIMATED QUANTITY 27 8" P.V.C. SDR 35 20'- 22' $28.00 10 $280.00 ASON : FIELD MEASURE VS. ESTIMATED QUANTITY 28 8° P.V.C. SDR 35 22' - 24' $28.00 3 $84.00 ASON : FIELD MEASURE VS. ESTIMATED QUANTITY 29 8" P.V.C. SDR 26 30' - 32' $32.00 10 $320.00 :SON: FIELD MEASURE VS. ESTIMATED QUANTITY 30 6" SERVICE WYES $49.00 1 $49.00 AASON : SERVICE REQUESTED BY DEVELOPER TO OUTLOT C 31 B 618 CURB & GUTTER $5.21 34 $177.14 :ASON : FIELD MEASURE VS. ESTIMATED QUANTITY TOTAL $55,264.54