MEMORANDUM t' '`r "`" ,-P.-.
I
T0: Don Ashworth, City Manager ;�;
.- ✓ apt
IFROM: Gary Warren, City Engineer t*} -'1
DATE: October 3, 1990
ISUBJ: Approve Contract Amendment No. 2 for Downtown : , _. , ..1
Redevelopment , Phase II -. -
Improvement Project No. 86-11B
The attached Contract Amendment No. 2 has been prepared to
I include new bid items and contract quantities as required by the
following modifications to the contract scope:
TH 5 Temporary Intersection Improvements
IA.
At the request of Rosemount, Inc. , the TH 5/Market Boulevard
intersection was upgraded from a right-in/right-out both
I north and south of TH 5 to a full intersection. The
upgrading to a full intersection required significant
additional work not included in the origianl contract
I documents . The improvements to the north side of TH 5 were
carried out by the contractor. Item A of Contract Amendment
No. 2 summarizes the additional work required.
IB. Concrete Sidewalk - Market Boulevard
In conjunction with the proposed site development of the
I Crossroads National Bank, the Market Boulevard trail system
and the TH 5 trail system, it was decided that a six-foot
concrete walk should be added to the east side of Market
I Boulevard from Bowling Alley Road to West 79th Street. This
walk was not included in the original plans and
specifications . Item B of Contract Amendment No. 2 provides
payment to the contractor for this work.
IAs you are aware, Rosemount Engineering has been billed for the
engineering and construction activities associated with the
I modified intersection of Market Boulevard at TH 5 . Concerning
the sidewalk addition to Market Boulevard, this was found
necessary in order to provide continuity with the trail section
I
1
I
Don Ashworth
October 3, 1990
Page 2
and crossing proposed for TH 5 at Market Boulevard. The City
currently has sidewalk and trail either built or planned ( in the
' case of the Ward property) across the entire frontage of Lake
Drive from the easterly border at Dell Road to Powers Boulevard.
The Market Boulevard segment therefore provides the necessary
' completion of this network.
The net impact to the project costs is an add of $57 , 810 . 22 for
an amended contract ceiling amount of $759 ,990 . 72. It is
' therefore recommended that the attached Contract Amendment No. 2
for the Downtown Redevelopment, Phase II Project No. 86-11B be
approved for execution.
ktm
Attachment: Contract Amendment No. 2
c: Gary Ehret, BRW
1
1
BRW Copy
City Copy V
• Contractor Cop}
inspector Copy
CITY OF CHANHASSEN
CONTRACT AMENDMENT
Project: Chanhassen Downtown Redevelopment Phase II
City Project No. : 86-11B
Amendment No. : (2) Two
Date: October 1, 1990
Contractor: Midwest Asphalt Corporation
The additions, revisions and corrections contained herein shall be made to the
contract documents for the project, and shall become a part of the Scope of
Work.
Description of Changes: I
A. The Contractor has performed additional work to construct temporary im-
provements for the Market Boulevard and Highway 5 intersection. The inter-
section improvements were made as directed by City staff to satisfy the
requests of Rosemount, Inc. , for the installation of a temporary signal
system at the intersection. I
The additional intersection improvements include earthwork, bituminous
paving, striping and signing. The additional intersection improvements
have resulted in the creation of a new bid schedule and pay items as
detailed below.
Bid Schedule J - TH 5 Temporary Intersection Improvements I
ADD
ORIGINAL QUANTITY , AMOUNT I
SEQ. NO./ UNIT CONTRACT INCREASE/ ADD/
Mn/DOT NO. ITEM UNIT PRICE QUANTITY (DECREASE) (DEDUCT)
1/
2021.501 Mobilization EA $450.00 0.00 3.00 $1,350.00
2/ I
2105.501 Common Excavation CY 1.50 0.00 810.00 1,215.00
3/
2105.507 Subgrade Excavation CY 1.50 0.00 1,926.00 2,889.00
4/
2105.523 Common Borrow CY 1.50 0.00 2,269.00 3,403.50
5/ Geotextile Fabric SY 0.58 0.00 350.00 203.00
CA2-1
I
I
11
ORIGINAL QUANTITY AMOUNT
11 SEQ. NO./ UNIT CONTRACT INCREASE/ ADD/
UNIT
Mn/DOT NO. ITEM PRICE QUANTITY (DECREASE) (DEDUCT)
I 6/ Aggregate Base
2211.503 Placed Class 5 TON $ 5.81 0.00 935.46 $5,435.02
7/ Bituminous Material
I2331.514 for Mixture TON 135.00 0.00 6.49 876.15
8/ Base Course
II2331.514 Mixture TON 8.90 0.00 354.00 3,150.60
9/ Bituminous Material
2341.504 for Mixture TON 135.00 0.00 6.30 850.50
I10/ Wearing Course
2341.508 Mixture TON 10.95 0.00 105.00 1,149.75
II11/ Bituminous Material
2357.502 for Tack Coat GAL 1.00 0.00 50.00 50.00
II12/ Bituminous Island LS 5,937.89 0.00 1.00 5,937.89
13/ Furnish and Install
II2564.531 Sign Panels Type C SF 22.00 0.00 121.00 2,662.00
14/ 4" Solid Line White
I0564.603 Paint LF 0.23 0.00 2,018.00 464.14
15/ 4" Double Solid
0564.603 Yellow Paint LF 0.47 0.00 2,275.00 1,069.25
I16/ 24" Solid Line
0564.603 Yellow Paint LF 1.80 0.00 303.00 545.40
I17/ Pavement Message
0564.602 Type I Turn EA 70.00 0.00 15.00 1,050.00
I 8/
1
2575.502 Seeding Type A AC 1,100.00 0.00 1.85 2,035.00
II19/ Sandblasting LF 0.52 0.00 4,440.00 2,308.80
20/ 3" Rigid Steel
IConduit LF 13.16 0.00 100.00 1,316.00
21/ Traffic Control LS 1,450.32 0.00 1.00 1,450.32
II Net Contract Change Add $39,411.32
II
CA2-2
II
I
I
B. The Contractor has performed additional work to construct concrete sidewalk
along Market Boulevard as requested by City staff. The sidewalk was
constructed along the east side of Market Boulevard from Bowling Alley Road
to the south end of the permanent Market Boulevard roadway construction.
The sidewalk construction also required the relocation of an existing
concrete storm sewer pipe apron.
The sidewalk construction has resulted in the creation of two new pay items
as detailed below:
Bid Schedule B - Roadway
ADD
ORIGINAL QUANTITY AMOUNT
SEQ. NO./ UNIT CONTRACT INCREASE/ ADD/
Mn/DOT NO. ITEM UNIT PRICE QUANTITY (DECREASE) (DEDUCT)
23/ 4" Concrete
2521.501 Sidewalk SF $ 2.95 0.00 4,542.00 $13,398.90
24/ Relocate 24" RC I
Pipe Apron EA 5,000.00 0.00 1.00 5,000.00
Net Contract Change Add $18,398.90
I
I
I
I
I
I
I
I
CA2-3
I
1
I
11 SUMMARY
Current Contract Amount $ 702,180.50
Item A Net Add $ 39,411.32
Item B Net Add $ 18,398.90
Contract Amendment No. 2 Add 57,810.22
Amended Contract Amount $ 759,990.72
APPROVALS:
' RECOMMENDED BY: BRW, Inc.
i
By: Alta, Title Project Manager Date / 3 9
I
i
I
ACCEPTED BY: Midwest Asphalt Corporation
By: 42-t - c cti- Title V 73. e-o/ci5; Uc 7c.) Date /c
II
I
APPROVED BY: City of Chanhassen
By: Title Date
1
CA2-4