MEMORANDUM u I TO: Don Ashworth, City Manager
FROM: Gary Warren, City Engineer
DATE: March 7, 1990
SUBJ: Accept Feasibility Study for Country Suites Hotel Site Project No. 89-25;
Waive Public Hearing; Order Plans and Specifications; Approve Plans and
Specifications and Authorize Advertising for Bids
The attached feasibility study covers the utility and surface improvements for
the Country Hospitality Suite Hotel site located in the southeast corner of
Market Boulevard and West 78th Street. The improvements scheduled for the site
include storm sewer, watermain, sanitary sewer, bituminous paving and concrete
curb and gutter, concrete sidewalks and site lighting. These elements are being
closely coordinated obviously with the Country Suites construction which is
currently underway.
The total project cost including 30% overhead is estimated in the feasibility
study to be $311,000. This figure has been adjusted dawn somewhat in the plans
and specifications phase to $304,400. These costs are proposed to be assessed
' entirely against the benefitting properties which are owned by Bloomberg
Canpanies, Inc. and CH Suites Partners. As noted in the appendix to the
feasibility study, both property owners have executed development contracts on
' file with the City waiving their public hearing and assessment contention rights.
The attached plans were prepared in concert with the developer's staff on the
hotel site. Minor modifications still need to be done to these plans to reflect
the bus access issue recently resolved with the developer. This will be
completed before the plan sets are distributed to bidders.
Although unusual, it appears that all elements of the project are in order for
the Council to entertain a recamiendation to accept the feasibility study, waive
the public hearing, order plans and specifications, approve plans and
specifications, and authorize advertising for bids for the Country Suites Hotel
Site Improvement Project No. 89-25.
ktm
' Attachments: 1. Feasibility study.
2. March 6, 1990 letter from BRW.
3. Construction plans.
c: Gary Ehret, BRW
Bloanberg Companies
CH Suites Partners
•
PLANNING
TRANSPORTATION
ENGINEERING
URBAN DESIGN
BRW. INC THRESHER SQUARE 700 THIRD STREET SOUTH • MINNEAPOLIS.MINNESOTA 55415 • PHONE 612'370-0700 FAX 612.370-1378
IIMarch 6, 1990
II Mr. Gary G. Warren, PE CITY OF CIIAMMRHASSEN
City Engineer GESI �D�
City of Chanhassen MAC 07 1990
II 690 Coulter Drive
Chanhassen, MN 55317
Country Hospitality Suites Site Improvements ENGINEERING DEP1.
IRE: City Project 89-25
IDear Gary,
We are currently completing the plans and specifications for the construction of
site improvements for the Country Hospitality Suites development. The plans and
II specifications detail the requirements for the construction of storm sewer, san-
itary sewer, and water main utilities to serve the site, as well as bituminous
paving, sidewalk construction, and site lighting. Existing building demolition,
I miscellaneous removals, site grading, and other related work are not included as
a part of the scope of this project since this work will be performed by the
site developer as required by the redevelopment agreements with the City. A
more detailed description of the work to be performed by the developer and by
IIthe City is provided in our March 1990 feasibility report for the improvements.
We have completed an Engineer's Estimate for the project as summarized below.
II The project cost estimate previously prepared for the feasibility study is also
shown for your information and comparison.
II COST ESTIMATE
March 6, 1990 •
Bid Engineer's Feasibility Study
ISchedule Item Estimate Estimate
A Bituminous Paving $ 96,500.00 $104,230.00
I B Storm Sewer 49,500.00
34,650.00 49,020.00
C Water Main 34,650.00
D Sanitary Sewer 14,500.00 13,450.00
E Lighting 39,000.00 37,850.00
$234,150.00 $239,200.00
II It should be noted that the estimates are for the construction costs onlx, and do
not include any allowances for administrative or overhead costs.
IAN AFFILIATE OF THE BENNETT.RINGROSE.WOLSFELD.JARVIS.GARDNER.INC GROUP
DAVID J BENNETT DONALD W RINGROSE RICHARD P WOLSFELD PETER E.JARVIS LAWRENCE J.GARDNER THOMAS F CARROLL CRAIG A AMUNDSEN DONALD E HUNT
MARK G SWENSON JOHN B.McNAMARA RICHARD D.PILGRIM DALE N.BECKMANN DENNIS J SUTLIFF JEFFREY L.BENSON RALPH C.BLUM DAVID L GRAHAM
IMINNEAPOLIS DENVER PHOENIX TUCSON ST.PETERSBURG
Mr. Gary G. Warren
March 6, 1990
Page 2
We recommend that the City Council authorize the advertisement for bids for this
project on Monday, March 12, 1990. If the Council chooses to proceed with this
project, a tentative schedule is outlined below. It is important to note that
the schedule for the public improvement work is dependent on the developer's
schedule for the building demolition, general removals, and grading of the site.
Plans and Specifications Approved March 12, 1990 1
Advertise for Bids March/April 1990
Receive Bids April 12, 1990
Award Contract April 23, 1990
Begin Construction May 7, 1990
Complete Construction July 16, 1990
Subject to City Council approval , we are prepared to proceed in this manner.
If you have any questions, please do not hesitate to call. I
Sincerely,
TL.AA-a
Gary A. hret, PE
Project Manager
GAE/sk