1 MEMORANDUM 0,*. '
TO: Don Ashworth, City Manager
I FROM: Charles Folch, City Engineer
1 DATE: September 9, 1992
SUBJ: Award of Bids for Phase I of Upper Bluff Creek Trunk Utilities
1 Project No. 91 -17
I The bid opening for the Phase I of the Upper Bluff Creek Trunk Utility Improvements Project
No. 91 -17 was previously scheduled for Tuesday, September 8, 1992, however, due to the size
I and complexity of this project, a few addendums were necessary during the bidding process to
clarify and define some revisions and corrections. Given the addendums and the Labor Day
holiday, staff and the project consultant felt it would be appropriate to allow some additional time
I for the planholders to prepare the bids. Therefore, the bid opening for the Phase I of the Upper
Bluff Creek Trunk Utility Improvement Project has been rescheduled to Friday, September 11,
1992 at 3:30 p.m. This of course will be too late to report the bidding results prior to Council
1 packet distribution.
Given the time constraints to complete the work during the remaining fall construction season,
I I would propose to maintain this item as scheduled on the agenda. Staff and the project
consultant will review the bids received and confirm the low bidder prior to Monday night's
Council meeting. At the meeting, I will present the results of the bid opening, announce the
1 confirmed low bidder, and recommend an award of contract.
jms
l Attachment
1 1. Letter from Bonestroo dated September 8, 1992.
I pc: Dave Hempel, Senior Engineering Technician
Phil Gravel, Bonestroo, Rosene, Anderlik and Associates
1
1 t4f PRINTED ON RECYCLED PAPER
SP-10-92 TI-3U 15 :2 5 B O N E S T R O O & ASSOC I A T E S P. 02
1
0110 G 9onestroe. PE WnWdnl A 'hinterd. PE airy F Rower. PI 1 1 ..,.wa +1 f'1
1 fill B �y ` n !n�
Rosene RWart W. . PF • KJ^ah A G'K)bOr1, PE IMntpl Manlno PE !Auk r r bt.min. PI
V !�^Ad44 VV It ph Anders
C Md rftr PF Room PrrlfCtk. PC MihxN Rau, PE Mot u..iv., Pt
M. 1 4 YoNalli. PF R1, hdRJ W Pow?, Pk A es M RN, Art P 1 Phanil . ,f.Wri u1 Pt
Rkli,itil Turner, Pt I).wul i) Lolktlta, PE. rhorno W Ptdarwur I Karr u, nrrwii PI
MOM Andean( ciiro I R Cook. P1 Robert C RIA I' . AJ,A, MKhder C Lynch. ('E 1- fhid i 1 „ I •.In, 1
1 thumJt 6 AO” PF J Ili A rWwdon. PE Joao R M84nn PE Peon 1 ..$,,,, el
Associates RUUart Z Cn
SuniKR. PF MAO A ri,p,y,>n, PE, krry D PtAnch, PI sti.rw,. I) .,N.A.iri PI
%WWI M MOW, C PA Michael r R1utn16rw,, Pt I(rnnuch P MCkrson, 1`1 ( etdo , Hr, «v rr
"wool C„ I1Wtark Tel K FIM. PE Mark R Rolls PC ( rwl,, A 1 ,,,.•,r1n
Tn
Engineers & Architects oMa% R Anderson, A I A. Mart A kip, Pt 1 Pn M Y.nbrnly
DOodkr C Suva*. PE Crory W Morten. PF Frdr1,. M I inf.r1
Trwma, E: Angus. PP O +Mel 1 Edgerton Pr l.n,.r 1 r•,rrwntl
September 8, 1992
1
III Mr, Charles Folch
City of Chanhassen
1 690 Coulter Drive
Chanhassen, MN 55317
1 Re: Upper Bluff Creek Dist. Utilities • Phase 1
City Project 91/17
Our File No. 39305
1 Dear Charles:
1 We have completed our final Engineer's estimate for City Project 91 -17, which is hid this
Friday. The estimated construction amount is $2,348,000.
1 The estimated construction costs for Phase 1 in the preliminary were approximately $1,840,000,
or $508,000 lower than the current estimate. The current estimate is higher than the report
estimate for the following reasons:
1
1.) The estimated costs for the proposed lift station have risen $370,000 from $440,000 to
i $815,000. The increased costs are due to additions to the lift station and additional
concrete and dewatering required by the high groundwater conditions at the site.
I 2.) The water main construction through the proposed Chanhassen Business Center site will
cost approximately $31,000 more because the site had not yet been graded
1 3) Pipe piling costs are approximately $36,000 more than estimated in the preliminary
report. This increase is due to a larger area of unsuitable soils than was originally
estimated,
1 4.) Approximately $38,000 in house services are included in the current estimate that were
1 not included in the original report estimate. The costs for these services will be assessed
to the developers.
5.) Sanitary sewer stubs crossing Bluff Creek were added for the proposed Chanhassen
1 Business Center and Bluff Creek Estates. The estimated additional cost for this extra
construction cost will be approximately $20,000,
1
S E P- 1 0- 9 2 T H U 1 5 : 2 6 B O N E S T R O O & ASSOCIATES P.03
1
1
6.) Finally, sanitary sewer and water main for the Stone Creek Addition have been included
in Phase 1. These utilities were originally scheduled to be in Phase 2. Therefore, an
estimated $160,000 that was listed as Phase 2 in the report is now part of Phase 1.
The attached table shows the estimated revenue from the proposed assessments. The estimated '
total revenue is $2,748,825. Using the estimated construction costs of $2,348,000 and a factor
of 21.5% for indirect costs, the total estimated project costs for Phase I are $2,848,000, This
results in a revenue shortfall of approximately $99,175.
We will further analyze the project costs compared to the preliminary report estimates once the
bids are received. Feel free to contact me if you have any questions or require any additional
information.
Sincerely, 1
BONES 00, ROSENE, ANDERLIK & ASSOCIATES, INC. 1
c,
Phil Gravel
PG:li '
1
1
1
1 1
1
1
SEP -10 -92_THU 1 5 :2S BONESTROO & ASSOCIATES P-04
i
1
1 ESTIMATED REVENUE FROM C.P. 91-17 PRASE 1
1
Parcel 1 (Redmond) Trunk Sanitary = 71,500 $ 71,500
Parcel 8 (Chan Land) Trunk Sanitary = 131,970
Trunk Water = 173,400 $305,320
1 Parcel 11 (Hans Hagen) Trunk Sanitary = 134,830 --
Trunk Water = 177,225
Lateral Sew. & Water = 322,785 $634,840
Parcel 12 (Ryan) Trunk Sanitary = 345,320
Trunk Water = 453,900
1 Lateral Sew. & Water = 254,080 $1,053,30()
Parcel 27 (Mattson) Trunk Sanitary = 177,510 $177,510
1 Parcel 29 (Grams) Trunk Sanitary = 43,650
Trunk Water = 57,375
Lateral Sew. & Water = 53,150 $154,175
' Parcel 34 (Mattson) Trunk Sanitary = 85,360 $85,360
Parcel 36 (Berms) Trunk Sanitary = 44,620
' Trunk Water = 58,650 ^ $103,270
SUBTQTAL $2,585,275
' Plus $2245 for small parcel residences 8,980
Plus future assessments from green acre parcels (Parcel 2, Parcr.1
1
; Parcel 32) 154,570
TOTAL $2,748,825
1
•
1
1
1