2b. Change order Lake Ann Park Utilities ..)._b
• . CITYOF
I si CHANHASSEN
1 Not,441,„.,,
.4„,
0 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
(612) 937 -1900 • FAX (612) 937 -5739
I
Apron by City Administrator
I MEMORANDUM briorsed ✓ ]:W PI
`codified
TO: Don Ashworth, City Engineer wed
" Det 4 - Z'1 7
1 FROM: Charles Folch, City Engineer Cc Cate Submitted to Commission
DATE: April 17, 1992 Date Submitted to Council
SUBJ: Approve Change Order No. 1 to Lake Ann Park Utilities q—,.'7 2 '
Project No. 91 -15
I The attached Change Order No.1 for the Lake Ann Park Utilities Project No. 91 -15 contains a few adjustments
g Project 7
to the contract scope for the project. The significant adjustment involves the addition of the remote transmission
I unit (RTU) to the lift station which will be tied into the City's telemetry system at a cost of $12,580.04. This
work would be completed by the City's telemetry contractor, Bentec Engineering Corporation. This cost
proposal appears to be comparable to the City's system -wide proposal for the telemetry system.
I Change Order No. 1 also includes the deletion of the emergency power generator connection plug which will,
in effect, yield a deduct of $364 from the contract. The other notable changes relate to the water system where
I a Woodford Model MK6B yard hydrant will be abed at no additional charge; however, it is proposed to add one
more yard hydrant to the project at an additional cost of $912.
The original contract amount was $108,057.64. With the addition on Change Order No. 1, the revised contract
1 amount would be $121,185.68. Again, the primary cost element to this change order involves the additional
remote transmission unit (RTU) which staff believes is a necessity to integrate with the system's overall
telemetric system and serve the needs of the park. It is therefore recommended that contract Change Order No.
I 1 in the amount of $13,128.04 be approved for the Lake Ann Park Utilities Project No. 91 -15 to establish a
revised contract amount of $121,185.68.
I jms
c: Dave Hempel Sr. Engineering Technician
Jerry Boucher, Utility Superintendent
I Bob Sellers, Van Doren Hazard Stallings
Max Danhenberger, B & D Underground
I Attachments: 1.
2. Letter from Bob Sellers, Van Doren Hazard Stallings dated April 9, 1992.
Change Order No. 1.
1
1
t4, PRINTED ON RECYCLED PAPER
1
VanDoren
Hazard
Stallings, Inc.
Architects • Engineers • Planners
1 April 9, 1992
Mr. Todd Hoffman
•
Park & Recreation Director
' City of Chanhassen
690 Coulter Drive
Chanhassen, MN 55317
1 Re: Lake Ann Park Utilities
VHS Project No. 91 -319
1 Dear Todd:
Enclosed are three (3) copies of the change order for Lake Ann Park
' to add the RTU to the lift station and other minor changes. If you
would please sign these copies and send them back to us we will
forward them to B & D Underground for their signature.
' I talked with Jerry Boucher and he seemed satisfied and indicated
he just wants the work done.
If you have any questions please call me.
Sincerely,
VAN DOREN - HAZARD - STALLINGS, INC.
/c,-4 5?-40-
' Robert L. Sellers
RLS /ev
1
1
1
I r,
1 ROFFMAN.L05 APR 1 0 1992
1 ¥ OF CHANHASSEN
1
1
DATE: April 7,1992
1
CHANGE ORDER
PROJECT: Lake Ann Park PROJECT NO.: 91 -319 1
Utilities
CONTRACTOR: B &D Underground, Inc. CHANGE-ORDER NO. ONE
1
The following changes are hereby made to the Contract Documents:
Add remote transmission unit (RTU) to lift station. Delete
emergency power generator plug and circuit. Change yard hydrants
to Woodford Model MK6B from Woodford Model W34 1
CHANGES TO THE CONTRACT PRICE: (See Attached Contractor Proposal)
Original Contract Price: $ 108,057.64
Total Previous Change Orders: $ 0.00 1
Contract Price as Adjusted by Previous
Change Orders $ 108,057.64 1
Amount This Change Order: $ 13,128.04
Revised Contract Amount: $ 121,185.68
CHANGES TO THE CONTRACT TIME:
The Contract Time will not change. 1
The Completion Date for all work under this Contract will be
ENDORSEMENT:
Project Manager: � �1 DATE: ?A Z
i
APPROVALS REOUIRED: +'
Contractor: DATE: 1
Owner: DATE:
1
•
CHORDER.FRM
11 LAKE
ANN PARK UTILITIES
CHANGE ORDER NO. ONE
Add Deduct
1. Add remote transmission unit (RTU) -
to lift station controls 12,580.04
1 2. Delete emergency power generator
connection plug and circuit from
' lift station controls 364.00
3. Substitute a Woodford Model MK6B
yard hydrant for Woodford Model W34 No Change
4. Add one additional yard hydrant
Woodford Model MK6B at bid unit
price 912.00
$13.492.04 $364.00
NET CHANGE IN CONTRACT PRICE - INCREASE $13,128.04