1k. Chuck's Grinding: Site Plan.1
CITY OF
y� CHANHASSEN
P.C. DATE: 8 -21 -96 l k"
C.C. DATE: 9 -9 -96
CASE: 96 -9 Site Plan
BY: Al- Jaff.v
� STAFF REPORT
a
PROPOSAL: Site plan review for a 16,704 square foot office /warehouse building - Chuck's
Grinding
LOCATION: Lot 5, Block 1, Chanhassen Business Center 2nd Addition. West of Audubon
Road, south of Chicago, Milwaukee, St. Paul & Pacific Rail Road, and northeast
of Commerce Drive.
APPLICANT: Pegasus, L.L.C.
5000 Glenwood Avenue
Minneapolis, MN 55422
(612) 377 -7090
'
PRESENT ZONING:
ACREAGE:
ADJACENT ZONING
'
AND LAND USE:
�
r
Planned Unit Development, PUD
2.42 acres
N - IOP, railroad, vacant
S - PUD, vacant
E - PUD, Jehovah Witness
W - PUD, Power Systems
WATER AND SEWER:.
PHYSICAL CHARACTER:
2000 LAND USE PLAN:
Available to site.
The site is devoid of vegetation.
Office/Industrial
action by City Aftinr
Endorsed
modified
(iejected g _ , g�
Q& Submitted to Commission
Date Submitted to Council
9 --y -96
Bluff C-
Elem Sc
Coulter
t0
Dr
C ( ') ulcer Blvd
St
Lake D
I
Lake
Ann
Lake
Ann
Park
Court
IFAIR
Chucks Grinding Inc.
September 9, 1996
Page 2
PROPOSAL /SUMMARY
The applicant is proposing a 16,704 square foot office warehouse building on Lot 5, Block 1,
Chanhassen Business Center 2nd Addition. There is potential future expansion area of an
additional 8,624 square feet on the east side of the proposed structure.
The applicant is proposing the use of rock face block. The PUD requires that all walls shall be
given added architectural interest through building design or appropriate landscaping. A
horizontal band runs along all four elevations which accentuate the building. A pitched roof
element adorns the entry way giving it added architectural interest. The overall design is of a
high quality providing variation and detail on the facade of the building.
The proposed landscape plan meets the minimum requirements of the ordinance Staff believes
that the proposed development meets the standards established as part of the PUD and is
recommending approval of the site plan subject to the conditions contained in this report.
' BACKGROUND
On January 13, 1992, the City Council approved the preliminary plat for the Chanhassen
Business Center as shown on the attached site plan. The PUD was amended on February 8, 1993
to allow for a church as a permitted use and the final plat for phase I of the project was approved.
' On April 24, 1995, the Chanhassen Business Center 2nd Addition, subdividing Outlot C into 7
lots, was approved by the City.
On September 25, 1995, the City Council approved the replat of Outlot A into 4 lots which is the
3rd Addition.
The Chanhassen Business Center is an industrial /office park on 93.7 acres. The original plat
consisted of 12 lots and 2 outlots. The ultimate development for this proposal was to have a total
of 700,000 square feet of building area with a mix of 20% office, 25% industrial and 55%
' warehouse.
GENERAL SITE PLAN /ARCHITECTURE
OVERVIEW
The proposed building is situated northwest of Commerce Drive. Access is gained off of
Commerce Drive. Parking is located to the northeast and west of the proposed building. Direct
views of the docks, which are located to the north of the building, will be semi - screened by the
building, a berm, and evergreens. The applicant has requested using sumac along the northern
portion of the property rather than evergreens, since sumac grows more rapidly and will screen
1 the docks from views of the residential area located north of the subject site.
Chucks Grinding Inc. '
September 9, 1996
Page 3 ,
The building height is 22 feet, located 170 feet from the north, 100 feet from the east, 20 feet
from the south, and 75 feet from the west property line.
Materials used on the structure will be integral color co concrete rock face and scored
smooth rock face concrete which accents the building. The rock face bands runs along all four
elevations of the building. The entrance into the building has a pitched canopy. The applicant
has not shown the trash enclosure location. The materials used to screen the trash enclosure shall ,
be the same type of block used on the building.
The overall design is of a high quality providing variation and detail on the facade of the ,
building.
DEVELOPMENT STANDARDS
The development standards will remain the same as previously approved with the PUD. ,
a. Intent
The purpose of this zone is to create a PUD light industrial /office park. The use of the PUD zone
is to allow for more flexible design standards while creating a higher quality and more sensitive
proposal. All utilities are required to be placed underground. Each lot proposed for development '
shall proceed through site plan review based on the development standards outlined below.
h. Permitted Uses
The permitted uses in this zone should be limited to light industrial, warehousing, and office as
defined below. The uses shall be limited to those as defined herein. If there is a question as to
whether or not a use meets the definition, the City Council shall make that interpretation.
1. Light Industrial The manufacturing, compounding, processing, assembling, packaging, '
or testing of goods or equipment or research activities entirely within an enclosed
structure, with no outside storage. There shall be negligible impact upon the surrounding
environment by noise, vibration, smoke, dust or pollutants.
2. Warehousing Means the commercial storage of merchandise and personal property. ,
3. Office Professional and business office, non - retail activity.
FINDING: The li ro osed uses of ht industrial and office are consistent with the parameters
p P g
established as part of the PUD.
r
t
Chuck's Grinding
September 9, 1996
Page 4
c. Setbacks
In the PUD standards, there is the requirement for landscape buffering in addition to building and
parking setbacks. The landscape buffer on Audubon Road is 50 feet, south of Lake Drive and
100 feet along the southern property line. The PUD zone requires a building to be setback 50
feet from the required landscape buffer and public right -of -ways. There is no minimum
requirement for setbacks on interior lot lines.
The following setbacks shall apply from the right -of -way:
Building Parking
Required (interior road system)
25'
15'
Provided Commerce Drive
55'
18'
FINDING: The proposed development meets or exceeds the minimum setbacks established as
part of the PUD.
d. Development Standards Tabulation Box
Chanhassen Business Center Second Addition
Lot #
Lot Size - Acres
Building Sq. Ft.
Building
Coverage
Impervious
1
3.56
40,000
26%
67%
2
1.55
17,000
26%
65%
3
1.81
19,000
24%
63%
4
2.68
34,000
29%
76%
5
2.42
29,000
28%
72%
6
2.74
27,000
23%
59%
7
2.16
26,000
28%
72%
Road
1.60
67%
Subtotal
18.52
192,000
26%
68%
TOTAL
j 93.02
603,500
2 3%
6001,
Chuck's Grinding
September 9 1996
Page 5
COMPLIANCE TABLE -
The PUD standard for hard surface coverage is 70% for office and industrial uses.
Parking Standards Office - 4.5 spaces per 1,000 square feet; Warehouse - 1 space per 1,000 for
first 10,000 square feet, then 1 space per 2,000 square feet; Manufacturing - 1 parking space for
each employee on the major shift and 1 space for each motor vehicle when customarily kept on
the premises. Staff has estimated the required parking at 24 spaces. The applicant has provided
31 spaces.
Building Square Footage Breakdown for entire development
Office
PUD
Chuck's Grinding
Building Height
2 stories
1 story
Building Setback
N -30' E -10'
N -150° E -100'
Church
5 -10' W -10'
S -20' W -75'
Parking stalls
24
31 stalls
Parking Setback
N -30' E -10'
N -30' E -20'
5 -10' W -10'
5 -10.2' W -10'
Hard surface
70%
43.6%
Coverage
Lot Area
1 acre
2.42 acres
Variances Required
- none
The PUD standard for hard surface coverage is 70% for office and industrial uses.
Parking Standards Office - 4.5 spaces per 1,000 square feet; Warehouse - 1 space per 1,000 for
first 10,000 square feet, then 1 space per 2,000 square feet; Manufacturing - 1 parking space for
each employee on the major shift and 1 space for each motor vehicle when customarily kept on
the premises. Staff has estimated the required parking at 24 spaces. The applicant has provided
31 spaces.
Building Square Footage Breakdown for entire development
Office
20%
120,700 sq. ft.
Manufacturing
25%
150,875 sq. ft.
Warehouse
54.09%
326,425 sq. ft.
Church
0.91%
5,500 sq. ft.
F�
Chuck's Grinding
September 9, 1996
Page 6
Total 100% 603,500 sq. ft.
FINDING: The proposed development meets the development standards established as part of
the PUD. The city has previously approved the following square footage within the Chanhassen
Business Center: church - 5,500 square feet; office - 34,021.5 square feet (National Weather
' Service, Power Systems, Paulstarr Enterprises and Highland, Control Products); and warehouse -
45,692.5 square feet (Power Systems, Paulstarr Enterprises and Highland, control products).
e. Building Materials and Design
1. The PUD requires that the development demonstrate a higher quality of architectural
standards and site design. All mechanical equipment shall be screened with material
compatible to the building.
2. All materials shall be of high quality and durable. Masonry material shall be used. Color
shall be introduced through colored block or panels and not painted block.
3. Brick may be used and must be approved to assure uniformity.
4. Block shall have a weathered face or be polished, fluted, or broken face.
5. Concrete may be poured in place, tilt -up or pre -cast, and shall be finished in stone,
textured or coated.
6. Metal siding will not be approved except as support material to one of the above
materials or curtain wall on office components or, as trim or as HVAC screen.
7. All accessory structures shall be designed to be compatible with the primary structure.
8. All roof mounted equipment shall be screened b walls of compatible appearing material.
Y p
Wood screen fences are prohibited. All exterior process machinery, tanks, etc., are to be
fully screened by compatible materials.
9. The use of large unadorned, prestressed concrete panels and concrete block shall be
prohibited. Acceptable materials will incorporate textured surfaces, exposed aggregate
and /or other patterning. All walls shall be given added architectural interest through
building design or appropriate landscaping.
Chuck's Grinding
September 9, 1996
Page 7
10. Space for recycling shall be provided in the interior of all principal structures for all '
developments in the Business Center.
FINDING: The applicant is proposing the use of integral color corduroy concrete rock face and
rock smooth face block. The PUD requires that all walls shall be given added architectural
interest through building design or appropriate landscaping. The plans include a horizontal ,
accent band surrounding the building. The building design is of a high quality and meets the
intent of the PUD design requirements.
L Site Landscaping and Screening
1. All buffer landscaping, including boulevard landscaping, included in Phase I area to be
installed when the grading of the phase is completed. This may well result in landscaping
being required ahead of individual site plan approvals but we believe the buffer yard and
plantings, in particular, need to be established immediately. In addition, to adhere to the
higher quality of development as spelled out in the PUD zone, all loading areas shall be
screened. Each lot for development shall submit a separate landscaping plan as a part of
the site plan review process.
2. All open spaces and non - parking lot surfaces shall be landscaped, rockscaped, or covered
with plantings and /or lawn material
3. Storage of material outdoors is prohibited unless it has been approved under site plan
review. All approved outdoor storage must be screened with masonry fences and /or
landscaping.
3. The master landscape plan for the CBC PUD shall be the design guide for all of the
specific site landscape developments. Each lot must present a landscape plan for
approval with the site plan review process. '
4. Undulating or angular berms 3' to 4' in height, south of Lake Drive along Audubon Road
shall be sodded or seeded at the conclusion of Phase I grading and utility construction.
The required buffer landscaping may be installed in phases, but it shall be required where
it is deemed necessary to screen any proposed development. All required boulevard
landscaping shall be sodded. f
S. Loading areas shall be screened from public right-of-ways. Wing walls may be required
where deemed appropriate. I
E
L
Chuck's Grinding
September 9, 1996
Page 8
FINDING: The applicant's landscaping plan consists of a total of 23 trees, including evergreens,
deciduous and ornamentals. Landscaping ordinance conditions for parking lots and street
frontage require the applicant to provide 22 trees on the lot. The landscaping design incorporates
considerable distances between plantings causing some concern for adequate screening of
impervious area and loading docks. The lot, however, is sufficiently screened by location and
topography to the extent that the minimal landscaping design will be appropriate in this
development. Due to the rather open design of the landscaping, the assumed lack of use of the
seeded area and the proximity to the Bluff Creek corridor, staff recommends that applicant
consider prairie or wildflower plantings in lieu of the seeded grass. Applicant may work with
staff to consider options.
g. Signage
All freestanding signs be limited to monument signs. The sign shall not exceed eighty
(80) square feet in sign display area nor be greater than eight (8) feet in height. The sign
treatment is an element of the architecture and thus should reflect with the quality of the
development. The signs should be consistent in color, size, and material throughout the
development. The applicant should submit a sign package for staff review.
2. Each property shall be allowed one monument sign located near the driveway into the
private site. All signs require a separate permit.
The signage will have consistency throughout the development. A common theme will
be introduced at the development's entrance monument and will be used throughout.
4. Consistency in signage shall relate to color, size, materials, and heights.
FINDING: The applicant has provided a monument sign plan and location. The sign has an
area of 20.4 square feet. The height of the sign is 3.4 feet. The sign must be located a minimum
of 10 feet from any property line. A wall mounted sign is shown along the east elevation of the
building. The letters are 20 inches tall. The sign meets ordinance requirements. All signs must
receive a permit prior to installation.
h. Lighting
Lighting for the interior of the business center should be consistent throughout the
development.
A decorative, shoe box fixture (high pressure sodium vapor lamps) with a square
ornamental pole shall be used throughout the development area for area lighting.
Chuck's Grinding
September 9, 1996
Page 9
3 Lighting equipment similar to what is mounted in the public street right-of-ways shall be
used in the private areas.
4. All light fixtures shall be shielded. Light level for site lighting shall be no more than 1/2
foot candle at the property line. This does not apply to street lighting.
FINDING: The applicant is showing lights mounted on the building. Lights must meet the '
standards outlined above.
WETLANDS
There are no wetlands on the site. '
GRADING I
The existing site is bordered by a relatively steep slope on the east and a railroad bed on the north
side. The overall site grading proposed is minimal as the site was graded previously in
accordance with the Chanhassen Business Center grading plan. The location and design of the
proposed berming may need to be modified. The recommended allowable slope for berms is 3:1.
The berms are proposed at 2:1 or steeper. Staff also questions the rationale for constructing
berms on the east side of the property on the existing slope. The applicant should re- evaluate the
need for berming along the east property line.
Staff is unaware if the earthwork quantities balance. The applicant should be aware that if any
excess excavation material is to be hauled to property within the City, the individual property
owner must obtain a grading permit through the Engineering Department prior to earthwork
activities commencing. Haul routes shall be pre- approved by the City and the applicant will be
required to maintain these haul routes and clean the streets of any dirt and mud accumulated from
vehicles tracking. Any damage to City streets, curbs or other public facilities will be the
responsibility of the applicant.
EROSION CONTROL
Type 1 erosion control is proposed to be installed at the northwest corner of the site. Additional '
erosion control fence needs to be installed along the west property line and along the curb line on
both sides of the proposed access point. A rock construction entrance shall also be installed and
maintained during construction.
DRAINAGE
F�
n
I I
Chuck's Grinding
September 9, 1996
Page 10
Regional Storm Water Ponding was provided off site as part of the original development;
therefore, no on -site ponding is necessary. The applicant is proposing to add two catch basin
inlets and to tie into the existing storm sewer system at Commerce Drive and the Northwest
corner of the property. It appears from the storm drainage calculations submitted that the storm
water drainage from the adjacent parcel to the east (Lot 1 Block 1, church property), was not
considered. This will increase runoff to the site and require additional catch basins. Also, at the
northeast corner of the building, (sludge pick -up area), a catch basin and storm sewer is needed
to convey stormwater out of this low area into the storm sewer system. The applicant should
work with City staff in developing a drainage plan which takes into account these items prior to
issuance of a building permit.
UTILITIES
Municipal water and sewer service is available from Commerce Drive. The appropriate
plumbing permits will need to be applied for and obtained through the City's Building
Department.
STREETS
Access to the site is proposed from the cul -de -sac at the east end of Commerce Drive. The drive
shall be constructed in accordance with the City of Chanhassen Standard Detail Plate 5207 for
industrial driveways. The plans propose concrete curb and gutter at the driveway entrance only.
The remaining drive aisles and parking lot is void of curb and gutter. Pursuant to City Code 20-
1118c), all parking lots and drive aisles shall be bordered with raised concrete curb and gutter or
equivalent approved by the City. The entire perimeter of the paved parking lot shall be bordered
' by B612 concrete curb and gutter with the exception of the northwest side which is slated for
future parking. Along the future parking area a temporary bituminous curb is acceptable until the
new parking facilities are constructed at which time concrete curb and gutter per City Ordinance
will be required. The parking stall outside corners shall have radii of five feet. The west and
south sides of the warehouse building should have either a five -foot wide sidewalk or curb and
gutter to protect the building from traffic. Landscaping could be planted to provide a buffer area
between the drive aisle and the building.
I LANDSCAPING
The applicant's landscaping plan consists of a total of 23 trees, including evergreens, deciduous
and ornamentals. Landscaping ordinance conditions for parking lots and street frontage require
the applicant to provide 22 trees on the lot. The landscaping design incorporates considerable
distances between plantings causing some concern for adequate screening of impervious area and
Chuck's Grinding
September 9, 1996
Page 11
loading docks. The lot, however, is sufficiently screened by location and topography to the
extent that the minimal landscaping design will be appropriate in this development. Due to the
rather open design of the landscaping, the assumed lack of use of the seeded area and the
proximity to the Bluff Creek corridor, staff recommends that applicant consider prairie or
wildflower plantings in lieu of the seeded grass. Applicant may work with staff to consider
options.
SITE PLAIN FINDINGS
In evaluating a site plan and building plan, the city shall consider the development's compliance
with the following:
(1) Consistency with the elements and objectives of the city's development guides,
including the comprehensive plan, official road mapping, and other plans that may
be adopted;
(2) Consistency with this division;
(3) Preservation of the site in its natural state to the extent practicable by minimizing
tree and soil removal and designing grade changes to be in keeping with the
general appearance of the neighboring developed or developing or developing
areas;
(4) Creation of a harmonious relationship of building and open space with natural site
features and with existing and future buildings having a visual relationship to the
development;
(5) Creation of functional and harmonious design for structures and site features, with
special attention to the following:
a. An internal sense of order for the buildings and use on the site and
provision of a desirable environment for occupants, visitors and general
community;
b. The amount and location of open space and landscaping;
J i
u
t
1
Chuck's Grinding
September 9, 1996
Page 12
C. Materials, textures, colors and details of construction as an expression of
the design concept and the compatibility of the same with adjacent and
neighboring structures and uses; and
d. Vehicular and pedestrian circulation, including walkways, interior drives
and parking in terms of location and number of access points to the public
streets, width of interior drives and access points, general interior
circulation, separation of pedestrian and vehicular traffic and arrangement
and amount of parking.
(6) Protection of adjacent and neighboring properties through reasonable provision
for surface water drainage, sound and sight buffers, preservation of views, light
and air and those aspects of design not adequately covered by other regulations
which may have substantial effects on neighboring land uses.
Finding: The proposed development is consistent with the comprehensive plan, the
zoning ordinance, the design guidelines established as part of the Chanhassen Business
Center PUD with the modifications outlined in the staff report, and the site plan review
requirements. The site has few existing natural amenities due to previous development in
the area. The site design is compatible and harmonious with the approved industrial
developments throughout the city.
PLANNING COMMISSION UPDATE
On August 21, 1996, the Planning Commission reviewed and approved this application. One
condition was added requiring berming and additional landscaping along the north edge of the
property to provide screening of the loading dock area.
The staff recommends the City Council adopt the following motion:
RECOMMENDATION
"The City Council approves Site Plan 96 -9 for Chuck's Grinding, Inc. as shown on the plans
dated received July 29, 1996, and subject to the following conditions:
Fire Marshal conditions:
a. Install and indicate on plan a post indicator valve (PIV) on water service.
Location must be reviewed and approved by the Chanhassen Fire Marshal.
Chuck's Grinding
September 9, 1996
Page 13
b. Indicate on utility plan, size of water service being extended into the building.
C. Comply with Chanhassen Fire Department/Fire Prevention Policy 04 -1991 (notes
to be included on all site plans).
d. Fire lane signs shall be installed on the west side of the building in compliance
with Fire Department Fire Prevention Policy 06 -1991. Contact Fire Marshal for
exact location.
e. Comply with Chanhassen Fire Department/Fire Prevention Policy 07 -1991
(policy regarding pre -fire plan drawing).
f. Comply with Chanhassen Fire Department /Fire Prevention Policy 29 -1992
(premise identification).
g. Comply with Inspection Division Water Service Installation Policy 34 -1993
(water service installation policy for commercial and industrial buildings).
h. Comply with Chanhassen Fire Department /Fire Prevention Policy 36 -1994
(maximum allowable size of domestic water service on a combination
domestic /fire sprinkler supply line).
I. Comply with Chanhassen Fire Department/Fire Prevention Policy 40 -1995 (fire
sprinkler system). I
2. The applicant shall meet with the Building Official as requested in his attached memo.
3. The applicant shall enter into a site development contract with the city and provide the
necessary financial security to guarantee compliance with the terms of approval.
4. All roof mounted equipment shall be screened by walls of compatible appearing material.
Wood screen fences are prohibited. All exterior process machinery, tanks, etc., are to be
fully screened by compatible materials. As an alternative, the applicant can use factory
applied panels on the exterior to the equipment that would blend in with the building
materials.
5. All freestanding signs shall be limited to monument signs. The sign shall not exceed
eighty (80) square feet in sign display area nor be greater than eight (8) feet in height.
The sign treatment is an element of the architecture and thus should reflect with the
quality of the development. A common theme will be introduced at the development's
' Chuck's Grinding
September 9, 1996
Page 14
entrance monument and will be used throughout. Each property shall be allowed one
monument sign located near the driveway into the private site. The monument sign must
maintain a ten foot setback from the property line. The signs should be consistent in
color, size, and material throughout the development. The applicant should submit a sign
package for staff review. A separate permit is required for all signage on site.
i 11. Additional Type I erosion control fence shall be installed along the west property line.
Erosion control measures shall be in place and maintained at all times until the site has
been fully restored, revegetated, and removal is authorized by the City. Failure to
maintain the erosion control measures will result in the issuance of stop work orders.
12. Revised storm drainage calculations which include the stormwater runoff from Lot 1
Block 1, Chanhassen Business Center Addition shall be submitted to the City Engineer
for review and approval. Conveyance of storm drainage in the sludge pick -up area needs
to be addressed. The applicant's engineer shall work with City staff in revising the
drainage plan to address the additional runoff from the lot to the east (Lot 1, Block 1,
Chanhassen Business Center).
6.
Lighting for the interior of the business center should be consistent throughout the
development. A decorative, shoe box fixture (high pressure sodium vapor lamps) with a
square ornamental pole shall be used throughout the development area for area lighting.
All light fixtures shall be shielded. Light level for site lighting shall be no more than 1 /2
foot candle at the property line. This does not apply to street lighting. Lighting
'
equipment similar to what is mounted in the public street right -of -ways shall be used in
the private areas. Wall pack units may be used provided no direct glare is directed off -
site and no more than ' /2 foot candle of light is at the property line.
7.
Park fees shall be paid in accordance with city ordinance requirements.
'
8.
The applicant shall provide documentation that the variety of elm specified on
landscaping plans is Dutch Elm Disease resistant. Also, the applicant shall work with
staff to explore options for alternative lawn plantings.
9.
All construction vehicles shall access the site at approved rock construction entrances
only. Haul routes shall be pre- approved by the City. The applicant will be required to
maintain haul routes and clean the streets of any dirt and mud accumulated from vehicles
tracking. Any damage to City streets, curbs or other public facilities will be the
responsibility of the applicant.
10.
The maximum allowable slope on berms shall be 3:1.
i 11. Additional Type I erosion control fence shall be installed along the west property line.
Erosion control measures shall be in place and maintained at all times until the site has
been fully restored, revegetated, and removal is authorized by the City. Failure to
maintain the erosion control measures will result in the issuance of stop work orders.
12. Revised storm drainage calculations which include the stormwater runoff from Lot 1
Block 1, Chanhassen Business Center Addition shall be submitted to the City Engineer
for review and approval. Conveyance of storm drainage in the sludge pick -up area needs
to be addressed. The applicant's engineer shall work with City staff in revising the
drainage plan to address the additional runoff from the lot to the east (Lot 1, Block 1,
Chanhassen Business Center).
Chuck's Grinding
September 9, 1996
Page 15
13. The perimeter of the paved parking lot shall be bordered by B612 concrete curb and
gutter with the exception of a portion of the west side which is slated for future parking.
Along the future parking area a bituminous curb is acceptable at this time. However,
when the future parking is added B612 concrete curb and gutter will be required. The
parking stall corners shall have radii of five feet. The west and south sides of the
warehouse building shall provide a buffer area between the drive aisle and the building.
14. All areas disturbed as a result of construction activities shall be immediately restored with
seed and disc - mulched or wood fiber blanket or sod within two weeks of completion of
each activity in accordance with the City's Best Management Practice Handbook.
15. The applicant should-re evaluate shall
move the berm from the east property line to the north property line to help screen
the parking lot and dock area. The berm shall be planted with coniferous trees, i.e.
arborvitae hedge to provide year round screening.
16. DEVELOPMENT STANDARDS
The development standards will remain the same as previously approved with the PUD.
a. Intent
The purpose of this zone is to create a PUD light industrial /office park. The use of the PUD zone
is to allow for more flexible design standards while creating a higher quality and more sensitive
proposal. All utilities are required to be placed underground. Each lot proposed for development
shall proceed through site plan review based on the development standards outlined below.
b. Permitted Uses
The permitted uses in this zone should be limited to light industrial, warehousing, and office as
defined below. The uses shall be limited to those as defined herein. If there is a question as to the
whether or not a use meets the definition, the City Council shall make that interpretation.
1. Light Industrial The manufacturing, compounding, processing, assembling, packaging, or
testing of goods or equipment or research activities entirely within an enclosed structure,
with no outside storage. There shall be negligible impact upon the surrounding
environment by noise, vibration, smoke, dust or pollutants.
2. Warehousing Means the commercial storage of merchandise and personal property.
t
Chuck's Grinding
September 9, 1996
Page 16
3. Office Professional and business office, non - retail activity.
c. Setbacks
In the PUD standards, there is the requirement for landscape buffering in addition to building and
parking setbacks. The landscape buffer on Audubon Road is 50 feet, south of Lake Drive and
100 feet along the southern property line. The PUD zone requires a building to be setback 50
feet from the required landscape buffer and public right -of -ways. There is no minimum
requirement for setbacks on interior lot lines.
The following setbacks shall apply:
Buildinp- Parking
Audubon Road Buffer & Setback
50' plus 50'
S0' plus 10'
South Property Line & Setback
100" plus 50'
100' plus 10'
Front & Rear ROW on Lake Drive
25'
15'
Interior Side Lot Line
10'
10'
Railroad Right of Way
30'
30'
Audubon Road north of Lake Drive
50'
20'
d. Development Standards Tabulation Box
Chanhassen Business Center Second Addition
Lot #
Lot Size - Acres
Building Sq. Ft.
Building
Coverage
Impervious
1
3.56
40,000
26%
67%
2
1.55
17,000
26%
65%
3
1.81
1900
24%
63%
4
2.68
34,000
29%
76%
5
2.42
29,000
28%
72%
Chuck's Grinding
September 9, 1996
Page 17
6
2.74
27,000
23%
59%
7
2.16
26,000
28%
72%
Road
1.60
Total
100%
67%
Subtotal
18.52
192,000
26%
68%
TOTAL
93.02
603,500
23%
60%
The PUD standard for hard surface coverage is 70% for office and industrial uses. The proposed
development meets this standard with an average of 58.5% hard surface coverage.
Building Square Footage Breakdown
Office
20%
120,700 sq. ft.
Manufacturing
25%
150,875 sq. ft.
Warehouse
54.09%
326,425 sq. ft.
Church
0.91%
5,500 sq. ft.
Total
100%
603,500 sq. ft.
e. Building Materials and Design
1. The PUD requires that the development demonstrate a higher quality of architectural
standards and site design. All mechanical equipment shall be screened with material
compatible to the building.
2. All materials shall be of high quality and durable. Masonry material shall be used. Color
shall be introduced through colored block or panels and not painted block.
3. Brick may be used and must be approved to assure uniformity.
4. Block shall have a weathered face or be polished, fluted, or broken face.
5. Concrete may be poured in place, tilt -up or pre -cast, and shall be finished in stone, textured
or coated.
f
Chuck's Grinding
September 9, 1996
Page 18
6. Metal siding will not be approved except as support material to one of the above materials
or curtain wall on office components or, as trim or as HVAC screen.
7. All accessory structures shall be designed to be compatible with the primary structure.
8. All roof mounted equipment shall be screened by walls of compatible appearing material.
Wood screen fences are prohibited. All exterior process machinery, tanks, etc., are to be
fully screened by compatible materials.
9. The use of large unadorned, prestressed concrete panels and concrete block shall be
prohibited. Acceptable materials will incorporate textured surfaces, exposed aggregate
and /or other patterning. All walls shall be given added architectural interest through
building design or appropriate landscaping.
10. Space for recycling shall be provided in the interior of all principal structures for all
developments in the Business Center.
I E Site Landscaping and Screening
1. All buffer landscaping, including boulevard landscaping, included in Phase I area to be
installed when the grading of the phase is completed. This may well result in landscaping
being required ahead of individual site plan approvals but we believe the buffer yard and
' plantings, in particular, need to be established immediately. In addition, to adhere to the
higher quality of development as spelled out in the PUD zone, all loading areas shall be
screened. Each lot for development shall submit a separate landscaping plan as a part of
the site plan review process.
' 2. All open spaces and non - parking lot surfaces shall be landscaped, rockscaped, or covered
with plantings and/or lawn material.
3. Storage of material outdoors is prohibited unless it has been approved under site plan
review. All approved outdoor storage must be screened with masonry fences and/or
landscaping.
4. The master landscape plan for the CBC PUD shall be the design guide for all of the
specific site landscape developments. Each lot must present a landscape plan for
approval with the site plan review process.
Chuck's Grinding
September 9, 1996
Page 19
5. Undulating or angular berms 3' to 4' in height, south of Lake Drive along Audubon Road
shall be sodded or seeded at the conclusion of Phase I grading and utility construction. The
required buffer landscaping may be installed incrementally, but it shall be required where it
is deemed necessary to screen any proposed development. All required boulevard
landscaping shall be sodded.
6. Loading areas shall be screened from public right-of-ways. Wing wall may be required
where deemed appropriate.
g. Signage
1. All freestanding signs be limited to monument signs. The sign shall not exceed eighty
(80) square feet in sign display area nor be greater than eight (8) feet in height. The sign
treatment is an element of the architecture and thus should reflect with the quality of the
development. The signs should be consistent in color, size, and material throughout the
development. The applicant should submit a sign package for staff review.
2. Each property shall be allowed one monument sign located near the driveway into the
private site. All signs require a separate permit.
3. The Signage will have consistency throughout the development. A common theme will be
introduced at the development's entrance monument and will be used throughout.
4. Consistency in signage shall relate to color, size, materials, and heights.
h. Lighting
1. Lighting for the interior of the business center should be consistent throughout the
development. The applicant's proposal is consistent with the lighting standards for the PUD
ordinance. The plans do not provide for street lighting. As with previous industrial
parks /roadways, the City has required the developer to install street lights throughout the
street system. The street lights should be designed consistent with the existing lighting
along Audubon Road.
2. A decorative, shoe box fixture (high pressure sodium vapor lamps) with a square
ornamental pole shall be used throughout the development area for area lighting.
3 Lighting equipment similar to what is mounted in the public street right -of -ways shall be
used in the private areas.
Chuck's Grinding
September 9, 1996
Page 20
4. All light fixtures shall be shielded. Light level for site lighting shall be no more than 1/2
candle at the property line. This does not apply to street lighting."
ATTACHMENTS
1. Chanhassen Business Center Preliminary Plans.
2. Memo from Phillip Elkin and Anita Benson dated August 13, 1996.
3. Memo from Steve Kirchman dated August 13, 1996.
4. Planning Commission minutes dated August 21, 1996.
5. Site plan dated July 29, 1996.
gAplan \sa\chucks
...._ _ ...... r..1.,,. a .. a
s
W � " ru— arum rre .�.. x .. „•.. rr a . +: � QF .d v' `I v
0 !LY .• W e •• W r, x e• ar • ,• J Y ^ •a° Q a f
4eer•u u.. u,w M. °.,r M » -'a ruwr r °r r •rr a ,r ve S V' �, E � IN
�u n �, ,w .r o•. Ji ff- i/ /,/ r' ���
"P + CHANHASSENI
W • v.r�` :..' r.:- �` i7 BUSINESS CENTFR'I Yo C i
1 a u
BLOCK 1 i I
een••r ..« ,e,.w Pd M er0 (/ l_ \ 1 I � j
BLOCK 1
ors r,•.. ew,.v ua y � .�a . u ran• \ � e / �'1 ' I I t
NANHASSENJ�bBUSINES5 i CENTER
a u�
SECOND / >m \ �b q, ADDITION I° poi
exrw ♦ v ° y d` . `:`�/ N/ \ \\ BLOCK / r p ..,i'
oo. •o ryo �/� \\\ 2 \\� ' \•t':'�fdi BLOCK 9 \\� .�.�• ij; mum
W a.: .w iu. \ � \ ;� \ I �,I ���\ v. r; ii �e+lt•ac1 ��I .v i'•- j ro
, .w v ..w ne r. f l. • \.v �� r ,(\ . +; es�., .mw'\_'•,'''i1 • ifa�,; �r / � :i
BLOCK 1
11 '� wr »' /a✓,' /�j / /'; / s
910, I } l I� _ _
JAY j./ I
v. » .• w ...� .. Sq Qr zl -,Af• OUTL0I` \ 0 'J ; t I r /� r y�\\ '\1l lv CHANHASSEN BUSINESS CENTER w ' i BLOCK, i III 1>I
� CIIANIIAS -- ,f la I a 1
DUSII IESS
o / / I II 1 II rxa nvo . Pmi I - 1I 1 n I ° I•
�� , / III 1 11 `�" I SECOND III ADDITION
/ 1 1 CHANHASSEN I ' I I
�' I9 BUSINESS CENSER k'
/ II I II
ouTLDT A
/ CHANHASSEN ounor A
II 1 ' I a�v'vva• w ,.v...r r III I I I {'� / °�
f BUSINESS CENSER f I W Q
/ ` In ocK a
t
0 .1 ^ � OUnol
T�i IT
.. o . >. • _
- 1111111 11:IIh ISIA IIi ISI AO0I ZION
BLUFF CREEK ESTATES IST ADDITION
r= m m= m== m m= m r m r == m m
MEMORANDUM
CITY OF
CHANHASSEN
690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
(612) 937 -1900 • FAX (612) 937 -5739
' TO: Sharmin Al - Jaff, Planner H
FROM: Phillip Elkin, Water Resources Coordin t r
' Anita Benson, Project Engineer
DATE: August 13, 1996 C�YJ
SUBJ: Review of Site Plan for Office Warehouse Building
Located west of Audubon Road, South of Chicago, Milwaukee, St. Paul & Pacific
a Railroad, and northeast of Commerce Drive.
PUD -IOP - Planning Case 96 -9 Site Plan Review
Upon review of the site plan documents prepared by Community Partners, Inc. dated July 29,
1996, we offer the following comments and recommendations:
' WETLANDS
' There are no wetlands on the site.
GRADING
The existing site is bordered by a relatively steep slope on the east and a railroad bed on the north
side. The overall site grading proposed is minimal as the site was graded previously in accordance
' with the Chanhassen Business Center grading plan. The location and design of the proposed
berming may need to be modified. The recommended allowable slope for berms is 3:1. The
berms are proposed at 2:1 or steeper. Staff also questions the rationale for constructing berms
' on the east side of the property on the existing slope. The applicant should re- evaluate the need
for berming along the east property line.
Staff is unaware if the earthwork quantities balance. The applicant should be aware that if any
excess excavation material is to be hauled to property within the City, the individual property
owner must obtain a grading permit through the Engineering Department prior to earthwork
activities commencing. Haul routes shall be pre - approved by the City and the applicant will be
required to maintain these haul routes and clean the streets of any dirt and mud accumulated from
' vehicles tracking. Any damage to City streets, curbs or other public facilities will be the
responsibility of the applicant.
Sharmin Al -Jaff
96 -9 Site Plan Review
August 13, 1996
Page 2
EROSION CONTROL
Type 1 erosion control is proposed to be installed at the northwest corner of the site. Additional
erosion control fence needs to be installed along the west property line and along the curb line on
both sides of the proposed access point. A rock construction entrance shall also be installed and
maintained during construction.
DRAINAGE
Regional Storm Water Ponding was provided off site as part of the original development;
therefore, no on -site ponding is necessary. The applicant is proposing to add two catch basin
inlets and to tie into the existing storm sewer system at Commerce Drive and the Northwest
corner of the property. It appears from the storm drainage calculations submitted that the storm
water drainage from the adjacent parcel to the east (Lot 1 Block 1, church property), was not
considered. This will increase runoff to the site and require additional catch basins. Also, at the
northeast corner of the building, (sludge pick -up area), a catch basin and storm sewer is needed
to convey stormwater out of this low area into the storm sewer system. The applicant should
work with City staff in developing a drainage plan which takes into account these items prior to
issuance of a building permit.
UTILITIES
Municipal water and sewer service is available from Commerce Drive. The appropriate plumbing
permits will need to be applied for and obtained through the City's Building Department.
STREETS
Access to the site is proposed from the cul -de -sac at the east end of Commerce Drive. The drive
shall be constructed in accordance with the City of Chanhassen Standard Detail Plate 5207 for
industrial driveways. The plans propose concrete curb and gutter at the driveway entrance only.
The remaining drive aisles and parking lot is void of curb and gutter. Pursuant to City Code 20-
1118c), all parking lots and drive aisles shall be bordered with raised concrete curb and gutter or
equivalent approved by the City. The entire perimeter of the paved parking lot shall be bordered
by B612 concrete curb and gutter with the exception of the northwest side which is slated for
future parking. Along the future parking area a temporary bituminous curb is acceptable until the
new parking facilities are constructed at which time concrete curb and gutter per City Ordinance
will be required. The parking stall outside corners shall have radii of five feet. The west and
south sides of the warehouse building should have either a five -foot wide sidewalk or curb and
gutter to protect the building from traffic. Landscaping could be planted to provide a buffer area
between the drive aisle and the building.
di
Sharmin Al -Jaff
96 -9 Site Plan Review
' August 13, 1996
Page 3
RECOMMENDED CONDITIONS OF APPROVAL
' 1. All construction vehicles shall access the site at approved rock construction entrances
only. Haul routes shall be pre- approved by the City. The applicant will be required to
maintain haul routes and clean the streets of any dirt and mud accumulated from vehicles
' tracking. Any damage to City streets, curbs or other public facilities will be the
responsibility of the applicant.
2. The maximum allowable slope on berms shall be 3:1.
' 3. Additional Type I erosion control fence shall be installed along the west property line.
Erosion control measures shall be in place and maintained at all times until the site has
been fully restored, revegetated, and removal is authorized by the City. Failure to
' maintain the erosion control measures will result in the issuance of stop work orders.
4. Revised storm drainage calculations which include the stormwater runoff from Lot I
' Block 1, Chanhassen Business Center Addition shall be submitted to the City Engineer for
review and approval. Conveyance of storm drainage in the sludge pick -up area needs to
be addressed. The applicant's engineer shall work with City staff in revising the drainage
' plan to address the additional runoff from the lot to the east (Lot 1, Block 1, Chanhassen
Business Center).
' 5. The perimeter of the paved parking lot shall be bordered by B612 concrete curb and gutter
with the exception of a portion of the west side which is slated for future parking. Along
the future parking area a bituminous curb is acceptable at this time. However, when the
' future parking is added B612 concrete curb and gutter will be required. The parking stall
corners shall have radii of five feet. The west and south sides of the warehouse
building shall provide a buffer area between the drive aisle and the building.
6. All areas disturbed as a result of construction activities shall be immediately restored with seed
' and disc- mulched or wood fiber blanket or sod within two weeks of completion of each activity
in accordance with the City's Best Management Practice Handbook.
7. The applicant should re- evaluate the need for berms along the east property line.
c: Charles Folch, Director of Public Works
g.\en g\ani 0p4196 -9.doc
CITY OF
CHANHASSEN
690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
(612) 937 -1900 • FAX (612) 937 -5739
MEMORANDUM
TO: Sharmin Al -Jaff, Senior Planner
FROM: Steve A, Kirchman, Building Official k. q'�,
DATE: August 13, 1996
SUBJECT: 96 -9 SPR (Chuck's Grinding, Inc.)
I was asked to review the site plan proposal stamped "CITY of CHANHASSEN, RECEIVED, AUG 02
19 9 6 , CHANHASSEN PLANNING DEPT- " for the above referenced project.
I have no comments or recommendations concerning this application at this time.
I would like to request that you relay to the developers and designers my desire to meet with them as early
as possible to discuss commercial building permit requirements.
g:\safety \sak\memos \plan \ckgmd 1
D ROCK -SAGE G.M.U.
RACK - MOUNTED
'S
IROY C.M.U.
3/S" RIC..., ,...��.
SITE S GN - ELEVATIO : SECTION
1/2' a T -0'
- MILLER
HANSON
WESTERBECK
BERGER, INC
ARCHfTECTS A PLANNERS
1201 H NE AVENUE
MINNINN EAPOLIS PO(JS. UN 55403
(612) 332 -5420, FAX (612) 332 -5425
PROJECT: CHUCK'S GRINDING, INC.
FILE NO. DATE DRAWN COMM. N0. SHEET NO.
7/30/96 MDS 96013
i
L- - - - - - - - - - - - - - - - - - -�
Planning Commission Meeting - August 21, 1996
Mancino: And I would also suggest that commissioners that would like to go to that City
Council meeting and obviously the City Council has our Minutes and sees our recommendations,
but you may want to follow this to the City Council meeting too. Great, thank you.
PUBLIC HEARING:,
SITE PLAN REVIEW OF AN OFFICE WAREHOUSE BUILDING WITH AN AREA OF
16,704 So. FT. ON PROPERTY ZONED PUD -IOP AND LOCATED WEST OF
AUDUBON ROAD, SOUTH OF CHICAGO, MILWAUKEE, ST. PAUL & PACIFIC
RAILROAD, AND NORTHEAST OF COMMERCE DRIVE, CHUCKS GRINDING.
Kate Aanenson presented the staff report on this item and asked for any questions.
Farmakes: On the south elevation. We would be seeing the pitched roof ..on the other side, you
visually have...
Aanenson: Yes.
Farmakes: It'd be the north elevation.
Aanenson: Right. This is the north elevation.
Farmakes: That ... visual element on the south elevation and it's much smaller.
Aanenson: Yes. Narrower. Yeah, narrower. Right. The other thing I did mention is the sign.
They are allowed the one free standing sign, which they have submitted. Again the sign is,
architecturally all the signs in this development are allowed the wall sign and the free standing
monument sign. The sign is consistent with the architecture of the building and we would
recommend approval of that as part of the site plan.
Mancino: Any other questions at this point? Is the applicant here, and do you wish to address
the Planning Commission please.
Tom Hill: Good evening. My name is Tom dill and I'm with a firm by the name of Dunbar
Development. I am, we are the project developer for a group called Pegasus L.L.C. which is the
owner of this project. I'd like to just quickly introduce the three team members I have with me.
Jim Winkels from Amcon Corporation who has done a lot of work here in the city, and Frank
Wilson from Miller-Hanson-Westerbeck ... architectural firm who also did Centennial Hill. I
could just walk you through the site quickly and give you an idea of what we have here. As Kate
mentioned, we're located in the Chan Business Park. In the 2" Addition. We're at the end of
the east cul-de -sac on Commerce Drive. We have a site that we have under control with the
Audubon Partnership. Just about 2 % acres ... right to the west of the church at the end of that
cul -de -sac and currently we have a lease with one user for the building, that's Chucks Grinding..
We are finalizing with Amcon the construction schedule and the costs. Architectural plans are
about 90% complete, not including some of the suggestions that staff has made. That we really
39
Planning Commission Meeting - August 21, 1996
have no problems with them and we're anxious to work with staff to go through those final
details. We are in the process of doing our final review of the development... Our construction
schedule is approved. We would go ahead and probably start in September and hopefully...
sometime in February. The building itself...
Mancino: Do you have materials?
Tom Hill: Yes I do. There's one block piece I'm missing which is the lower block.
The ... block. I don't have that... As you come in the cul -de -sac, this is the face of the building
you'll see. The entry that we've been working with Sharmin on. We spent a lot of time with her
on the landscaping issues as well as the entrance and design of the exterior of the building. So
we do have an entry into the building and this, of course is all the office space. About 2,600
square feet of finished office space. The building, the back portion of the building is about, I
think it has about 18 foot clear. 22 foot clear exterior height in back. The building is designed
with a corduroy concrete block. The lower section of the building entrance... extends around the
entire building. That's a smooth faced score. It gives this small detail throughout it. And that's
also highlighted by these sections up on top. The top of the building, the metal flashing along the
roof here, also ties in with the roof scheme here in front. So it pulls it all together. You can see
here with, our user, Chucks Grinding had asked us to look at with some windows in the shop
production area so we did include windows and I think if you look through the plan, you'll see
the windows do surround the entire building so it does break up, although this is not a seemingly
large building, it does break up the look of the building. Also it provides a nice environment for
the employees inside. In the building itself, Chucks Grinding is a company that's based in
Minnetonka right now. It's been in business for 25 some years and they were looking, they came
to us and they were looking for ... so they will bring about 20 production people to the city and
then there's, I think I'd call it 3 %2 office.
Joyce: Is it grinding tools I take it?
Tom Hill: No, it's precision machine. And like I said, Chuck Reuter is the family. Chuck just
passed away just a few months ago unfortunately but his family still owns the business. His wife
is involved and his son and a daughter so it's a family held business. It has been... They're very
excited about being out here. They've very excited. They're in Minnetonka now and they want
to get away from a multi - tenant situation and control their own destiny... This is the color that
will be the metal roof and the facia. The metal facia goes around the top end of the building.
This is the metal window frames and door frames. This is the color of the block that goes,
there's a smooth face for it. It's that band that goes around the entire building. And then the
bottom base block is a tan color block, and it's pretty close to what you see here...better idea
since I don't have a sample of that... But we feel it's a fairly attractive building. Our user is very
happy with it. As I said before, we worked I think fairly closely with staff to get to where we
need to be in this. We have 31 parking stalls on the site. Those include employee parking and
also staff parking, for the office staff in front. There are three dock doors in the back. The dock
doors all face the north over the railroad. We have worked with staff to provide the appropriate
amounts of screening. To screen those from future houses that ... and also from the traffic that's
on Audubon. As I mentioned before, we're very comfortable with what staff has worked with us
.,
Planning Commission Meeting v August 21, 1996
on. We're, as I mentioned before, excited about moving forward and finalizing those details.
Finalizing our plans and I guess I would just be ready to answer any questions.
Mancino: Okay. Any questions from commissioners at this point?
Joyce: What is sludge?
Tom Hill: I'm sorry?
Joyce: What is sludge?
Tom Hill: Sludge is a by product of the grinding process. They use a coolant in grinding metal.
So when they're grinding the metal, they use a coolant that runs over the metal and it picks up
metal particles that are ground off the material. It's not a hazardous material in any way but they
do collect it and then store it in a dumpster and then a company like BFI comes up and picks it up
every couple, I think it's twice a month.
Joyce: Just like a regular sized dumpster like a garbage.
Tom Hill: Yes. Just like a box.
Mancino: The next question is, what happens next?
Tom Hill: It is a quite an issue just for Chucks just purely by it's weight. Because we have a
dumpster that holds metals instead of trash so it's quite a process ... come in the building. There
was one other issue in the staff report they mentioned a condition about trash storage and you
mentioned screening. All trash storage will be inside.
Mancino: Tom, could you explain to me a little bit, when I went out there to the site, one of the
things that I noticed on that north property line is that ... explain a little bit of the grading to me.
Is that you can see the view shed from your north property line, you can see all the way to
Highway 5. I mean you can see the Bluff Creek. You can see the whole valley when you're
standing up there.
Tom Hill: From this site?
Mancino: Yes. From the north, from your north property line or from...
Tom Hill: On the railroad tracks.
Mancino: Out of the building. Where the railroad is. So my question is, how will there be year
round screening of, number one parking to some degree. And most assuredly for the dock area.
Tom Hill: Well I think the, I'd have to.
41
1
�I
Planning Commission Meeting - August 21, 1996
Mancino: Is there a berm that is going to do it?
Tom Hill: No, I don't think your plans have a berm as such and we worked with staff pretty
closely about what to put in the area and I think we had, in the original plan we submitted we
increased the number of evergreens up in that area.
Mancino: There are three.
Tom Hill: And there was also some discussion about using sumac in that area, which is very fast
growing. That does... screening for the winter though but there are still some evergreens in that
area and our understanding was that staff was fairly... around the docks. Towards that area to the
north...
Mancino: Okay. So there is going to be no berming at all? I know that's what Pillsbury did. I
would then, will suggest adding some more year round screening in that area just to add to the
three trees that are there. Thank you. Is there anyone else from your team that wishes to
approach, to present to the Planning Commission?
Tom Hill: I think we're all done. Thank you very much.
Mancino: Thank you. May I have a motion and a second to open this for a public hearing.
Farmakes moved, Skubic seconded to open the public hearing. The public hearing was
opened.
Mancino: This is open for a public hearing. Anyone wishing to address the Planning
Commission, please do so. Seeing none, may I have a motion to close, and a second, the public
hearing.
Skubic moved, Joyce seconded to close the public hearing. The public hearing was closed.
Mancino: Comments from commissioners. Bob.
Skubic: I don't really have anything to say here that's already been said except... welcome
another business into the city. I'm just glad to have a professional business.
Joyce: Nothing more.
Mancino: Kevin.
Mancino: Jeff. Okay. I don't really either. The only condition that I would like to add, oh wait
one question.. I would like to add more screening on that north side. I would not like to see the
sumac used, because it won't be year round screening and you do have just a wide open view
shed of that whole area. The Bluff Creek area. So I would like to, it could certainly be a
combination of the trees that are already there and then some arborvitae hedge on the perimeter
��pj
Meeting - August 21 1996
Planning Commission g gus ,
of the parking lot. Right there. So those are my only additional comments. Date, I do have a '
question on a recommendation, just because I haven't seen this before in staff s writing. On
number 4, all roof mounted equipment shall be screened by walls of compatible appearing ,
material. And then it says all exterior process machinery, tanks, etc. are to be fully screened by
compatible materials. As an alternative the applicant can use factory applied panels to the
exterior of the equipment. What is that? ,
Aanenson: We have some industrial users in the city that need cooling tanks outside the
buildings, such as Rosemount ... and what we found in the past is they can't apply certain '
screening materials to them because they come from the manufacturer in a certain way and they
are large. Sometimes they're 20 -30 feet high. So we've kind of just put that as a standard
condition now. That if they can't be manufactured with, you know painted to match the building,
that they come with some other type of applied panel that would work to screen it, because
sometimes as the use may change in a building, and they need to add, that sort of thing, we want '
to make sure that that's covered. For example Pillsbury which has large coolant systems for the
freezers. What we decided there is actually just to let them disappear in the sky. Actually just let
them come from the factory unpainted because then it becomes a maintenance problem, and to
try to put fencing up there, the wind load is.
Mancino: It will blow off. I
Aanenson: Yes, right. So I guess we wanted just, it's kind of a catch all. We're starting to put
that in now. I
Mancino: Is there any planning for outdoor storage at all?
Tom Hill: No. There is no outside storage. '
Mancino: Okay, thank you. Thank you for that. '
Joyce: I do have a question... Condition 15 Date. The applicant should re-evaluate the need for
berms along the east property line. Do we need to do something with that? ,
Aanenson: I think that ties back in to Nancy's comment. The year round screening.
Hempel: That detail was actually mine. My condition.
Aanenson: Oh sorry, '
Hempel: They were placing a berm on a very steep side slope on the east side which really had
no effect. May I suggest relocating that berm to the northerly side to help improve the screening.
Aanenson: Right. So it ties back in to Nancy's comment, right. I
Mancino: Great.
43 '
1
Planning Commission Meeting - August 21, 1996
1
Aanenson: And that goes back to the prairie thing where we were saying, you know you're really
1 basing the topography, not accomplishing anything trying to do that there so.
Mancino: Okay, good. Boy, I drove around that complex, that business complex today and it's
really, really looking good.
1 Aanenson: It's coming along.
Mancino: Yeah. Everybody takes such good care of the buildings and I don't know, it's a good
1 looking complex. So we're happy to have you. May I have a motion?
Joyce: I'll make a motion. That the Planning Commission recommends approval of Site Plan
1 #96 -6 for Chucks Grinding Inc. as shown on the plans dated received July 29, 1996 and subject
to the following conditions 1 through 16. I think we should strike 15 though and I'll put in 16
which will state, relocating the berm from the eastern property line to the northern property line
and also on that berm, maybe working with staff to help with the screening of the parking lot and
dock area. Consider coniferous type of trees, as an example arborvitae hedge, that sort of thing.
1 Mancino: Is there a second to the motion?
Skubic: Second.
1 Mancino: Motion has been made and seconded. Any discussion?
1 Joyce moved, Skubic seconded that the Planning Commission recommend approval of Site
Plan #96-9 for Chucks Grinding Inc. as shown on the plans dated Received July 29, 1996,
and subject to the following conditions:
1 1. The applicant shall meet with the Fire Marshal.
1 2. The applicant shall meet with the Building Official as requested in his attached memo.
1 3. The applicant shall enter into a site development contract with the city and provide the
necessary financial security to guarantee compliance with the terms of approval.
1 4. All roof mounted equipment shall be screened by walls of compatible appearing material.
Wood screen fences are prohibited. All exterior process machinery, tanks, etc., are to be
fully screened by compatible materials. As an alternative, the applicant can use factory
1 applied panels on the exterior to the equipment that would blend in with the building
materials.
' 5. All freestanding signs shall be limited to monument signs. The sign shall not exceed
eighty (80) square feet in sign display area nor be greater than eight (8) feet in height.
The sign treatment is an element of the architecture and thus should reflect with the
i
1
Planning ommission Meeting - August 21, 1996 1
g g �
quality of the development. A common theme will be introduced at the development's
entrance monument and will be used throughout. Each property shall be allowed one
monument sign located near the driveway into the private site. The monument sign must '
maintain a ten foot setback from the property line. The signs should be consistent in
color, size, and material throughout the development. The applicant should submit a sign
package for staff review. A separate permit is required for all signage on site.
6. Lighting for the interior of the business center should be consistent throughout the
development. A decorative, shoe box fixture (high pressure sodium vapor lamps) with a '
square ornamental pole shall be used throughout the development area for area lighting.
All light fixtures shall be shielded. Light level for site lighting shall be no more than
foot candle at the property line. This does not apply to street lighting. Lighting
equipment similar to what is mounted in the public street right -of -ways shall be used in
the private areas. Wall pack units may be used provided no direct glare is directed off-
site and no more than % foot candle of light is at the property line.
7. Park fees shall be paid in accordance with city ordinance requirements.
& The applicant shall provide documentation that the variety of elm specified on
landscaping plans is Dutch Elm Disease resistant. Also, the applicant shall work with
staff to explore options for alternative lawn plantings.
9. All construction vehicles shall access the site at approved rock construction entrances '
only. Haul routes shall be pre- approved by the City. The applicant will be required to
maintain haul routes and clean the streets of any dirt and mud accumulated from vehicles
tracking. Any damage to City streets, curbs or other public facilities will be the '
responsibility of the applicant.
10. The maximum allowable slope on berms shall be 3:1. '
11. Additional Type I erosion control fence shall be installed along the west property line.
Erosion control measures shall be in place and maintained at all times until the site has '
been fully restored, revegetated, and removal is authorized by the City. Failure to
maintain the erosion control measures will result in the issuance of stop work orders. '
12. Revised storm drainage calculations which include the stormwater runoff from Lot 1
Block 1, Chanhassen Business Center Addition shall be submitted to the City Engineer '
for review and approval. Conveyance of storm drainage in the sludge pick -up area needs
to be addressed. The applicant's engineer shall work with City staff in revising the
drainage plan to address the additional runoff from the lot to the east (Lot 1, Block 1,
Chanhassen Business Center).
13. The perimeter of the paved parking lot shall be bordered by B612 concrete curb and '
gutter with the exception of a portion of the west side which is slated for future parking.
Along the future parking area a bituminous curb is acceptable at this time. However,
45 '
Planning Commission Meeting - August 21, 1996
when the future parking is added B612 concrete curb and gutter will be required. The
parking stall comers shall have radii of five feet. The west and south sides of the
' warehouse building shall provide a buffer area between the drive aisle and the building.
14. All areas disturbed as a result of construction activities shall be immediately restored with
seed and disc- mulched or wood fiber blanket or sod within two weeks of completion of
each activity in accordance with the City's Best Management Practice Handbook.
15. The applicant shall move the berm from the east property line to the north property
line to help screen the parking lot and dock area. The berm shall be planted with
coniferous trees, i.e. arborvitae hedge to provide year round screening.
All voted in favor and the motion carried.
Mancino: The motion carries and goes to City Council.
Aanenson: The 9 1h .
Mancino: On?
Aanenson: September 9`
1 Mancino: September 9` Thank you.
' PUBLIC HEARING:
PRELIMINARY PLAT REQUEST TO REPLAT THREE LOTS AND THREE
OUTLOTS INTO THREE LOTS AND ONE OUTLOT AND PHASING
' CONSTRUCTION/REMODELING OF THE ENTERTAINMENT COMPLEX INTO
TWO PHASES, IN AN AREA ZONED BG, GENERAL BUSINESS AND CBD,
CENTRAL BUSINESS DISTRICT, LOCATED NORTH OF THE RAILROAD TRACKS,
EAST OF MARKET BOULEVARD AND SOUTH OF WEST 78 " H STREET,
CHANHASSEN ENTERTAINMENT CENTER, LOTUS REALTY.
' Kate Aanenson presented the staff report on this item.
' Mancino: Is the applicant here?
Vemelle Clayton: I'm Vernelle Clayton, 422 Santa Fe Circle... should probably say is, just to
review this a little bit more. As you know several months ago we approved this from a
' complex... facade, boardwalk, and parking... are coming back in for subdivision. When we
started, so we.'re back in for a subdivision. Everything's taken a little bit longer than we thought
' it would but it's not that things haven't been happening for the project. At the time we started
this project, back when we were thinking it would be all developed as one entity and we brought
it in as one entity. As it evolved and before we went through the planning process, planning
46