1f. North Bay 2nd Addition: Extension of Work Hours.1
1
O
' MEMORANDUM
CITY OF
690 COULTER DRIVE • P.O. BOX 147 0 CHANHASSEN, MINNESOTA 55317
(612) 937 -1900 • FAX (612) 937 -5739
' TO: Charles Folch, Director of Public Works
FROM: Dave Hempel, Assistant City Enginee
' DATE: October 9, 1996
OFFICIAL ENGINEERING COPY
Rewived
R loon No.
m'ed ° Engineer
Date
Approved by City Cam;;
Date
' SUBJ: Consider Extension of Work Hours - Enebak Construction
North Bay 2 °d Addition - Project No. 95 -20
Staff has received a request from Enebak Construction contractor for Rottlund Homes (North
Bay r Addition), for an extension to the City's permitted construction hours on Saturdays.
' Currently, city ordinance and development contract restrict construction activities on Saturdays
from,9:00 a.m. to 5:00 p.m. The contractor is requesting a 2 -1/2 hour extension to that workday.
Given the remote proximity of residential development, staff is in support of the request for an
' earlier start up time. Staff recommends that the City Council grant a temporary extension to
working on Saturdays from 7 :00 a.m. to 5 :30 p.m. conditioned upon staff not receiving
complaints from area residents. If staff receives complaints, the contractor will be required to
' revert back to normal construction hours on Saturdays.
jrns
Attachment: 1. Location map.
' 2. Letter from Enebak Construction dated September 16, 1996.
c Dave Klee, Enebak Construction
' \bfsl\vo0e gB " jeds\aoAhbayln&cxftUonofhowxdoc
i
1 OP
1 September 16, 1996
ensan consTRUCTion compRny
P.O. Box 458 - Northfield, Minnesota 55057 - 507 - 645 -8962 612 - 333 -1307
1 David Hemple
City of Chanhassen
690 Coulter Drive
1 P.O. Box 147
Chanhassen, MN 55317
1 Regarding: North Bay 2nd Addition
The Rottlund Company
1 Dear Mr. Hemple:
Enebak Construction began site grading at North Bay 2nd Addition on
September 13, 1996. Due to our late start on the project it will
1 be necessary to work additional hours on Saturday to try to
complete as much of the project this fall as possible.
1 Enebak Construction requests permission from the City of Chanhassen
to start work at 7:00 a.m. and work until 5:30 p.m. No work will
be performed on Sunday.
1 We would like these extended Saturday hours to continue until
November 30, 1996.
1 Thank you for your time in considering this request. If you have
any questions, please contact me at 333 -1307.
1 Sincerely,
p&4 , X&
1 Dave Klee
Project Manager
1 DK /sk
1 17 1996