6. Preliminary Plat to subdivide 35.83 acres into 45 single family lots, two outlots and a neighborhood parkQ U - J Q Q LLJ CITY OF L e CHANHASSEN STAFF REPORT PC DATE: April 19, 1995 CC DATE: May 8, 1995 CASE #: 93 -11 SUB LP PROPOSAL: Preliminary Plat to Subdivide 35.83 Acres into 45 Single Family Lots, Two Outlots and a Neighborhood Park LOCATION: North of Kings Road, west of Minnewashta Parkway to the Victoria it pd str8�� Limits / Endorsed 1� Du-' f } APPLICANT: Harstad Companies Loucks and Associates Modl£Pe Reject 2191 Silver Road 72000 Hemlock Lane ----- New Brighton, MN 55112 Maple Grove, MN 555369 sub' 53 S7 - 111ed to Coawa PRESENT ZONING: RSF, Residential Single Family ACREAGE: 35.83 acres (gross) 17.74 acres (net) DENSITY: 1.2 units /acre gross 2.48 units /acre net ADJACENT ZONING AND LAND USE: N - RSF, Single Family S - RSF, Single Family E - RSF, Single Family W - Victoria WATER AND SEWER: Available to the Site PHYSICAL CHARACTER: The site has a varied topography with the high point running north and south through the center of the plat. There is a significant stand of trees in the northwest corner of the site. 2000 LAND USE PLAN: Low Density Residential 640• Harstad Companies April 19, 1995 Page 3 is proposing the extension of the easterly leg of White Oak Lane as a cul -de -sac to serve this 0 Harstad Companies April 19, 1995 Page 5 Surface Water Management Plan The City has prepared and adopted a Surface Water Management Plan (SWMP) to serve as a tool to protect, preserve and enhance water resources. The plan identifies, from a regional perspective, the storm water quantity and quality improvements necessary to allow future development to take place and minimize its impact to downstream water bodies. In general, _ the water quantity portion of the plan uses a 100 -year design storm interval for ponding and a 10 -year design storm interval for storm sewer piping. The water quality portion of the plan uses William Walker, Jr.'s Pondnet model for predicting phosphorus concentrations in shallow _ water bodies. An ultimate conditions model has been developed at each drainage area based on the projected future land use, and therefore, different sets of improvements under full development were analyzed to determine the optimum phosphorus reduction in priority water bodies. Storm Water Quality Fees The SWMP has established a connection charge for water quality systems. The cash dedication will be equal to the cost of land and pond volume needed for treatment of the phosphorus load leaving the site. The requirement for cash in lieu of land and pond construction shall be based upon a schedule in accordance with the prescribed land use zoning. Values are calculated using the market values of land in the City of Chanhassen plus a value of $2.50 per cubic yard for excavation of the pond if the applicant constructs the pond or $4.00 per cubic yard for excavation of the pond if the City constructs the pond. Fees are reduced based on the costs of the developers contribution to the SWMP design parameters. The proposed SWMP quality charge has been calculated at $800 /acre for single family residential developments. This proposed development of 27.55 acres would then be responsible for a water quality connection charge of $22,040. Since the applicant is proposing to construct water quality basins in accordance with the City's SWMP, these fees will then be waived. Storm Water Ouantitv Fees The SWMP has established an connection charge for different land uses based on an average, city -wide rate for the installation of water quantity systems. This cost includes all proposed Harstad Companies April 19, 1995 ' Page 6 surface water quantity fees for construction of improvements in accordance with SWMP ' which include such items as outlet control devices, trunk storm sewer pipes, pond oversizing, etc. Credits towards this fee will be reviewed after the final construction plans have been approved by the City. ' DRAINAGE AREAS ' The site is divided into two drainage subdistricts with the westerly one quarter of the site draining west into wetlands located within the City of Victoria. These wetlands are part of the Lake St. Joe basin and drain into Lake St. Joe from the west. The storm drainage plan ' should also be analyzed by the applicant's engineer in order to meet the City's Surface Water Management Plan (SWMP). The drainage areas have changed enough since the original set of plans that staff requires a new set of hydrologic calculations for the site. ' The pond in the park should be designed to pretreat approximately 16.5 acres of runoff according to the SWMP. If there is additional acreage to this pond due to a change in the watershed boundaries, the pond size should account for the additional runoff. Ponding must meet Walker's Pondnet standards of approximately 65% total phosphorus removal before it is discharged off -site. The SWMP calls for a 12 pipe to be directed south under Kings road ' and continue on to Lake St. Joe where the treated stormwater can be discharged. If the adjacent property owners on the south side of Kings Road (Morgan/Scott) are willing to grant the City a drainage and utility easement, the City will credit the applicant to install the storm ' sewer from Kings Road down to Lake St. Joe. If the City is not granted a drainage and utility easement, then the pond will have to be enlarged to a water quantity pond and will be required to maintain pre - developed runoff rates off -site for a 100 -year 24 -hour storm. This ' means the runoff will continue to drain underneath Kings Road through the Morgan/Scott parcel to Lake St. Joe as it exists with predevelopment conditions. ' The runoff to the southwest portion of the site should be evaluated for pre - developed and post developed conditions. Additional runoff to this area especially from impervious surfaces may require a sediment pond prior to discharging into the wetland located just east of this site in Victoria. Also, City ordinance requires that stormwater runoff from the site must be controlled at pre - developed runoff rates. ' There will be some stormwater discharge from the southeast corner of the site and Kings Road that will be conveyed via storm sewer through Outlot A south of Kings Road which is ' proposed to be dedicated to the City. A sediment pond is necessary to pretreat the runoff from the road before it discharges into Lake St. Joe. The sediment trap should be designed to remove 35% phosphorus according to Walker's Pondnet model. Harstad Companies April 19, 1995 Page 7 GRADING The City half - section maps indicate and existing 33 -foot wide right -of -way for Kings Road. However, after further research by the city attorney's office, it appears the City has not been conveyed the necessary right -of -way as shown on the half - section maps. The city attorney's office has advised staff that in cases such as this, where the existing gravel road has been maintained (i.e. snow plowing, grading, etc.) by the City for over six years, the City attains prescriptive rights to the public right -of -way for Kings Road which is generally defined to be limited to the travelled portion of the roadway along with the shoulder, drainage ditch, inslope and any land deemed to be a necessary appurtenance for the roadway. In this situation, Kings Road has been maintained by the City for over the six -year period. The width of Kings Road varies from 20 feet to 23 feet, thus limiting the public right -of -way use to this area. The existing roadway is a substandard rural street meandering back and forth within the proposed right -of -way. At the west end of Kings Road the roadway is entirely outside the 33 -foot "right -of- way ". The City has received a request from the applicant to perform a 429 public improvement project to construct Kings Road. The City considered the request and required that an escrow be supplied to the City to perform a feasibility study. However, the applicant did not provide the City with the escrow and thus, the petition was not acted upon. Staff has met again with the applicant to discuss the issues involved in performing a 429 project to upgrade Kings Road. A 429 public improvement project requires a feasibility study, public hearing and authorization by the City Council. The applicant, through negotiation with the City, is proposing to dedicate a 50 -foot wide right -of -way which includes the existing Kings Road gravel surface to construct the new street. Staff has compromised on the City's standard 60 -foot wide right -of -way as a part of negotiations. The preliminary grading plan proposes to grade the entire site. For the most part, the site is devoid of trees except in the northwest corner of the site. This area is proposed to be served by a private street and the lots (4 -8, Block 3) custom graded at time of building permit. Due to the size of the parcel, it is anticipated that the applicant will proceed with several phases in order to complete the overall development. In conjunction with upgrading Kings Road the grading appears to be contained within the proposed right -of -way and not encroaching upon the properties south of Kings Road with the exception of Outlot A for a storm sewer and sediment trap. The proposed street grades along Kings Road exceeds the City's ordinance (0.50% to 7.0 %). A variance would be required for the street grades. Staff is concerned with a proposed drainage swale on Lot 24, Block 3. Due to the contributing drainage, staff believes this area will be saturated most of the time. Staff recommends the grading be adjusted if possible to sheet drain across the rear yard into the wetlands. Staff will be reviewing this after the final drainage calculations are submitted. In conjunction with final platting and the construction plan review process, staff will require the applicant to supply drainage plans providing the pre - developed and post- developed I Harstad Companies April 19, 1995 ' Page 8 drainage areas along with runoff calculations for pre - development and post - development ' conditions for 10 -year and 100 -year 24 -hour storm events. Storm water runoff from the site shall maintain the pre- developed conditions for a 100 -year, 24 -hour storm duration. The grading plan shall also reflect the normal and high water elevations in the wetlands and storm ' water ponds for both pre - developed and post - developed conditions. Water quality ponds shall be designed and constructed in accordance with the Walker Pondnet model which essentially uses a 2 -inch rainfall, however, the rate of phosphorus retention will vary on the function ' and value of the wetlands downstream. In addition, detailed drainage plans and calculations indicating drainage to individual catch basins will also be required. ' UTILITIES There appears to be at least one existing structure (house) on the parcel located in the vicinity of the parkland. The applicant shall be responsible for obtaining and complying with the necessary agency permits. A majority of the site is capable of being serviced by municipal sanitary sewer and water by extending utilities from Minnewashta Parkway along Kings Road. A lift station is proposed to service the westerly portion of the development. The applicant should size the lift station to accommodate future development south of Kings Road (approximately 10 acres). The lift station will also need to be fitted with a telemetry system ' as consistent with the other City lift stations and well houses. The City has agreed to share the cost of this telemetry system on a 50/50 basis with the applicant. The applicant has also requested that the City compensate them for the oversizing of the lift station. The City does not have a funding mechanism to assist the applicant in the cost of constructing the lift station without doing a public improvement project ( §429 assessable project) which has been discussed previously with the applicant. If the applicant wishes to further pursue City cost ' participation of the lift station, they should formally petition the City. The City is currently scheduling developments and capital improvement projects for 1996 and 1997. All petitions received by the City at this point will most likely be considered for a late 1996 or 1997 public improvement project. The westerly one -third of this development is dependant on the lift station to provide sanitary sewer service as proposed. Without the lift station, the westerly one -third of the development should be considered premature. The lift station design will be further reviewed during the construction plan and specification review process. ' The plans are providing utility stubouts for the future extension to the adjacent parcels to the north and east. The plans also propose to install individual utility services to the existing homes south of Kings Road. Contingent upon parkland acquisition, the City is proposing to ' contribute towards a portion of the utility and street costs along Kings Road. According to City ordinance, the parcel south of Kings Road must hook up to the new utilities within 12 months after the utilities are operational if it is within 150 feet of the utilities. ' Upon review of the utility plan layout, it appears fire hydrants have been revised in accordance with the City Fire Marshal's recommendations. Staff has reviewed the alignment Harstad Companies April 19, 1995 Page 9 of the utility lines and recommends relocating the forcemain and sanitary sewer line proposed between Lots 25 and 26, Block 3 to the westerly edge of Lot 25, Block 3 and Outlot B and between Lots 24 and 25, Block 3 to avoid future conflicts with the homes. In addition, this will result in the sanitary sewer line being much shallower. These types of revisions will be further addressed during the construction plan and specification review process. Detailed construction plans and specifications for the street and utility improvements will be required for review by staff and City Council approval in conjunction with final plat approval. The street and utility improvement shall be designated and constructed in accordance with the City latest edition of the Standard Specifications and Detail Plates. The applicant will be required to enter into a development contract with the City and provide the necessary financial security to guarantee installation of the public improvements and conditions of approval. As with other typical city developments, the moisture content in the soil is relatively high and the City has employed the use of draintile behind the curbs for improving both road sub -base drainage as well as providing a discharge point for household sump pumps. The applicant should be aware that the City will be requiring with the street and utility construction to include a draintile system for those lots which do not abut a wetland or storm pond. In addition, subdivision in the past have required up to a 2 -foot granular subcut for the street section. The applicant should be advised that soil conditions may require some sort of modification to the typical street sections. The appropriate drainage and utility easements should be dedicated on the final plat for all utilities and ponding areas lying outside the right -of -way. The easement shall be a minimum of 20 feet wide. The City will also require that all ponding areas be designed to provide access for maintenance equipment. The design shall be subject to approval by the City Engineer. EROSION CONTROL The grading plan does provide minimal erosion control measures (Type 1); however, adjacent to all wetland areas the erosion control fence should be Type III. All site restoration and erosion control measures shall be in accordance with the City's Best Management Practice Handbook. Additional erosion control fence (Type I) may be required by the City behind the curbs during new home construction. STREETS Access to the development is proposed via Kings Road which is a narrow gravel roadway between 20 to 23 feet wide. Kings Road is proposed to be upgraded to urban street standards to adequately address traffic and ordinance requirements. The City's urban standards consist Harstad Companies April 19, 1995 ' Page 10 of a 31 -foot wide back -to -back bituminous street section with concrete curb and gutter. According to the ordinance right -of -way shall be 60 feet wide which the plans propose. On Kings Road the applicant is proposing to dedicate 50 feet of the normally required right -of- way. The City has compromised on the right -of -way width as a part of negotiations. The ' applicant will be constructing Kings Road only up to Country Oaks Road. Outlot B will not be able to subdivide until Kings Road is upgraded to a full urban city street. The Outlot (B) may be subject to assessments for the cost of upgrading Kings Road in the future. A 5 -foot ' wide concrete sidewalk is proposed along the west side of Country Oaks Lane. The site will eventually be connected to the existing Country Oaks Road to the north once the Hallgren parcel develops. On the east side of this development there exists a combination of parcels (Headla/Wenzel) which could be further subdivided. Access to the Headla/Wenzel parcels has been considered at this time. The Headla parcel abuts Stratford Lane which is ' only constructed for approximately 250 feet west of Minnewashta Parkway. When Stratford Ridge was platted an Outlot B was created for future extension and deeded to the Stratford Ridge Homeowners Association versus the City. Ms. Hallgren gains access to her property ' through/over this Outlot. Access to the Headla/Wenzel parcels is provided with the extension of White Oak Lane. A temporary cul -de -sac is proposed at the east end of White Oak Lane. Barricades shall be placed at the end of the temporary cul -de -sac and a sign indicating that "THIS STREET WILL BE EXTENDED IN THE FUTURE." Staff will also place this condition within the development contract which is recorded against all of the parcels in the development. With the exception of Kings Road, street grades appear to be within the City's ordinance. On Kings Road the street was designed to be compatible with the existing topography which ' resulted in street grades between 0.49% to 10.00 %. Staff recommends a variance to the City ordinance be approved. Lot 32, Block 3 will have street access and utility service from Country Oak Lane. The home should be required to access Country Oak Lane as well. ' PARK AND RECREATION In the interest of fulfilling this recommendation, a series of meetings between the City of ' Chanhassen and Harstad Companies were held throughout 1994 and to date. The acquisition of the park, among other issues, were discussed at these meetings. Specific to the park ' acquisition, the following information was forwarded to Harstad Companies. Generally, the transaction would entail the following elements: 1. The city would accept the dedication of parkland from Harstad Companies. This dedication would equal their required dedication per city ordinance. The land area Harstad Companies April 19, 1995 Page 11 requested would commence at the property's eastern border (Lake Minnewashta) and extend to the west. This dedication would entail approximately 1.75 acres. 2. The remainder of the park would be purchased from Harstad Companies. 3. In assuming ownership of the park, the city would accept the responsibility for its portion of public improvements. These improvements generally include street and curb construction and utility costs (sanitary sewer, water and storm sewer). More specifically, the city would pay for its 50 % of the Kings Road improvements along the park frontage and underlying improvements including grading sewer and water, and associated curb, a water and sewer unit (to accommodate any future hookup) and stormwater costs. On January 24, 1995, the Commission recommended the following: Park The plat shall include a 8± acre park at the northwest intersection of where Kings Road currently is located and Minnewashta Parkway. The acquisition of the park to be accomplished through park dedication (1.8 acres) and purchase (6.28± acres). This acquisition shall be a condition of final plat approval. A purchase agreement shall be negotiated by the city contingent upon city council approval. Full park fee credit shall be granted as a part of these negotiations. Trail Acceptance of full trail dedication fees in force upon building permit application is recommended. Current trail fees are $300 per single family residential unit. COMPLIANCE TABLE Block 1 Lot Area (15,000 s.f. required) Street Frontage (90' required) Lot Depth (125' required) Lot 1 15,588 90 169 Lot 2 15,728 93 169 Lot 3 18,335 100 176 Lot 4 18,272 110 155 Lot 5 18,769 90 193 C 1 0 Harstad Companies April 19, 1995 Page 12 Lot 6 16,750 106 182 Lot 7 15,724 101 150 Lot 8 15,003 100 1 150 Lot 9 15,003 100 1 150 Block 2 Lot Area (15,000 s.f. required) Street Frontage (90' required) Lot Depth (125' required) Lot 1 15,605 90 171 Lot 2 15,057 90 162 Lot 3 15,590 100 151 Lot 4 16,991 114 1 150 Block 3 Lot Area (15,000 s.f. required) Street Frontage (90' required) Lot Depth (125' required) Lot 1 15,001 100 150 Lot 2 15,001 100 150 Lot 3 15,001 100 150 Lot 4 15,001 100 150 Lot 5 15,001 96 137 Lot 6 17,304 100 137 Lot 7 25,631 106 220 Lot 8 29,889 136 220 Lot 9 19,069 136 140 Lot 10 15,023 106 140 Lot 11 15,193 90 140 Lot 12 15,057 90 141 Lot 13 15,108 102 145 Harstad Companies April 19, 1995 Page 13 Lot 14 15,001 100 150 Lot 15 15,001 100 150 Lot 16 16,497 110 150 Lot 17 18,302 107 150 Lot 18 15,062 100 150 Lot 19 15,249 100 152 Lot 20 15,318 100 147 Lot 21 15,959 118 147 Lot 22 15,317 116 142 Lot 23 24,025 90 128 Lot 24 18,467 90 128 Lot 25 21,765 90 157 Lot 26 15,264 117 137 Lot 27 15,154 100 151 Lot 28 15,341 100 152 Lot 29 15,716 105 145 Lot 30 15,225 105 145 Lot 31 15,225 105 145 Lot 32 15,150 105 144 FINDINGS 1. The proposed subdivision is consistent with the zoning ordinance; Finding: The subdivision meets all the requirements of the RSF, Residential Single Family District lot dimension and area requirements. No variances are being requested. Staff is proposing access via a private drive for four lots off of White Oak Lane. The DNR supports the averaging of the lot sizes and frontages in the Shoreland District. Harstad Companies April 19, 1995 ' Page 14 2. The proposed subdivision is consistent with all applicable city, county and regional ' plans including but not limited to the city's comprehensive plan; Finding: The proposed subdivision is consistent with applicable plans. The ' proposed density of the development is consistent with the comprehensive plan. 3. The physical characteristics of the site, including but not limited to topography, soils, vegetation, susceptibility to erosion and siltation, susceptibility to flooding, and storm water drainage are suitable for the proposed development; Finding: The proposed site is suitable for development. The conditions of the staff report should mitigate all vegetation, soil and storm water issues. 4. The proposed subdivision makes adequate provision for water supply, storm drainage, sewage disposal, streets, erosion control and all other improvements required by this chapter; ' Finding: The proposed subdivision is served by adequate urban infrastructure as part of the improvements required of the subdivision. ' 5. The proposed subdivision will not cause environmental damage; ' Finding: Staff is requesting the applicant provide a woodland management plan. This plan should preserve the integrity of the woodland canopy. ' 6. The proposed subdivision will not conflict with easements of record. Finding: The proposed subdivision will not conflict with existing easements, but rather will expand and provide all necessary easements. 7. The proposed subdivision is not premature. A subdivision is premature if any of the ' following exists: ' a. Lack of adequate storm water drainage. b. Lack of adequate roads. C. Lack of adequate sanitary sewer systems. ' d. Lack of adequate off -site public improvements or support systems. Finding: The proposed subdivision is provided with adequate urban ' infrastructure and is located within the Metropolitan Urban Services Area (MUSA) line. Kings Road will have to be built to city urban standards Harstad Companies April 19, 1995 Page 15 between Minnewashta Parkway and Country Oaks Road in order for this subdivision to go forward. PLANNING COMMISSION UPDATE On April 19, 1994, the Planning Commission recommended preliminary plat approval for the Oaks at Minnewashta. The neighbors of the area were concerned about access to their property during construction. The commission asked that a meeting be held with the neighbors to the resolve this issue before final plat. The other issue at the Planning Commission meeting was the drainage through the Morgan /Scott property. On Wednesday, May 3, 1995, staff met with Ms. Morgan, Ms. Scott and their attorney to discuss the concerns they had with the proposed drainage from the development. Staff is working with Morgan /Scott to find an equitable compensation for the drainage easement to extend storm sewer from this development underneath Kings Road towards Lake St. Joe. At the time of final plat, staff intends to have this issue resolved with Morgan /Scott. RECOMMENDATION Staff recommends the Planning Commission adopt the following motion: "The Planning Commission recommends approval of the preliminary plat #93 -11 to subdivide 35.83 acres into 45 single family lots and two outlots as shown on the plans dated April 7, 1995 and subject to the following conditions: 1. Upon completion, the developer shall dedicate to the City the utilities and street within all public right -of -way and drainage and utility easements for permanent ownership. Maintenance access routes shall be provided to all storm water ponding. The routes are subject to review and approval by the City Engineer. The appropriate drainage and utility easements should be dedicated on the final plat for all utilities and ponding areas lying outside the right -of -way. The easement shall be a minimum of 20 feet wide. 2. All areas disturbed during site grading shall be immediately restored with seed and disc mulched or wood fiber blanket or sod within two weeks of completing site grading unless the City's Best Management Practice Handbook planting dates dictate otherwise. All areas disturbed with slopes of 3:1 or greater shall be restored with sod or seed and wood fiber blanket. 3. All utility and street improvements shall be constructed in accordance with the latest edition of the City's Standard Specifications and Detailed Plates. Detailed street and ' Harstad Companies April 19, 1995 ' Page 16 utility plans and specifications shall be submitted for staff review and City Council ' approval in conjunction with final plat approval. 4. The applicant shall apply for and obtain permits from the appropriate regulatory ' agencies (i.e. Watershed District, MWCC, Health Department, DNR) and comply with their conditions of approval. ' S. The applicant shall enter into a development contract with the City and provide the necessary financial security to guarantee compliance with the terms of the development contract. ' 6. Storm drainage discharge from the site shall maintain the predeveloped runoff conditions. The applicant shall provide detailed storm sewer and ponding calculations ' for a 10 -year and 100 -year storm event of a 24 -hour duration. Water quality and quantity ponding calculations shall be submitted in accordance with the City's SWMP for the City Engineer to review and approve. ' 7. The applicant shall have soil borings performed on the site and submit a soils report to the City for review prior to issuance of building permits. ' 8. Lot 32, Block 3 shall take direct access from Country Oaks Lane and not Kings Road unless Kings Road has been upgraded to City standards. 9. A report or letter of clarification prepared by a qualified wetland delineator shall be submitted to the City documenting the location and integrity of all wetlands on the ' site. If there are wetlands on the site they shall be staked, surveyed and included on the grading and drainage plan. In addition, a buffer strip shall be incorporated by City ' ordinance. 10. The proposed development shall be responsible for SWMP water quality and quantity connection fees of $22,040 and $54,549, respectively. SWMP water quality and ' quantity connection fees may be credited /reduced depending on the applicant's contribution to on -site storm drainage improvements according to the City's SWMP ' design parameters. 11. Storm drainage from the southwest portion of the site shall be evaluated for pre and ' post - development condition. The City shall determine, based on the amount of impervious surface contributing to the wetlands located in the southwest portion of the site, whether or not a sediment basin will be required to pretreat runoff prior to ' discharging runoff into the wetlands. Harstad Companies April 19, 1995 Page 17 12. Outlot A shall be dedicated to the City by warranty deed for construction of a sediment basin and parkland. 13. Staff recommends granting a variance to the City's ordinance regarding street grades. Street grades on Kings Road shall be permitted up to 10 %. 14. The existing structures on the site shall be razed within 30 days after the final plat has been recorded. The applicant shall be responsible for obtaining and complying with the appropriate permits for demolition of all structures, wells and septic systems. 15. Detailed grading, drainage, erosion control and tree removal plans shall be required by the City for review and approval prior to issuance of building permits on Lots 4 through 8, Block 3. 16. All private driveways shall be built in accordance to the City's Ordinance No. 209 17. The lift station shall be designed to accommodate future development south of Kings Road (approximately 10 acres) and the City's telemetry system. The City will be responsible for up to a maximum of 50% of the cost of the telemetry system. 18. The applicant shall include with the street construction a drain tile system behind the curbs on all lots which do not directly abut a wetland or storm drainage pond. The drain tile system shall be designed and constructed in accordance with City standards and detail plates. 19. Erosion control fence adjacent to all wetland areas shall be the City's Type III. Erosion control fence on the entire site shall be maintained by the applicant until the entire site has been revegetated and removal is authorized by the City. 20. Barricades shall be placed at the end of the temporary cul -de -sac on White Oak Lane and a sign indicating that "THIS STREET WILL BE EXTENDED IN THE FUTURE." 21. Park The plat shall include a 8± acre park at the northwest intersection of where Kings Road currently is located and Minnewashta Parkway. The acquisition of the park to be accomplished through park dedication (1.8 acres) and purchase (6.2 acres). This acquisition shall be a condition of final plat approval. A purchase agreement shall be negotiated by the city contingent upon city council approval. Full park fee credit shall be granted as a part of these negotiations. Harstad Companies April 19, 1995 ' Page 18 Trail ' Acceptance of full trail dedication fees in force upon building permit application is recommended. Current trail fees are $300 per single family residential unit,with 1/3 of ' these fees to be paid at the time of final plat. 22. The applicant shall escrow with the city their fair share of the costs to extend Kings Road west of Country Oaks Road or a conveyance placed on the deed of Outlot B that these future lots will be responsible for 50% of the costs to upgrade Kings Road west of Country Oaks Road. ' 23. A woodland management plan shall be prepared as per city ordinance Section 18.61 (d). Prior to final plat approval, tree conservation easements shall be developed ' between staff and the applicant. Preservation of the red cedar trees will be evaluated. 24. Within 3 years after final plat approval, Outlot B must be subdivided consistent with ' the approved plat. After that time, Outlot B will subject to city ordinances in effect. 25. All park land shall be designated as an outlot on the final plat. ' final 26. Street names are subject to review and approval by Public Safety prior to plat approval. ' Road 27. A neighborhood meeting shall be held to resolve tree locations along Kings and access to the existing homes during construction prior to final platting. ' 28. Lots adjacent to the two ag/urban wetlands shall maintain the ordinance ' requirements of a 40' setback and 10' buffer strip. ATTACHMENTS ' 1. Memo from Dave Hempel dated April 11, 1995. 2. Letter from DNR dated February 1, 1995 3. Memo from Steve Kirchman dated February 6, 1995. ' 4. Letter from Lee Harvey dated March 2, 1995 5. Hearing notice 6. Park and Recreation minutes dated January 24, 1995. ' 7. Memo from Todd Hoffman dated January 9, 1995. 8. Preliminary plat dated April 7, 1995. CITY OF CHANHASSEN 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317 (612) 937 -1900 • FAX (612) 937 -5739 MEMORANDUM TO: Kate Aanenson, Planning Director FROM: Dave Hempel, Assistant City Engineer A",' --s Diane Desotelle, Water Resources Coordinator DATE: April 11, 1995 SUBJ: Preliminary Plat Review for The Oaks of Minnewashta File No. 94 -2 LUR WETLANDS It appears that there may be a small wetland north of Kii southwest corner of the site (Outlot B and Lot 25, Bloc confirmation of exemption from the wetland permit proc on site, they should be staked, surveyed, and included on buffer strip width as required by City Ordinance. In any is required from a qualified wetland delineator. ; Road on Lot 9, Block 1 and in the 3). A wetland alteration permit or is necessary. If there are wetlands grading and drainage plan with the ise, a report or letter of clarification The City has prepared and adopted a Surface Water Management Plan (SWMP) to serve as a tool to protect, preserve and enhance, water resources. The plan identifies, from a regional perspective, the storm -water quantity and quality improvements necessary to allow future development to take place and minimize its impact to downstream water bodies. In general, the water quantity portion of the plan uses a 100 -year design storm interval for ponding and a 10- year design storm interval for storm sewer piping. The water quality portion of the plan uses William Walker, Jr.'s Pondnet model for predicting phosphorus concentrations in shallow water bodies. An ultimate conditions model has been' developed at each drainage area based on the projected future land use, and therefore, different sets of improvements under full development were analyzed to determine the optimum phosphorus reduction in priority water bodies. Kate Aanenson The Oaks of Minnewashta ' April 11, 1995 Page 2 ' Storm Water Quality Fees ' The SWMP has established a connection charge for water quality systems. The cash dedication will be equal to the cost of land and pond volume needed for treatment of the phosphorus load leaving the site. The requirement for cash in lieu of land and pond construction shall be based ' upon a schedule in accordance with the prescribed land use zoning. Values are calculated using the market values of land in the City of Chanhassen plus a value of $2.50 per cubic yard for excavation of the pond if the applicant constructs the pond or $4.00 per cubic yard for excavation of the pond if the City constructs the pond. Fees are reduced based on the costs of the developers contribution to the SWMP design parameters. The proposed SWMP quality charge has been calculated at $800 /acre for single family residential developments. This proposed ' development of 27.55 acres would then be responsible for a water quality connection charge of $22,040. Since the applicant is proposing to construct water quality basins in accordance with the City's SWMP, these fees will then be waived. Storm Water Quantity Fees ' The SWMP has established an connection charge for different land uses based on an average, city -wide rate for the installation of water quantity systems. This cost includes all proposed SWMP trunk systems, culverts, and open channels and stormwater ponding areas for temporary runoff storage. The connection charge is based on the type of land use for the area. Fees will be based on the total developable land. Undevelopable area (wetlands), public parks, and existing ' development is exempt from the fees. The fees are negotiable based on the developers contribution to the SWMP design parameters. Single family residential developments will have a connection charge of $1,980 per developable acre. This proposed single family residential development of 27.55 acres would then be responsible for a water quantity connection charge of $54,549. The City will apply credits to the applicant's surface water quantity fees for construction of improvements in accordance with SWMP which include such items as outlet ' control devices, trunk storm sewer pipes, pond oversizing, etc. Credits towards this fee will be reviewed after the final construction plans have been approved by the City. ' DRAINAGE AREAS The site is divided into two drainage subdistricts with the westerly one quarter of the site draining west into wetlands located within the City of Victoria. These wetlands are part of the Lake St. Joe basin and drain into Lake St. Joe from the west. The storm drainage plan should also be analyzed by the applicant's engineer in order to meet the City's Surface Water Management Plan ' (SWMP). The drainage areas have changed enough since the original set of plans that staff requires a new set of hydrologic calculations for the site. t Kate Aanenson The Oaks of Minnewashta April 11, 1995 Page 3 The pond in the park should be designed to pretreat approximately 16.5 acres of runoff according to the SWMP. If there is additional acreage to this pond due to a change in the watershed boundaries, the pond size should account for the additional runoff. Ponding must meet Walker's Pondnet standards of approximately 65% total phosphorus removal before it is discharged off -site. The SWMP calls for a 12" pipe to be directed south under Kings road and continue on to Lake St. Joe where the treated stormwater can be discharged. If the adjacent property owners on the south side of Kings Road (Morgan /Scott) are willing to grant the City a drainage and utility easement, the City will credit the applicant to install the storm sewer from Kings Road down to Lake St. Joe. If the City is not granted a drainage and utility easement, then the pond will have to be enlarged to a water quantity pond and will be required to maintain pre- developed runoff rates off -site for a 100 -year 24 -hour storm. This means the runoff will continue to drain underneath Kings Road through the Morgan /Scott parcel to Lake St. Joe as it exists with predevelopment conditions. The runoff to the southwest portion of the site should be evaluated for pre- developed and post developed conditions. Additional runoff to this area especially from impervious surfaces may require a sediment pond prior to discharging into the wetland located just east of this site in Victoria. Also, City ordinance requires that stormwater runoff from the site must be controlled at pre- developed runoff rates. There will be some stormwater discharge from the southeast corner of the site and Kings Road that will be conveyed via storm sewer through Outlot A south of Kings Road which is proposed to be dedicated to the City. A sediment pond is necessary to pretreat the runoff from the road before it discharges into Lake St. Joe. The sediment trap should be designed to remove 35% phosphorus according to Walker's Pondnet model. GRADING The City half- section maps indicate and existing 33 -foot wide right -of -way for Kings Road. However, after further research by the city attorney's office, it appears the City has not been conveyed the necessary right -of -way as shown on the half - section maps. The city attorney's office has advised staff that in cases such as this, where the existing gravel road has been maintained (i.e. snow plowing, grading, etc.) by the City for over six years, the City attains prescriptive rights to the public right -of -way for Kings Road which is generally defined to be limited to the travelled portion of the roadway along with the shoulder, drainage ditch, inslope and any land deemed to be a necessary appurtenance for the roadway. In this situation, Kings Road has been maintained by the City for over the six -year period. The width of Kings Road varies from 20 feet to 23 feet, thus limiting the public right -of -way use to this area. The existing roadway is a substandard rural street meandering back and forth within the proposed right -of -way. At the west end of Kings Road the roadway is entirely outside the 33 -foot "right -of- way ". The City has ' received a request from the applicant to perform a 429 public improvement project to construct Kings Road. The City considered the request and required that an escrow be supplied to the City to perform a feasibility study. However, the applicant did not provide the City with the escrow ' and thus, the petition was not acted upon. Staff has met again with the applicant to discuss the issues involved in performing a 429 project to upgrade Kings Road. A 429 public improvement project requires a feasibility study, public hearing and authorization by the City Council. The ' applicant, through negotiation with the City, is proposing to dedicate a 50 -foot wide right -of -way which includes the existing Kings Road gravel surface to construct the new street. Staff has compromised on the City's standard 60 -foot wide right -of -way as a part of negotiations. The preliminary grading plan proposes to grade the entire site. For the most part, the site is devoid of trees except in the northwest corner of the site. This area is proposed to be served by ' a private street and the lots (4 -8, Block 3) custom graded at time of building permit. Due to the size of the parcel, it is anticipated that the applicant will proceed with several phases in order to ' complete the overall development. In conjunction with upgrading Kings Road the grading appears to be contained within the proposed right -of -way and not encroaching upon the properties south of Kings Road with the exception of Outlot A for a storm sewer and sediment trap. The ' proposed street grades along Kings Road exceeds the City's ordinance (0.50% to 7.0 %). A variance would be required for the street grades. ' Staff is concerned with a proposed drainage swale on Lot 24, Block 3. Due to the contributing drainage, staff believes this area will be saturated most of the time. Staff recommends the grading be adjusted if possible to sheet drain across the rear yard into the wetlands. Staff will ' be reviewing this after the final drainage calculations are submitted. In conjunction with final platting and the construction plan review process, staff will require the applicant to supply drainage plans providing the pre - developed and post- developed drainage areas along with runoff calculations for pre - development and post- development conditions for 10 -year and 100 -year 24 -hour storm events. Storm water runoff from the site shall maintain the pre- ' developed conditions for a 100 -year, 24 -hour storm duration. The grading plan shall also reflect the normal and high water elevations in the wetlands and storm water ponds for both pre - developed and post - developed conditions. Water quality ponds shall be designed and constructed in accordance with the Walker Pondnet model which essentially uses a 2'/2 -inch rainfall, however, the rate of phosphorus retention will vary on the function and value of the wetlands downstream. In addition, detailed drainage plans and calculations indicating drainage to individual catch basins will also be required. 1 UTILMES Kate Aanenson The Oaks of Minnewashta ' April 11, 1995 Page 4 ' received a request from the applicant to perform a 429 public improvement project to construct Kings Road. The City considered the request and required that an escrow be supplied to the City to perform a feasibility study. However, the applicant did not provide the City with the escrow ' and thus, the petition was not acted upon. Staff has met again with the applicant to discuss the issues involved in performing a 429 project to upgrade Kings Road. A 429 public improvement project requires a feasibility study, public hearing and authorization by the City Council. The ' applicant, through negotiation with the City, is proposing to dedicate a 50 -foot wide right -of -way which includes the existing Kings Road gravel surface to construct the new street. Staff has compromised on the City's standard 60 -foot wide right -of -way as a part of negotiations. The preliminary grading plan proposes to grade the entire site. For the most part, the site is devoid of trees except in the northwest corner of the site. This area is proposed to be served by ' a private street and the lots (4 -8, Block 3) custom graded at time of building permit. Due to the size of the parcel, it is anticipated that the applicant will proceed with several phases in order to ' complete the overall development. In conjunction with upgrading Kings Road the grading appears to be contained within the proposed right -of -way and not encroaching upon the properties south of Kings Road with the exception of Outlot A for a storm sewer and sediment trap. The ' proposed street grades along Kings Road exceeds the City's ordinance (0.50% to 7.0 %). A variance would be required for the street grades. ' Staff is concerned with a proposed drainage swale on Lot 24, Block 3. Due to the contributing drainage, staff believes this area will be saturated most of the time. Staff recommends the grading be adjusted if possible to sheet drain across the rear yard into the wetlands. Staff will ' be reviewing this after the final drainage calculations are submitted. In conjunction with final platting and the construction plan review process, staff will require the applicant to supply drainage plans providing the pre - developed and post- developed drainage areas along with runoff calculations for pre - development and post- development conditions for 10 -year and 100 -year 24 -hour storm events. Storm water runoff from the site shall maintain the pre- ' developed conditions for a 100 -year, 24 -hour storm duration. The grading plan shall also reflect the normal and high water elevations in the wetlands and storm water ponds for both pre - developed and post - developed conditions. Water quality ponds shall be designed and constructed in accordance with the Walker Pondnet model which essentially uses a 2'/2 -inch rainfall, however, the rate of phosphorus retention will vary on the function and value of the wetlands downstream. In addition, detailed drainage plans and calculations indicating drainage to individual catch basins will also be required. 1 UTILMES Kate Aanenson The Oaks of Minnewashta April 11, 1995 Page 5 There appears to be at least one existing structure (house) on the parcel located in the vicinity of the parkland. The applicant shall be responsible for obtaining and complying with the necessary agency permits. A majority of the site is capable of being serviced by municipal sanitary sewer and water by extending utilities from Minnewashta Parkway along Kings Road. A lift station is proposed to service the westerly portion of the development. The applicant should size the lift station to accommodate future development south of Kings Road (approximately 10 acres). The lift station will also need to be fitted with a telemetry system as consistent with the other City lift stations and well houses. The City has agreed to share the cost of this telemetry system on a 50/50 basis with the applicant. The applicant has also requested that the City compensate them for the oversizing of the lift station. The City does not have a funding mechanism to assist the applicant in the cost of constructing the lift station without doing a public improvement project ( §429 assessable project) which has been discussed previously with the applicant. If the applicant wishes to further pursue City cost participation of the lift station, they should formally petition the City. The City is currently scheduling developments and capital improvement projects for 1996 and 1997. All petitions received by the City at this point will most likely be considered for a late 1996 or 1997 public improvement project. The westerly one - third of this development is dependant on the lift station to provide sanitary sewer service as proposed. Without the lift station, the westerly one -third of the development should be considered premature. The lift station design will be further reviewed during the construction plan and specification review process. The plans are providing utility stubouts for the future extension to the adjacent parcels to the north and east. The plans also propose to install individual utility services to the existing homes south of Kings Road. Contingent upon parkland acquisition, the City is proposing to contribute towards a portion of the utility and street costs along Kings Road. According to City ordinance, the parcel south of Kings Road must hook up to the new utilities within 12 months after the utilities are operational if it is within 150 feet of the utilities. Upon review of the utility plan layout, it appears fire hydrants have been revised in accordance with the City Fire Marshal's recommendations. Staff has reviewed the alignment of the utility lines and recommends relocating the forcemain and sanitary sewer line proposed between Lots 25 and 26, Block 3 to the westerly edge of Lot 25, Block 3 and Outlot B and between Lots 24 and 25, Block 3 to avoid future conflicts with the homes. In addition, this will result in the sanitary sewer line being much shallower. These types of revisions will be further addressed during the construction plan and specification review process. Detailed construction plans and specifications for the street and utility improvements will be required for review by staff and City Council approval in conjunction with final plat approval. The street and utility improvement shall be designated and constructed in accordance with the City latest edition of the Standard Specifications and Detail Plates. The applicant will be Kate Aanenson The Oaks of Minnewashta April 11, 1995 Page 6 required to enter into a development contract with the City and provide the necessary financial security to guarantee installation of the public improvements and conditions of approval. As with other typical city developments, the moisture content in the soil is relatively high and the City has employed the use of draintile behind the curbs for improving both road sub -base drainage as well as providing a discharge point for household sump pumps. The applicant should be aware that the City will be requiring with the street and utility construction to include a draintile system for those lots which do not abut a wetland or storm pond. In addition, subdivision in the past have required up to a 2 -foot granular subcut for the street section. The applicant should be advised that soil conditions may require some sort of modification to the typical street sections. The appropriate drainage and utility easements should be dedicated on the final plat for all utilities and ponding areas lying outside the right -of -way. The easement shall be a minimum of 20 feet wide. The City will also require that all ponding areas be designed to provide access for maintenance equipment. The design shall be subject to approval by the City Engineer. EROSION CONTROL The grading plan does provide minimal erosion control measures (Type I); however, adjacent to all wetland areas the erosion control fence should be Type III. All site restoration and erosion control measures shall be in accordance with the City's Best Management Practice Handbook. Additional erosion control fence (Type I) may be required by the City behind the curbs during new home construction. STREETS Access to the development is proposed via Kings Road which is a narrow gravel roadway between 20 to 23 feet wide. Kings Road is proposed to be upgraded to urban street standards to adequately address traffic and ordinance requirements. The City's urban standards consist of a 31 -foot wide back -to -back bituminous street section with concrete curb and gutter. According to the ordinance right -of -way shall be 60 feet wide which the plans propose. On Kings Road the applicant is proposing to dedicate 50 feet of the normally required right -of -way. The City has compromised on the right -of -way width as a part of negotiations. The applicant will be constructing Kings Road only up to Country Oaks Road. Outlot B will not be able to subdivide until Kings Road is upgraded to a full urban city street. The Outlot (B) may be subject to assessments for the cost of upgrading Kings Road in the future. A 5 -foot wide concrete sidewalk is proposed along the west side of Country Oaks Lane. Kate Aanenson The Oaks of Minnewashta April 11, 1995 Page 7 The site will eventually be connected to the existing Country Oaks Road to the north once the Hallgren parcel develops. On the east side of this development there exists a combination of parcels (Headla/Wenzel) which could be further subdivided. Access to the Headla/Wenzel parcels has been considered at this time. The Headla parcel abuts Stratford Lane which is only constructed for approximately 250 feet west of Minnewashta Parkway. When Stratford Ridge was platted an Outlot B was created for future extension and deeded to the Stratford Ridge Homeowners Association versus the City. Ms. Hallgren gains access to her property through /over this Outlot. Access to the Headla/Wenzel parcels is provided with the extension of White Oak Lane. A temporary cul -de -sac is proposed at the east end of White Oak Lane. Barricades shall be placed at the end of the temporary cul -de -sac and a sign indicating that "THIS STREET WILL BE EXTENDED IN THE FUTURE ". Staff will also place this condition within the development contract which is recorded against all of the parcels in the development. With the exception of Kings Road, street grades appear to be within the City's ordinance. On Kings Road the street was designed to be compatible with the existing topography which resulted in street grades between 0.49% to 10.00 %. Staff recommends a variance to the City ordinance be approved. Lot 32, Block 3 will have street access and utility service from Country Oak Lane. The home should be required to access Country Oak Lane as well. RECOMMENDED CONDITIONS OF APPROVAL Upon completion, the developer shall dedicate to the City the utilities and street within all public right -of -way and drainage and utility easements for permanent ownership. Maintenance access routes shall be provided to all storm water ponding. The routes are subject to review and approval by the City Engineer. The appropriate drainage and utility easements should be dedicated on the final plat for all utilities and ponding areas lying outside the right -of -way. The easement shall be a minimum of 20 feet wide. 2. All areas disturbed during site grading shall be immediately restored with seed and disc mulched or wood fiber blanket or sod within two weeks of completing site grading unless the City's Best Management Practice Handbook planting dates dictate otherwise. All areas disturbed with slopes of 3:1 or greater shall be restored with sod or seed and wood fiber blanket. 3. All utility and street improvements shall be constructed in accordance with the latest edition of the City's Standard Specifications and Detailed Plates. Detailed street and utility plans and specifications shall be submitted for staff review and City Council approval in conjunction with final plat approval. Kate Aanenson The Oaks of Minnewashta April 11, 1995 ' Page 8 ' 4. The applicant shall apply for and obtain permits from the appropriate regulatory agencies (i.e. Watershed District, MWCC, Health Department, DNR) and comply with their conditions of approval. ' 5. The applicant shall enter into a development contract with the City and provide the necessary financial security to guarantee compliance with the terms of the development ' contract. 6. Storm drainage discharge from the site shall maintain the predeveloped runoff conditions. ' The applicant shall provide detailed storm sewer and ponding calculations for a 10 -year and 100 -year storm event of a 24 -hour duration. Water quality and quantity ponding calculations shall be submitted in accordance with the City's SWMP for the City Engineer ' to review and approve. 7. The applicant shall have soil borings performed on the site and submit a soils report to ' the City for review prior to issuance of building permits. ' 8. Lot 32, Block 3 shall take direct access from Country Oaks Lane and not Kings Road unless Kings Road has been upgraded to City standards. ' 9. A report or letter of clarification prepared by a qualified wetland delineator shall be submitted to the City documenting the location and integrity of all wetlands on the site. If there are wetlands on the site they shall be staked, surveyed and included on the ' grading and drainage plan. In addition, a buffer strip shall be incorporated by City ordinance. ' 10. The proposed development shall be responsible for SWMP water quality and quantity connection fees of $22,040 and $54,549, respectively. SWMP water quality and quantity connection fees may be credited /reduced depending on the applicant's contribution to on- ' site storm drainage improvements according to the City's SWMP design parameters. 11. Storm drainage from the southwest portion of the site shall be evaluated for pre and post- ' development condition. The City shall determine, based on the amount of impervious surface contributing to the wetlands located in the southwest portion of the site, whether or not a sediment basin will be required to pretreat runoff prior to discharging runoff into ' the wetlands. 12. Outlot A shall be dedicated to the City by warranty deed for construction of a sediment ' basin and parkland. Kate Aanenson The Oaks of Minnewashta April 11, 1995 Page 9 13. Staff recommends granting a variance to the City's ordinance regarding street grades. Street grades on Kings Road shall be permitted up to 10 %. 14. The existing structures on the site shall be razed within 30 days after the final plat has been recorded. The applicant shall be responsible for obtaining and complying with the appropriate permits for demolition of all structures, wells and septic systems. 15. Detailed grading, drainage, erosion control and tree removal plans shall be required by the City for review and approval prior to issuance of building permits on Lots 4 through 8, Block 3. 16. All private driveways shall be built in accordance to the City's Ordinance No. 209. 17. The lift station shall be designed to accommodate future development south of Kings Road (approximately 10 acres) and the City's telemetry system. The City will be responsible for up to a maximum of 50% of the cost of the telemetry system. 18. The applicant shall include with the street construction a drain tile system behind the curbs on all lots which do not directly abut a wetland or storm drainage pond. The drain tile system shall be designed and constructed in accordance with City standards and detail plates. 19. Erosion control fence adjacent to all wetland areas shall be the City's Type III. Erosion control fence on the entire site shall be maintained by the applicant until the entire site has been revegetated and removal is authorized by the City. 20. Barricades shall be placed at the end of the temporary cul -de -sac on White Oak Lane and a sign indicating that "THIS STREET WILL BE EXTENDED IN THE FUTURE ". ktm c: Charles Folch, City Engineer g: \eng \projects \oaksm inn \harstad2.ppr 1 1 1 ' MEMORANDUM 1 1 CITY OF CHANHASSEN 690 COULTER DRIVE • P.O. BOX 147 0 CHANHASSEN, MINNESOTA 55317 (612) 937 -1900 • FAX (612) 937 -5739 TO: Kate Aanenson, Planning Director FROM: Steve A. Kirchman, Building Official `�,(•�� DATE: February 6, 1995 SUBJECT: 93 -11 SUB -file 2 (The! Oaks of Minnewashta, Hardstad Companies) I was asked to review the proposed subdivision plans stamped "CITY OF CHANHASSEN RECEIVED, JAN 17 1995 CHANHASSEN PLANNING DEPT. " for the above referenced project. Analysis: Elevations. Proposed lowest floor level e: elevations and garage floor, elevations are adequate plan review by the Public Safety While this information is provide, because of the preliminary grading plan, many of the evations, top of foundation required in order to insure ind Engineering Departments. of the scale and complexity designations are unreadable. Dwelling Type., The proposed type of dwelling to enable the Inspecti Department to perform time of building,permit SE, SEWO, TU, 'W0). , mus 11 standard designations 7 process. I have inclu designations. designations are necessary Department and Engineering iew of the structure at the esignations (FLO or RLO, R, t be used for proposed dwelling types. These essen the chance for errors during the plan review 9eci the 1993 memo which Lists and explains these Soils Report. In addition, a soils report showing details and locations of house pads and verifying suitability of natural and fill soil is required for plan review purposes. House Pads. House pads shown on the grading plan scale to 35' by 60'. Building offsets, three car garages and three & four season porches typically cause house pads to extend beyond forty feet in width. A fifty foot wide pads will accommodate most dwellings and should be the minimum pad width. Corrected house pads must be oversized to properly distribute Kate Aanenson February 6, 1995 Page 2 building loads. Pad limits are shown next to the proposed dwellings in many cases. The limits of the corrected pads should be separated from the dwelling by one foot for every foot of depth of the dwelling footings. Street Names. In order to avoid conflicts and confusion, street names, public and private, must be reviewed by the Public Safety Department. Proposed street names are not included with the submitted documents. Demolition Permits. Existing structures on the property which will be demolished will require demolition permits. Proof of well abandonment must be furnished to the City and a permit for septic system abandonment must be obtained and the septic system abandoned prior to issuance of a demolition permit. Recommendations: The following conditions should be added to the conditions of approval. 1. Enlarge the grading plan to make the lowest floor level elevations, top of foundation elevations and garage floor elevations legible. This should be done prior to final plat approval. 2. Revise the grading plan to show standard designations for dwellings. This should be done prior to final plat approval. 3. Submit soils report to the Inspections Division. This should be done prior to issuance of any building permits. 4. Revise grading plan to permit a fifty foot wide building pad with correct oversizing. 5. Submit street names to the Public Safety Department, Inspections Division for review prior to final plat approval. 6. Obtain demolition permits. This should be done prior to any grading on the property. enclosure: 1/29/93 Dwelling Type Designation memo g: \safety \sak \memos \plan \hardstad.ka2 t TO: FROM: DATE: SUBJ: CITY OF CHANHASSEN 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317 (612) 937 -1900 • FAX (612) 937 -5739 Inspections, Planning, & Engineering Staff Steve A. Kirchman, Building Official 4- cr . k January 29, 1993 Dwelling Type Designation We have been requesting on site plan reviews that the developer designate the type of dwelling that is acceptable on each proposed lot in a new development. I thought perhaps it might be helpful to staff to explain and diagram these designations and the reasoning behind the requirements. FW or RLO Designates Front Lookout or Rear,Lookout This includes dwellings with tite basement floor level approximately 8' below grade at its, deepest with the surrounding grade sloping down to approximately 4' above the basement floor level. R Designates Rambler. This includes dwellings with the basement floor level approximately 8' below grade with the surrounding grade approximately level. This would include two story's and many 4 level dwellings. SL Designates Split Entry. This includes dwellings with the basement floor level approximately 4' below grade with the surrounding grade approximately level. SLrWO Designates Split En Walk Out This includes dwellings with the basement floor level approximately 4' below grade at its deepest with the surrounding grade sloping down to lowest floor level. TU Designates Tuck Under. This includes dwellings with the basement floor level approximately 8' below grade at its deepest with the surrounding grade sloping down to the lowest floor level in the front of the dwelling. WO Designates Walk Out This includes dwellings with the basement floor level approximately 8' below grade ' at its deepest with the surrounding grade sloping down to the lowest floor level in the rear of the dwelling. / r TU r SE R SEWO WO FLO -,, of RLO ' Inspections staff uses these designations when reviewing plans which are then passed to the engineering staff for further review. Approved grading plans are compared to proposed building plans to insure compliance to approved conditions. The same designation must be used on all documents in order to avoid confusion and incorrect plan reviews. IP14W PRINTED ON RECYCLED PAPER trm �SnT ATE Of �J Ll EE 1% ( 0 UQ DEPARTMENT OF NATURAL RESOURCES METRO WATERS - 1200 WARNER ROAD, ST. PAUL, MN 55106 PHONE NO. 772 - 7910 FILE NO. February 1, 1995 Kathryn Aanenson, Planning Director City of Chanhassen 690 Coulter Drive, P.O. Box 147 Chanhassen, MN 55317 RE: Harstad Companies, Lake Minnewashta (10 -9P) and Lake St. Joe (10- 11:), City of Chanhassen, Carver County (City 93 -11 SUB - File 2) Dear Ms. Aanenson: We have reviewed the site plans (received January 20, 1995) for the above - referenced project (Sections 5 and 6, T116N, R23W) and have the following comments to offer: 1. Lake Minnewashta (10 -9P) and Lake St. Joe (10 -11P), Public Waters, are on the proposed site. Any activity below the ordinary high water (OHW) elevation, which alters the course, current or cross - section of Public Waters, is under the jurisdiction of the DNR and may require a DNR permit. The OHW for Lake Minnewashta is 944.50' (NGVD, 1929) and the OHW for Lake St. Joe is 945.2' (NGVD, 1929). It appears there are wetlands on the site that are not under DNR Public Waters Permit jurisdiction. You should be aware that the project may be subject to federal and local wetland regulations. The Department may provide additional comments on the project through our review of applications submitted under these other regulatory programs. 2. It appears that most of the stormwater is routed through settling basins, which is good. We would object to having the stormwater routed directly to Lake Minnewashta or Lake St. Joe. 3. There should be some type of easement, covenant or deed restriction for the properties adjacent to the wetland areas. This would help to ensure that property owners are aware that the U.S. Army Corps of Engineers and the City of Chanhassen have jurisdiction over the areas and that the wetlands cannot be altered without appropriate permits. 4. The 100 -year flood elevation of Lake Minnewashta is 945' (NGVD, 1929). All the work that is done for this project must comply with applicable floodplain regulations of both the city and the Minneahaha Creek Watershed District. 5. Lake St. Joe has a shoreland classification of Natural Environment and Lake Minnewashta has a shoreland classification of Recreational Development. The entire project area is within the shoreland districts of these lakes. The development must be consistent with city's shoreland management regulations. In particular you should note: a. The project area contains steep slopes. Topographic alterations should be minimized in these areas. AN EQUAL OPPORTUNITY EMPLOYER Kathryn Aanenson February 1, 1995 ' Page 2 b. The vegetation and topography should be retained in a natural state in the shore impact zones. The minimum shore impact zone is an area within 37.5' of Lake Minnewashta or within 75 of Lake St. Joe. ' C. The structures in the development should be screened from view from Lake St. Joe and Lake Minnewashta using topography, existing vegetation, color, and other means approved by the city. 6. The following comments are general and apply to all proposed developments: a. Appropriate erosion control measures should be taken during the construction period. The Minnesota Construction Site Erosion and Sediment Control Planning Handbook (Board of Water & Soil Resources and Association of Metropolitan Soil and Water Conservation Districts) guidelines, or their equivalent, should be followed. b. If construction involves dewatering in excess of 10,000 gallons per day or 1 million gallons per year, the contractor will need to obtain a DNR appropriations permit. It typically takes approximately 60 days to process the permit application. ' C. If construction activities disturb more than five acres of land, the contractor must apply for a stormwater permit from the Minnesota Pollution Control Agency (Dan Sullivan @ 296 - 7219). ' d. The comments in this letter address DNR - Division of Waters jurisdictional matters and concerns. These comments should not be construed as DNR support or lack thereof for a particular project. ' Thank you for the opportunity to comment. Please contact me at 772 -7910 should you have any questions regarding these comments. ' Sincerely, tz- Joe Richter Hydrologist JR /cds ' c: Minnehaha Creek Watershed District, Kristen George U.S. Army Corps of Engineers, Gary Elftmann Chanhassen Shoreland File Lake St. Joe File (10 -11P) NOTICE OF PUBLIC HEARING PLANNING COMMISSION MEETING Wednesday, APRIL 5, 1995 7:00 P.M. City Hall Council Chambers 690 Coulter Drive Project: The Oaks at Minnewashta Developer: Harstad Companies Location: North of Kings Road, West of Minnewashta Parkway Notice: You are invited to attend a public hearing about a development proposed in your area. Harstad Companies is proposing a revised preliminary plat of 35.83 acres of property into 45 single family lots and 2 outlots on property zoned RSF, Residential Single Family and located north of Kings Road and west of Minnewashta Parkway. What Happens at the Meeting: The purpose of this public hearing is to inform you about the developer's request and to obtain input from the neighborhood about this project. During the meeting, the Planning Commission Chair will lead the public hearing through the following steps: 1. Staff will give an over view of the proposed project. 2. The Developer will present plans on the project. 3. Comments are received from the public. 4. Public hearing is closed and the Commission discusses project. The Commission will then make a recommendation to the City Council. Questions or Comments: If you want to see the plans before the meeting, please stop by City Hall during office hours, 8:00 a.m. to 4:30 p.m., Monday through Friday. If you wish to talk to someone about this project, please contact Kate at 937 -1900 ext. 118. If you choose to submit written comments, it is helpful to have one copy to the Planning Department in advance of the meeting. Staff will provide copies to the Commission. Notice of this public hearing has been published in the Chanhassen Villager on March 22, 1995. C RY & NADINE NELSON RALPH & P. KARCZEWSKI WARREN & JANET RIETZ 048 RED CEDAR COVE 7054 RED CEDAR COVE 7058 RED CEDAR COVE XCELSIOR MN 55317 EXCELSIOR MN 55331 EXCELSIOR MN 55331 AVID & A. PRILLAMAN COY & SANDRA SHELBY ROBERT & JUDY ROYER 7064 RED CEDR COVE 7068 RED CEDAR COVE 7074 RED CEDAR COVE XCELSIOR MN 55317 EXCELSIOR MN 55331 EXCELSIOR MN 55331 & SARAH MANEY BERNARD & ALYCE FULLER DONALD & B. BITTERMANN � HN 78 RED CEDAR COVE 7075 RED CEDAR COVE 7085 RED CEDAR COVE EXCELSIOR MN 55331 EXCELSIOR MN 55331 EXCELSIOR MN 55331 1 OUIS/LUANN GUTHMUELLER DEBRA HOFER PHILIP PITSCH 095 RED CEDAR COVE 7098 RED CEDAR COVE 7099 RED CEDAR COVE XCELSIOR MN 55331 EXCELSIOR, MN 55331 EXCELSIOR MN 55331 RED CEDAR COVE TWNHOUSE KEVIN & CYNTHIS CUDDIHY ALLIN & SHIRLEY KARIS BOX 181 3900 STRATFORD RIDGE 3920 STRATFO RIDGE VCCELSIOR . MN 55331 EXCELSIOR MN 55331 N EXCELSIOR MN 55331 t AN STREIF JEFFREY & JANICE ADAMS W. SCOTT MORROW & 3940 STRATFORD RIDGE 3960 STRATFORD RIDGE CYNTIA M. HOUSE XCELSIOR MN 55331 EXCELSIOR MN 55331 3980 STRATFORD RIDGE I EXCELSIOR MN 55331 WELLS CURRENT RESIDENT TERRY & BONNIE LABATT 1 ARTON 1000 STRATFORD RIDGE 4001 STRATFORD RIDGE 3981 STRATFORD RIDGE XCELSIOR MN 55331 EXCELSIOR MN 55331 EXCELSIOR MN 55331 ITH & KATHRYN BEDFORD WILLIAM J. MUNIG CHARLES & C. CRUICKSHANK 09 61 STRATFORD RIDGE 6850 STRATFORD RIDGE 3921 STRATFORD RIDGE EXCELSIOR MN 55331 EXCELSIOR MN 55331 EXCELSIOR MN 55331 DOUGLAS & JANET REICHERT CURRENT RESIDENT HAROLD & ELAINE TAYLOR STRATFORD RIDGE 3881 STRATFORD RIDGE 3861 STRATFORD RIDGE 1 901 XCELSIOR MN 55331 EXCELSIOR MN 55331 EXCELSIOR MN 55331 I �E VIN & SUELLYN TRITZ STRATFORD RIDGE HOA MARK & JULIE GRUBE 851 STRATFORD RIDGE RD C/O KEITH F. BEDFORD 3931 COUNTRY OAKS DRIVE JJXCELSIOR MN 55331 3961 STRATFORD RIDGE EXCELSIOR MN 55331 EXCELSIOR MN 55331 CRAIG &LINDA MACK LOREN H. BEAUDOIN BRUCE & JENNIFER LINN 3941 COUNTRY OAKS DRIVE 133 SPRING VALLEY CIRCLE 4001 COUNTRY OAKS DRIVE EXCELSIOR MN 55331 EXCELSIOR MN 55331 EXCELSIOR MN 55331 LOREN L. BENSON & TODD & FRANCIS BOYCE JEROME M. BACH LEE & JUANITA HARVEY 4011 COUNTRY OAKS DRIVE C/O NORWEST BANK, TRUSTEE 7120 KINGS ROAD EXCELSIOR MN 55331 6TH MARQUETTE EXCELSIOR MN 55331 MINNEAPOLIS MN 55479 -0046 BARBARA B. WILSON 7050 KINGS ROAD EXCELSIOR MN 55331 KRISTIN & JERRY KORTGARD 3901 GLENDALE DRIVE EXCELSIOR MN 55331 � r DAVID & MARbARE BORRIS 4071 KIND ROAD . EXCELSIOR 'MN 55331 DARYL & DEBRA KIRT 50 HIL' L STREET CHANHASSEN MN, 55317' JEFFRY H. HALLGREN & MICHELLE GEORGE 355 HIGHWAY 7 EXCELSIOR MN 55331 LINDA A SCOTT & SUSAN E. MORGAN 4031 KINGS ROAD EXCELSIOR MN 55331 JOHN P. BAUMTROG 7141 MINNEWASHTA PKWY EXCELSIOR MN 55331 MARK & DONNA MALINOWSKI 7250 MINNEWASHTA PKWY EXCELSIOR MN 55331 HOLY CROSS LUTHERAN LEE ANDERSON CHURCH OF MINNESOTA PLEASANT ACRES HOA 4151 HIGHWAY 7 ' RT. 1 EXCELSIOR MN 55331 EXCELSIOR MN 55331 JAMES & R. BOYLAN 6760 MINNEWASHTA PKWY. EXCELSIOR MN 55331 JAMES & JEFFREY KERTSON 6810 MINNEWASHTA PKWY EXCELSIOR MN 55331 RLK ASSOCIATES 922 MAIN STREET HOPKINS MN 55343 TERRY FORBORD LUNDGREN BROS. 935 EAST WAYZATA BLVD. WAYZATA, MN 55391 ROBERT MOREHOUSE 4410 HIGHWAY 25 WATERTOWN MN 55388 LARRY WENZEL 6900 MINNEWASHTA PKWY EXCELSIOR, MN 55331 JENNIFER J. HALLGREN 375 HIGHWAY 7 EXCELSIOR MN 55331 LOWELL & J. CARLSON R. 1 BOX 822A EXCELSIOR MN 55331 STATE OF MINNESOTA DEPT. OF TRANSPORTATION METRO SQUARE BUILDING ST. PAUL MN 55101 JAMES & ARLENE CONNOR 3901 RED CEDAR POINT ROAD EXCELSIOR MN 55331 JOANN HALLGREN 6860 MINNEWASHTA PKWY EXCELSIOR MN 55331 KENNETH & DUANE E. LUND 395 HIGHWAY 7 , EXCELSIOR MN 55331 DAVID HEADLA 6870 MINNEWASHTA PKWY EXCELSIOR, MN 55331 ' u 7120 Kings Rd. ' Excelsior, MN 55331 March 25,1995 ' Planning Commission City of Chanhassen 690 Coulter Drive Chanhassen, MN 55317 Regarding: The Oaks Development by Harstad Companies ' Dear Members: My wife and I live at the dead end of Kings Road, in the city of Victoria Our only access to the external world is via Kings Road and Minnewashta Parkway which lie entirely within Chanhassen. Our access has been adversely affected during the Minnewashta ' Parkway renovation, and the more recent development project at the north end of Minnewashta Parkway. Unlike the obstructionist opinions expressed by many of our neighbors, we have no objections to the plans for the orderly residential development in this area, and defer that judgment entirely to the cognizant municipal authorities. There is, however, one suggestion ' that we would like to have you consider, regarding our egress and access during the construction period: The prime contractor of such projects are usually contentious in not blocking public accesses, because of their continuing vulnerability to officialdom during construction. This ' attitude does not extend to the many subcontractors who intermittently deliver supplies and/or services. The prime contractor has no financial or legal responsibility for the criminal trespass or ordinance violations of his subs. They have wreaked their havoc and are gone before any appropriate action can be initiated Our suggestion is to make it the prime contractors responsibility, during construction, to ' continuously provide suitable all weather parking for him and his subcontractors on his own private property, and to require his posting of a bond which is partially forfeited if he or any subcontractors commit criminal actions such as blocking public access, trespass, or ' property damage. This is a pro - active way to prevent the actions which were so pervasive and created such a burden during previous construction projects in the area. I While the developer could argue that this puts an unreasonable financial burden on him, this is more fair than shifting the inevitable financial burdens to the people in the local community that will otherwise be affected by the project Ste, y� Lee E. Harvey Park and Rec Commission - January 24, 1995 Andrews: What we've done in the past is, just when a conflict comes up, call Todd and we'll get it worked out. Huffman: I won't be there for the January 23rd meeting. Well, how about if I just let you know tonight that I won't be there last night. LAND SUBDIVISION PROPOSAL: PRELIMINARY PLAT OF 37+ ACRES OF PROPERTY ZONED RESIDENTIAL SINGLE FAMILY INTO 43 TO 53 LOTS LOCATED NORTH OF KING ROAD AND WEST OF MINNEWASHTA PARKWAY HARSTAD COMPANIES. Todd Hoffman presented the staff report on this item. Andrews: Mr. Birch, if you'd like to come address the commission. John Birch: My name is John Birch. It gets pronounced a number of ways because it's got the h on the end. First of all I have to say that I'm from ... and Associates. We are the company that has done preliminary plat. This is per Mr. Harstad's wants and wishes. Apparently he has done some marketing strategies and found out that the perceived park area that the city wants is some of the highest valued land because of the close proximity to the lake and they decided that that's what they would prefer to do is build single family residences in here and if the city would want more park, the idea would be to cut these lots off in this area here. Taking just 4 single family lots and then the 10 acres of park which would be back in this area. That's what Mr. Harstad has asked me to convey to you. He never showed up with his plan. Apparently he has talked to someone about it. I don't know if it was Todd or whoever it was at the city but he felt that the 10 acres of park in that area would be more equitable for him because of the costs involved in building streets that he would incur. In essence what would happen is, in this plan when the park is here, he would have to incur a lot of cost to build a road to this point in here with zero value. In other words, he gets no value back on it. All his costs are involved and he would have to offset all of this road cost with the exception of what the city picks up, with the rest of the lots, it becomes a real high premium on those lots. Andrews: Do you know what it costs per foot to build a roadway like that? John Birch: I can give you a rough idea. It's right around $250.00 a running foot. Andrews: And how many feet are we looking at along the proposed park along the lake? 12 I Park and Rec Commission - January 24, 1995 ' John Birch: I'd have to guess. I don't remember exactly what that was. I think, it's probably about 1,800 to 2,000 feet I believe. ' Andrews: So that works out to be about, does anybody have a calculator with them here. t Hoffman: $800.00 to $1,000.00. John Birch: So you have to get to this point over here which is zero value. So it's going to ' be pretty close to $1,000.00. But the streets, curb and gutter, storm sewers, sanitary sewer, the approximately cost that we use just for a rough estimate ... is right around $250.00 a ' running foot. Andrews: And does the property owner adjacent pick up part of that cost? ' John Birch: No. That's part of the problem. Kings Road has platted. What happens is ... that all of the land that Kings Road is on this property. None of it is on this property. So not ' only does he build this or have to build this road but he's got no recourse to get money back from these people who now have a nice road against their property and can develop their properties. Andrews: I would have to assume that there's more linear feet in a curved roadway than a straight roadway. John Birch: In this instance here? Is that what you're saying? ' Andrews: Yes. John Birch: Yes there is. But with this type of alignment, what happens is, now he can offset the cost of these higher value lots. He provides the roadway, gets the lots in here. If he builds this road with the park system here, he's got no way to offset the cost of that roadway at all. And it does get very expensive. Because that's an upfront cost. He also has ' to provide the bond of 150% of the total cost. And all of that becomes quite a burden. Lash: Can someone refresh my memory as to why we decided on that specific location on ' this parcel. I know there had been discussion of locating it in other areas and I can't recall right off. Andrews: Access was the main. 13 Park and Rec Commission - January 24, 1995 Lash: Okay, that's what I was thinking. Because of the park deficient nature of that area we wanted it to be more accessible to the parkway? Andrews: And we wanted it to be on the trail system too. I guess one of my frustrations here, some of the reasons I was asking the cost questions is, I count up approximately 8, maybe 10 lots that are affected by the change in plat. I have nothing to base my guesses on here other than to say that if those lots are worth $10,000.00 more a piece because they're closer to the lake, you know that's $80,000.00 potentially for the property, or for the developer here to perhaps increase his sale. But at the same time he's got to build some additional roadway and now he's sat on that property for another 6 months. He's hired more architects. More planners. More engineers. More attorneys to look at the property. It's very frustrating for me as a part of our Park Board that this is an area, as a Park Board, we've been looking for a quality piece of property for a number of years with very few opportunities. Fortunately, or unfortunately, the Harstad property came along. Depending on who's side of the fence you're on I think here. But we look at the location here as being one of, there's a right way to do it and a wrong way to do it from our standpoint and I guess my opinion is to locate the property in a distant corner of the parcel makes it inaccessible and not meeting our needs and that's why, in both cases when this project came before us, we were quite strong in our recommendation that that's why we wanted it located where it was. And when it left here last year I think, young Mr. Harstad, I think it was. John Birch: Paul. Andrews: Paul Harstad. There's no way that he misunderstood our intentions on that night because he came in here and he was I think a little shocked at the reception that he received because I think he figured we were going to go along with what he thought was a plat similar to this and there was no way. So I guess I'm going to have to speak personally that I'm disappointed to see this back again. I understand what you're talking about as far as the costs here. I mean there is a trade off here and I would think through the, there is a fairness issue here that I think is dealt with through prior court cases I would imagine. If a property owner is deprived of his, or injured by action of another, he has a right to recover that injury through fair treatment or through the legal recourse. So I guess I would argue that ultimately in the ideal world this should work out to be fair, and I'm hoping that it will. For that reason I'm going to recommend that we follow the recommendation. That's my personal opinion so. John Birch: The only thing I would say is, first of all he's got 12 lots, not 8 lots that he can ... from. Again, if there was a way to realign the road to get down, or when the costs were to be, we've looked at it a couple three different ways. Our company's, I haven't personally looked at it over the period of time. I've only been working on it for about the last 3 to 4 14 I Park and Rec Commission - January 24, 1995 months but we've got a number of sketches in our office trying to come up with a reasonable solution and because of the way the King's Road was originally aligned, it went down on this property owner's property. All of it. None of it was split on the line the way it normally is and so it does, it throws all the burden onto this property. Hoffman: That piece of information is new information to me. I've had a number of conversations with our engineers and our planners over some possibilities with the funding of that roadway. It was certainly represented, due to past experience to the property owners on ' the south side of Kings Road that it would be difficult, it may be difficult to convince the City Council to assess those people but they still benefit from it so, it's ... to assume that they ' could be assessed on the south side of Kings Road as well. So this is a new piece of information presented... investigate on behalf of the commission. Andrews: I agree with what you're saying Todd but yet I don't feel that's within our area of concern. I mean we'd like to see it fairly divided, because it should be. It should be ideally but. ' Hoffman: You're correct. That will be for the City Council. ' Andrews: That's for them to decide. And I think we have to look at the pure issue which is where should a park be. How does it best serve our city. Yes, it may create an adverse impact. I would have to admit you're not the first representative of a developer here that's come in here and said I'd like you to build your park somewhere else. I would say that happens virtually every time. For some reason, I don't know if it's coincidence but usually they prefer to have the park on the least valuable property. Usually on the most isolated ' corner, on the lowest quality land and I think I've figured out why. But in this situation we feel that as a Park Board, and you were here for part of our study here earlier of our parkland, that we have a very scarce resource to work with here that we need to protect. I ' mean 20 -30 years from now I don't want to have to look at kids or grandkids and say geez, you know. There almost was a nice park here. But we decided it really wasn't that big of a deal and we decided we'd build it back in the woods there but, you know we could go back ' there but it's kind of hard to find it or it doesn't really hook up to anything quite the right way. I can't do that. ' Lash: You can walk to it but you can walk an extra mile. Andrews: Yeah. You can walk to it but once you're there, you can't see the lake anymore. ' You know the neighbors wish they had something closer to the lake but geez, you know the developer wanted to put houses there. Boy that's just, to me this is an issue, there's a right ' way and a wrong way and in spite of the fact that this is going to result in less dollars for the 15 Park and Rec Commission - January 24, 1995 developer in his pocket, as we've discussed many times here, the developer isn't going to live in the development. Most likely. And he'll be on his way to some other city to put in a development using the same arguments again and we're left with a property that wasn't done the best way it could have been done. So that's a personal opinion. Berg: I couldn't say it as well as you but the issues for me are, we are so incredibly deficient in that area and the access of the spot we've already decided upon. Or that we recommended and I strongly support your point of view. Roeser: So do I. I agree. I think that's the best spot for that park. Huffman: Do you want to make a motion? Roeser: I have no reason to change my mind and move it back up into there. I can think of no reason why we would want to do that. John Birch: Are there any other questions I can answer? Thank you. Andrews: We need to make a, or are we staying on our prior motion or do we need to make one here? Hoffman: It's a new application. Andrews: A new application would require a motion then. Huffman: I'd like to move that, the correct verbiage being that we're under the new user friendly rules, do I have to read the entire park and trail again? Do I have to read the whole thing? I'd like to reference that, make a motion that for the park, the plat should include a 10 acre park at the northwest intersection of Kings Road and Minnewashta Parkway. The acquisition of the park to be accomplished through park dedication and purchase of 1.72+ acres and purchase of 7.4 acres. This acquisition shall be conditioned of final plat approval. A purchase agreement shall be negotiated by the City contingent upon City Council approval. Full park fee credit shall be granted as part of these negotiations and acceptance of full trail dedication fees in force upon building permit application is recommended. Current trail fees are $300.00 per single family residential unit. Andrews: I've got one clarification I'd like to add if I could. And that would be to the reference to the northwest corner of Kings Road be where the road currently lies. Not as where it's shown on this plat. 16 I Park and Rec Commission - January 24, 1995 ' Me g er: Second. ' Andrews: Any further discussion? Huffman moved, Meger seconded that the Park and Recreation Commission recommend ' approval of the Oaks at Minnewashta with the following conditions of approval in regard to parks and hails: Park ' The plat shall include a 10± acre park at the northwest intersection of where Kings Road currently is located and Minnewashta Parkway. The acquisition of the park to be accomplished through park dedication (1.72 acres) and purchase (7.48 acres). This acquisition shall be a condition of final plat approval. A purchase agreement shall be negotiated by the city contingent upon City Council approval. Full park fee credit shall be granted as a part of these negotiations. ' Trail ' Acceptance of full trail dedication fees in force upon building permit application is recommended. Current trail fees are $300.00 per single family residential unit. ' All voted in favor and the motion caned unanimously. SELECTION OF REPRESENTATIVE FOR DISTRICT 112 COMMUNITY EDUCATION ' ADVISORY COUNCIL. Hoffman: This is an issue that just won't go away. I'll let you take it from there. ' Huffman: No. ' Lash: You were our second choice. Actually you were our first choice but you weren't here so we didn't nominate you. ' Huffman: Bless you. Andrews: Well, are there are any volunteers here? Can we volunteer paid staff people? Are ' we allowed to do that? ' Berg: What happens if we don't have somebody? 17 CITY OF CHANHASSEN 1 1 1 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317 (612) 937 -1900 • FAX (612) 937 -5739 1 TO: Park and Recreation Commission FROM: Todd Hoffman, Park and Recreation Director O/ DATE: January 19, 1995 SUBJ: The Oaks at Minnewashta, Preliminary Plat, Harstad Companies Exactly one year ago the commission reviewed a preliminary plat of Harstad Companies for this same site. The staff report reviewing that application dated January 25, 1994 is attached. On the evening of Tuesday, January 25, 1994, the commission took public comment on this proposal, heard from the applicant and made the following recommendation to the city council: Roeser moved, Manders seconded that the Park and Recreation Commission recommend the City Council approve the preliminary plat as presented with the inclusion of acquisition of the l0 acre park depicted in Park Plan A including the lakeshore property. The acquisition of the park is to be accomplished through park dedication of 1.72 acres and purchase of 7.48± acres. This acquisition shall be a condition of final plat approval. A purchase agreement shall be negotiated by the city attorney contingent upon City Council approval, full park fee credit ($38,700) on 43 homes is to be granted as a part of these negotiations. Acceptance of full trail dedication fees in force upon building permit'application is recommended. Current trail fees are $300 per single family; residential unit. All voted in favor and the motion carried unanimously. In the interest of fulfilling this recommendation, a series of meetings between the City of Chanhassen and Harstad Companies were held throughout 1994. The acquisition of the park, among other issues, were discussed at these meetings. Specific to the park acquisition, the following information was forwarded to Harstad Companies. Generally, the transaction would entail the following elements: 1. The city would accept the dedication of parkland from Harstad Companies. This dedication would equal their required dedication per city ordinance. The land area MEMORANDUM ' The Oaks at Minnewashta January 19, 1995 Page 2 requested would commence at the property's eastern border (Lake Minnewashta) and extend to the west. This dedication would entail approximately 1.75 acres. 2. The remainder of the park would be purchased from Harstad Companies. ' 3. In assuming ownership of the park, the city would accept the responsibility for its portion of public improvements. These improvements generally include street and curb construction and utility costs (sanitary sewer, water and storm sewer). More specifically, the city would pay for its half of the street and associated curb, a water and sewer unit (to accommodate any future hookup) and stormwater costs. Unfortunately, Harstad Companies has informed the city that they misunderstood the city's position. Believing that the city would pay the full cost of public improvements for both sides of the street along the park's frontage. As I informed Harstad Companies, such an ' arrangement has, to my recollection, never been consummated by the city. It would not be in the best interests of the public to do so. Harstad Companies' options are to ask the City Council to authorize construction of the road and assess the abutting properties, or in the interest of their proposed development, assume the costs of that portion of Kings Road. Harstad Companies has informed us that they do not accept the premise on which the city's proposal is based and have chosen to submit a second preliminary plat. This proposed plat again does not incorporate the recommendations of the Park and Recreation Commission. ' You will note that this submittal, dated January 13, 1995, includes 49 lots, proposes a partial vacation of Kings Road, and includes 2.6 acres of parkland split between two locations, one on the western edge of the plat adjacent to the City of Victoria and the other, labeled as ' Outlot "A" Park, adjacent to Lake Minnewashta. I have informed Mr. Paul Harstad of my disapproval of this plan based on its lack of compliance with the desires communicated by the Park and Recreation Commission. ' RECOMMENDATION ' It is recommended that the Park and Recreation Commission recommend approval of The Oaks at Minnewashta with the following conditions of approval in regard to parks and trails: Park ��;OA The plat shall include a 10± acre park at the northwest intersection oPKings Road and Minnewashta Parkway. The acquisition of the park to be accomplished through park dedication (1.72± acres) and purchase (7.48 acres). This acquisition shall be a condition of final plat approval. A purchase agreement shall be negotiated by the city contingent upon city council approval. Full park fee credit shall be granted as a part of these negotiations. Trail ' Acceptance of full trail dedication fees in force upon building permit application is P P gP recommended. Current trail fees are $300 per single family residential unit.