DATE: December 5, 1990
' SUBJ: Reject Bids for Market Square 72" Storm Sewer Extension
Project No. 90-13
On September 10 , 1990 , the City Council awarded the bid for the
Market Square 72" storm sewer extension to the low bidder,
' Northdale Construction, in the amount of $87 ,290 . This award was
conditioned on the City receiving the necessary financial
guarantees for the cost of these improvements from the developer
of the Market Square retail center. Since that time, the Market
' Square developers have not been able to consummate their deal.
This office was recently advised that the earliest this might
happen is February of 1991 .
In light of this fact, and the likelihood that if the City would
re-bid this project in the spring of 1991 that we could receive
' better competitive quotes (we only received two bids this time) ,
it is recommended that the City Council reject all bids for the
Market Square 72" Storm Sewer Extension and authorize
readvertising for bids for this project in the spring of 1991
consistent with the developer' s time schedule for Market Square.
ktm
' Attachment: September 5 , 1990 staff report
' c: Gary Ehret, BRW
I
I
I
CITYOF
11/441,0 ,4 CHANHASSEN
1
690 COULTER DRIVE • P.O. BOX 147• CHANHASSEN, MINNESOTA 55317
I F` (612) 937-1900 • FAX (612) 937-5739 Rte TIC Y Mmlfasttet'
Newt DC0/4'
MEMORANDUM ryoeHw!
TO: Don Ashworth, City Manager -&- °
Clete Se :. K u;''rn}sa:^
' FROM: Gary Warren, City Engineer
DKa j -!' c tr Coutel
DATE: September 5 , 1990
9-,o -9 o
' SUBJ: Award of Bids, Market Square 72-inch Storm Sewer Extension
Project No. 90-13
As will be recalled, Council authorized advertising for bids at
the August 13 , 1990 meeting. The project in question completes
the 72-inch storm sewer which lies along the southerly boundary
' of the Market Square property near the railroad tracks. This
project is necessary in order to better facilitate the site
development for Market Square and also to improve and minimize
' the safety hazards that the open ditch swale poses under
high-flow conditions.
Bids were opened on August 30, 1990 and two bids were received as
noted in the attached correspondence from BRW. We find the low
bid of $87 ,290 to be responsive to the solicitation. The City is
very familiar with Northdale 's work and we find this bid to be
' acceptable and within their capabilities.
It is therefore recommended that Improvement Project No. 90-13 be
' awarded to Northdale Construction in the amount of $87,290.
ktm
' Attachment: Letter from BRW dated September 5, 1990.
c: Gary Ehret, BRW
Todd Christopherson, AMCON
I
I
I
•
I
•
! V TRANSPORTATION
ENGINEERING
URBAN DESIGN
BRW INC THRESHER SQUARE • 700 THIRD STREET SOUTH 'MINNEAPOLIS.MINNESOTA 55415 • PHONE 612'370-0700 FAX 612/370-1378 I
•
September 5, 1990 I
Mr. Gary Warren, PE
City Engineer
City of Chanhassen
690 Coulter Drive
Chanhassen, MN 55317 1
RE: CONTRACT AWARD
MARKET SQUARE STORM SEWER EXTENSION PROJECT
CP 90-13
Dear Mr. Warren:
On Thursday, August 30, 1990, bids were received and opened for the above
referenced project. The bids which were received are as follows:
Bidder Amount
1. Northdale Construction $ 87,290.00
2. G.L. Contracting $ 95,861.00
Engineer's Estimate $ 91,075.00
All bids were submitted with proper bid guarantees in the amount of ten percent
P P 9 P
(10%) of the total bid price as required by the project specifications. A
tabulation was performed to verify the bid amounts, and both bids were found to
be correct. A bid tabulation summary sheet is attached for your information.
The original Engineer's Estimate presented to the City Council as a part of the
approval of the project plans and specifications was $99,500.00. Subsequent to
City Council approval , the Market Square developer expressed some concern
regarding the project cost, and suggested that a portion of the earthwork for the
project could be performed by his grading contractor. The project plans and
specifications were modified to include a reduction in the earthwork required for
the project, resulting in a reduction in our Engineer's Estimate to $91,075.00.
AN AFFILIATE OF THE BENNETT.RINGROSE.WOLSFELD.JARVIS.INC.GROUP
DAVID J BENNETT DONALD W RINGROSE RICHARD P WOLSFELD PETER E.JARVIS THOMAS F.CARROLL CRAIG A.AMUNDSEN DONALD E.HUNT MARK G SWENSON
JOHN B MCNAMARA RICHARD D.PILGRIM DALE N.BECKMANN DENNIS J.SUTLIFF JEFFREY L.BENSON RALPH C BLUM DAVID L GRAHAM GARY J ERICKSON
MINNEAPOLIS DENVER PHOENIX TUCSON ST.PETERSBURG SAN DIEGO I
i .
Mr. Gary Warren, PE
September 5, 1990
Page 2
The low bidder is Northdale Construction with a total bid price of $87,290.00.
The Northdale Construction bid is $3,785.00 below our Engineer's Estimate, a
difference of approximately four percent (4%) . Although only two bids were
received for the project, it appears that pricing was competitive.
Northdale Construction has been the contractor for other projects in which BRW,
Inc. , has been involved as well as for other projects in the City of Chanhassen.
We feel that they are an adequate contractor and are capable of performing the
' work required by this project. We, therefore, recommend award of the Market
Square Storm Sewer Extension Project, CP 90-13, to Northdale Construction for the
low bid price of $87,290.00.
• Subject to City Council approval , we anticipate commencing construction by
September 17, 1990. All work required by the project will be completed by
October 19, 1990. It should be noted that. this schedule assumes that Riley-
Purgatory-Bluff Creek Watershed and Soo Line Railroad permit approval will be
obtained by the developer prior to the scheduled start of construction. Any
' delay in permit approvals may impact the project schedule.
Please call if you have any questions, or if we can provide any additional
information.
' Sincerely,
BRW,
Gary A. Ehret, PE
Project Manager
GAE/lml
Attachment
cc: File 7-9019
1
1
?RW FILE: 7-9019
09/04/90
BID TAP SUMMARY SHEET
MARKET SQUARE STORM SEWER
EXTENSION PROJECT
CITY OF CHANHASSEN PROJ. 90-13
BID * CONTRACTOR SCHEDULE A Grand Total
1 NORTHDALE CONSTRUCTION CO. INC 87290.00 87290.00
2 G.L. CONTRACTING. INC. 95861.00 95861.00
•
N - - - r - N - NM MI MN EN 111111 EN I - -
OM NM UM I 111111 NM • ' NM I MN I IIIIII MI MN • M Mg ,-
•
s'
/ BID SCHEDULE A - STORM SEWER
l ITEM NO./ CONTRACT NORTHDALE CONSTRUCTIO G.L. CONTRACTING. INC
MNDOT NO. ITEM UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
' IF SALVAGE 72" APRON EA 2.00 750.00 1500.00 686.60 1373.20
2104.523 W/ TRASHGUARD
i 2/ SALVAGE EXISTING RIPRAP CY 100.00 5.00 500.00 10.30 1030.00
l 2105.533 CL II
3/ 72" RCP CL II LF 268.00 135.00 36180.00 154.30 41352.40
2503.541
` 4/ 33" RCP CL II LF 8.00 50.00 400.00 45.50 364.00
2503.541
5/ 12" RCP CLII LF 75.00 20.00 1500.00 20.80 1560.00
l 2503.541 .
6/ 12" RC APRON WITH EA 2.00 500.00 1000.00 425.80 851.60
2501.515 TRASHGUARD
7/ SPECIAL STORM STRUCTURE LS 1.00 12000.00 12000.00 23607.20 23607.20
L'. W/ CASTING
8/ PIPE SUBGRADE CORRECTIONLF 225.00 66.00 14850.00 47.20 10620.00
9/ STRUCTURE EXCAVATION CY 2000.00 1.50 3000.00 1.10 2200.00
l 2451.501 CLASS U
10/ GRANULAR BACKFILL (CV) CY 2000.00 6.50 13000.00 4.60 9200.00
2451.503
`
11/ STABILIZING AGGREGATE TN 300.00 7.50 2250.00 8.70 2610.00
2105.543
12/ SEEDING AC 0.80 1200.00 960.00 1122.00 897.60
2575.501
13/ EROSION CONTROL SILT LF 50.00 3.00 150.00 3.90 195.00
' FENCE, TYPE I
l ' .
. SUBTOTALS! 87290.00 95861.00
l
1.
1.
■