2011-56 CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE: October 10, 2011 RESOLUTION NO: 2011 -56
MOTION BY: Laufenburger SECONDED BY: Tjornham
A RESOLUTION APPROVING DEDUCT CHANGE ORDER NO. 1 TO
THE HIGH ZONE WATER TOWER PROJECT NO. 11 -03
WHEREAS, on August 22, 2011, the Council accepted a bid for the High Zone Water
Tower Project No. 11 -03. The project cost is $2,096,001.00.
WHEREAS, change orders are necessary to make changes that may arise during
construction.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approves Change Order No. 1 for the following items on the High Zone Water Tower Project No.
11-03:
- Replace 205 LF of 18 -inch HDPE watermain with 18 -inch PVC C900 DR18.Replace 204 LF of
14 -inch HDPE storm sewer pipe with 15 -inch RCP CL 5 Gasketed joint pipe.
- Replace 55 LF of 24 -inch HDPE storm sewer pipe with 24 -inch RCP CL 5 Gasketed joint pipe.
- Replace stairs for mezzanine access with ladder and safety climb system per spec.
- Reduce the size of the mezzanine access enclosure to two sides 10'x10'.
The change order decreases the contract by $37,707.00.
Passed and adopted by the Chanhassen City Council this 10 day of October, 2011.