1b. Kerber Pond Slope Stabilization: Approve Quote0
CITY OF
CNANHASSEN
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317
Administration
Phone: 952.227.1100
Fax: 952.227.1110
Building Inspections
Phone: 952.227.1180
Fax: 952.227.1190
Engineering
Phone: 952.227.1160
Fax: 952.227.1170
Finance
Phone: 952.227.1140
Fax: 952.227.1110
Park & Recreation
Phone: 952.227.1120
Fax: 952.227.1110
Recreation Center
2310 Coulter Boulevard
Phone: 952.227.1400
Fax: 952.227.1404
Planning &
Natural Resources
Phone: 952.227.1130
Fax: 952.227.1110
Public Works
7901 Park Place
Phone: 952.227.1300
Fax: 952.227.1310
Senior Center
Phone: 952.227.1125
Fax: 952.227.1110
MEMORANDUM
TO: Todd Gerhardt, City Manager
FROM: Paul Oehme, Director of Public Works /City Engineer .q'
py—T e - --,
DATE: April 23, 2012
SUBJ: Kerber Pond Slope Stabilization, Project No. 11 -09: Approve Quote
PROPOSED MOTION
"Approve Quote in the amount of $64,310.00 to Parrot Contracting, Inc. for
Kerber Park Pond Stabilization Improvements."
City Council approval requires a simple majority vote of the City Council present.
BACKGROUND
In 2008, the City reconstructed Laredo Drive and constructed a rain garden feature
and stormwater pond in Kerber Park Pond. These improvements were made to help
treat the stormwater runoff before it entered Lotus Lake. The construction of the
stormwater pond took place on a steep hillside which required excavation and
regrading to construct the pond. The work was completed the fall of 2008. Starting
in the spring of 2009 the slope of the
north facing hillside has slowly been
moving. The contractor for the Laredo
Drive project has been out several
times to try to correct the problem but
the hillside keeps moving. Staff hired
a geotechnical firm to complete a soils
investigative report to try to figure out
why the slope is moving and what can
be done to correct the problem. A site
survey and soil borings were also taken
on the slope. The report identified
several potential causes %J the failure.
One of the main causes of the problem is a sand lenses at the bottom of the hillside
Web Site that was unknown prior to the slope failure. This sand lenses acts as a relief for
www.ci.chanhassen.mn.us ground water in the hillside. During wet times of the year, ground water flows out of
the hillside and made the newly placed soil on the hillside unstable.
The pond area required soils to be removed to construct the pond. The soils that were
planned to be removed consisted of organic soil that was suitable and planned to be
Chanhassen is a Community for Life - Providing for Today and Planning for Tomorrow
Todd Gerhardt
Kerber Pond Slope Stabilization: Approve Quote
April 23, 2012
Page 2
used as topsoil for on the street project. Underneath the organic soil some clay material was also
necessary to be removed. However, it was found after start of the excavation of the pond the organic
soils and some of the clay contained a small amount of asphalt. These soils were not suitable for the
contractor to use on the project. Since the soils could not be used on the project, the material would
have needed to be trucked to a dump site which would have cost $40 /cubic yard to dispose of or a
$160,000 change order. Instead of trucking the material off site it was determined the best course of
action was to use this material on the north side of the stormwater pond next to Kerber Pond.
Because of the change in soil placement, more soil material was needed to be graded around the
pond. During the construction of the pond, the moisture content of the material brought in from the
street project was over optimum moisture content because of the rain fall that took place during
construction and consequently had lower soil strength. Staff did discuss trying to dry out the
material before it was placed however this option was dismissed because of the time involved drying
the material and there was no guarantee there would be good weather to completely dry the material.
Also staff did discuss with the contractor replacing the material with offsite drier fill. The contractor
price for this work was excessive and staff did not think the price was worth the cost at that time. In
hindsight, if the change order for new dry material was approved to be placed, the slope may still
have failed due to ground water seeping out of the hillside.
Several corrective measures were reviewed to address the problem. These options included:
1. Full or partial slope reconstruction with normal weight fill.
2. Full or partial slope reconstruction with light weight fill.
3. Fill pond and regrade hillside.
4. Sheet piling.
Staff is recommending replacing the full slope
failure area with normal weight fill that has low
moisture content. Based on the geotechnical
report, this option has the greatest safety factor
and therefore the best chance of success. This
option is also less costly then options 2 -4. This
option also includes constructing a drainage layer
with drain tile so ground water can discharge out
of the hillside without causing soil failure.
Staff has received two quotes for the recommended fix. The quotes received are as follows:
Parrott Construction, Inc. $64,310.00
Minger Construction, Inc. $77,935.00
Parrott Construction, Inc. has worked on several City projects. Their work has been acceptable.
The project has been budgeted for in 2012 CIP (SWMP #43). Funding is proposed to be split equally
between the Street Pavement Management Fund and the Surface Water Utility Fund. The work is
anticipated to start mid July.
Attachments: Resolution & CIP Sheet
g: \eng \public \_2000 -2009 public projects \_2008 projects \08 -01 2008 street improvements \bkgd apry quote kerber pnd slope.doc
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE: April 23, 2012 RESOLUTION NO: 2012-
MOTION BY:
SECONDED BY:
A RESOLUTION APPROVING A QUOTE FOR THE
KER13ER POND SLOPE STABILIZATION
PROJECT NO. 11 -09
WHEREAS, quotes were received for the Kerber Pond Slope Stabilization Project No. 11-
09; and
WHEREAS, it appears the quote from Parrott Contracting, Inc. in the amount of
$64,310.00 is the lowest responsible quote.
NOW THEREFORE, BE IT RESOLVED by the Chanhassen City Council:
1. The mayor and clerk are hereby authorized and directed to enter into a contract with Parrott
Contracting, Inc. in the name of the City of Chanhassen for the Kerber Pond Slope
Stabilization Project No. 11 -09, according to the plans and specifications therefore
approved by the City Council and on file in the office of the city clerk.
Passed and adopted by the Chanhassen City Council this 23` day of April, 2012.
ATTEST:
Todd Gerhardt, City Manager
Thomas A. Furlong, Mayor
YES NO ABSENT
Capital Improvement Program 2012 thru 2016
City of Chanhassen, MN
Project # SWMR043
Project Name Kerber Park Storm Pond Slope Stabilization Imp
Account #1 720 - 7025 -xxxx
Account #2
Account #3
Account #4
Department
Surface Water Management
Contact
Paul Oehme
Type
Improvement
Useful Life
Category
SWMP
Priority
n/a
lieseriptton ' Total Project Cost: $115,000
This project would stabilize the slope next to the storm water pond. The project includes removing the unstable soils from the slope, installing
draintile and replacing them with better materials.
Justification
The slope next to the storm water pond is not stable at this time. This pond was constructed along with the Laredo Drive Street Improvement
project. The contractor which constructed the pond tried several times to stabilize the slope unsuccessfully. Do to the nature of the soil,
unexpected springs and groundwater, wet weather since the pond was completed and lack of mature vegetation, the slope never stabilized. If the
slope is not stabilized soon, the movement of soil could impact private property.
Expenditures
Total
aenance
2012 2013 2014 2015 2016
115,000
115.000
Total 115,000 115,000
Funding Sources 2012 2013 2014 2015 2016 Total
Street Pavement Management 57,500 57,500
Surface Water Utility Fund 57,500 57,500
Total 115,000
115,000
118