2a-2 Approve Dev Contract for Stone Creek 2nd Addition Project 93-17 C 1 TY 0 F
......................
4
. ,
CHANHASSEN
, of ,
1 ,
690 COULTER DRIVE 0 P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
il (612) 937-1900 • FAX (612) 937-5739
1 MEMORANDUM
TO: Charles Polch, City Engineer
4 '()
1 FROM:: Dave Hempel, Assistant City Engineer 4. „ N 1\
DATE: July 22, 1993
SUBJ:
ApproVe Development Contract and Construction Plans and Specifications for
- ,
Stone. Creek Second Addition - Project No. 93-17
1
Attached is a copy of the development contract for the abo :, eferenced project The contract has been drafted
I to include the conditions of final plat approval process ';'1 ;, is also considered before the City Council on
Monday, July 20, 1991 Should any of the conditions be i ,,, eio, modified or new ones added, the development
contract should be amended ccordingly. - The construction costs for the public improvements have been
confirmed by staff and the required security is calculated in the amount of $78,595.00 and an administration fee
' 1 of $2,823.00.
.,„
The developer's engineer, Charles Plow; has submitted detailed construction plans and specifications for the
I street and utility improvements in Stone Creek Second Addition Which have been reviewed by staff. The plans
and specifications require some minor revisions and additions prior* final acceptance and construction. Staff
requests the City Council grant staff the authority to administratiely approve the final set of plans and
.
ll specifications after revisions provided by staff are incorporated in the documents by the developer's engineer.
, _
It is therefore recommended that tIneiiinstruction plans and s' - . : dons dated June `7, 1993 and the
development contract dated July 20993 for Stone Creek Second Addition, Project No. 93-17, be approved
i •
111 conditioned upon receiving teoteeis financial security in the amount $78
Po the necessary r 5 95.00 and the administrative
, .i> , ,
fee of. $2,823.00. In addition, the m ,=,r,'s e i 1- ,ieeT , work with and complete revisions to the
construction plans and siiedficilkint ..ii =, , ed by i 74 9 - 44 : 4461 *: ,
, . 1,.. , . . , •
ktm
.r.,.., .. le,- tat ,,,,..„;
, , ., ., . i',,, - .,;12,T.,u0 rITTiliat;', 4 •*r.
Attachments: L Construction Iiiiii ..,.,,.,: tions are available.. for ', Mew in the Engineering
1 Department).
Development, Contract.
3. Breakdown of Administratiota.
I c: Hans Hagen, Hans Hagen Inc. OFFICIAL ENGINEERING COPY
, deceived
1 ' Revision No. ,
Approved by City Engineer
II Date '7101, 113 Orlia-144
Approved by City Counod
a rt
II
I Nor PRINTED ON RECYCLED PAPER Date
. ....
1
CITY OF CHANHASSEN
DEVELOPMENT CONTRACT
(Developer Installed Improvements)
STONE CREEK SECOND ADDITION
' SPECIAL PROVISIONS
r AGREEMENT dated July 26 , 1993, by and between the
CITY OF CHANHASSEN, a Minnesota municipal corporation (the "City "),
and HANS HAGEN HOMES, INC. (the "Developer ").
1. Request for Plat Approval. The Developer has asked the
City to approve a plat for STONE CREEK SECOND ADDITION(referred to
in this Contract as the "plat "). The land is legally described on
the attached Exhibit "A ".
' 2. Conditions of Plat Approval. The City hereby approves
the plat on condition that the Developer enter into this Contract
and furnish the security required by it.
' 3. Development Plans. The plat shall be developed in
accordance with the following plans. The plans shall not be
attached to this Contract. With the exception of Plan A, the plans
' may be prepared, subject to City approval, after entering the
Contract, but before commencement of any work in the plat. If the
plans vary from the written terms of this Contract, the written
' terms shall control. The plans are:
Plan A--Plat approved by the Chanhassen City Council on
July 26, 19 93 , prepared by E. G. Rud & Sons, Inc.
Plan B -- Grading, Drainage and Erosion Control Plan dated
June 16, 1992, revised June, 1993, prepared by
E. G. Rud and Sons, Inc.
Plan C- -Plans and Specifications for Improvements dated
June 7, 1993, prepared by Charles W. Plowe,
' Consulting Engineer and approved by the
Chanhassen City Council on July 26, 1993.
1
1
SP -1
1
4. improvements. The Developer shall install and pay for
the following:
A. Storm Water Drainage System
B. Streets
C. Concrete Curb and Gutter
D. Street Signs
E. Street Lights
F. Site Grading and Site Restoration
G. Underground Utilities (e.g. gas, electric,
telephone, CATV)
H. Setting of Lot and Block Monuments
I. Surveying and Staking
5. Time of Performance. The Developer shall install all
required improvements by November 15, 1994. The Developer may,
however, request an extension of time from the City. If an
extension is granted, it shall be conditioned upon updating the
security posted by the Developer to reflect cost increases and the
extended completion date.
6. Security. To guarantee compliance with the terms of this '
Contract, payment of special assessments, payment of the costs of
all public improvements, and construction of all public
improvements, the Developer shall furnish the City with a letter of
credit from ,a bank, cash escrow, or equivalent ( "security ") for
$ 78,595.00 The amount of the security was calculated as 110%
of the following: 1
On -site storm sewer $ 10,000.00
Streets $ 44,000.00
Street lights and signs $ 500.00
Erosion control /site restoration . . . $ 10,650.00
Engineering, surveying, and inspection $ 6,300.00
TOTAL COST OF PUBLIC IMPROVEMENTS . $ 71,450.00 ,
This breakdown is for historical reference; it is not a restriction
on the use of the security. The security shall be subject to the
approval of the City. The security shall be for a term ending
December 31, 1994. The City may draw down the security, without
notice, for any violation of the terms of this Contract. If the
required public improvements are not completed at least thirty (30)
days prior to the expiration of the security, the City may also
draw it down. If the security is drawn down, the draw shall be
used to cure the default. With City approval, the security may be
reduced from time to time as financial obligations are paid, but in
no case shall the security be reduced to a point less than 10% of
the original amount until all improvements are complete and
accepted by the City.
7. Notice. Required notices to the Developer shall be in
writing, and shall be either hand delivered to the Developer, its
employees or agents, or mailed to the Developer by certified mail
at the following address: 1
SP -2
II
II Hans Hagen Homes, Inc.
Attn: Hans Hagen
941 NE Hillwind Road, Suite 300
I Fridley, MN 55432
Telephone: (612) 572 -9455
1 Notices to the City shall be in writing and shall be either hand
delivered to the City Manager, or mailed to the City by registered
mail in care of the City Manager at the following address:
I Chanhassen City Hall, 690 Coulter Drive, P.O. Box 147, Chanhassen,
Minnesota 55317, Telephone (612) 937 -1900.
8. Other Special Conditions.
1 A. A tree conservation and wetland buffer easement
shall be placed on the plat. All building sites in the tree
1 conservation or wetland buffer shall be shown on the building
permit.
B. The applicant shall convey to the city a temporary
1 easement for the temporary cul -de -sac at the end of Boulder Road.
In addition, a sign shall be installed on the barricades stating
that the street (Boulder Road) will be extended in the future.
1 C. The applicant shall receive and comply with all
pertinent agency permits, i.e. Watershed Districts.
1 D. A deceleration an acceleration lane on northbound
County Road 19 (Galpin Blvd.) shall be provided along with a bypass
turn lane on southbound County Road 19 to improve turning movements
II into the development. A by -pass lane is not proposed with the
first addition. Staff believes traffic volume will not warrant a
by -pass at this time. Also, existing right -of -way along Galpin
1 Boulevard is deficient to construct the by -pass lane. However, in
the future when traffic counts achieve warrants for a bypass lane,
the developer will be required to construct said bypass lane.
II E. A permit from the railroad (Twin City Western) will
be required for any grading or construction activity within the
railroad right -of -way.
I F. The proposed earth berm along County Road 19 shall
be reduced or relocated easterly to provide adequate room for
1 future trail considerations.
G. All areas disturbed during site grading shall be
II immediately restored with seed and disc - mulched or wood -fiber
blanket within two weeks of site grading on or before November 15,
1993, except in areas where utilities and streets will be
constructed yet that year. All areas disturbed with a slope of 3:1
II or greater must be restored with sod or seed.
H. The developer shall construct the utility and street
II improvements in accordance with the 1993 edition of the City's
1 SP -3
Standard Specifications and Detail Plates and shall prepare final 1
plans and specifications and submit for City approval.
I. As a condition of final plat approval, the applicant
shall enter into a development contract and provide the financial
security to guarantee construction of the improvements and payment
of any pending assessment.
J. The applicant /builder shall provide, at the time of
building permit application, a tree removal plan and grading permit
for 11 wooded lots, specifically, Lots 3 through 10, Block 3 and
Lots 2 -4, Block 2.
K. The applicant shall meet the conditions of the
Rezoning #92 -2 and the Wetland Alteration Permit #92 -3.
L. If after three years from the date the final plat is
approved by the City Council, the remaining public utility and
street improvements (Stone Creek 2nd Addition) are not constructed,
the city shall proceed with a 429 public improvement project and
assess the costs back to the benefitting properties. The
developers and /or property owners shall waive any and all
procedural and substantive objections to the special assessment,
including but not limited to hearing requirements and any claim
that the assessment exceeds the benefit to the property.
M. The applicant shall provide the city with a revised
grading plan with the following modifications: 1
1. Lot and block numbers that correspond to the final plat.
2. Lots adjacent to ponding areas shall have a lowest floor
elevation a minimum of 3 feet above the pond high water
level.
3. Relocate the emergency overflow proposed on the west pond
to the south end adjacent to the outlet pipe.
4. Drainage and utility easements shall be adjusted to
encompass the high water level of each pond.
I
1
1
SP -4
1
1 N. The following setback shall apply on those lots that
have tree conservation easements:
I Lot Lot Width Lot Home Conservation
Area Depth Setback Easement
1 Preliminary
Phase II
Plat
I Block 4 Block 2
1 Lot 10 Lot 4 15,000 90 165 25
Lot 11 Lot 3 15,000 90 165 20 90
I Lot 12 Lot 2 15,000 90 165 25 90
1
Preliminary Phase II
1 Plat
BLOCK 5 Block 3
1 Lot 14 Lot 10 15,300 90 167 20 90
1 Lot 15 Lot 9 16,200 95 180 20 90
Lot 16 Lot 8 18,000 95 197 20 90
1 Lot 17 Lot 7 18,900 90 207 20 90
1 Lot 18 Lot 6 18,000 90 205 20 90
Lot 19 Lot 5 18,000 90 197 20 90
1 Lot 20 Lot 4 24,020 80* 195 25 110
1 Lot 21 Lot 3 19,060 78 180 30 120
1 0. The final plat shall dedicate the right -of -way of
B oulder Road to the north line of Outlot B and that portion of
Stone Creek Drive lying east of Boulder Road.
1
P. The property labeled as park be dedicated on the
II final plat as an outlot and deeded to the city as park land.
SP -5
1
I/
Q. Boulder Road should be labeled and dedicated on the
final plat.
R. A drain tile system shall be included with the
street construction plans.
S. The trail along the south of Timberwood subdivision
shall be constructed with the lots adjacent to it are platted.
T. The park /trail shall be extended to abut Timberwood
Drive.
9. General Conditions. The general conditions of this
Contract, approved by the City Council on February 22, 1988, are
attached as Exhibit "B" and incorporated herein.
1
1
1
1
1
1
1
1
1
1
1
1
SP -6
1
11
11 CITY OF CHANHASSEN
' BY:
Donald J. Chmiel, Mayor
(SEAL)
11 AND:
Don Ashworth, City Manager
DEVELOPER: HANS HAGEN HOMES, INC.
1
BY:
Its
STATE OF MINNESOTA )
' (
COUNTY OF CARVER ) ss.
The foregoing instrument was acknowledged before me this
day of 19 , by Donald J. Chmiel, Mayor, and by
Don Ashworth-, City Manager, of the City of Chanhassen, a Minnesota
' municipal corporation, on behalf of the corporation and pursuant to
the authority granted by its City Council.
' NOTARY PUBLIC
STATE OF MINNESOTA )
I ( ss.
COUNTY OF )
The foregoing instrument was acknowledged before me this
day of , 19 , by
•
NOTARY PUBLIC
DRAFTED BY:
Campbell, Knutson, Scott & Fuchs, P.A.
317 Eagandale Office Center
1380 Corporate Center Curve
Eagan, Minnesota 55121
(612) 452 -5000
' SP -7
1
CONSENT 1
fee owners of all or part of the subject property, the development
of which is governed by the foregoing Development Contract, affirm
and consent to the provisions thereof and agree to be bound by the
provisions as the same may apply to that portion of the subject
property owned by them.
Dated this day of , 19 ,
STATE OF MINNESOTA )
( ss.
COUNTY OF
The foregoing instrument was acknowledged before me this '
day of , 19 ,
NOTARY PUBLIC
DRAFTED BY:
Campbell, Knutson, Scott
& Fuchs, P.A.
317 Eagandale Office Center
1380 Corporate Center Curve
Eagan, Minnesota 55121
(612) 452 -5000
1
1
1
SP -8
11
11
CITY OF CHANHASSEN
DEVELOPMENT CONTRACT
1 (Developer Installed Improvements)
EXHIBIT "B"
1 GENERAL CONDITIONS
1. Right to Proceed. Within the plat or land to be platted,
' the Developer may not grade or otherwise disturb the earth, remove
trees, construct sewer lines, water lines, streets, utilities,
public or private improvements, or any buildings until all the
' following conditions have been satisfied: 1) this agreement has
been fully executed by both parties and filed with the City Clerk,
2) the necessary security and fees have been received by the City,
3) the plat has been recorded with the County Recorder's Office of
' the County where the plat is located, and 4) the City Engineer has
issued a letter that the foregoing conditions have been satisfied
and then the Developer may proceed.
2. Phased Development. If the plat is a phase of a multi -
phased preliminary plat, the City may refuse to approve final plats
' of subsequent phases if the Developer has breached this Contract
and the breach has not been remedied. Development of subsequent
phases may not proceed until Development Contracts for such phases
are approved by the City.
3. Effect of Subdivision Approval. For two (2) years from
the date of this Contract, no amendments to the City's
' Comprehensive Plan, except an amendment placing the plat in the
current urban service area, or official controls shall apply to or
affect the use, development density, lot size, lot layout or
' dedications of the approved plat unless required by state or
federal law or agreed to in writing by the City and the Developer.
Thereafter, notwithstanding anything in this Contract to the
contrary, to the full extent permitted by state law the City may
require compliance with any amendments to the City's Comprehensive
Plan, official controls, platting or dedication requirements
enacted after the date of this Contract.
1 4. Improvements. The improvements specified in the Special
Provisions of this Contract shall be installed in accordance with
City standards, ordinances, and plans and specifications which have
been prepared and signed by a competent registered professional
engineer furnished to the City and approved by the City Engineer.
The Developer shall obtain all necessary permits from the
Metropolitan Waste Control Commission and other agencies before
proceeding with construction. The City will, at the Developer's
expense, have one or more construction inspectors and a soil
engineer inspect the work on a full or part -time basis. The
Developer shall instruct its engineer to respond to questions from
the City Inspector(s) and to make periodic site visits to satisfy
' that the construction is being performed to an acceptable level of
quality in accordance with the engineer's design. The Developer or
GC -1
1
I/
his engineer shall schedule a preconstruction meeting at a mutually
agreeable time at the City Council chambers with all parties
concerned, including the City staff, to review the program for the
construction work. Within sixty (60) days after the completion of
the improvements and before the security is released, the Developer
shall supply the City with the following: (1) a complete set of
reproducible Mylar as -built plans, (2) two complete sets of blue
line as -built plans, (3) two complete sets of utility tie sheets,
(4) location of buried fabric used for soil stabilization, (5)
location stationing and swing ties of all utility stubs, (6) bench
mark network, and (7) a 200 scale and a 500 scale reproducible 11 Mylar copy of the plat.
5. Iron Monuments. Before the security for the completion
of utilities is released, all monuments must be correctly placed in
the ground in accordance with Minn. Stat. § 505.02, Subd. 1. The
Developer's surveyor shall submit a written notice to the City
certifying that the monuments have been installed. ,
6. License. The Developer hereby grants the City, its
agents, employees, officers and contractors a license to enter the
plat to perform all work and inspections deemed appropriate by the
City in conjunction with plat development.
7. Site Erosion Control. Before the site is rough graded, '
and before .any utility construction is commenced or building
permits are issued, the erosion control plan, Plan B, shall be
implemented, inspected, and approved by the City. The City may
impose additional erosion control requirements if they would be
beneficial. All areas disturbed by the excavation and backfilling
operations shall be reseeded forthwith after the completion of the
work in that area. Except as otherwise provided in the erosion
control plan, seed shall be certified seed to provide a temporary
ground cover as rapidly as possible. All seeded areas shall be
fertilized, mulched, and disc anchored as necessary for seed
retention. The parties recognize that time is of the essence in
controlling erosion. If the Developer does not comply with the
erosion control plan and schedule of supplementary instructions
received from the City, the City may take such action as it deems
appropriate to control erosion at the Developer's expense. The
City will endeavor to notify the Developer in advance of any
proposed action, but failure of the City to do so will not affect
the Developer's and City's rights or obligations hereunder. No
development will be allowed and no building permits will be issued
unless the plat is in full compliance with the erosion control
requirements. Erosion control needs to be maintained until
vegetative cover has been restored, even if construction has been
completed and accepted. After the site has been stabilized to
where, in the opinion of the City, there is no longer a need for
erosion control, the City will authorize the removal of the erosion
control, i.e. hay bales and silt fence. The Developer shall remove
and dispose of the erosion control measures.
8. Clean up. The Developer shall maintain a neat and
orderly work site and shall daily clean, on and off site, dirt and 1
GC -2
11
11 debris, including blowables, from streets and the surrounding area
that has resulted from construction work by the Developer, its
agents or assigns.
II 9 . Acceptance and Ownership of Improvements. Upon
completion and acceptance by the City of the work and construction
I required by this Contract, the improvements lying within public
easements shall become City property. After completion of the
improvements, a representative of the contractor, and a
representative of the Developer's engineer will make a final
I inspection of the work with the City Engineer. Before the City
accepts the improvements, the City Engineer shall be satisfied that
all work is satisfactorily completed in accordance with the
II approved plans and specifications and the Developer and his
engineer shall submit a written statement attesting to same with
appropriate contractor waivers. Final acceptance of the public
improvements shall be by City Council resolution.
I 10. Claims. In the event that the City receives claims from
laborers, materialmen, or others that work required by this
II Contract has been performed, the sums due them have not been paid,
and the laborers, materialmen, or others are seeking payment out of
the financial guarantees posted with the City, and if the claims
I are not resolved at least ninety (90) days before the security
required by this Contract will expire, the Developer hereby
authorizes the City to commence an Interpleader action pursuant to
Rule 22, Minnesota Rules of Civil Procedure for the District
II Courts, to draw upon the letters of credit in an amount up to 125%
of the claim(s) and deposit the funds in compliance with the Rule,
and upon such deposit, the Developer shall release, discharge, and
I dismiss the City from any further proceedings as it pertains to the
letters of credit deposited with the District Court, except that
the Court shall retain jurisdiction to determine attorneys' fees.
II 11. Park and Trail Dedication. Prior to the issuance of
building permits for residential construction within the plat, the
Developer, its successors or assigns, shall pay to the City the
II park and trail dedication fees then in force pursuant to Chanhassen
City Ordinances and City Council resolutions.
I 12. Landscaping. Unless the lot already has one tree in the
front yard of suitable species, the Developer or lot purchaser
shall plant a tree in the front yard of every lot in the plat.
I Suitable trees include:
Maples Ash
Linden Basswood
I Green Ash Birch
Honey Locust Ginko (male only)
Hackberry Kentucky Coffee Tree
II Oak
Other species of trees may be approved by the building inspector.
Trees which can cause a public nuisance, such as cotton producing
II trees, or can be a public hazard, such as bug infestation or weak
GC -3
II
i /
bark, are prohibited. The minimum tree size shall be two and
one -half (2%) inches caliper, either bare root in season, or balled
and burlapped. The trees may not be planted in the boulevard (area
between curb and property line). In addition to any sod required
as a part of the erosion control plan, Plan B, the Developer or lot
purchaser shall sod the boulevard area and all drainage ways on
each lot utilizing a minimum of four (4) inches of topsoil as a
base. Seed or sod shall also be placed on all disturbed areas of
the lot. If these improvements are not in place at the time a
certificate of occupancy is requested, a financial guarantee in the
form of cash or letter of credit shall be provided to the City. '
Improvements are to be completed during the first growing season
after issuance of the certificate of occupancy. After satisfactory
inspection, the financial guarantee shall be returned. The City
has established the financial guarantee at $1,000.00; however, this
may be increased annually based upon cost. These requirements
supplement, but do not replace, specific landscaping conditions
that may have been required by the City Council for project '
approval.
13. Warranty. The Developer warrants all work required to be
performed by it against poor material and faulty workmanship for a
period of two (2) years after its completion and acceptance by the
City. All trees, grass, and sod shall be warranted to be alive, of
good quality, and disease free at the time of planting. All trees
shall be warranted for twelve (12) months from the time of
planting. The Developer or his contractor(s) shall post a letter
of credit or other security acceptable to the City to secure the
warranties at the time of final acceptance.
14. Lot Plans. Prior to the issuance of building permits, an
acceptable Grading, Drainage, Erosion Control, and Tree Removal
Plan shall be submitted for each lot as required in the Special
Provisions, for review and approval by the City Engineer. Each
plan shall assure that drainage is maintained away from buildings
and that tree removal is consistent with City Ordinance.
15. Existing Assessments. Any existing or pending
assessments against the plat will be re- spread against the plat in
accordance with City standards.
16. Street Lighting. The Developer shall have installed and 1
pay for street lights in accordance with City standards. A plan
shall be submitted for the City Engineer's approval prior to the
installation. Before the City signs the final plat, the Developer
shall pay the City a fee of $200.00 for each street light installed
in the plat. The fee shall be used by the City for furnishing
electricity for each light for twenty (20) months. 1
17. Street Signs. All street name and traffic signs required
by the City as a part of the public improvements shall be furnished
and installed by the City at the sole expense of the Developer.
GC -4
11
1
18. House Pads. The Developer shall promptly furnish the
City "as- built" plans indicating the amount, type and limits of
fill on any house pad location.
' 19. Responsibility for Costs.
A. The Developer shall pay an administrative fee in
' conjunction with the installation of the plat improvements. This
fee is to cover the cost of City Staff time and overhead for items
such as review of construction documents, preparation of the
Development Contract, monitoring construction progress, processing
pay requests, processing security reductions, and final acceptance
of improvements. This fee does not cover the City's cost for
' resident construction inspections. The fee shall be shall be
calculated as follows:
i) if the cost of the construction of public
' improvements is less than $500,000, three
percent (3 %) of construction costs;
' ii) if the cost of the construction of public
improvements is between $500,000 and
$1,000,000, three percent (3 %) of construction
costs for the first $500,000 and two percent
(2 %) of construction costs over $500,000;
iii) if the cost of the construction of public
improvements is over $1,000,000, two and
one -half percent (2f %) of construction costs
for the first $1,000,000 and one and one -half
' percent (1% %) of construction costs over
$1,000,000.
Before the City signs the final plat, the Developer shall deposit
with the City a fee based upon construction estimates. After
construction is completed, the final fee shall be determined based
upon actual construction costs. The cost of public improvements is
' defined in paragraph 6 of the Special Provisions.
B. In addition to the administrative fee, the Developer
' shall reimburse the City for all out -of- pocket costs incurred by
the City for providing resident construction inspections. This
cost will be periodically billed directly to the Developer based on
the actual progress of the construction. Payment shall be due in
accordance with Article 17E of this Agreement.
C. The Developer shall hold the City and its officers
and employees harmless from claims made by itself and third parties
for damages sustained or costs incurred resulting from plat
approval and development. The Developer shall indemnify the City
and its officers and employees for all costs, damages, or expenses
which the City may pay or incur in consequence of such claims,
including attorneys' fees.
GC -5
1
I/
D. In addition to the administrative fee, the Developer 1
shall reimburse the City for costs incurred in the enforcement of
this Contract, including engineering and attorneys' fees.
E. The Developer shall pay in full all bills submitted 1
to it by the City for obligations incurred under this Contract
within thirty (30) days after receipt. If the bills are not paid
on time, the City may halt all plat development work and
construction, including but not limited to the issuance of building
permits for lots which the Developer may or may not have sold,
until the bills are paid in full. Bills not paid within thirty
(30) days shall accrue interest at the rate of 8% per year.
F. In addition to the charges and special assessments
referred to herein, other charges and special assessments may be
imposed such as, but not limited to, sewer availability charges
( "SAC "), City water connection charges, City sewer connection
charges, and building permit fees.
20. Developer's Default. In the event of default by the
Developer as to any of the work to be performed by it hereunder,
the City may, at its option, perform the work and the Developer
shall promptly reimburse the City for any expense incurred by the
City, provided the Developer is first given notice of the work in
default, not less than four (4) days in advance. This Contract is
a license for the City to act, and it shall not be necessary for
the City to seek a Court order for permission to enter the land.
When the City does any such work, the City may, in addition to its
other remedies, assess the cost in whole or in part.
21. Miscellaneous. '
A. Construction Trailers. Placement of on -site
construction trailers and temporary job site offices shall be
approved by the City Engineer as a part of the pre- construction
meeting for installation of public improvements. Trailers shall be
removed from the subject property within thirty (30) days following
the acceptance of the public improvements unless otherwise approved
by the City Engineer.
B. Postal Service. The Developer shall provide for the '
maintenance of postal service in accordance with the local
Postmaster's request.
C. Third Parties. Third parties shall have no recourse 1
against the City under this Contract.
D. Breach of Contract. Breach of the terms of this
Contract by the Developer shall be grounds for denial of building
permits, including lots sold to third parties.
E. Severabilitv. If any portion, section, subsection, '
sentence, clause, paragraph, or phrase of this Contract is for any
reason held invalid, such decision shall not affect the validity of
the remaining portion of this Contract.
GC -6
II
11 F. Building Permits. Building permits will not be
issued for constructing homes in the plat until sanitary sewer,
watermain, and storm sewer have been installed, tested, and
II accepted by the City, and the streets needed for access have been
paved with a bituminous surface.
I G. Waivers /Amendments. The action or inaction of the
not constitute a waiver or amendment to the provisions
of this Contract. To be binding, amendments or waivers shall be in
writing, signed by the parties and approved by written resolution
II of the City Council. The City's failure to promptly take legal
action to enforce this Contract shall not be a waiver or release.
I H. Release. This Contract shall run with the land and
may be recorded against the title to the property . After the
Developer has completed the work required of it under this
Contract, at the Developer's request the City Manager will issue a
II Certificate of Compliance. Prior to the issuance of such a
certificate, individual lot owners may make as written request for
a certificate applicable to an individual lot allowing a minimum of
I ten (10) days for processing.
I. Insurance. Developer shall take out and maintain
I until six (6) months after the City has accepted the public
improvements, public liability and property damage insurance
covering personal injury, including death, and claims for property
damage which may arise out of Developer's work or the work of its
I subcontractors or by one directly or indirectly employed by any of
them. Limits for bodily injury and death shall be not less than
$500,000 for one person and $1,000,000 for each occurrence; limits
II for property damage shall be not less than $200,000 for each
occurrence; or a combination single limit policy of $1,000,000 or
more. The City shall be named as an additional insured on the
I policy, and the Developer shall file with the City a certificate
evidencing coverage prior to the City signing the plat. The
certificate shall provide that the City must be given ten (10) days
advance written notice of the cancellation of the insurance. The
I certificate may not contain any disclaimer for failure to give the
required notice.
1 J. Remedies. Each right, power or remedy herein
conferred upon the City is cumulative and in addition to every
other right, power or remedy, expressed or implied, now or
I hereafter arising, available to City, at law or in equity, or under
any other agreement, and each and every right, power and remedy
herein set forth or otherwise so existing may be exercised from
time to time as often and in such order as may be deemed expedient
II by the City and shall not be a waiver of the right to exercise at
any time thereafter any other right, power or remedy.
I K. Assignability. The Developer may not assign this
Contract without the written permission of the City Council. The
Developer's obligation hereunder shall continue in full force and
effect even if the Developer sells one or more lots, the entire
II plat, or any part of it.
GC -7
II
II
L. Construction Hours. The normal construction hours f
under this contract shall be from 7:00 a.m. to 7:00 p.m. on
weekdays, from 9:00 a.m. to 5:00 p.m. on Saturdays with no such
activity allowed on Sundays or any recognized legal holidays.
II
Operation of all internal combustion engines used for construction
or dewatering purposes beyond the normal working hours will require
City Council approval. Under emergency conditions, this limitation II may be waived by the consent of the City Engineer.
Any approved work performed after dark shall be adequately
illuminated. 1
M. Access. All access to the plat prior to the City
accepting the roadway improvements shall be the responsibility of II the Developer regardless if the City has issued building permits or
occupancy permits for lots within the plat.
N. Street Maintenance. The Developer shall be
II
responsible for all street maintenance until streets within the
subdivision are accepted by the City. Warning signs shall be
placed by the Developer when hazards develop in streets to prevent
II
the public from traveling on same and directing attention to
detours. If streets become impassable, the City may order that
such streets shall be barricaded and closed. The Developer shall II maintain a smooth roadway surface and provide proper surface
drainage. The Developer may request, in writing, that the City
plow snow on the streets prior to final acceptance of the streets.
I The City shall have complete discretion to approve or reject the
request. The City shall not be responsible for reshaping or damage
to the street base or utilities because of snow plowing operations.
The provision of City snow plowing service does not constitute
final acceptance of the streets by the City. II
O. Soil Treatment Systems. If soil treatment systems
are required, the Developer shall clearly identify in the field and
protect from alteration, unless suitable alternative sites are
first provided, the two soil treatment sites identified during the
platting process for each lot. This shall be done prior to the
I
issuance of a Grading Permit. Any violation /disturbance of these
sites shall render them as unacceptable and replacement sites will
need to be located for each violated site in order to obtain a 111 building permit.
P. Variances. By approving the plat, the Developer
represents that all lots in the plat are buildable without the need
II
for variances from the City's ordinances.
Q. Compliance with Laws, Ordinances, and Regulations. II In the development of the plat the Developer shall comply with all
laws, ordinances, and regulations of the following authorities:
1. City of Chanhassen; 1
2. State of Minnesota, its agencies, departments
and commissions; II 3. United States Army Corps of Engineers;
GC -8
1
4. Watershed District(s);
5. Metropolitan Government, its agencies,
departments and commissions.
R. Proof of Title. Upon request, the Developer shall
furnish the City with evidence satisfactory to the City that it has
the authority of the fee owners and contract for deed purchasers
' too enter into this Development Contract.
S. Soil Conditions. The Developer acknowledges that
' the City makes no representations or warranties as to the condition
of the soils on the property or its fitness for construction of the
improvements or any other purpose for which the Developer may make
use of such property. The Developer further agrees that it will
indemnify, defend, and hold harmless the City, its governing body
members, officers, and employees from any claims or actions arising
out of the presence, if any, of hazardous wastes or pollutants on
11 the property, unless hazardous wastes or pollutants were caused to
be there by the City.
T. Soil Correction. The Developer shall be responsible
for soil correction work on the property. The City makes no
representation to the Developer concerning the nature of
suitability of soils nor the cost of correcting any unsuitable soil
conditions which may exist. On lots which have no fill material a
soils report.from a qualified soils engineer is not required unless
the City's building inspection department determines from
observation that there may be a soils problem. On lots with fill
material that have been mass graded as part of a multi -lot grading
project, a satisfactory soils report from a qualified soils
engineer shall be provided before the City issues a building permit
for the lot. On lots with fill material that have been custom
graded, a satisfactory soils report from a qualified soils engineer
shall be provided before the City inspects the foundation for a
' building on the lot.
1
1
1
i
1
1
GC -9
1
1
CITY OF CHANHASSEN
STONE CREEK SECOND ADDITION
PROJECT NO. 93 -17
BREAKDOWN OF ADMINISTRATION FEES - 7/22/93 1
1
Estimated Total Cost of Public Improvements $ 71,450.00
Improvement Co is Under $500,000) $ 2
- 3% of Public s ( $ ) 2,143.00
- Street Lighting Charge (for electricty) 1
2 @ $200 $ 400.00
- Final Plat Process (Attorney Fee for Review and Recording of Plat 1
and Development Contract) $ 200.00
- Recording Fees 1
a. Development Contract $ 25.00
b. Plat Filing $ 30.00
c. Easements (Turnaround) $ 25.00
1
TOTAL ADMINISTRATION FEES $ 2,823.00
1
1
1
1
1
1
1
1
1
(7, ,etz7T" /ON re, /7 a — 2
11 P. In lieu of park and trail fees the property labeled
a s park shall be dedicated on the final plat as an outlot and
deeded to the City as park land. In addition, the developer shall
construct an 8 -foot wide bituminous trail segment between -Lot_ 5.,_.,
Block 1 and Lot 1, Block 2 from Boulder Drive to the rear property
line of said lots.
1 Q. Boulder Road should be labeled and dedicated on the
final plat.
R. A drain tile system shall be included with the
street construction plans.
S. The trail along the south of Timberwood subdivision
shall be constructed with the lots adjacent to it are platted.
T. The park /trail shall be extended to abut Timberwood
Drive.
9. General Conditions. The general conditions of this
Contract, approved by the City Council on February 22, 1988, are
attached as Exhibit "B" and incorporated herein.
1
1
1
1
1
1
1
1
1
1
SP -6
1