1b. 2011 Street Rebahilitation Project No. 11-01: Approve Plans and Specification; Authorize Advertisement for Bids16
CIUOF MEMORANDUM
CUMflMSEN TO: Paul Oehme, Director of Public Works /City Engineer'
7700 Market Boulevard FROM: Alyson Fauske, Assistant City Engineer
PO Box 147
Chanhassen, MN 55317
DATE: February 28, 2011 D�to
Administration SUBJ: 2011 Street Rehabilitation Project No. 11 -01: Approve Plans and
Phone: 952.227.1100 Specifications; Authorize Advertisement for Bids
Fax: 952.227.1110
Building_lnspections
Phone: 952.227.1180
I .PROPOSED MOTION
Fax: 952.227.1190
present.
Fax: 952.227.1110
"The City Council is recommended to approve the plans and specifications for
Engineering
City Project No. 11 - 2011 Street Rehabilitation Project and authorize the
y
Phone: 952.227.1160
advertisement for bids.
Fax: 952.227.1170
Finance
City Council approval requires a simple majority -vote of the City Council
Phone: 952.227.1140
present.
Fax: 952.227.1110
Park & Recreation
BACKGROUND
Phone: 952.227.1120
Fax: 952 ,227.1110
At the October 11 2010 work s staff reviewed with Counci the proposed
2011 Street Improvement project areas.
Recreation Center
2310 Coulter Boulevard
On October 25 2010 the Cit Coun authorize the re aration of the
y p p
Phone: 952.227.1400
feasibility study,
Fax: 952.227.1404
Plannin &
9
Staff held a neighborhood ope house on December 8, 2010.
Natural Resources
Phone: 952.227.1130
On December 13, 20 10, the City Coun accepted the fea report and called
Fax: 952.227.1110
the public hearing.
Public Works
Staff held a nei meeting on January 12, 2011 to discuss the proposed
1591 Park Road
Phone: 952.227.1300
Timberwood Drive /Stone C reek Court street connection.`
Fax: 952,227.1310
At the February 14, 2+ 11 work Session, the C1` ty Council directed staff to
Senior Center
abandon plans for an emergency connection from Tinaberwood Drive to Stone
Phone: 952.227.1125
Creek Court.
Fax: 952.227.1110
Web Site
www.ci.chanhassen.mn.us
Chanhassen is a Community for Life - Providing for Today and Planning for Tomorrow
2011 Street Rehabilitation Project 11 -01:
Approve Plans &Specs; Authorize Ad for Bid
February 28, 2011
Page 2
Overview
This year's proposed street project includes three areas which generally include the Timberwood
Drive neighborhood, Santa Vera Drive area and West 78 Street area from Powers Boulevard to
Market Boulevard. Approximately 2,000 feet of trails is proposed to be resurfaced along the
Highway 5 corridor and in the Stone Creek neighborhood. The project also includes expanding
the south parking lot at City Hall to accommodate 12 additional parking stalls.
ti
Lake Ann
3
0
~- - HIGHWAY -5 est 78th St �
El
C - Blvd �-� ------- -------- -- \ - -.
_., �._:�-
L,.
CI
�.
L. '
a� a te
.Q
4
.e ke Susan
Purpose and Need for Street Improvement
The streets proposed for rehabilitation were selected based on the pavement condition scores and
site investigations. These streets can no longer be maintained cost effectively with minor
maintenance techniques such as seal coating. The streets in general have deteriorated, because of
the age. The potholes and other pavement problems present have created poor driving conditions
and have weakened the subgrade soils. The pavement condition indices are shown on the maps
below; a score of 100 represents a new street and 0 represents a completely deteriorated street.
Pavements between 45 and 65 are generally considered needing a rehabilitation or overlay.
G: \ENG \PUBLIC \_2011 PROJECTSU 1-012011 street project \app plans & specs 02 -28 -1 l.docx
2011 Street Rehabilitation Project 11 -01:
Approve Plans &Specs; Authorize Ad for Bid
February 28, 2011
Page 3
Streets in this condition range should be rehabilitated at this time then wait until the street
condition gets much worse. Waiting much longer, the streets would most likely deteriorate more
rapidly and cost more to make improvements in the future. If left unimproved, the streets would
most likely need to be reconstructed and would require a greater assessment. The City's
pavement management plan has identified streets for improvements over the 10 years which are
currently being programmed and planned for. If projects are delayed, they would most likely not
be proposed for improvements for at least another 10 years. Delaying projects will cost more in
the future, create more complaints about the condition of the roadway, and create more patch
work and cost for the Public Works department.
Proiect Area #1: Urban Commercial
This project area consists of 0.71 miles of streets within the western portion of the downtown
core. The projected PCIs range from 17 to 71 within this project area, however staff
recommends a mill and overlay is warranted on the roads with higher PCI's since these segments
are collector roads. The streets segments with the lower PCI's are not collector roads and would
benefit from a mill and overlay. The average PCI for the area is 44 which is within the general
guidelines for overlays.
A 3" mill and overlay is anticipated on W. 78 Street and a 2" overlay on the side streets.
Included in the project would be new loop detectors at all the signalized intersections. Some
damaged curb and gutter will also be replaced.
Soil borings for this project area indicate that there is between eight and nine inches of
bituminous over 17 to 19 inches of gravel and one foot of sand.
G: \ENG \PUBLIC \_2011 PROJECTSA 1-012011 street project \app plans & specs 02 -28 -1 Ldocx
2011 Street Rehabilitation Project 11 -01:
Approve Plans &Specs; Authorize Ad for Bid
February 28, 2011
Page 4
Protect Area #2: Urban Residential
There are approximately 1.07 miles of streets within this project area.
The project generally consists of replacing damaged and settled curb, repairing severely
distressed pavement areas, edge milling the streets and paving a 2" overlay. Drain the will be
installed along a portion of Chippewa Trail and Saratoga Drive to alleviate some of the drainage
issues within this area.
The soil borings indicate that there is between four and eight inches of asphalt and over six to
eight inches of gravel in this area.
Drainage improvements to the intersection of Kerber Boulevard and Santa Vera Drive and at the
end of Saratoga Drive cul -de -sac are also proposed.
The bolts to some gate and hydrant valves should be replaced at this time. It's thought some of
these valves may experience problems in the near future because of the age of the system and
soils condition.
Staff proposes a separate assessment roll for Santa Vera Drive west of Kerber Boulevard since
the area is all multi - family units.
G: \ENG\PUBLIC \_2011 PROJECTS\ 11-0 1 2011 street project \app plans & specs 02 -28 -1 Ldocx
2011 Street Rehabilitation Project 11 -01:
Approve Plans &Specs; Authorize Ad for Bid
February 28, 2011
Page 5
Proiect Area #3: Rural Residential
Staff proposes that a full depth mill and overlay be
performed due to the condition of the streets. The
millings of the streets would be used as aggregate
base. A 4" pavement section is proposed based on
the soils engineer's recommendation. The
feasibility report was based on a 3" pavement
section, but the contingency included in the
estimate should cover the cost for the additional
bituminous.
Proiect Area #4: Trail Maintenance
Along with overlay projects, the City has
included trail segments that are in need of repair
or replacement. The Parks Maintenance
Department used updated trail pavement
condition data and site investigation to determine
the proposed trail segments in the 2011
resurfacing project. The trails proposed to be
replaced are shown on the right.
Originally, the proposal included a segment of
trails along Highway 5 between Great Plains
Boulevard and Highway 101. This segment was
deleted from the project since MnDOT's
proposed turn lane improvements along
Highway 5 may impact this trail segment.
Additional trails along the Stone Creek corridor
have been added in lieu of the Highway 5 trail.
These trail segments show signs of significant deterioration and should be replaced. The budget
for this work is $75,000. These improvements will not be assessed.
G: \ENG \PUBLIC \_2011 PROJECTSU 1 -01 2011 street project \app plans & specs 02- 28- 11.docx
2011 Street Rehabilitation Project 11 -01:
Approve Plans &Specs; Authorize Ad for Bid
February 28, 2011
Page 6
Pro iect Area #5 South East City Hall Parking Lot Expansion
This project is proposed to maximize the existing
parking lots at City Hall. Currently, the parking lots
at City Hall are over capacity when seniors and
library events are planned during the day.
City staff has tried to schedule events so parking
demand is spread out during the day; however these
initiatives have only been somewhat successful.
The proposed parking lot expansion would remove
most of the center median from the parking lot, move
the north curb line six feet to the north and reconstruct
the parking lot entrances. The work would allow for
3
12 additional parking stalls. The cost for the project - -. a
is budgeted at $70,000 and would be funded by the Capital Replacement Fund.
improvements will not be assessed.
These
Permits and Approvals
A permit is required from the Department of Natural Resources for the replacement of the
culvert under the trail. Permits are also required from Carver County and the Minnesota
Department of Transportation for the trail work within the Powers Boulevard right of way.
FUNDING
Funding for the project is anticipated to come from several sources. Forty percent (40 %) of the
street improvement cost would be assessed back to the benefiting property owners per the City's
assessment practice. The remaining 60% of the street cost would be a City cost. Assessment
amounts are proposed to be specific to each project area.
Funding Source Amount Engineering
Budgeted Estimate
Assessments /Revolving Assessment Fund $1 $1
Street Pavement Maintenance Fund $ 300 $ 6500
Capital Replacement Fund
$ 70 $ 60
$1 $1
Cost estimates include 5% indirect costs and 15% contingency. A 10% contingency was used
for the commercial area since the scope of work in this area is more clearly defined.
G: \ENG \PUBLIC \_2011 PROJECTS\1 1 -01 201 1 street project \app plans & specs 02 -28 -1 Ldocx
2011 Street Rehabilitation Project 11 -01:
Approve Plans &Specs; Authorize Ad for Bid
February 28, 2011
Page 7
Staff feels this project will receive many very competitive bids due to the shortage of work
available for contractors to bid on.
RCHEDI TT .F,
The assessment hearing is tentatively scheduled for April 25, 2011. The anticipated construction
schedule is as follows:
Timberwood Drive Area and Trail Improvements
W. 78 Street and Santa Vera Drive Areas
City Hall Parking Lot
Attachments: 1. CIP Pages
2. Resolution
Mayl l to July 1, 2011
July 11 to August 26, 2011
September 5 to September 30, 2011
G:\ENG\PUBLIC\ 2011 PROJECTS\1 1 -01 201 1 street project \app plans & specs 02 -28 -1 l.docx
apital Improvement Program
ity of Chanhassen, MN
:Project # ST -012
Project Name Annual Stre Improvement Program
Account #1 601 -xxxx -4751
Account #2
Account #3
Account #4
2011 thru 2015
Department Street Improvements
Contact Paul Oehme
Type Improvement
Useful Life Unassigned
Category Streets/Highways
Priority n/a
P escription Total Project Cost: $9,700,000
annual project to rehabilitate and reconstruct streets in the City. Current 5 -year plan shows the followin
residential 2011 - Timberwood Drive neighborhood, Saratoga, Santa Vera Chi P' g nei ghborhood areas:
>treet (Powers Blvd to Market Blvd) PP ewa icha and Kerber (S of W 78th), Target lane and W 78th
2012 - Greenbriar, Fir Tree, Elm Tree, Dogwood, Shore Drive and Maplewood
2013 - Greenwood Shores and West 78th Street (Powers p d Circle (Reconstruction)
(P s to Market}
2014 - Dartmouth Drive and Cypress Drive
2015 - Carver Beach area (south and west of Carver Beach Road)
!ustification
'fie City uses a Pavement Management System to monitor the condition of the City
fe of the street and is cost effective, a street will eventually deteriorate streets. While proper preventative maintenance extends the
y e to a point that further maintenance is no longer cost effective.
' ehabilitation projects extend the life of the street. In cases with utility r
ty poor sub grade needs to be replaced or where streets have deteriorated
a point where rehabilitation will no longer be practical reconstruction of the street is necessa
cents of the protect and scope of work. ry• A feasibility study is written to consider the
'rior Expenditures 2011 2012 2013 --
2014 2015 Total
3,200 Construction 1,500,000 1,700 000
11200,000 1,100,000 1,000,000 6
Utal Total 1,500,000 1 1200 -
,000 1,100,000 1 6,500,000
rior Funding Sources 2011 2012 2013 2014 2015 Total
,3,200,000 Assessment/Revolving Assess 1,200,000 117001000 1 1,100,000 1,000,000 fi,200,000
Dtal Street Pavement Management 300
300,000
Total 1,500,000 11700 11200,000 1 , 1,000,000 6,500,000
Iget Impact/Other
Project may decrease maintenance costs.
107
Capital Improvement Program 2011 thm 2015
City of Chanhassen, N4N
Project # MB -016
Project Name City gall Parking Lot Expansion
Account #1 400 - 0000 -4706 Account #3
Account #2 Account #4
Description
Expansion of the lower east parking lot at City Hall adding ten new spaces.
Justification
Additional parking capacity is needed for City Hall, senior center, library and park.
Department
Expenditures
2011 2012
PaulOehme
Construction
70,000
Useful Life
Total
70,000
Engineering
Funding Sources
2011 2012
Capital Replacement Fund
70,000
Total
70,000
3
p i
T
Budget Impact/Other
t
Department
Municipal Buildings
Contact
PaulOehme
Type
Improvement
Useful Life
Category
Engineering
Priority n/a
Total Project Cost: $70,000
2013 2014 2015 T otal
7 0,000
70,000
2013 2014 2015 T otal
70,000
70,000
71
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE: Febru ry 28, 2011 RESOLUTION NO:
MOTION BY:
SECONDED BY:
2011-
A RESOLUTION APPROVING PLANS AND SPECIFICATIONS
AND AUTHORIZING AD FOR BIDS FOR THE 2011 STREET
IMPROVEMENT PROJECT NO. 11 -01
WHEREAS, pursuant to the resolution passed by the Council on January 24, 2011, the City
Engineer has prepared plans and specifications for the 2011 Street Improvement and has presented
such plans and specifications to the Council for approval;
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council:
1. Such plans and specifications, a copy of which can be reviewed at the office of the City
Engineer, are hereby approved.
2. The city clerk shall prepare and cause to be inserted in the official city newspaper and
Finance & Commerce, an advertisement for bids upon the making of such improvement under such
approved plans and specifications. The ad shall be published at least three times, shall specify the
work to be done, shall state that bids will be opened and that the responsibility of the bidders will
be considered by the Council at 7:00 PM on Monday, April 25, 2011, for the 2011 Street
Improvement Project No. 11 -01, in the Council Chambers of the City Hall. Any bidder whose
responsibility is questioned during consideration of the bid will be given an opportunity to address
the Council on the issue of responsibility. No bids will be considered unless sealed and filed with
the clerk and accompanied by a bid security payable to the clerk for 5% of the amount of such bid.
Passed and adopted by the Chanhassen City Council this 28 day of February, 2011.
ATTEST:
Todd Gerhardt, City Manager
Thomas A. Furlong, Mayor
YES NO ABSENT