C Water Treatment Plant UpdateCITYOF
CHANHASSEN
7700 Markei Boulevard
PO Box 147
Ohanhassen !,/1N 553!7
Administration
Phone: 952227 1100
,~a×: 9522271110
Building Inspections
P 9ne 952227 1180
Fax: 952 227 1190
Engineering
Phc, ne: 952 227 1160
Fax; 9522271170
Finance
Phone 952 227 114(1
Fax: 952 227 1110
Park & Recreation
Phon,-' 952227 1120
Fax: 952227 1110
231D Coulter Boule,~ard
P,hc, r'~ 952 227 1400
Fax 952 2271404
Planning &
Natural Resources
Phc;ne 9522271130
Fax: 952 2271110
Public Works
!591 Park Boad
Phone 952 2271300
Fax: 952 227 1310
Senior Center
Phone: 952 2271125
Sb~ ~27 11s
Web Site
s'¢,,w,' ( i challhasser', xsn Lis
MEMORANDUM
TO:
FROM:
DATE:
Todd Gerhardt, City Manager
Paul Oehme, City Engineer/Dir. of Public Works
August 3, 2004
SUB J:
Water Treatment Plaint Site Selection Update - Project No. 04-08
BACKGROUND
On the July 26, 2004 Council work session staff presented updated information on
the Preliminary investigation Report for the Water Treatment Plaint (WTP). This
information gave a review of cost benefit analysis of the Lotus Lake Wellfield site
compared to the Ready Mix site located at the east end of 79th Street. Staff also
presented Council with pros and cons for the two available sites. In addition, staff
presented Council with two concept drawings for locating the WTP on the Ready
Mix site.
The Preliminary Investigation Report for the proposed Lotus Lake WTP (dated
May 24, 2004) was presented to the City Council at the June 14, 2004 work
session. There have been some questions about some of the items stated in that
report such as setback requirements, possible treatment plant site constraints, and
new well locations.
As a brief review of the items addressed in the May 24, 2004 Preliminary
Investigation Report, the following are WTP constraints that were investigated:
Potential Constraints
1. Distribution System Capacity
2. Feasible Well Locations
3. Treatability of the Well Water
4. Suitability of Available WTP Sites
An amendment to the Preliminary Investigation Report will address questions
raised about Items 2 and 4, Feasible Well Locations and Suitability of Available
WTP Sites.
Suitability of Available WTP Sites
A critical sheet included in Subsection 4.4, Suitability of Available WTP Sites, of
the May 24, 2004 Preliminary Investigation Report, was the sheet showing the
Minnesota Department of Health (MDH) setback requirements and separation
distances for wells and WTP facilities. That critical sheet identified 50 feet as the
The City of Chanhassen ·
Todd Gerhardt
August 3, 2004
Page 2
setback requirement for any WTP structures from the property line. Utilizing a 50-foot setback
fei' siting a 6,000 gpm WTP at the Ready Mix site appeared to render that site unusable. It also
made the Lotus Lake Wellfield site very tight but workable. As a result, the consultant was lcd
to believe that the Ready Mix site was not usable if the 50-foot setbacks had to be maintained.
Upon review of the regulations and discussions with the MDH staff, it seemed rcasonable to
review these requirements at a meeting on site with representatives from the MDH, the City, and
SEH, Inc. On July 1, 2004, representatives from the City, MDH, and SEH, Inc. met and
reviewed both potential treatment plant sites. What came out of that meeting was that the 50-
foot setback requirement could be reduced to a 20-foot setback, in addition, information must be
obtained about potential contaminant threats from potential spills that could occur from the
raih'oad tracks. Also, verification of the existing sanitary sewer lines must be shown where they
may impact the water treatment plant sites.
DISCUSSION
Because of this new information, the Ready Mix site now comes back into play as a viable site
for the WTP. Using 20 feet as the setback requirement/'or the building, the Ready Mix site
becomes workable.
Since both sites are now viable, the pros and cons of each site must be reviewed to compare the
two sites. Both the Ready Mix site and the Lotus Lake Wellfield site have issues concerning
design, construction, security, safety, expandability, etc. that must be considered in selecting a
potential site. Also, if the plant were to be located at the Ready Mix site, what would be the best
location to maximize future development of the site? The following is a brief comparison of the
pros and cons for each site.
g:\cng\watcr treatment\background workscssion 080904.doc
Todd Gerhardt
August3,2004
Page 3
Ready Mix Site - West End
Pros:
· Site alh)ws more design flexibility
· Not close to residential homes
· Large clearwell possible
· Detached backwash tanks possible
· Excavated material may be able to be
left on site
· Better protection fi'om raih'oad spill then
cast end of Ready Mix site
· Better use of site for future devek)pment
· Opportunity cost fi)r sale of east half of
property
COILS:
· Construction staging somewhat limited
· Limited width for building design
· Limited access to plant area
· Less visible location for security then
east end of Ready Mix site
· Possible raih'oad spill hazard although
not its great a east end of Ready Mix site
· Additional raw and distribution
watemain necessary.
· More costly then building at east end of
Ready Mix site
Ready Mix Site - East End
Pros:
· Site allows more design flexibility
· Not close to residential homes
· Large clearwell possible
· Detached backwash tanks possible
· Visible location for security
· Room to alter plant in the future if
necessary
· Most of the excavated material could
be left on site
COILS:
· Construction staging somewhat limited
· Limited width for building design
· Limited access to plant area
· Possible raih'oad spill hazard
· Additional raw and distribution
watemain necessary.
· Additional cost to construct access to
site
PRELIMINARY COST ASSUMPTIONS
Lotus Lake Wellfield Site
Pros:
· Well controls located within WTP
(remove existing well houses)
· Visible location for security
· Redevelopment of entire Ready Mix
site
Cons:
· Construction staging limited
· Cost to remove excavation material
· Limited size of site reduces design
flexibility
· Close to residential homes
· Limited clearwell capacity
· Well isolation distances
· Disruption to residents during
construction
· Shared use of site by public
· Elimination of open space at park
· Tennis courts required to be replaced
· Security concerns if tennis courts are
built next to treatment plant
· No room to alter plant in the future if
necessary
A preliminary project cost of $10.5 million for a 6,000 gpm gravity filtration WTP was reported
in the May 24, 2004 report for the Lotus Lake Wellfield site. Costs to construct the treatment
plant at the east side of the Ready Mix site will not alter significantly the project cost estimate of
$10.5 million. The Ready Mix site will need additional raw water and distribution watermain
installed and additional work to construct access to the site. However, the Ready Mix site allows
for greater staging opportunities over the Lotus Lake Wellfield site which will reduce the
construction cost. in addition the Ready Mix site may allow for the excavated material to be left
on site unlike the Lotus Lake Wellfield site. If the treatment plant were to be built at the wcst
end of the Ready Mix site, additional costs would be incurred over the east end of the Ready Mix
site due to the additional amount of excavation, additional waterproofing of the Plant, and
removal of the existing cul-de-sac and landscape features.
g:\eng\walcr trcanncntXbackground workscssion 080904.doc
Todd Gerhardt
August 3, 2004
Page 4
Excavated Material
Sale of Property
Construction Staging
Street Construction
Tennis Court Reconstruction
Site Comparisons
Ready Mix Site vs. Lotus Lake Well Field
Ready Mix Site
West End East End Lotus Lake
($40,000) ($25,000) ($100,000)
$705,672 $200,376 $906,048
($25,000) ($25,000) ($ 00,000)
($ ! 50,000)* ($ ! 50,000)* N/A
N/A N/A ($160,000)
Net Total: $490,672 $376 $546,048
This analysis shows that the west end of the Ready Mix site would be approximately $55,000
more expensive to build the treatment plant on then the Lotus Lake well field site if future sale of
the Ready Mix site is considered into the equation.
Note:
Construction costs will vary for each site depending on the groundwater table. Also,
construction costs will vary depending on the architectural and landscape features
included in the project.
OPPORTUNITY COST FOR READY MIX SITE
The preliminary findings showed a portion of the Ready Mix site could be developed in the
future if a treatment plant were sited at this location. The area with the most redevelopment
potential appears to be the easterly end of the site. Approximately 1.8 acres could be
redeveloped at this location if a WTP were construed at the west end. However, if future wells
were to be constructed at this location, development area could be smaller. Due to the
topography of the site, development of the west end of the site would be more difficult and less
area could be developed.
g:\eng\watcr treatment\background xvorkscssion 080904.doc
Todd Gerhardt
August 3, 2004
Page 5
RECOMMENDATIONS
While each of the sites have potential drawbacks and issues to resolve, it now appears that the
Ready Mix site is a viable location for a WTP based on the recent information gathered from the
MDH, the pros and the cons identified and the opportunity costs associated with each site. It
appears siting the treatment plant on the west side of the ready mix site and selling the east end
of the ready mix site for future development is the best alternative for thc City long term.
If Council agrees with the recommendation of constructing the treatment plant on the west side
of the Ready Mix site, the next step would be to entel' into a contract with a consultant for design
and construction of the water treatment plant. A Request For Qualifications (RFQ) was
distributed in 2001 to a select list of consultants for witter treatment. The RFQ was conceived to
take the City fi'om study phase all the way through construction. The RFQ, however, did not
address cost for services provided. Staff is recommending a RFP bc solicited for design and
construction services. Attached is a draft RFP and Scope of Services (SOS) staff has drafted for
council review.
If this project is moved forward, the preliminary schedule would be as follows:
Execute Engineering Contract
Complete Preliminary Design
Complete Final Design
Award Construction Contract
Substantial Completion of Construction
October 11, 2004
January 2005
April 2005
May 2005
August 2006
Attachments
g:\cng\watcr treatment\background workscssion 080904.doc
Attachment B
Scope of Services
General
The proposed East Water Treatment Plant (East Plant) will be built at the end of 79th
Street and have a rated capacity of 8.64 million gallons per day (MGD). The East Plant
will remove iron, manganese and other contaminates. No softening of the water will be
provided.
Existing 79th Street should be extended as shown on the concept plan under this project.
Currently Wells 2, 5 and 6 will be treated by the East Plant. A new raw watermain will be
needed to bring the raw water to the plant from the existing wells. The existing 20" water
main on site is anticipated to continue to be used as the trunk distribution watermain. An
additional 3 to 4 wells will ultimately be treated by the East Plant. The plant should be
equipped for by passing. The site for the treatment plant should be planned for an
additional two wells (1 Jordan aquifer and 1 drift well). This project should consider the
best location for these future wells and plan for raw water collection pipes.
The design of the plant should consider maximizing the unused land for future sale and
development. The excavated material from the treatment plant should be placed and
regraded on the east end of the site to plan for the development. A preliminary wetland
survey of the site has found no wetlands.
The scope of work includes:
· Design phase services to include preparation of construction documents
describing the East Plant construction suitable for obtaining competitive
construction bids.
· Bid phase services.
° Construction phase services to include contract administration and
construction observation.
· Assistance during start-up of the East Plant.
PROJECT MANAGEMENT
The consultant will, at a minimum, provide the following services.
Preliminary & Final Design Phase
Tasks
Kick off meeting with City staff to tour the East Plant site and confirm overall project
objectives.
Complete a topographic survey of the site to use in preparing construction documents.
Complete a geotechnical exploration required for facility design.
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
Complete one glacial drift test well and pumping test on site to determine potential yield
of future well and determine well location.
Complete site review by a qualified wetland delineator to confirm that there are no
wetlands on-site.
The design of the plant must address the following needs:
The Consultant firm shall provide an analysis and cost/benefit review of both
gravity and pressure type filtration systems. The analysis shall include but not be
limited to initial construction costs, long term operational costs, flexibility of each
system to treat additional elements as standards change or demand
necessitates, the ability of each system to effectively and efficiently remove iron,
manganese and other contaminates from the water supply, ease of operation of
each system (manpower needed, availability of replacement parts and materials,
etc.), the discharge of the waste product, ability of the plant to expand or be
modified in the future. This shall be a comprehensive review and
recommendation on the "best" plant to meet the current and future needs of the
City.
Assessment of radium/radon exposure in the plant. Include measures to
minimize operators' exposure risk in facilities.
Design for the proper size of the clear well and filter backwash tanks.
Provisions for water overflow and discharge from filter backwash tanks.
Design shall include parallel operation of the treatment process to allow one half
of the facilities to be taken out of service for repair or maintenance while
maintaining operation of the other half.
Architectural features should incorporate of the following items into the facility
design:
· 1 Office space/control room
· 1 Small break room
· 1 Meeting area
· Access for chemical delivery
· Parking for staff and visitors
Architectural style and materials is anticipated to match the existing exterior of
Chanhassen City Hall.
Evaluate and provide for security measures to maximize security of the treatment
area. Security system should include consideration of potential future homeland
defense security requirements.
Evaluation of future regulatory requirements and consideration of contingency
space to accommodate additional treatment processes.
2
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
9. Analyze and provide a recommendation to the type of chlorination and chemicals
to be utilized for the treatment plant.
10. The City's existing SCADA system is currently being upgraded. The new plant
will need to be incorporated into the system
11. Sludge disposal conveyance system.
12. As much excavated material from the treatment plant should be placed and
regraded on the east end of the site to plan for future development.
13. The Consultant shall provide all additional information necessary for design
consideration.
Prepare a preliminary design report, suitable for presentation to the Chanhassen City
Council, to include:
· A description of the new facilities.
· Schematic layouts of the plant site improvements.
· A preliminary list of drawings and specification sections.
· A hydraulic profile of the plant.
· An opinion of probable plant construction cost.
Review the preliminary design report with City staff and assist with a presentation to the
City Council. The Consultant should anticipate preparing documents and presentations
at three (3) Council meetings
Review the preliminary design report at one (1) Planning Commission meeting and
assist with the presentation
Coordinate and obtain necessary permits and approvals for the project. The cost of the
permits themselves will be paid directly by the City.
Review the final design and bidding documents with City staff at two points during final
design.
Deliverables:
Four copies of plans and specifications for review by the City at two points during final
design.
An updated opinion of probable construction cost at two points during final design,
including an opinion of probable construction cost five days prior to the bid date.
Two copies of final bidding documents for the City's use.
An adequate number of copies of the bidding documents for use in soliciting construction
bids.
3
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
Bid Phase
Tasks
Prepare and coordinate publication of an advertisement for bids and distribute bidding
documents.
Coordinate and attend a pre-bid meeting and site tour.
Receive and respond to questions from potential bidders and issue addendum(s), as
required.
Attend the construction bid opening, review and tabulate bids received, and prepare a
recommendation for award.
Deliverables
Advertisement for bids.
Pre-bid meeting and site tour summary as required.
Addendum(s), as required.
Tabulation of bids.
Recommendation for award of the construction contract.
Construction Phase
Tasks
Coordinate, attend, and conduct a preconstruction conference.
Administer the construction contract, including: · Review of Contractor submittals.
· Review and processing of partial pay estimates submitted by the Contractor.
· Assistance with interpretation of the construction documents.
Provide construction staking.
Provide full-time resident inspection during the course of the construction project.
Conduct periodic construction progress meetings and provide meeting minutes.
Review and/or prepare Field Orders, as required.
Initiate and/or prepare Change Orders, as required.
Maintain record documents for the City until project completion, including shop drawings,
testing records, construction photos, operation and maintenance manuals, etc.
4
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
Provide regular construction progress updates to the City.
Coordinate and participate in start-up of plant and coordinate supplier provided training
for appropriate systems.
Prepare an operations and maintenance manual for use by City staff.
Deliverables
Meeting minutes from the preconstruction conference and construction progress
meetings.
Three hard copies plus one electronic copy (Microsoft Word) of an operations and
maintenance manual (to be provided no less than three months prior to any scheduled
training for appropriate systems or start-up of the Plant).
Three hard copies plus one electronic copy (AutoCAD) of Record Drawings (to be
provided within one year of project acceptance).
One copy of record documents, including shop drawings, testing records and
construction photos.
5
Request for Proposals (RFP)
Project Overview
The City of Chanhassen (City) is soliciting proposals for professional engineering
services for the preliminary design, final design, bidding and construction phases of the
East Water Treatment Plant (East Plant). The treatment plant is proposed to be built on
a 3.15 acre parcel the City currently owns which is in close property to existing wells and
future well sites. The land not used for water treatment is anticipated to be sold for
future private development.
Proiect Backqround
In January 2003 the City completed a Water Supply, and Distribution System Master
Plan which evaluated the need for treating the City water for Iron, manganese and other
contaminates and also looked at options for future plant locations. In December of 2003
a Citizen Advisory Panel (CAP) recommended treating the water at two water treatment
facilities. In January, 2004 the City council adjusted water rates and water connection
charges to help pay for the construction and operation of the treatment plants. In May,
2004 a Pilot Plant study, Lotus Lake Well Field study and Preliminary Investigation
Treatment Plant report was completed for the East Plant.
The East Plant is proposed to be constructed at the end of W. 79th Street and have a
rated capacity of 8.64 million gallons per day (MGD). A drawing showing the proposed
treatment plant site and site concept is included as Attachment A to this RFP.
The design of the plant should consider maximizing the unused land for future sale and
development. A preliminary wetland survey of the site found no wetlands.
Scope of Services
A general Scope of Services is included as Attachment B to this RFP.
Information about the RFP
Questions about the technical aspects of the project and the selection process, or the
administration of the project, should be directed to Mr. Paul Oehme, Director of Public
Works, at 952-227-1169 or by email at poehme@ci.chanhassen.mn.us. All responses to
questions submitted will be submitted to all RFP holders.
A copy of the plot plant test is included in the RFP along with a drawing showing existing
utilities in the area and a site survey. As-built drawings are available for review at City
Hall. Please contact Matt Saam, Assistant City Engineer, at 952-227-1164 to review
these drawings.
Proposal Content and Format
The proposals should include the elements listed below. Page limits are listed in
parentheses.
General information and a brief history of the consultant's firm. Include
similar information on key subconsultants proposed for the project. [2
pages]
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
2. A summary of the consultant's understanding of the project including the
type of plant proposed to be built. [1 page]
3. A detailed description of the consultant's approach to completing all
phases of the project. Include a statement about the consultant's
approach to quality assurance and document management. [3 pages]
4. Identify the key project team members and describe their specific roles on
the project. Include key subconsultant firms, and their specific role. [3
pages]
5. Include one-page resumes for key members of the project team, including
field service personnel during construction. [1 page per team member, 1
per subconsultant]
6. Describe relevant experience and provide information on at least three
reference projects completed in the last five years. Include specific
descriptions of proposed team members' roles on reference projects.
Provide a contact name and information for each of the projects. Also
provide the engineer's construction cost estimate, the successful bidder's
price, and the final construction cost (including all change orders). [5
pages]
7. Include a proposed schedule for the project, including completion of
design and construction phases in bar chart form. [1 page]
8. Include a workplan showing a breakdown of tasks and effort for each
team member associated with each of the project phases. Show
proposed hourly rates for each team member and the total proposed fee
for the project. [2 pages]
Proposals should follow the Table of Contents listed below. The sections of the proposal
should be separated using tabs.
I. General Information
II. Project Understanding
III. Project Approach
IV. Proposed Project Team
V. Resumes
VI. Experience
VII. Schedule
VIII. Workplan and Fee
Submission of Proposals
Submit five (5) copies of the proposal. Proposals should be addressed to:
Mr. Paul Oehme, P.E.
Director of Public Works/City Engineer
City of Chanhassen
7700 Market Boulevard
P.O. Box 147
Chanhassen, MN 55317-0147
Proposals will be accepted until 4:00 p.m. on Friday, September 3, 2004.
2
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
Evaluation Criteria and Selection Process
The proposals will be evaluated by a selection panel consisting of members of the City
of Chanhassen staff.
The City requests that interested consultants refrain from personally contacting any City
staff regarding this process or its opportunities in order to ensure that the selections
occur on each consultant's merits based on its proposal and interview.
From the proposals received, the City will select up to three firms for interviews. A final
scope of services and contract will be negotiated with the selected consultant·
Proposals will be evaluated on the basis of the following criteria.
· Demonstrated understanding of the requirements of the project.
· Consultant firm and subconsultant key project staff experience and qualifications
with water treatment plant design, construction administration and start-up
services.
· Record of past performance on similar projects with comments and opinions of
references.
· Proposed approach and scheduling.
· Clarity and consciousness and organization of the proposal.
· Proposed fee.
The City shall not be liable for any expenses incurred by the consultants including but
not limited to expenses associated with the preparation of the proposal, attendance at
interviews, or final contract negotiations.
The City reserves the right to reject any and all proposals or to request additional
information from any or all proposers.
Contract Form
The City reserves the right to negotiate the final terms and conditions of the contract to
be executed. Should the City and a consultant be unable to mutually agree upon the
entire contract, the City reserves the right to discontinue negotiations, select another
consultant or reject all of the proposals. Upon completion of negotiations agreeable to
the City and consultant, an hourly fee plus expenses type of contract shall be executed.
Contractinq Ethics
No elected official or employee of the City who exercises any responsibilities in
the review, approval or implementation of the proposal or contract shall
participate in any decision, which affects his or her direct or indirect financial
interest.
It is a breach of ethical standards for any person to offer, give, or agree to give
any City employee or Council person, or for any City employee or Council person
to solicit, demand, accept, or agree to accept from another person or firm, a
gratuity or an offer of employment whenever a reasonable prudent person would
conclude that such consideration was motivated by an individual, group or
3
East Water Treatment Plant
City of Chanhassen
City Project No. 04-08
corporate desire to obtain special, preferential, or more favorable treatment than
is normally accorded to the general public.
3. The consultant shall not assign any interest in this contract and shall not transfer
any interest in the same without the prior written consent of the City.
4. This consultant shall not accept any private client or project which, by nature,
places it in ethical conflict during its representation of the City.
Policy for En.qa.qin.q Professional Consultin,q Services
1. RFP Procedures--All consultants for various services will be selected in
accordance with the City's Policy.
Project Schedule
Tentative completion dates for project milestones are listed below.
Proposals Due
Notification of Short List/Interviews
Interviews
Execute Contract
Complete Preliminary Design
Complete Final Design
Award Construction Contract
Substantial Completion of Construction
4:00 p.m., September 3, 2004
September 10, 2004
Week of September 20, 2004
October 11,2004
January, 2005
April, 2005
May, 2005
August, 2006
Attachments
A - East Treatment Plant Site Concept
B - Scope of Services
C- Utility/Contour Site Map
g:\eng\water treatment\rfp\rfp -draft,72304.doc
4