3d. Approve Con Plans and Specs for Hwy 101 Turn Lanes at Pleasant View Road and Cheyenne Trail Project 91-6 S.P. 1010-07 3L
C ITYOF
it° 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
(612) 937 -1900 • FAX (612) 937 -5739
.,� ow 6 City Admtni+rator
trsed ✓ DLO A
1 MEMORANDUM Modified
Rejected
Date 5 -9 3
TO: Charles Folch, City Engineer Date Submitted to Commissiofl
FROM: Dave Hempel, Assistant City Engineer 0(44$‘,/ Date Submitted to Council
1 DATE: May 3, 1993
SUBJ: Approve Construction Plans and Specifications and Cooperative Agreement;
' Authorize Advertising for Bids for Trunk Highway 101 Turn Lanes at Pleasant
View Road and Cheyenne Trail - Project No. 91 -6, S.P. 1010 -07
1
After over two years from the initial request for a joint cooperative agreement with MnDOT
for the construction of right turn lanes along southbound Trunk Highway 101 at Pleasant
View Road and Cheyenne Trail, I am pleased to present for approval a cooperative
agreement and construction plans and specifications. The attached cooperative construction
' agreement has been drafted by the Minnesota Department of Transportation (MnDOT) to
address specific responsibilities with regards to construction, maintenance and cost sharing.
MnDOT will reimburse the City 100% of the construction costs for the right turn lanes
' except for the hydrant relocation on Pleasant View Road. In addition, MnDOT will
reimburse the City 8% of the engineering costs involved with construction of the turn lanes.
The estimated project cost is $55,077. MnDOT has allotted $64,483.16 which includes the
8% construction engineering and contingencies.
Staff has also reviewed the attached construction plans and specifications prepared by Van
1 Doren - Hazard - Stallings, Inc. dated April 1, 1993. The plans and specifications have already
received approval from MnDOT. In an effort to expedite letting of the project, staff also
requests the City Council authorized advertising for bids for the Trunk Highway 101 Turn
1 Lane Project at Pleasant View Road and Cheyenne Trail. It is staffs intent to place an
advertisement for bids in the May 14, 1993 issues of the local paper as well as the
Construction Bulletin. The bid opening date has been scheduled for May 24, 1993 for
' consideration at the City Council on the same date. Staff is trying to let the bid prior to
June, 1993 whereas the State's fiscal budget year typically nears the end and the construction
dollars that have been allocated for the 1993 construction season may be forfeited.
1 �s
t«► PRINTED ON RECYCLED PAPER
1
•
1 Charles Folch
May 3, 1993
Page 2
RECOMMENDATION
' It is therefore recommended that the City Council approve Cooperative Agreement No.
ty PP P �
' 70266 with the State of Minnesota along with the construction plans and specifications
prepared by Van Doren - Hazard- Stallings, Inc. dated April 1, 1993 for construction of right
turn lanes on Trunk Highway 101 at Cheyenne Trail and Pleasant View Road, S.P. 1010 -07
' (TH101 =187). It is also recommended that the City Council authorized advertising for bids
for the Trunk Highway 101 turn lanes at Pleasant View Road and Cheyenne Trail, City
Project No. 91 -6, State Project No. 1010 -07 (TH101 =187).
' ktm
' Attachments: 1. Cooperative Agreement No. 70266.
2. Proposed Resolution.
3. Construction Plans (specifications are available in the
Engineering office for review).
NOTE TO COUNCIL: Please leave your copy of the construction plans behind for staff to
collect at the end of the meeting.
1
1
1
' OFFICIAL ENGNEERINt COPY
Received
Revision No
1 Approved byc Engineer
Date s/tV
APProved try City Councis
1
1
PRE - LETTING STATE OF MINNESOTA AGREEMENT NO.
SERVICES DEPARTMENT OF TRANSPORTATION
SECTION COOPERATIVE CONSTRUCTION 70266
AGREEMENT
S.P. 1010 -07 (T.H. 101 =187)
State Funds
Agreement between
ORIGINAL
The State of Minnesota AMOUNT ENCUMBERED
Department of Transportation, and
The City of Chanhassen $64,483.16
Re: State cost turn lane construction
by the City on T.H. 101 at
Cheyenne Trail and Pleasant View AMOUNT RECEIVABLE
Road in Chanhassen
(None)
1
1
1
THIS AGREEMENT is made and entered into by and between the State of
Minnesota, Department of Transportation, hereinafter referred to as
the "State" and the City of Chanhassen, Minnesota, acting by and
1
through its City Council, hereinafter referred to as the "City ".
1
1
ATTACHMENT 1 1
1
70266
I WITNESSETH:
1
WHEREAS the City is about to perform turn lane construction and other
1 associated construction upon, along and adjacent to Trunk Highway
No. 101 from Engineer Station 9 +60.00 (Cheyenne Trail) to Engineer
I Station 14 +90.50 (480 feet north of Pleasant View Road) within the
II corporate City limits in accordance with City - prepared plans,
specifications and /or special provisions designated by the City as
1 Project No. 91 -06 and by the State as State Project No. 1010 -07
(T.H. 101 =187); and
111
1 WHEREAS the City has requested participation by the State in the
costs of the turn lane construction; and
1
WHEREAS the State is willing to participate in the costs of the turn
1 lane construction and associated construction engineering as
hereinafter set forth; and
1 WHEREAS Minnesota Statute section 161.20, subdivision 2 authorizes
the Commissioner of Transportation to make arrangements with and
1 cooperate with any governmental authority for the purposes of
I constructing, maintaining and improving the trunk highway system.
1
1
1 2
1
1
70266
IT I8, THEREFORE, MUTUALLY AGREED AS FOLLOWS:
1
ARTICLE I - CONSTRUCTION BY THE CITY
Section A. Contract Award and Construction 1
The City shall receive bids and award a construction contract to the
lowest responsible bidder, subject to concurrence by the State in
that award, in accordance with State - approved City plans, 1
specifications and /or special provisions designated by the City as
Project No. 91 -06 and by the State as State Project No. 1010 -07 1
(T.H. 101 =187). The contract construction shall be performed in
accordance with State - approved City plans, specifications and /or
special provisions which are on file in the office of the City's 1
Engineer, and are made a part hereof by reference with the same force
and effect as though fully set forth herein. 1
Section B. Documents to be Furnished to the State
The City shall, within 7 days of opening bids for the construction 1
contract, submit to the State's State Aid Agreements Engineer at
Golden Valley a certified copy of the low bid and an abstract of all
bids together with the City's request for concurrence by the State in
the award of the construction contract. The City shall not award the 1
construction contract until the State advises the City in writing of
its concurrence therein.
1
1
3 1
1
70266
Section C. Cancellation of Agreement
Each party to this agreement reserves the right to withdraw from and
cancel this agreement within 30 days after the opening of bids if
either party determines any or all bids to be unsatisfactory.
' Withdrawal from or cancellation of the agreement shall be
accomplished by either party serving a written notice thereof upon
the other.
Section D. Direction, Supervision and Inspection of Construction
The contract construction shall be under the direction of the City
and under the supervision of a registered professional engineer;
' however, the State cost participation construction covered under this
agreement shall be open to inspection by the State's Metropolitan
' Division Engineer at St. Paul or his authorized representatives. The
City shall give the State Aid Agreements Engineer five days notice of
its intention to start the contract construction.
1
Responsibility for the control of materials for the State cost
1 participation construction covered under this agreement shall be on
the City and its contractor and shall be carried out in accordance
with Specifications No. 1601 through and including No. 1609 as set
forth in the State's current "Standard Specifications for
Construction ".
1
1 4
1
70266 1
Section E. Completion of Construction
The City shall cause the contract construction to be started and
completed in accordance with the time schedule in the construction '
contract special provisions. The completion date for the contract
construction may be extended, by an exchange of letters between the
appropriate City official and the State Division Engineer's
authorized representative, for unavoidable delays encountered in the
performance thereof.
1
Section P. Additional Construction, Plan Chancres, Etc. 1
The State shall not participate in the cost of any contract
construction that is in addition to the State cost participation
construction covered under this agreement unless the necessary State
funds have been encumbered prior to the performance of the additional
contract construction and the terms and conditions in the following '
paragraph have been met.
All changes in the plans, specifications and /or special provisions '
for the State cost participation construction covered under this
agreement and all addenda, change orders and /or supplemental '
agreements entered into by the City and its contractor for State cost
participation construction covered under this agreement must be '
approved in writing by the State Division Engineer's authorized
representative before payment is made by the State therefor.
1
5
i
11
1 70266
Section G. Compliance with Laws, Ordinances and Regulations
' The City shall, in connection with the award and administration of
the construction contract and the performance of the contract
construction, comply and cause its contractor to comply with all
' Federal, State and Local laws, including Minnesota Statute section
16B.101, and all applicable ordinances and regulations.
1 Section H. Right -of -Way, Easements and Permits
The City shall, without cost or expense to the State, obtain all
1 rights -of -way, easements, construction permits and /or any other
permits and sanctions that may be required in connection with the
' contract construction, and shall promptly furnish the State with
' certified copies of the documents for those rights -of -way, easements,
construction permits and /or other permits and sanctions.
The City shall, within 90 days after satisfactory completion of the
' City -owned utilities contract construction, submit to the Director of
the State's Pre - Letting Services Section five copies of a permit
' application, including "as built" sketches, for all City -owned
1 utilities constructed upon and within the trunk highway right -of -way.
Application for permits shall be made on State form "Application For
1 Utility Permit On Trunk Highway Right -Of -Way" (Form TP2525).
1
6
I
70266 1
ARTICLE II - BASIS OF PAYMENT BY THE STATE
Section A. SCHEDULE "I" '
A Preliminary SCHEDULE "I" is attached hereto and made a part hereof
by reference. The Preliminary SCHEDULE "I" includes all anticipated
State cost participation construction items and the construction '
engineering cost share covered under this agreement.
Section B. State Cost Participation Construction
The State shall, at the percentage indicated, participate in the
following construction to be performed upon, along and adjacent to
Trunk Highway No. 101 at the intersections with Cheyenne Trail and
Pleasant View Road within the corporate City limits under State '
Project No. 1010 -07 (T.H. 101 =187).
With the exception of the hydrant relocation at the intersection of
Trunk Highway No. 101 and Pleasant View Road, 100 Percent shall be
the rate of cost participation in all of the turn lane construction ,
and associated construction, as described and tabulated on Sheet
No. 2 of the attached SCHEDULE "I ". '
Section C. Construction Engineering Costs
The State shall pay a construction engineering charge in an amount
equal to 8 percent of the total cost of the State participation
construction covered under this agreement.
r
7
1
70266
Section D. Addenda, Change Orders and Supplemental Agreements
' The State shall share in the costs of construction contract addenda,
' change orders and /or supplemental agreements which are necessary to
complete the State cost participation construction covered under this
' agreement and which have been approved in writing by the State
Division Engineer's authorized representative.
' Section E. Settlements of Claims
The State shall pay to the City its share of the cost of any
' settlements of claims made with the City's contractor.
All liquidated damages assessed the City's contractor in connection
with the construction contract shall result in a credit shared by the
State and the City in the same proportion as their total construction
cost share covered under this agreement is to the total contract
construction cost before any deduction for liquidated damages.
' ARTICLE III - PAYMENT BY THE STATE
Section A. Estimate and Advancement of the State's Cost Share
It is estimated that the State's share of the costs of the contract
construction plus the 8 percent construction engineering cost share
and a $5,000.00 contingency amount is the sum of $64,483.16 as shown
in the attached Preliminary SCHEDULE "I ". The attached Preliminary
SCHEDULE "I" was prepared using estimated unit prices. Upon receipt
and review of the construction contract bid documents described in
Article I, Section B. of this agreement, the State shall then decide
i
8
11
70266 1
whether to concur in the City's award of the construction contract
and, if so, prepare a Revised SCHEDULE "I" based on construction 1
contract unit prices. The contingency amount is provided to cover
overruns of the plans estimated quantities of State cost
participation construction and /or State - approved additional
construction including construction engineering costs.
1
The State shall advance to the City the State's total estimated cost
share, less contingency amount, as shown in the Revised SCHEDULE "I"
after the following conditions have been met:
1
1. Encumbrance by the State of the State's total estimated cost
1
share, including contingency amount, as shown in the Revised
SCHEDULE "I ".
2. Execution and approval of this agreement and the State's
transmittal of same to the City along with a copy of the Revised
1
SCHEDULE "I" and a letter advising the City of the State's
concurrence in the award of the construction contract.
a written request from City
3. Receipt by the State of wri r q f the y or the for
of funds. The request shall include certification
1
by the City that the construction contract has been executed by
all necessary parties. '
9
1
1
70266
Whenever it appears the cost of the State participation construction
' covered under this agreement is about to exceed the current amount of
encumbered State funds, the City shall notify the State Division
Engineer's authorized representative in writing prior to performance
of the additional State cost participation construction.
Notification shall include an estimate in the amount of additional
funds necessary to complete the State cost participation construction
including construction engineering costs and the reason(s) why the
' current amount encumbered will be exceeded. The State shall, upon
its approval of the additional State cost participation construction,
submit a request for encumbrance of the necessary additional funds to
the Minnesota Department of Finance. That action will have the
effect of amending this agreement so as to include the State's share
' of the costs of the additional construction.
Should the City cause the performance of additional contract
' construction which would otherwise qualify for State cost
participation covered under this agreement, but for which the State
has not previously encumbered funds, that additional contract
' construction is done at the City's own risk. The City shall notify
the State Division Engineer's authorized representative in writing of
the additional State cost participation construction. Notification
shall include an estimate in the amount of additional funds necessary
' to cover the additional State cost participation construction
including construction engineering costs and the reason(s) why the
current amount encumbered was exceeded. If the State approves the
' 10
1
1 =
70266 1
additional State cost participation construction, the City's claim
for compensation along with a request for encumbrance of the 1
necessary additional funds shall be submitted to the Commissioner of
Finance for review pursuant to Minnesota Statute section 16A.15,
subdivision 3, but no guarantee is made that the claim will be
approved by the Commissioner of Finance. If the Commissioner of
Finance certifies the claim for compensation and the request for 1
encumbrance of the necessary additional funds therefor, that action
will have the effect of amending this agreement so as to include the
State's share of the costs of the additional construction.
If the State determines that the submittal of a claim for 1
compensation is warranted and it is deemed legally necessary to
supplement this agreement, and if the claim is approved and a 1
supplement to this agreement in connection with the claim is prepared
and processed, the first $3,000.00 of the claim will not be eligible
for payment. 1
Section B. Records Keeping and Invoicing by the City
The State shall provide the City with a Payment Processing Package
containing a Modified SCHEDULE "I" form, instructions, and samples of
documents for processing final payment of the State participation 1
construction cost covered under this agreement.
1
The City shall keep records and accounts that enable it to provide
the following prior to final payment
the State with th g P P Ym ent by the State:
11 1
1
1
70266
1. A copy of the Modified SCHEDULE "I" which includes final
1 quantities of State cost participation construction.
2. Copies of the City contractor's invoice(s) covering all contract
construction.
3. Copies of the endorsed and canceled City warrant(s) or check(s)
paying for final contract construction, or computer
1 documentation of the warrant(s) issued certified by an
' appropriate City official that final construction contract
payment has been made.
4. Copies of all construction contract change orders and /or
1 supplemental agreements.
I 5. A certification form attached to a copy of the Final SCHEDULE
"I ", both of which shall be provided by the State. The
certification form shall be signed by the City's Engineer in
charge of the contract construction attesting to the following:
a. Satisfactory performance and completion-of all contract
' construction in accordance with State - approved City plans,
specifications and /or special provisions.
b. Acceptance and approval of all materials furnished for the
' State cost participation construction covered under this
12
1
1
70266 1
agreement relative to compliance of those materials to the
State's current "Standard Specifications for Construction ". '
c. Full payment by the City to its contractor for all contract
construction.
6. When requested by the State, copies, certified by the City's
Engineer, of material sampling reports and of material testing
results for the materials furnished for the State cost
participation construction covered under this agreement.
7. A copy of the "as built" plan sent to the State Aid Agreements '
Engineer.
i
8. A formal invoice (original and signed) in the amount due the
City as shown in the Final SCHEDULE I " .
As provided by Minnesota Statute section 16B.06, subdivision 4, the
books, records, documents, and accounting procedures and practices of
the City relevant to this agreement are subject to examination by the
contracting department or agency, and either the legislative auditor
or the State auditor as appropriate. '
Section C. Final Payment by the State 1
Upon completion of all contract construction, the State shall prepare
a Final SCHEDULE "I" based on final quantities of State cost
13 1
1
1
1 70266
participation construction and shall submit a copy to the City. If
I the final cost of the State participation covered under this
agreement exceeds the amount of funds advanced by the State, the
1 State shall promptly pay the difference to the City without interest.
1 If the final cost of the State participation covered under this
agreement is less than the amount of funds advanced by the State, the
I City shall promptly return the balance to the State without interest.
Procedures relevant to preparation of the Final SCHEDULE "I" and
1 final payment of the State participation cost covered under this
I agreement are detailed in the Payment Processing Package, which the
State shall furnish the City.
1
Pursuant to Minnesota Statute section 15.415, the City waives claim
I for any amounts less than $2.00 over the amount of State funds
previously advanced to the City, and the State waives claim for the
I return of any amounts less than $2.00 of those funds advanced by the
1 State.
1 ARTICLE IV - GENERAL PROVISIONS
Section A. Replacement of Castings
I The City shall furnish its contractor with new castings and /or parts
I for all inplace City -owned facilities constructed hereunder when
replacements are required, without cost or expense to the State.
1
1
1 14
70266 1
Section B. Maintenance by the City
Upon satisfactory completion of the storm sewer facilities and City 1
owned facilities construction to be performed within the corporate
City limits under the construction contract, the City shall provide
for the proper maintenance of those facilities, without cost or
1
expense to the State.
1
Section C. Additional Drainage
Neither party to this agreement shall drain any additional drainage
into the storm sewer facilities to be constructed under the
1
construction contract, that was not included in the drainage for
which the storm sewer facilities were designed without first
1
obtaining permission to do so from the other party. The drainage
areas served by the storm sewer facilities constructed under the
construction contract are shown in a drainage area map, EXHIBIT
1
"Drainage Area ", which is on file in the office of the State's
Division Hydraulics Engineer at Golden Valley and is made a part
hereof by reference with the same force and effect as though fully
set forth herein. 1
Section D. Claims
The City at its own sole cost and expense shall defend, indemnify,
save and hold harmless the State and all of its agents, officers and
employees of and from all claims, demands, proceedings, actions or
causes of action of whatsoever nature or character arising out of or
by reason of contract construction, construction engineering and /or
15 1
70266
maintenance covered under this agreement including an action or claim
which alleges negligence of the State, its agents, officers and
employees.
All employees of the City and all other persons employed by the City
in the performance of contract construction, construction engineering
1 and /or maintenance covered under this agreement shall not be
considered employees of the State. All claims that arise under the
' Worker's Compensation Act of the State of Minnesota on behalf of the
employees while so engaged and all claims made by any third parties
as a consequence of any act or omission on the part of the employees
while so engaged on contract construction, construction engineering
and /or maintenance covered under this agreement shall in no way be
1 the obligation or responsibility of the State.
Section E. Nondiscrimination
The provisions of Minnesota Statute section 181.59 and of any
applicable ordinance relating to civil rights and discrimination
1 shall be considered part of this agreement as if fully set forth
herein.
1 Section F. Agreement Approval
Before this agreement shall become binding and effective, it shall be
1 approved by a City Council resolution and receive approval of State
and City officers as the law may provide in addition to the
' Commissioner of Transportation or his authorized representative.
1 16
1
1
70266 1
IN TESTIMONY WHEREOF the parties have executed this agreement by their
authorized officers. 1
DEPARTMENT OF TRANSPORTATION CITY OF CHANHASSEN 1
Recommended for approval:
By 1
By t:'4eA /7 Mayor
G Director
�,
Pre-Letting Services Section Date 1
P g
1
By By
Division Engineer City Manager
Approved: Date
DEPARTMENT OF ADMINISTRATION
By
State Design Engineer Approved:
Date 1
(Date of Agreement) By
(Authorized Signature)
OFFICE OF THE ATTORNEY GENERAL
Date
Approved as to form and execution:
DEPARTMENT OF FINANCE
By Approved: 1
Special Asst. Attorney General
By 1
(Authorized Signature)
Date
1
17 1
1
MI OM = OMM OM MO MN NM MI 1111111 NM OM NM MIII MI NM WM M
PRELIMINARY SCHEDULE "I"
Agreement No. 70266
City of Chanhassen Preliminary: April 20, 1993
S.P. 1010 -07 (T.H. 101 =187)
State Funds
Turn lane construction performed under
City Contract with
located on T.H. 101 at Chevenne Trail and Pleasant View Road in the City of Chanhassen
STATE COST PARTICIPATION
From Sheet No. 2 $55,077.00
Construction Engineering (8 %) 4,406.16
Subtotal $59,483.16
(1) Contingency Amount 5,000.00
Total Amount to be Encumbered $64,483.16
(1) For the State's use only as described in the body of the agreement
- 1 -
70266
(P) = PLAN QUANTITY
ITEM NUMBER � S.P. I UNIT I QUANTITY I UNIT PRICE I COST
MOBILIZATION LUMP SUM 1.00 3,000.00 3,000.00
, 2101.511 CLEARING AND GRUBBING LUMP SUM 1.00 1,000.00 1,000.00
2104.501 REMOVE METAL CULVERT LIN. FT. 121.00 6.00 726.00
2104.505 REMOVE BITUMINOUS PAVEMENT SO. YD. 195.00 2.00 390.00
, 2104.513 SAWING BITUMINOUS PAVEMENT LIN. FT. 1,105.00 2.00 2,210.00
2104.523 SALVAGE METAL CULVERT EACH 1.00 150.00 150.00
2105.501 COMMON EXCAVATION (P) CU. YD. 976.00 3.00 2,928.00
2105.523 COMMON BORROW (LV) CU. YD. 1,218.00 5.00 6,090.00
_ 0105.605 DITCH CLEANING ROAD STA. 4.25 300.00 1,275.00
2211.501 AGGREGATE BASE CLASS 5 TON 550.00 7.00 3,850.00
2331.508 TYPE 31 WEARING COURSE MIXTURE TON 100.00 40.00 4,000.00
2331.514 TYPE 31 BASE COURSE MIXTURE TON 245.00 35.00 8,575.00
2357.502 BITUMINOUS MATERIAL FOR TACK COAT GALLON 125.00 2.00 250.00
2501.521 22" SPAN RC PIPE -ARCH CULVERT CL IIA LIN. FT. 70.00 35.00 2,450.00
2501.567 15" CS SAFETY APRON & GRATE, DES 3128 EACH 2.00 200.00 400.00
2501.567 15" RC SAFETY APRON & GRATE, DES 3128 EACH 1.00 250.00 250.00
2501.567 18" RC SAFETY APRON & GRATE, DES 3128 EACH 1.00 300.00 300.00
2501.567 22" SPAN RC SAFETY APR & GRATE, DES 3128 EACH 2.00 500.00 1,000.00
2503.511 15" RC PIPE SEWER LIN. FT. 166.00 24.00 3,984.00
2503.511 18" RC PIPE SEWER . LIN. FT. 12.00 30.00 360.00 ,
2503.511 18" CS PIPE SEWER LIN. FT. 18.00 15.00 270.00
2503.573 INSTALL SALVAGED METAL CULVERT EACH 1.00 150.00 150.00
2506.502 , CONST DRAINAGE STRUCTURE DESIGN SPECIAL , EACH 1.00 1,500.00 1,500.00
2511.501 RANDOM RIPRAP, CLASS II CU. YD. 24.00 75.00 1,800.00
0563.601 TRAFFIC CONTROL LUMP SUM 1.00 4,000.00 4,000.00
0564.602 F & I TRAFFIC SIGNS AND POSTS EACH 2.00 250.00 500.00
0564.602 PAVEMENT MESSAGE (RIGHT ARROW) PAINT EACH 4.00 50.00 200.00
0564.603 4" SOLID LINE -- WHITE PAINT LIN. FT. 1,490.00 .60 894.00
0573.603 SILT FENCE, TYPE 2 LIN. FT. 210.00 2.50 525.00
2575.501 SEEDING ACRE .25 2,500.00 625.00
2575.505 SODDING TYPE LAWN SO. YD. 475.00 3.00 1,425.00
TOTAL $55,077.00
(1) 100% STATE - $55,077.00
- 2 -
MO MN MIN M MI MN INE NM MN NM NM NM MN INOI NM Mil NM MN MN
1
70266
CITY OF CHANHASSEN
1 RESOLUTION
BE IT RESOLVED that the City of Chanhassen enter into Agreement No. 70266 with the
State of Minnesota, Department of Transportation for the following purposes, to -wit:
to provide for payment by the State to the City of the State's share of the cost of turn lane
construction and other associated construction to be performed upon, along and adjacent to
1 Trunk Highway No. 101 from Engineer Station 9 +60.00 (Cheyenne Trail) to Engineer
Station 14 +90.50 (480 feet north of Pleasant View Road) within the corporate City limits in
accordance with plans, specifications and /or special provisions designated by the City as
1 Project No. 91 -06 and by the State as State Project No. 1010 -07 (T.H. 101 =187).
BE IT FURTHER RESOLVED that the proper City Officers are hereby authorized and
directed to execute such agreement.
' CERTIFICATION
' State of Minnesota
County of Carver
1 City of Chanhassen
I hereby certify that the foregoing Resolution is a true and correct copy of the resolution
presented to and adopted by the Council of the City of Chanhassen at a duly authorized
meeting thereof held on the day of , 1993, as shown by the
minutes of said meeting in my possession.
City Manager
(Signature)
(Type or print name)
1
1 ATTACHMENT ?