1n. Plans & Specs for Lake Drive East 1 ,
... .
CITY OF 1 ,
I .
, .
, _, 1 , e
. „ , CHANHASSEN
• „. , . , . n . ,
• •if
690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
(612) 937-1900 • FAX (612) 937-573n by c+ ,Administrator
Endorsed ✓ lkt_k
MEMORANDUM Mecat)d___
I Rejected
Date te 3 -/ c7
TO: Don Ashworth, City Manager m-_
Date Submitted to Commission
I FROM: Gary Warren, City Engineer
Date Submitted to to Comet]
DATE: March 7 , 1990 ______1 _ -..2.1._
I SUBJ: Approve Plans and Specifications for Lake Drive East from
Dakota Avenue to Dell Road, Project No. 89-6A; Authorize
Advertising for Bids
IIThe attached construction plans have been prepared as directed by
the City Council at its November 9, 1989 meeting. The plans have
II been prepared in concert with a number of activities which are
occurring at the same time in this area, namely MnDOT design of
the Trunk Highway 5 improvements including the extension of Dell
I Road south and Dakota Avenue, site plan improvements for the
McDonald' s site and site development and long-range planning for
the Datasery (Sunlink ) property.
IThe project scope includes the construction of a 36-foot wide
collector roadway with concrete curb and gutter, street lights
and a concrete walk on the north side 'of the roadway from Dakota
I Avenue to Dell Road. The road has been designed in compliance
with MnDOT standards and as such parking is to be prohibited on
the south side of the roadway.
1 The McDonald's site plan expansion is being done partly to
provide tractor trailer parking stalls on the McDonald's property
which should greatly alleviate the congestion and parking
Idifficulties which currently exist in this portion of the
roadway. Similarly, the roadway alignment through the existing
portion of Lake ' Drive East will - be improved geometrically to
I reduce the sharpness of the curves in this area in order to bring
the road into compliance with MnDQT' s State-Aid standards.
I The revised construction cost estimate for this project is
$751 ,416. This is approximately $50,000 above the feasibility
study estimate due to the addition of 510 feet of 42-inch storm
sewer which was deleted from the Trunk Highway 5 , MnDOT project.
II Sanitary sewer, watermain, one-half of the storm sewer and a
portion of the roadway are intended to be assessed against the
II
I
II
Don Ashworth
II March 7 , 1990
Page 2
I benefitting properties, primarily the Datasery property. The
remaining project costs are to be covered through a combination
of participation by MnDOT with its cooperative agreement on Trunk
IHighway 5 and funds from the tax increment district.
There are two minor wetland impacts which will require a wetland
I alteration permit. These are identified in the attached February
21 , 1990 letter from OSM and result in approximately 1/2 acre of
wetland which will be lost as a result of these improvements .
Mitigation is intended to be included in the City' s Eckankar pond
Iproject near County Road 17 and Trunk Highway 5.
Similar to the MnDOT project, the schedule has slipped slightly
I on the Lake Drive East project; however, we still are intent on
bidding this project at this time. We anticipate a bid opening
date of April 13 , 1990 with a construction start-up as soon as
I road restrictions are removed in May.
It is therefore recommended that the attached construction plans
for the Lake Drive East project from Dakota Avenue to Dell Road
I be approved and authorized for bidding. It is further
recommended that a no parking zone be established for the south
side of this roadway from Dakota Avenue to Dell Road.
1 ktm
Attachments: 1. Plans .
I
2 . February 21 , 1990 letter from OSM.
c: Bud Osmundson, OSM
I
I
I
I
I
I
1
Orr
- Schelen
_ s Mayeron&
IF Associates,Inc.
2021 East Hennepin Avenue
Minneapolis,MN 55413
612-331-8660
FAX 331-3806
Engineers
Surveyors
Planners
CITY OF CHANHASSEN I
February 21, 1990 EOM
FEB 26 1990
Ms. JoAnn Olsen ENGINEERING DEPT.
Senior Planner
City of Chanhassen
690 Coulter Drive
Chanhassen, MN 55317
RE: Lake Drive East, Wetland Impact FEB 2 6 1990
OSM Comm. No. 4358
CITY_OF.CHANHASSEN
Dear Ms. Olsen:
The City of Chanhassen is proposing to improve Lake Drive East from its point '
of intersection with Dakota Avenue to a point 900 feet east of this intersection.
Existing utilities in the area will also be improved, and a limited amount of
wetland alteration will result from these improvements. This letter is written
in support of a wetland alteration permit. The permit application is attached.
The existing land use in the vicinity is vacant and is zoned for
commercial/industrial uses. All of the vacant land is surrounded by established
development.
Improved Lake Drive East will cross three different types of landscape and will
impact wetland, as well as upland grass areas and woodland.
A site visit has been made and the wetland areas have been identified and located '
as a result of an on-site investigation. There are two primary areas of upland
wetland that will be impacted. These areas have been staked in the field, mapped
and depicted as Area A - West and Area B - East on exhibit 1. Information on
the west and east wetland is provided below.
AREA A - WEST
A total of 14,375 square feet of wetland is present in the Area A - West. There
are three different types of wetland located here including Type 2 - inland fresh
meadow, Type 3 - inland shallow fresh marshes, and Type 6 - shrub swamp. 11
Attachment A provides a description of all types of wetland referenced in this
letter.
2,625 square feet of wetland in the Area A - West would be impacted by the '
improvement to Lake Drive East. The types and amount of wetland impacted is
summarized in the following table.
1
AREA A - West
' Wetland Area Impacted
Type 2 Impacted 975 square feet
Type 6 Impacted 650 square feet
' Wetland Area Not Impacted 12,750 square feet
Total Wetland Area 14,750 square feet
' 88% of the wetland, 12,750 square feet, in the Area A - West will not be impacted
by this road construction.
' AREA B - EAST
A total of 19,000 square feet of wetland exists in Area B - East. There are a
' variety of wetland types scattered throughout this area and the types change
according to elevation and the location of low pockets or the ditch. Therefore,
it is very difficult to determine the exact amount of wetland area according to
' type in Area B - East. There are five different wetland types that exist here;
Type 2 - fresh meadow, Type 3 - shallow fresh marsh, Type 5 - open water, and
a combination of Types 6 and 7 shrub and wooded swamps. In order to quantify
the areas of wetland in Area B - East, it is possible to discuss the percentage
' of wetland types based on site observation. This information is summarized in
the table below.
' AREA B - EAST
Wetland Area Impacted
Type 2 Impacted 10% 1,900 square feet
' Type 3 Impacted 7% 1,330 square feet
Type 5 Impacted 3% 570 square feet
Types 6 & 7 Impacted 80% 15,200 square feet
' Total Wetland Area 19,000 square feet
' All the wetland in Area B - East will be impacted by the improvement of the
roadway and utilities. It should also be noted that with the construction of
the storm water improvements that the ditch will be removed and the source of
surface water for Area B - East will be eliminated.
WOODLAND
' There is a third area of woodland between Area A - West and Area B - East. Based
on the site visit and an analysis of observed vegetation types, it was determined
that this is not a wetland. Upland varieties, primarily young oak trees, were
observed and this provides evidence that it is not wetland.
' COMPENSATION
' 20,625 square feet, .47 acres, of wetland will be lost to the improvement of Lake
Drive East and utilities. Compensation measures can be taken to replace this
wetland, and based on the probable future of development on the site,
' compensation will need to occur elsewhere within the city. Considering the
limited amount of area to be restored, it is suggested that only one type of
1
6 and 7 - shrub and wooded swamps, provide the most advantage to wildlife.
Therefore, expanding one of these types of wetland would provide the most
benefit.
_Permit requirements of other agencies, such as the Corp of Engineers, should be
reviewed prior to construction. '
It is planned that the bid date for this project will be April 6, 1990. Please
advise us of any additional work that will be required to keep this project on
schedule. If you have any questions, please call Pete Willenbring at 378-6399.
Sincerely,
ORR-SCHELEN-MAYERON
& ASSOCIATES, INC.
Laurie McRostie Peter R. Willenbring, P.E. j
Landscape Architect Manager, Water Resources Department '
cc: Gary Warren
Bud Osmundson
Pete Willenbring
Enclosures
/lmt '
1
I
ATTACHMENT A
1 WETLAND DESCRIPTION
' Type 2 - Fresh Meadow. The soil usually is without standing water during most
of the growing season but is waterlogged within at least a few inches of its
surface. Vegetation includes grasses, sedges, rushes, and various broad-leaved
' plants. Meadows may fill shallow lake basins, sloughs, or farmland depressions,
or these meadows may border shallow marshes on the lakeward side. Hay is often
cut from such wetland areas.
Type 3 - Shallow Fresh Marsh. The soil is usually waterlogged during the growing
season; often it is covered with as much as 6 inches or more of water.
' Vegetation includes grasses, bulrush, spikerush, and various other marsh plants
such as cattail , arrowhead, pickerelweed, and smartweed. These marshes may
nearly fill shallow lake basins or sloughs, or they may border deep marshes on
the landward side. They are also common as seep areas on irrigated lands.
Type 5 - Open Water. Shallow ponds and reservoirs are included in this wetland
' type. Water is usually less than 10-feet deep and is fringed by a border of
emergent vegetation such as cattail and bulrush. Submergent or floating
vegetation (mainly at water depths of less than 6 feet) includes pondweed,
wildcelery, coontail , watermilfoil and waterlily.
Type 6 - Shrub Swamp. The soil is usually waterlogged during the growing season,
I and is often covered with as much as 6 inches of water. Vegetation includes
alder, willow, and dogwood. Shrub swamps usually occur along sluggish streams
and on floodplains.
Type 7 - Wooded Swamp. The soil is waterlogged to within a few inches of its
' surface during the growing season, and is often covered with as much as 1 foot
of water. Wooded swamps occur mostly along sluggish streams, on floodplains,
on flat uplands, and in very shallow lake basins. In Minnesota, tree species
include tamarack, white cedar, black spruce, balsam fir, red maple, and black
' ash.
1
WETLAND ALTERATION PERMIT
EVALUATION WORKSHEET
To Be Completed By Applicant and Submitted with Application
(Attach additional sheets if necessary) i
1. WETLAND DESCRIPTION:
Size: See Attached Letter for Description '
Class: Type:
Location: Lakeside Streamside Upland ,
Watershed District: Riley-Purgatory Creek Watershed
Area of Open Water:
Drainage Flows To: Rice Lake Marsh '
Vegetation Types:
Soil Types:
2. DESCRIPTION OF PROPOSED ALTERATION: ,
Fill of .47 acres of wetland area.
3. PURPOSE OF PROPOSED ALTERATION:
Improve Lake Drive East and local utilities.
4 . APPLICABLE WETLAND ORDINANCE SEC TION: Sec. 20.437
1
5. A. DISCUSS THE IMPACTS ON THE PROPOSED DEVELOPMENT IF NO ,
ALTERATION IS MADE:
Roadway and utility improvements would not be possible. '
I
I
5 . B. IDENTIFY AND DISCUSS OTHER ALTERNATIVES TO WETLAND
ALTERATION:
Lake Drive East is in existance. Improvement would not be possible
without the proposed wetland alteration.
' C. IDENTIFY THE ADVANTAGES AND DISADVANTAGES OF THE PROPOSED
ALTERATION:
' The area infrastructure will be improved, storm water drainage will
be more controlled and directed. Wildlife habitat primarily for
small mammals and birds will be eliminated.
' 6 . USING THE WETLAND ORDINANCE STANDARDS AS A GUIDE, DETERMINE
WHETHER THERE ARE ANY INCONSISTENCIES BETWEEN THE ORDINANCE
AND PROPOSED ALTERATION:
1
i —2
I
WETLAND WETLAND
AREA B - EAST
AREA A - WEST 19,000 SQ.FT.
14,375 SQ.FT. I 19,000 SQ.FT. 1M:
BLOCK 1 1625 SQ.FT. IMPACTED \LI
LOT 1 ,1° ''
IMCDONALDSI •A:: •ii,� � HOODED 11�
• . CHANHAVEN PLAZA AREA
��-+�,����' BLOCK 1
LOT 2 /PO t b/. ` 0 �/ �'
WOODL ND / co, . •
. lie,
a BLOCK 2 ~`" �
O LOT 1 �,
4
LI
+�1 r* 1soi LAKE DRIVE — EAST ■1■101
*** **+► ***********************At*** 0 •Y
0 0
I CHANHAVEN ESTATE
..._ .. .........,.....,..n,.,,,,
— — — OM MI MIN WM MI NM — —.