6 Water Treatmnt Plant Contract
CITY OF
CHANHASSEN
7700 Markel BOlle'lalG
PO Boy 147
MN55317
Administration
Phcr:e 952227 í 100
952 227.1110
BUilding Inspections
Pholle 952 227.1180
Fay 9522271 ! 90
Engineering
priOlY 952227 1160
Fay. 952 227 1 Î 70
Finance
PIClI8. 952 22711,10
Fay 952227 Î 110
Park & Recrea!lon
P11]llP 9522271120
Fay 952227 1110
Celìter
2310 Boulevaru
PI·ûlli: 952227 1400
952227.1404
Planning &
Natural Resources
952 2271130
Fax 952 22ì.l11O
Public Works
1591 Road
952 227.1300
952227 1310
Senior Center
Pllone 952.227.1125
Fay 952227 1110
Web Site
The City of Chanhassen · A
[.
MEMORANDUM
TO:
Todd Gerhardt, City Manager
Paul Oehme, City Engineer/Dir. of Public Works _ "~
OP )'
October 14, 2004
FROM:
DATE:
SUBJ:
Approve Contract for Design and Construction Administration
Services with SEH, Inc. for Water Treatment Plant - Project No.
04-08
BACKGROUND
At the October 11, 2004 City Council Worksession, staff updated Council on the
status of selecting a consultant for design and construction administration of the
Water Treatment Plant. Staff reviewed with the Council the process used to short
list consultants for interviews and the scoring criteria used.
Staff sent out requests for proposals (RFP) to seven local design firms. On
September 17,2004, the City received five proposals. The proposals were
reviewed in detail and scored by staff. The scoring of the proposals was weighted
heavily towards the firm's experience with design and construction of water
treatment plants, experience of personnel proposed, understanding of the project
and services required, and fee amount. Staff weighted the scoring of the
proposals heavily towards experience of the firm and qualification of personnel
proposed. The scoring was set up this way because the design will have
significant grading, utility, mechanical, and electrical challenges.
After the proposals were scored, three firms were selected for interviews. The
firms, SEH, Inc., Bolten & Menk, and Bonestroo & Associates, interviewed the
week of September 27, 2004. The firms were then scored again based on the
interview information. Again, the scoring was weighted towards the experience
of the personnel proposed and firm's experience plus the understanding of the
services required. Fees were also ranked.
Based on the interviews and scoring, the following ranking was determined:
Personnel proposed for this project (individual resumes and experience):
1. SEH, Inc.
2. Bolten & Menk, Inc.
3. Bonestroo & Associates
comrllullliy WIPl clearllakes
Todd Gerhardt
October 14,2004
Page 2
Firm experience (quantity and quality of work):
1. SEH, Inc.
2. Bonestroo & Associates
3. Bolten & Menk, Inc.
Understanding of Services Required:
1. SEH, Inc.
2. Bonestroo & Associates
3. Bolten & Menk Inc.
Interview and Proposal:
1. Bonestroo & Associates
2. SEH, Inc.
3. Bolten & Menk, Inc.
RFP fee proposed:
1. Bonestroo & Associtate
2. Bolten & Menk, Inc.
3. SEH,Inc.*
*fee amount revised based on Council comments.
SEH, Inc. had proposed a base bid number consistent with the RFP staff sent out
to all consultants. This fee ranked SEH, Inc. third at an amount of $698,500.
However, SEH, Inc. included the design and construction administration services
of future Well Nos. 10 and 11. This item was not consistent with the RFP. SEH,
Inc. has reviewed their fee to reflect the RFP solicitation. The new fee, $638,500,
reflects the RFP solicitation and is $60,000 lower then the previous bid reflecting
the removal of the Well Nos. 10 and 11 design and construction administration.
Staff over estimated the cost for the Well Nos. 10 and 11 fees in the background
of the October 11, 2004 worksession. SEH, Inc. thought it was important to
include this work in the contract because well work is an important component to
the water treatment plant site and SEH Inc.'s knowledge that the City will need
additional potable well capacity in the near future.
DISCUSSION
Staff is recommending the City enter into a contract for design and construction
administration services with SEH, Inc. for the Water Treatment Plant. The review
process for this work emphasized personnel that would work on the plant, firm
experience, and reference checks. The emphasis was placed mainly on these
areas because the design will have significant grading, utility, mechanical, and
electrical challenges. The complexity of designing and constructing a treatment
plant should not just be fee based. The City needs to contract with the best
personnel available on design and construction because it becomes extremely
Todd Gerhardt
October 14,2004
Page 3
expensive to fix problems later if the design was not correct the first time. The
chosen site will make the design challenging and will not allow for many changes
because of the small footprint of land.
The SEH, Inc. team ranked first for personnel because of their key personnel's
years of experience in design and construction administration on water treatment
plants. Jim Norton, Project Manager, has 38 years of experience designing and
managing water treatment plants. Jay Whitaker, Senior Project Engineer, has 35
years of water and wastewater plant design experience. Randal Leppala, Project
Design Leader, has 30 years of engineering experience. John Thom, Operations
and Maintenance Specialist, has 34 years of experience managing water utilities,
pilot plant studies, plant operations training and start-up, writing water treatment
plant operations procedures manuals, and diagnosing problems with plant
operations. Michael Bebault, resident project representative, has over 20 years of
construction experience as a field superintendent and project manager. No other
firm had personnel with this amount of experience.
The firm experience of SEH, Inc. was ranked first because of the type, size and
characteristics of the treatment plants they have recently built. The RFP
requested to submit at least three relevant projects completed in the last five years.
In the last five years, SEH, Inc. designed and constructed plants for the City's of
Eagan, Sauk Rapids, and Hudson, WI. They are currently constructing water
treatment plants in Plymouth and Minnetonka. The total construction cost of all
the plants at time the bids were received was over $52,200,000. Bonestroo &
Associates, the next highest ranked experienced firm, identified plants built or
under construction in the last 5 years in the City's of Cokato, Spring Lake Park,
Chaska, Hinkley, Sartell, and Virginia. The total construction cost at time of bids
received was about $29,700,000. Bolten & Menk's identified plants built in the
last five years in the City's of Andover, Buffalo, Windom, Litchfield, LeSueur,
and Alexandria. Most of these plants were small plants (2-3 MGD) except for the
Andover and Buffalo plants (6-7 MGD). Some of SEH, Inc.'s projects are
similar in scope to the City of Chanhassen's plant and had some of the same
design challenges we will face. Also, SEH, Inc. has shown the most experience
with designing a treatment plant on small and confined site.
Staff has called all of SEH, Inc.'s references. The City of Sauk Rapids, however,
has not returned repeated voice mail messages. All references checked had
positive things to say about the firm and would hire their service again for water
plant design and construction services if needed. The City of Eagan did have an
issue at the end of the construction project with communication with sub
disciples. This, however, can be attributed to management staff at SEH, Inc. tUI11
over during the end of the construction period. SEH, Inc. has indicated they were
working on the issue.
Todd Gerhardt
October 14, 2004
Page 4
Staff also checked with several of Bonestroo & Associates' references and they
too had positive things to say about the firm and would hire their services again
for water plant design and construction services if needed. The City of Chaska
commented their water treatment plant was behind schedule and were having
difficulty with start up due to contractor problems. They also have areas of
defective workmanship.
Staff has also checked with Bolten & Menk's references. They too had positive
things to say about the firm and would hire their services again for water plant
design and construction services if needed. However, the project manager that is
proposed for the City of Chanhassen plant was not a project manager on any of
the referenced projects.
The City of Chanhassen has used SEH, Inc.'s services for the recent plant site
selection study, Lotus Lake well field study and the pilot plant study. This firm
has the most understanding of the issues with siting the plant at the ready mix site
and water quality issues. Staff feels that design would proceed best using the
same firm.
Bonestroo & Associates showed very good understanding of the project and what
would be needed to build the plant. Bolten & Menk's preliminary design
approach to the Chanhassen Plant runs contrary to the pilot study. Most of the
Bolten & Menk plants are designed with detention tanks which provide a more
conservative approach to treating the water. The detention tank will cost more to
design and construct. The pilot plant study indicated that a detention tank is not
necessary for treatment. Also, it is not clear from staff's perspecti ve where the
detention tank could be located due to the site constraints.
Based on the information that staff has gathered it is our recommendation to enter
into a contract with SEH, Inc. for design and construction administration services
of the Water Treatment Plant.
The City Attorney has review the contract and finds it in order.
Attachment
g:\eng\water treatment\background 102504 era.doe
RFP Fee Proposals
521
403
924
428
278
o
445
2.666
227
2,080
96
5,514
Ex
---¡132,958
$396,984
$529,942
00 $10,446
2,005 $186,734
44 $5,536
7,689 $732,658
$85,792
$195,911
$281,703
$29,352
$244,332
$13,680
$569,067
2,406
340
2,852
120
6,687
e
$128,700
$228,100
$356,800
$43,300
$220,049
$18,351
$638,500
2,422
355
1,934
150
5,838
Plant
Expens
$38,130
$324,350
$362,480
$16,850
$256,845
$16,790
$652,965
Water Treatment
3,460
164
2,879
190
7,086
n
Bid(
Construction Phase
Start Up
Contract Amount Total
$26,720.00
$5,000.00
Solicited quotes2
ncluded ~xpenses
???
I
$9,000.00
$10,000.00
Solicited quotes 1
$16,300.00
$5,000.00
Solicited quotes
n expenses
$5,000.00
Solicited quotes
ncluded
Estimated Misc. Expenses 3
Soil Borings
Well Pump Test
Solicited quotes
$601,910
$732,658
expenses related to the project
$588,067
pump test
telephone and other
$659,800
Bonestroo proposed the well pump test for $9,000
HR Green received a quote of $35,090 for a wel
Miscellaneous expense include mileage
$657,965
2.
3.
Note
Total
Cost
SEH
October 25, 2004
RE: City of Chanhassen
East Water Treatment Plant
City Project No. 04-08
SEH No. P-CHANH0502.00
Mr. Paul Oehme, PE
Director of Public Works/City Engineer
City of Chanhassen
7700 Market Boulevard
P.O. Box 147
Chanhassen, MN 55317
Dear Paul:
This letter supplements the Master Agreement for Professional Engineering Services between the City of
Chanhassen, Owner, and SEH dated July 14, 2004 and addresses providing services in connection with
the East Water Treatment Plant, City Project No. 04-08 (hereinafter called the "Project"). The scope of
said services is detailed in the attached Exhibit E.
Our services will consist of conducting studies and investigations, preparing a report containing the
findings of the studies and investigations along with our recommendations for the Project, preparing a
preliminary design based on the approved studies and report, preparing final design documents based on
the approved preliminary design, providing assistance with receiving bids for the work and negotiating a
construction contract with the successful bidder, providing construction services including resident
project representative services during construction, and assistance during the start-up, all as set forth in
this letter, Exhibit E, and the Master Agreement for Professional Engineering Services between SEH and
City of Chanhassen dated July 14,2004.
The fee for our services, which you agree to pay for, will be billed hourly with a not to exceed maximum
fee of $638,500 including reimbursables, except as otherwise addressed in this Supplemental Letter
Agreement and the Master Agreement for Professional Engineering Services.
We will also furnish such Additional Services as you may request.
Payment for additional services shall be based on the time required to perform the services and the
billable rates for the principals and employees engaged directly on the project, plus charges for expenses
and equipment, as described in the Master Agreement.
We will start our services promptly after receipt of your authorization. Our services will be completed
after 24 months. If there are delays in the Project that are beyond our control, you agree to grant
additional time and compensation to complete the services.
Any changes by the Owner in the site plan, landscaping, building layout, room arrangements, or
elevations after the 30 percent plan review will be considered additional work and paid for as described in
the Master Agreement. During the construction services phase any construction work desired by the
Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196
SEH is an equal opportunity employer I www.sehinc.com I 651.490.2000 I 800.3252055 I 651.490.2150 fax
Owner beyond the hours shown in Exhibit E will also be considered additional work and paid for as
described in the Master Agreement.
This letter and the Master Agreement for Professional Engineering Services dated July 14, 2004 along
with Exhibit E represent the entire understanding between you and us in respect of the Project and may
only be modified in writing signed by both of us. If it satisfactorily sets forth your understanding of our
agreement, please sign the enclosed copy of this letter in the space provided below and return it to us.
Sincerely,
SHORT ELLIOTT HENDRICKSON INC.
ð-f 1~
James P. Norton, PE
Sr. Principal/Director, Water Services
x:\ae\¡,;klllh\050200\] -gt:ll\ 12-suh\supplettt'[(K10her 19.Jt\c
Accepted by:
City of Chanhassen
By:
Date:
Authorized Client Signature
~~
OJ
1\1 u;
õ - 0
III eo
G).!!~
CD.. 'i:
C _ II
~ 5!
¿ g ~w
G) caW...
:2 !]~
co I- II )c
"2 Qifw
1\1 _::I
.s:: 1\1 0
(J :¡::I:
Õ êÞ ~
~~~
õ ~
~~~
.... b§
1~
>-'-'
I: E
1¡:!tj
E ~ 0
:;0°
w;o
~:i
>-w"
JOS~Jd PJOM
I~JµQt3 p..IlI! r.I!Uell~
UE!:J!UII:1iIl.U6!SõI(J
1~~3
UQSUaJOg uopt'HIS
~u!6u3 þõI!(Ud rr.-tJµQEI
IP!WII:JS ø,w¡g u..atutpal
u6!$õJQIII!:>!U~'3aft
ZUlaM WO.1
J98U!6U3 I~OJd I'I'3!UlI'qoan
¡JellU!aJS ~µe"
JOssa::KUd p,J0M. H3S
IInRQaa r.J)J!n· a^!tl1Jua~J(I<;IU
pafoJd 'UQP!~H
wotfl Ullor - JS!I'IiI'!:JQdS
~ueUQIU!ew pu\!' UO!l2læO
Aa~z ueo
)S!lvpodS 6u!¡eoo
JõÞP!aM IRed
UJ!!::J!ulI:Þa.l u6!saa S'S~Jd
lI1?dda, epueu
J:JPr.¡q u6!saa þafoJd
UO$Ullor OOJO
JaaU!6U3 ~OJd ~Jd
weuJng UE'O
U~:)Ul:;J9.lleJRþGijl:)JV
PIOAV'l PPO.l
pelNaJV a¡enpeJE)
MO oweno
1:ÞaIII:JJV
sa~nH aA8(]jX0::l ,\pueu
SlÆ'!:»!UII:ÞII.lIIiIJnl:JRIJS
3)VJQu<r.:IS
~U!6U3 pafOJd lnUµ1aQS
pJII!Mõiltg ~ed JaQU!6u3
~OJd "IS eJnl:Þnl1S
~IOÐa!lnr
UE!::!tUII:;JQ.lVl
uosqo:Jer k:lUII!N
þ:ölP.\,:UY ~pue,
J:JQIS~U pelS
Ue!:>!ulI:;J9.l1l^!3
J'oIweJ)t zAlIvpn6eJds uoser
Ja9u!6u3 pafoJd I!^!::>
e¡a'õI6JOHIV
MaJ:) .bAJns I!^!:)
l),In)l fi!eJ::>/PIDqWeM8uMM.
15!6otoa&()jPAwJ~U43ðloa(J
J311eÞ.IIM Ñer
J3au!6u3IacölfOJd -JS
UOJON W!r
J~IJ~ ¡aaOJd ledpU!Jd
II:::JSµ;K>.iaJflW
Ja6e~n a:::J!A.JôJS ~13
i
o
;0
.
.
>-
¡¡
!
! 1
· " ~. 3 · ßi . ; " ~
~i ~
... ... ... ... ... ...!..... ...
ì '
~i ~ .. "
-
--~
·
·
-
·
·1 I
, -- -----t--
2' .
----
·
· .
·
· .'
..
·
~i
g,
o¡ M
i . i:
~ ~' ~,
~ ~. i'
d~'i
~ Æ; ; ~
~ ~¡ !
,,,H'H
'1i ~ ~: î w õi
] ~ ~¡ i! ~ ~
W¡ ÆI !, ~ ð ~
i _I . .
'.
f<-
¡
.-
-. -
- - ;--
~,
", '
~
--
., :! .
.
. ~--
"
re
I
!
~i
,! .
!-. -:01- -
. N
· . N
;
~, ¡¡I 8 ~
~ ¡;;
~ -
~
~ ~ !I <
i
" . ~
I
,i -H--
· .
§ e "
;
~:
;--
,.¡
"
-
,
~i ....
<oj", 10
,
--'--
'" <0 10:
."; e
.
~ ~
~ ,
, .
" .
¡
~ ~
;
~i ...
· .
;;
·
Ë
.. .
--i--
12 ~ ....
c- -
~ .
·
· .
.
"
" . "
· ~ .
N' ¡
:3 ~ ~ ...
;
~ . '. N
·
--
.
~ 10 <0
~... ""
, .
" "
.'
,
-
" -" "¡ .
,
, .:
" ~ -;-.--
.. -
.
i I : ~ :
~ i ;j ~
I ~ ~i ~ ~
~ ~ ;i ~ r ü: i !
s ~ "I ~ "' 1; j i ~
· ~ !il . . . ~II n
idl ~H~:
ï_ jE r_d n f t j
~ '! !¡ ! ! = ~I Æ !
· .;11:;; ~ "~ I
; j ~i... : ~ ~ ir ! ~
~ ... Il.' úJ I- 0 ð a:¡ d: U.I ~-
t- III "'! ~ _ '" ...1 ... ."
~'
n
II ~:
l
E.
" 9
~ i j:
;: Ë
i¡
~! ! ¡
iE 01 ;1 ~ ~' -
!j ~ ~ ¡!
j i¡ ~ " u'
1f1. n
~i :!! ~ {:
~.', !I~:.,.· !'.
"'i .0: Æ:!
~! Æ I- ß: ~i
"'i '" -I "'i .., ...
~I
ni.
~ g; ~
-:- ,.¡:
I ~
... ...i...
~ ~ ~
~
~.: I ~
· , I
·
·
'.
..,i ~
,
·
·
·
,--
·
- -
--
·
: .
<0 '" ~
· --
"
· ,
,
.. '
-t-
~1--
-~
·
T .-t-
i .-+
·
:
,. --~-- -
l--!
· 01 . ~ ~:
· ': .
· ¡-
,
!
i
¡
..
A
·
·
·
~
~
·
E
I
~ j
¡ i
.. '
·
¡
Ii
u
~
i
i ¥
. £
I !
-
o .
,If I
I I
B: ~
~, -,
¡-
I
iHiL
" Ii of' "
... - ...1...
~' A' :t: 5 ::1.
!
,
1-'
¡ . -I - "
,
!"
j
>;
"
--'--...-
~
.
-
:
.!
,
i- "
:! '
¡ ~i" "
." r . .
] :
--,
o
·
.d-
, " 'j
.
.
·
.
, "
-~~ -
-~
. .' ",
.,
--~
~¡ ~
~ .1 §
WI ",!:j
. -
. .
~ ~
I
I .1
- I
I
. .
If: ... ~ ... ~
·
,
. .
e .
-, -
. ~
·
-- ,-
--
~
e
g .
· "
· , " .
.. !
, " " ~
" ..
·
I
-j
·
¡
I
·-1-
i
L
i
[--
-+-
I
21 .
..
·
¡ i
§ ¡!"ª
q!
Hi:
~ III ð
d;
d~
! ~!
'i ai i
l !i i
-+ ..
! I !
! ~ i
: . i
. i Iv
~ i; i I
j: fi Ii ! ~
~ i i ! i
-81 ~ ~ !
~ ~; ; i
il i 'I I ~
., £ ~ 0: ¡¡
~ ¡ ;; i! ~
,j õ . ~ .
!; ; d:! ¡
q ! r:¡
11 ~ ~ ~I .
]i! ~ ~ §i !
~i 8 13 a:1 U.I
r- "'\ '" ~ ~I ::
.i .
,
! a
...'...
l
.
i
--
o
on
i
~
II ·
sj ;
.'
§
·
~
~
·
~
Ë
¡:
~
g
¡¡
·
~ í
Ii
·
·
!
"
g
:
-
-
-
~
~
~
~
ft
.
,
,
1
,
"
¡¡ ~
d
: ~IJ
() [¡ i
! ! .8 ~
:. ~~
i ~! i! ~ :
~ ~I ~"i
~ !: !: ~ I
i '~ ~