1c. Approve Change Order No1 to Well No. 3 Repair ContractCITY OF /C,- �HANBASSEN MEMORANDUM 1 1 1 1 1 1 1 1 1 1 1 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317 (612) 937 -1900 • FAX (612) 937 -5739 TO: Don Ashworth, City Manager FROM: Charles Folch, Director of Public Works DATE: August 20, 1996 SUBJ: Approve Change Order No. 1 to Well No. 3 Repair Contract Project No. 94 -3 -3 400 by City Administrator, Endo►ssd DwA Modified Rejected Dot °' 2 / - `�L Date Submitted to Commisft Date $Omitted to Council -z�- I& The contract for the repairs to Well No. 3, Project No. 94 -3 -3, has been completed; however, a contract amendment (change order) needs to be administrated before final payment on the project can be made. You may recall that the repair work to Well No. 3 primarily consisted of the removal and disposal of the existing turbine well pump and high- service booster pump and replacement with a new vertical line -shaft turbine pump. The associated piping in the well house was also rearranged to facilitate a future well point. There are basically two parts to Change Order No. 1. The first involves a deduction to the contract amount for some additional expenses incurred by the City for an extra start -up date process due to the system not being completed within the contract time schedule. This amounts to a deduct to the contract of $606.06. The other element of the change order involves a reduction in cost due to downsizing the diameter of the head connection from a 10 -inch to an fl- inch for the column. This amounts to a deduct of $883.00. The total amount of Change Order No. 1 is a deduct in the amount of $1,489.06 which yields a revised contract amount of $87,250.94. The original contract amount was $88,740.00. With the approval of this change order (contract deduction), final payment on this contract can be made. Staff recomm6hds that Change Order No. 1, a deduction in the amount of $1,489.06, be approved for the contract for repairs to Well No. 3, Project No. 94 -3 -3. ktm ' Attachments: 1. Letter from Bonestroo dated July 29, 1996. 2. Change Order No. 1. g.\en&har1es \we113 change order.doc Bonestroo Rosene Anderlik & Associates Engineers & Architects July 29, 1996 Mr. Charles Folch City of Chanhassen 690 Coulter Drive P.O. Box 147 Chanhassen, MN 55317 RE: Municipal Well No. 3 Rehab. Our File No. 39327 Dear Charles: Attached is the final Change Order No. 1 in the deducted amount of $1,489.06 for the above - mentioned project. The deduct in contract price is due to two items. One item is for liquidated damages as previously discussed due to lack of Contractor organization. The other item is for the decreasing of the well pump column from a 10" diameter specified down to an 8" diameter column size. Please add this Change Order to the August 12 City Council Agenda for approval. Upon approval we will put together the final pay request for this project. After Council approval and signature, please return the one signed copy to us and mail one signed copy to Municipal Builders. If you should have any questions at all concerning the final change order, please give me a call. Thank you for your time in this matter. Yours very truly, BONESTROO, ROSENE, ANDERLIK & ASSOCIATES Tim Grinstead Encl. cc: Dick Foster - Bonestroo &. Assoc. Phil Gravel - Bonestroo & Assoc. Bonestroo, Rosene, Anderlik and Associates, Inc. is an Affirmative Action /Equal Opportunity Employer Principals Otto G Bonestroo. P E . Joseph C Anderlik, P E . Marvin L Sorvala. P E . Richard E Turner, P E . Glenn R. Cook, P E.. Thomas E Noyes, P E . Robert G Schunicht, P.E Jerry A Bourdon. P E . Robert W Rosene. P.E and Susan M. Eberlin, C P A , Senior Consultants Associate Principals Howard A Sanford, P E . Keith A Gordon, P E . Robert R Pfefferle, P E Richard W Foster, P E.. David O Loskota, P E . Robert C. Russek, A I A . Mark A Hanson, P.E Michael T Rautmann, P.E . Ted K Field. P.E Offices St Paul, Rochester and Willmar, MN . Mequon, WI �nniversery 1956 -199/; 72 5 1Y /nct HinF��e.a�r Z/. . cr n -11 eRhi rr19> >ono - i1'11, i '3 i Ainn " RM Bonestm Owner. City of Chanhassen, 690 Coulter Dr., Chanhassen, MN 55317 Date July 23,19% o Artderlk Contractor: Municipal Builders, Inc., 17125 Roanoke St. NW, Anoka, MN 55304 Assodatw er ', iArdik Bond Co.: United Fire dt Casualty Co., P.O. Box 73909, Cedar Rapids, IA 52407 Bond No. 54 -80715 CHANGE ORDER NO. 1 WELL HOUSE NO.3 REHABILITATION File 39327 Description of Work Part 1 Liquidated Damages: This change reimburses the owner for the expense of A/E and city staff time for an additional facility start up day due to electronic controls not being complete in lieu of charging liquidated damages. The following break down is for cost incurred by the Owner due to unsuccessful start -up of Well No. 3. Part 2 Decrease in Well Pump Column: This change is necessary to match the head connection which reduced the 10" diameter column down to an 8" diameter column. No. Item Part 1: Liquidated Damages A/E: 7 hours @ $58.50/hour 64 miles @ $0.29 /mile Owner: 4 hours @ $32.00/hour 2 hours @ 25.00/hour Total Part 1- Deduct Contract Unit Unit Quantity Price jUL ' 1996 ENGINEERIN DEPT. Total Amount $409.50 $18.56 $128.00 $50.00 ($606.06) Part 2: Decrease in well pump column Total Part 2 - Deduct Total Change Order No.1 39327/co.wbl LS 1 883 ($883.00) ($883.00) ($1,489.06) Original Contract Amount $88,740.00 Previous Change Orders $000 This Change Order No. 1 ($1,489.06) Revised Contract Amount (including this change order) $87,250.94 Recommended for Approval by: BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC. Approved by Contractor. Municipal B" ders, c. M-4 � s. cc: Owner Contractor Bonding Company Bonestroo & Assoc. date. Approved by Owner. City of Chanhassen 39327/co.wbl