3.5 Contract Amendment #1 for HNTB Audubon Rd 3r5-
-�
CITY OF
CHANHASSEN
690 COULTER DRIVE • P.O. BOX 147• CHANHASSEN, MINNESOTA 55317
(612) 937-1900 • FAX (612) 937-5739
MEMORANDUM
' TO: Don Ashworth, City Manager -
FROM: Charles Folch, Asst. City Engineer
DATE: April 2, 1991 �_ _. - . .. _ .,
SUBJ: Approve Contract Amendment No. 1 HNTB Engineering Services
' Contract on Audubon Road South - Project No. 89-18
This item was presented before the City Council at their regular meeting on
March 25, 1991 and was tabled pending their request for information. It is my
understanding that Council's primary concern was to receive a better explanation
of the reason for the contract amendment and a description of the remaining work
to be completed on the project. Understandably so, it was the Council's feeling
that this was a substantial amendment amount.
Attached you will find two letters from Chet Harrison of HNTB, the project
engineer. The first letter, dated April 2, 1991, describes the need for the
additional services and distinguishes the portion of the contract amendment that
has been actually performed in 1989 and the remaining portion for work to be
completed in 1991. It is apparent that the original contract for services
neglected to account for construction survey staking. This alone accounts for
nearly half of the proposed contract amendment.
The other letter, dated March 28, 1991, spells out the remaining project work
and corresponding engineering services to be completed on the project in the
spring of 1991. This is directly associated with the larger portion of the pro-
posed contract extension amount.
Chet Harrison will be present at the City Council meeting on April 8, 1991 to
discuss these and any other questions or concerns that you or the Council may
have concerning this matter.
If this additional information and tentative discussions at the meeting on
Monday night prove to satisfy the questions raised by the Council, I would
therefore again recommend that the City Council approve amending the Engineering
Services Contract with HNTB for the Audubon Road Improvement Project No. 89-18
establishing a revised ceiling of $65,600.00.
Attachments: 1. Correspondence fran HNTB Dated April 2, 1991
2. Correspondence from HNTB Dated March 28, 1991
3. Correspondence from HNTB Dated February 19, 1991
4. Correspondence from HNTB Dated July 26, 1990
c: Chet Harrison, Jr., HNTB
Dave Hempel, Sr. Engineering Technician
i
I
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
• HNITB HOWARD NEEDLES TAMMEN &BERGENDOFF G'00 France
ARCHITECTS ENGINEERS PLANNERS Avenue South
Suite 260
IApril 2, 1991 .Winnea)ol,s, Minnesota
P »j_i>
(612) 920-4666
Mr. Charles Folch
Assistant City Engineer
' City of Chanhassen
690 Coulter Drive
Chanhassen, Minnesota 55317
' RE: Audubon Road, City Project 89-18
Dear Mr. Folch:
The original engineer's estimate for professional service for construction did not include costs
for survey construction staking. It only contained survey costs to establish horizontal and
vertical control to be used to do the construction staking.
Survey for control was estimated at 75 hours. The estimated cost to do the construction staking
was 300 hours but was not included in the original estimate. This additional construction staking
' costs accounts for the additional $10,000 spent to date.
The previously approved contract administration costs and inspection are presently within
budget. However, because construction was not completed during the 1990 construction season,
we are requesting an additional $12,500 to complete the contract administration, inspection,
construction staking, record drawing and preparation of assessment costs.
I intend to be present at the April 8th council meeting to answer any questions you may have
regarding past or future anticipated professional engineering fees.
' Sincerely,
' HOWARD NEEDLES TAMM BERGENDOFF
v
' Chester J. Harrison Jr., P.E.
Project Engineer
' CJH/mst
13831/Folth.402
P•rsners Charles T Henmgen PE.Dane•J Spigai PE.John L Cotton PE,Francis X Hall PE.Robert S Coma PE.Oone,o A Dupes PE,William Love FAtA
Robert 0 Mole,PE.James L Tuttle.Jr PE.Hugh E Schaal PE Cary C.Goodman AIA.Gordon H.Slaney.Jr PE.Harvey K Hammond Jr PE.Stephen G Goddard PE
onn W Wight,Jr PE,Richard 0 Beckman PE.Richard L Farnan AIA.Douglas E Prescott.PE
As•oelatos Kendal T Lincoln CPA.Roberts W Smithem PE.Harry O Bertossa PE.Ralph E Robison PE.Stanley I-Mast PE.Waiter Snarko PE.Ross L Jensen AiA.
Frank T Lamm BE H Jerome Butler PE,Braise M Carrier.BE,Micneei P Ingerdla PE,Bernard L.Prince PE.Steonen B Quin^RE.Saul A Jacobs PE.Ewing H Miller FAIA
Douglas C Mynre PE,Carl J Mellea PE,Daniel F Becker PE.Donald P Keuth PE.Ronald L.Hardie PE,Thomas L.WlIllams AIA Dennis E Conklin BE Joan E Kupke PE
Rodney P Pally PE,Steven M Reiss AIA,Robert A Leick PE,Glenn 0 Sadulsky PE,Benjamin A Whisler PE.Roger S Aus_,n BE Joan D Brothers PE,
Charles L O'Reilly,Jr PE,Robert M Sloan PE,Douglas A Boyd AIA,Raymond J McCabe PE.Thomas A Skinner PE.Paul A.Yerossi PE.F Cnrietopher Ormond ASLA AICP
Roland W.Frerking AIA,James T Kienle AIA,Terry K Miller AIA,Roger C Ward PE,Maurice O.Miller PE.Robert L Watson AIA
Offices Alexandria,VA.Atlanta,GA.Beton Rouge.LA.Boston,MA.Charleston.WV.Chicago.IL.Cleveland.OH.Concord.CA.Dallas.TX.Denver CO.Fairfield.NJ,
Hartford.CT Houston.TX.Indlanepblis,IN,Irvine,CA.Kansas City.MO.Louisville,KY Lexington,MA,Los Angeles.CA,Miami,FL.M■Iwaukee.WI,Minneapolis,MN.
New York,NY Oklahoma City,OK,Orlando.FL.Overland Park,KS,Philadelphia.PA,Phoenix,AZ.Raleigh.NC.Seattle.WA,Tampa,FL.To-se.OK W.imington.OE
1
HNTBHOWARD NEEDLES TAMMEN &BERGENDOFF 6'00 France i
ARCHITECTS ENGINEERS PLANNERS Avenue Soul/,
Suite 260
I
Minnea/x)lis, ,19inuesota
March 28, 1991
55435
(6/2) 920-4666 I
Mr. Don Ashworth
City Manager
City of Chanhassen I
690 Coulter Drive
Chanhassen, Minnesota 55317
RE: Audubon Road Project No. 89-18 I
Dear Mr. Ashworth:
I
To further clarify the additional Engineering Services to complete the Audubon Road
projects, we are herein listing work to be completed in the Spring of 1991:
I
1. Placing of the final wear course of bituminous asphalt.
2. Complete shouldering of the rural section of roadway.
I
3. Complete site grading adjacent to the roadway.
4. Landscape (sodding, topsoil, and seeding) disturbed areas adjacent to roadway.
5. Complete grading and landscaping for storm sewers and drainage ditches.
I
6. Construct pedestrian walk and fencing across the railroad bridge.
7. Pave trail system south of future Lake Drive West to Heron Drive.
8. Survey constructed utilities for record drawings.
I
9. Prepare record drawings.
10. Prepare final construction costs for the final assessment role.
There may be other additional tasks that are not listed here. We can discuss these and any
other concerns at the City Council meeting on April 8, 1991. I apologize for not being at
the last City Council meeting due to a family emergency. I
Sincerely, i
HOWARD NEEDLES TAM & BERGENDOFF
ejtk,..1- ' ; _-/-1,44, '',_
I
Chester J. Harrison Jr., P.E.
Project Engineer
I
RECEIVED
CJH/mst
MAR 2 9 1991 '
cc: Charles Folch, Asst. City Engineer, City of Chanhassen CITY_OF CHANNASSEN
13831/Asbwor h.Ltt
I
Partners Charles T Hennigan PE.Daniel J-Soigai PE,John L-Cotton PE.Robert S Coma PE,Donald A Dupes PE_James L Tuttle. Jr PE.Hugh E Schail PE
Cary C Goodman AIA Gordon H Slaney,Jr PE.Harvey K_Hammond,Jr PE.Stephen G Goddard PE,John W Wight.Jr PE.Richard 0 Beckman PE,Richard L Farnan AlA
Douglas E-Prescott PE,Ronald L Hartle PE
Associates Kendall T Lincoln CPA,Roberts W.Smithem PE,Harry D.Bertossa PE,Ralph E.Robison PE,Stanley I Mast PE.Walter Snarko PE.Frank T.Lamm PE.
H Jerome Butler PE,Blelse M.Carriere PE.Michael P Ingerdla PE.Bernard L Prince PE,Stephen B Guinn PE.Saul A.Jacobs BE Ewing H.Miller FA1A.
Douglas C.Myhre PE.Carl J Mellea PE,Daniel F Becker PE,Donald P Keuth PE.Thomas L.Williams Al....Dennis E Conklin PE.John E Kupke PE.Rodney P Pell.PE.
Steven M Reiss AIA,Robert A_Leick PE.Glenn D.Sadulsky PE.Benjamin A.Whirler PE,Roger S.Austin PE.John D.Brothers PE.Charles L.O'Reilly.Jr PE.
Robert M.Sloan PE,Douglas A.Boyd AIA.Raymond J.McCabe PE,Thomas A.Skinner PE.Paul A.Yarossi PE.F Christopher Ormond ASLA AICP,Roland W Frerking AIA. '
James T.Kienle AlA,Terry K.Miller AIA,Roger C.Ward PE,Maurice D.Miller PE.Robert L.Watson AIA
Offices Alexandria.VA.Atlanta.GA.Baton Rouge,LA,Boston.MA.Charleston.WV Chicago,IL.Cleveland.OH.Concord.CA.Dallas.TX.Denver CO.Fairfield.NJ.
Hartford.CT,Houston.TX.Indianapolis.IN.Irvine,CA.Kansas City.MO.Louisville.KY Lexington,MA.Los Angeles,CA.Miami.FL.Milwaukee,WI,Minneapolis.MN.
New V4,,NY Oklahoma City OK.Orland..FL.Overland Park.KS Phiiadelnhia.PAPhnen,x 47 Rain,n■Sr Sn:,i i ie 4/11 T-,..,..a 41 T„0.Mk”ui i nr
I
I HNTB HOWARD NEEDLES TAMMEN &BERGENDOFF 6-00 France
ARCHITECTS ENGINEERS PLANNERS Aven u'.South
I
suite'260 I
Minneapolis. tfcnnec.,ta
February 19, 1991 554.35
I (61?1 920--1666
Mr. Gary Warren
ICity of Chanhassen 1
690 Coulter Drive
P.O. Box 147
IChanhassen, Minnesota 55317 _ - _ _,
RE: Audubon Road Project No. 89-18
IRevised Engineer Estimate for Construction Services
IDear Mr. Warren:
I have reviewed past, present, and future engineering costs for the referenced project.
IHNTB's letter dated July 26, 1990, provided an estimate of our staffing requirements to
- construct Audubon Road. If the project had been completed during 1990, the estimate for
I project management and inspection would have been adequate to build the street.
However, the estimate to do the construction staking was probably insufficient from the
start. The actual construction staking has taken approximately 340 hours. An additional
1O hours were needed to survey the followin areas: additional slo a stakin on Mi iel
1 propert Araina,.ge ditch design and construction stakin or the new drairaagg ditciulong
L man Road additional cross sections an s o•e stakin. on the Basins •ro•e design
I survey and construction staking for new storm sewer north of Heron Drive, and additional
slope staking required on the Stockdale property.
I CONSTRUCTION ENGINEERING SERVICES
COST TO DATE
I 1/18/91 Estimated
Estimated Spent to Complete Total
I Project Manager 240 205 60 265
Survey 75 439 80 519
Inspection 630 567 100 667
IRecord Drawing 67 10 _2 ......122
1,012 1,221 297 1,518 .
' P C^.a^es T -.en^.par PE-O .. .1 Sc.pa PE.Jan-.L Cotta.,PE.Frenc.s X Me. PE.Posen S.Come PE.Donac A D..o.e•PE.W.....-.Love FA•A.
Boaer:C M e PE.Janes^ T..tte-J-s PE...,.e-E Sons'PE Cary C GooDman A.A.Go•oon M Sinner.Jr PE.Mervsy K Memmonc.J•'PE.Eteonen 0 Goocarc PE.
JCrr A y.•.n.Jr PE C:-•a^__Bere.,e^PE.P.a^.a^O L.Fern,AIA Doug..E Prescott.PE
Aseoeleces Ke"ce T -.nee,CPA Cooe-ts.n 5-..t.ne^.PE.harry D Berto.e.PE.Pao,E Floaso•,PE.Stanley I Mast PE.Water Snerko PE.Pose L Jeros-A:A
Pre^.T:_e--FE.In.lore-re B..s'er PE B sae M Cerr.are PE M.cnee'P■•p•ro.e PE.Bernard L Prince PE.Steonan B O...nn PE.Sac A Jeco0e PE En"np M M,.'er FAA■
Do..p as C My.^e PE.Cr J Me ea PE.Dan.e F Beaks PE.Dante P Keetn PE.Po-a,::L Me-tre PE.TnOmea L Wilma Denn..E Canon PE.Jonas E Kooks PE
=zone, P Pe 0 PE.Stever M Pest A.A.Soren A Lelek PE.Glenn O Seay.eoy PE.Ben..m.n A Sneer PE.Paper S Aua4n PE.Jonn C Bretners PE
OnsTes L D 0.e y.Jr PE.Rowrt M&oa,PE.Do:pua A.Bose AIA.Pey^wna J McCeoe PE.Thomas A.Stunner PE.Pm.,A Varese.PE.F Cerytoon.r D,•nono AS_A AICP
Pc Casa W c..er..np An Je.nes-K..^e A.A.Te^ry K M.e^A.A.Poo."C Were PE.Meur.0 0 We CE.Peters L.Watson Aet
Offices A • e e LA.At.ente GA.Bete-Poops.LA.Boston.MA.Cre rusten.WV.Cn,c.po.IL.C.evsene.OM.Concore.CA.De.aa.TX.0 CO.Fe-le a NJ.
r.•rt.e^o C' n u ._ TK.Ina..neca'.e IN Ir ,ne,CA.K C,ty.MO.LOU.ayse.KT.Leempten,MA.LOS Anoeea.CA.M:a...FL.M.'w•ukee.WI.M.nneaOO•.s.MN
hew vc^.'s' 0 Darr a S t. OK.Onenot P.OverCno Park KSPre eeleANe.PA.PnO.n,..AZ.F4r.pn.NC.S.ettre.WA.Te'no.FL.Tuw.OK.W.m.npton.DE
�l
I
•
Mr. Gary Warren
February 19, 1991
Page 2
i
Hours x Avg.
Hourly Rate Total '
Project Manager 265 x $60 $15,900
Survey 519 x $35 18,165
Inspection 667 x $40 26,680
Record 67 x $65 4,355
Expenses 500
TOTAL $65,600
i
Based on the fact that the construction extended beyond October 15, 1990 and the fact that
the project will not be completed until June, 1991, we are requesting that our construction '
engineering contract be increased to $65,600. We are presently studying the intersection
ca acity and level of sere-ior Audubon Road and Heron Drive as an additional
transportation planning service (Estimated Study Cost $1,000.00). '
If you have any questions or need additional information, please call me.
Sincerely,
Y
HOWARD NEEDLES TAMMEN & BERGENDOFF '
•
Chester J. Harrison, Jr.
CJH/mst '
cc: Charles Folch, Assistant City Engineer
13831•31LllWanm218
•
•
I
� � HOWARD NEEDLES TAMMEN S BERGENDOFF 6700 France
ARCHITECTS ENGINEERS PLANNERS Avenue South
Suite 260
' July 26, 1990 Minneapolis,Minnesota
55435
' Mr. Gary G. Warren, P.E. (672)920.4666
City Engineer
City of Chanhassen l.c�
' 690 Coulter Drive, P.O. Box 147 ✓
Chanhassen, Minnesota 55317 COO
1 RE: Audubon Road South - Upgrade; City Project No. 89-18
Dear Mr. Warren:
1 With the award to Imperial Developers, Inc., we would like to proceed into the construction phase
for the project. We propose that the compensation will be on a cost plus with a maximum. We
have attached a description of the proposed person hour estimate and fees. The estimated hours for
1 Construction Inspection are based on a full-time Resident Project Representative (as described in an
Appendix "B" of the contract) on the site for about 11 weeks and periodic visits by office personnel
for inspection of utility construction. We will request, if necessary, additional funds if the
maximum amount is exceeded in the future.. We also have enclosed a-copy of correspondence
1 indicating our latest overhead rate which is slightly higher than last years overhead rate. The
multiplier, using the new overhead rate is 2.69 [(134.24% + 100%) x 1.15].
1 Regarding the additional services for preparation
as pre aration of easements, we estimate
total amount spent
of Frid av_Jula a ou t1,OOI Cft i"s rkin witli the •ro•e owner and some
easements will change wi a e_ ion_ o e t • ow • 'eron "rive. `ie_estimatean a.• tinnal
repo: aun o a out o c m. e e e a a ic�`l"ional services for easemen `For your information
1 we a ac e a summary o e estimate. ees or e •i erent task and services.
We have forwarded the contracts to Imperial Developers, Inc. in a separate letter dated July 25,
1 1990.
Unless you have any objections, we will proceed to contact GME Consultants, Inc. and have them
perform the necessary construction and density testing. GME will bill you directly for their
1 services.
Please contact us if you have any questions or comments.
1 Sincerely,
HOWARD NEEDLES TAMMEN & BERGENDOFF
Harald P. Eriksen CITY OF CHANHASSEN
1 Project Manager WLS`yII 7f 1
HPE/mst D UL5
Attachment JUL `'7 1990
1 `P"'8'n;Ay 12 Ltr ENGINEERING DEPT.
1 P Cf.ry.T H.nnlp.n PE.Came!J.Bev..PE.Jonn L.Cotton PE.Franc..X.M.II PE.Robert S.Come PE.Donate A OvOo•PE.W,IINhr Loy.FAIR.
Robert O Moo-PE.J.me•L.Tutu..Jr PE.Hupp E 5en•u PE.Cory C Goodman AIA.Gordon H.Sammy.Jr PE.Wryy K-Wmrnond.Jr PE.Stephen G.Godd.ro PE.
Jonn W Mpnt Jr PE.Fl■ch.rd O.B.Ckm.n PE
A..e•mt..Don FI Ort PE.Kamen T L.neom CPA,Robert.W.Sm t...m PE.tarry O.B•rtoe..PE.R.Ipn E.F1ob..on PE.Coen P Counts PE.Stanley I.Meet PE.
Pee...t W An,,.PE.Welter Sharko PE.J.mee O.FIU...X PE.Flo..L Jensen AIA.Fronk T.Carom PE.Poneid W.Arena AIA.M.J•rom.Butts,PE.Btea.M.Corriere PE.
M,cneel P Indere,.PE.Gernert'L.Pro..PE.Stephen a Guinn PE,S.,,1 A.J•eobs PE.Evens'M Meier FAIR,Oouptes C.Myhre PE.Cori J.MNIM PE.Canal F Becks PE.
B,Cn.-O L.F•.n.n AIA.Oon.IO P K•uth PE.Coyote.E.Pr•acett PE.Remelt!L.Herter PE.Pob.rt W.Lu.eornb•PE.Thomas I..MUM..AIA,Donnie E.Conkkn PE.
Jonn E Kuck•PE.Rodney P Pena PE.Steven M.Poole AIA.Robert A.L•.ek PE.GI•nn O.S.auteky PE.B•n,n.n A.Whrsler PE.Floor S Aust.n PE.Jonn D.Brothers PE.
Cherish L.0P•.,Jr PE.Report M 5b.n PE
WNW.Aus.non...VA.At1•ntu.GA.Awun,TX.B•tOn PO,W.LA.Boston.MA,Charleston.WV.Ch¢spo.IL.Cteywnd.OM.dams.TX,Oenvr.CO.Fsw'.•,d.NJ.Hertford.CT.
Hou.ton,TX.Ind..n•ool,s.IN.',mho.CA.K.n...Crty.MO.Lesinpton,KY.L•s.npton.MA.LOe Anp•lee.CA.M..mi.FL.M,I.r.uk••.WI.M,nn..poks,MN.New York.NY
AUDUBON ROAD SOUTH t,. GRADE HOWARD NEE..L.ES TAMMEN & BERGENDOFF
CONSTRUCTION PHASE
PERSON HOUR ESTIMATE 07/26/90 '
TASKS PROJECT TECH/ SUBTOTAL
ENGINEER ENGINEER SURVEYOR SUPPORT HOURS . '
CONSTRUCTION STAKING 75 75
CONSTRUCTION INSPECTION 630 630 '
OFFICE ADMINISTRATION&MEETING 145 35 60 240
TOTAL HOURS 145 665 75 60 945 I
AVERAGE DIRECT
EMPLOYEE CLASSIFICATION HOURS RATE SALARY
Project Engineer 145 $23.50 $3,408
Engineer 665 $16.00 $10,640
Surveyor 75 $14.00 $1,050
Technician /Support 60 $13.50 $810
TOTALS 945 $15,908
ESTIMATED DIRECT SALARY COST $15,908
OVERHEAD (134.24%) $21,354
SUBTOTAL - $37,262 '
FEE (15.00% OF SUBTOTAL) $5,589
ESTIMATED DIRECT EXPENSES
ESTIMATED TOTAL FEE $43,151 ,