Loading...
1a. Site Plan for McGlynn Bakeries C 1 T O F PC DATE: 11/7/90 la+ \1 CHA1 'HAE1 CC DATE: 11/19/90 `1r CASE #: 88-3 SITE Olsen/k I ED I STAFF REPORT ilPROPOSAL: Conditional Use Permit and Site Plan for Expansion to the McGlynn Production Plant Facility IF— z VI 46 LOCATION: Southwest corner of Highway 5 and Audubon Road, Lot 1, Block 1, McGlynn Park k - r°_ ^r.1 r i El APPLICANT: McGlynn Bakeries, Inc. �`` ' I Q 1 McGlynn Drive t': _'__/C/i?3a____ Chanhassen, MN 55317 '� ` /i/7/t -_ ID:_111-9c IIPRESENT ZONING: IOP, Industrial Office Park IACREAGE: 37 acres IDENSITY: ADJACENT ZONING AND LAND USE: N -IOP, Vacant I Q S -IOP, Vacant E -IOP, Chanhassen Lakes Business Park QW -A-2, Vacant IWATER AND SEWER: Water and sewer is available to the property. IW PHYSICAL CHARACTER. : The subject property is currently developed I. with the McGlynn _Warehouse and Food Processing facility. The site slopes to the south towards the Milwaukee Railroad Tracks. I 2000 LAND USE PLAN: Industrial I , II 11 11 McGlynn CUP and Site Plan November 7, 1990 Page 2 ' SUMMARY The applicant is requesting approval for expansion to the ' conditional use permit and site plan for the addition of a 53,000 sq. ft. production area and a 3,600 sq. ft. refrigeration/equipment room. The production plant addition is located south of the ' existing production plant and east of the office area. The refrigeration equipment room is located on the northeast corner of the existing production plant. ' The applicant is also in the process of expanding the parking area located at the southerly portion of the site which was approved administratively by the Planning Director. The applicant .is providing screening for both the parking lot expansion and the plant expansion. The applicant is maintaining all of the existing setbacks. The expansion is also consistent with the City's ' original approval of McGlynn's when several conceptual building expansions were illustrated. Site access and utilities will remain unchanged. The building expansions meet the requirements of the IOP District and staff is recommending approval of the site plan ' and conditional use permit with appropriate conditions. BACKGROUND ' On April 11, 1988, the City Council approved a conditional use permit request for food processing facilities and site plan review ' for the McGlynn Bakeries located at the southwest corner of Highway 5 and Audubon Road (Attachment #1) . The applicant then revised the building layout to support a different type of food processing than what was proposed originally and also proposed to subdivide the ' 69.7 acre parcel into one lot and two outlots. Since the applicant had already received the conditional use permit for food processing, staff did not require the applicant to go through ' another conditional use permit. The original plan for food processing resulted in a fresh food product. The new plan resulted in a frozen food product. Since the site plan had been amended, the applicant was required to receive an amended site plan approval. On August 8, 1988, the City Council approved the subdivision of ' 69.7 acres into one lot and two outlots and approved the amended site plan review for a 161,700 sq. ft. building for office, warehouse and food processing for McGlynn Bakeries (Attachment #2) . ' The site was developed in 1989. In October of 1990, Planning Director Paul Krauss approved an administrative site plan for a parking lot expansion for McGlynn ' Bakeries. The Planning Director found that the parking lot expansion constituted a minor amendment to the approved site plan and was consistent with prior city actions regarding the site. The I McGlynn CUP and Site Plan f November 7, 1990 Page 3 parking lot expansion did not require variances and did not represent a significant increase in the intensity of the use. The administrative approval was subject to several conditions (Attachment #3) . The Planning Commission was made aware of the administrative approval for the site plan expansion on September 19, 1990 (Attachment #4) . The parking lot expansion is located at the southwest corner of the site adjacent to the existing parking lot. Extensive berming and landscaping will screen the parking lot from views from the Timberwood residential neighborhood (located to the west) . Construction work on this' expansion is currently in process. A copy of the signed conditions of approval is attached as an appendix to this report. General Site Plan/Architecture The applicant is requesting approval for expansion to the conditional use permit and site plan for the addition of a 53,000 sq. ft. production area and a 3,600 sq. ft. refrigeration/equipment room. The production plant addition is located south of the existing production plant and east of the office area. The refrigeration equipment room is located on the northeast corner of the existing production plant. The total lot coverage with the addition to the production plant and parking area is 30.7% impervious surface. The IOP District allows a maximum of 70% impervious surface coverage. The building height will be maintained at it's existing height of 28 feet and all existing setbacks are being maintained with both the plant expansion and parking lot expansion. The building addition will be made of the same material as the existing production plant. In fact, it will be constructed by relocating pre-cast concrete panels from the existing exterior wall on the south side of the building to the southerly exterior wall. Since the plant expansion is further screening the views of the office area staff has no objection to this in principal, however, we are concerned with the visual impact of the large blank wall that is eseentially devoid of architectural interest. The west facing office component is architecturally acceptable but it is overshadowed by the size of the high bay section of the building. Staff is recommending that the applicant propose some means of extending some of the architectural features of the office portion of the building along the southerly and easterly wall of the plant addition. We believe that this can be accomplished by reliance on the creativity of the project architect. We do not wish to limit this creativity but believe that something more than painting should be employed. I McGlynn CUP and Site Plan November 7, 1990 . Page 4 ILandscaping ' The applicant is proposing additional landscaping around the new and existing parking lot to further screen the parking area from the south. Staff is recommending that the Colorado Green Spruce be extended along the south entrance leading to the southerly parking ' lot to provide additional screening of the parking area and the new addition to the building. The landscaping that is being proposed by the applicant meets or exceeds the landscaping requirements of ' the ordinance. Acces JParkina ' The site plan expansion is maintaining the existing access points from the site to Audubon Road. As mentioned earlier, the parking lot is being expanded for a total of 464 parking spaces. The ' parking spaces required by the Zoning Ordinance is 290, therefore, the applicant is greatly exceeding the required parking stalls required by the ordinance. However, they believe that this level ' of parking is required to meet their operational needs. Utilities No new public utility service will be required to serve the addition. Existing water and sewer lines will need to be relocated out of the path of the new expansion. These are private lines and ' the relocation will be designed to meet city standards. Grading/Drainage ' The bulk of site grading and drainage issues were addressed during staff's administrative review of the parking lot expansion. ' COMPLIANCE TABLE - IOP DISTRICT Ordinance Proposed ' Building Height 4 stories 1 story ' Building Setback N-30' E-30' N-45' E-158 ' S-10' W-10' S-+500' W-362 ' Parking stalls 290 stalls 464 stalls Parking Setback N-30' E-30' N-45' E-300' S-10' W-10' S-+500' W-362 ' Lot Coverage 70% 30.7% Lot Area 1 acre 37 acres I McGlynn CUP and Site Plan I November 7, 1990 Page 5 PLANNING COMMISSION UPDATE On November 7, 1990, the Planning Commission unanimously recommended approval of the McGlynn Conditional Use Permit and Site Plan Amendment with Conditions #2-#6 of the staff recommendation. Condition #1 was revised to reflect the new plan provided by the applicant and recommended for approval by staff, which provided extensive landscaping with large evergreens and deciduous trees along the southerly building wall of the production plant expansion. The landscaping was provided instead of changing the architectural features of the building which was initially requested by staff. The proposed landscaping will break up the expanse of the building wall and will resolve staff's concerns with the visual effect of the proposed expansion. At the November 5, 1990, City Council meeting, it was discussed whether or not the Council felt comfortable with staff permitting the footing permit to be issued to McGlynn to commence the expansion to the facility prior to the applicant receiving final approval from the City Council on November 19, 1990. The City Council agreed that the footing permit could be issued if the Planning Commission recommended approval of the conditional use permit and site plan and that no significant changes were made to the plan. Since the Planning Commission unanimously approved the requestand staff was comfortable with the landscaping provided to break up the expanse of the southerly building wall, staff did allow the footing permit to be issued prior to final approval by the City Council. The footing permit was issued with the City receiving a letter of credit to cover all improvements for the expansion, including the required landscaping. I RECOMMENDATION The site plan and conditional use permit expansion conforms to the requirements of the ordinance and staff is recommending approval. "The City Council approves Site Plan #88-3 and Conditional Use Permit #88-2 for McGlynn Bakeries for expansion to the production plant area and refrigeration equipment room as shown on the site plan dated October 16, 1990, with the following conditions: 1. The applicant provide staff with a plan indicating how the landscaping features of the office will be extended to the production plant addition. 2. The applicant shall provide additional Colorado Green Spruce along the south entrance leading into the southerly parking • lot. 1 11 • 11 McGlynn CUP and Site Plan November 7, 1990 Page 6 ' 3. Comply with conditions of approval of staff's administrative approval of the parking lot expansion (attachment) . ' 4. The applicant shall obtain and comply with all conditions of the Watershed District permit. ' 5. Working hours shall be between 7:00 a.m. and 6:00 p.m. , Monday through Saturday with no work allowed on Sundays or holidays. 6. To guarantee compliance with the conditions of approval, the ' applicant shall furnish the City with a letter of credit from a bank or a cash escrow in the amount of $6,000. The security will be released by the City upon satisfaction that the ' conditions contained herein have been complied with. " ATTACHMENTS 1. City Council minutes dated April 11, 1988. 2. City Council minutes dated August 8, 1988. 3 . Administrative approval of parking lot expansion. 4. Planning Commission minutes dated September 19, 1990. 5. Memo from Dave Hempel dated October 31, 1990. 6. City Council minutes dated November 5, 1990. 7. Planning Commission minutes dated November 7, 1990. 8. Letter to Mr. John Prichard dated November 9, 1990 and letter of credit. 9. Site plan dated October 16, 1990. • I 1 I I , N. -. it CHANHASSEN CITY COUNCIL II REGULAR MEETING IFAPRIL 11, 1988 Mayor Hamilton called the meeting to order. The meeting was opened with the II Pledge to the Flag. COUNCILMEMBERS PRESENT: Councilman Geving, Councilman Boyt and Councilman I Johnson COUNCILMEMBERS ABSENT: Councilman Horn II STAFF PRESENT: Don Ashworth, Barbara Dacy, Larry Brown, Lori Sietsema and Roger Knutson I APPROVAL OF AGENDA: Councilman Geving moved, Mayor Hamilton seconded to approve the agenda as presented with the addition by Councilman Boyt of a citywide trash pick-up under Council Presentation. All voted in favor and motion carried. CONSENT AGENDA: Mayor Hamilton moved, Councilman Geving seconded to approve II the following consent agenda items pursuant to the City Manager's recommendations: II IL ' a. Conditional Use Permit Approval for Food Processing Facilities and Site Plan Review for McGlynn Bakeries. C. First Reading of Rezoning, Subdivision and II 9 Wetland Alteration Permit Approval for Minnewashta Meadows, Gary Carlson. II1. Resolution #88-28: Mi.nnewashta Meadows Subdivision Petition for Public Improvement File No. 88-2. e. Resolution #88-29: Cable Television, Request to Transfer Ownership. I f. Resolution #88-347: City Hall Expansion: 1) Approval of Plans and Specifications II 2) Authorize Bids 3) Approve Architectural Agreement I g. Accounts Payable dated April 11, 1988 • i. City Council Minutes dated March 28, 1988 1 Planning Commission Minutes dated March 16, 1988 All voted in favor and motion carried. I 1...: CONSENT AGENDA: (B) SUBDIVISION AND WETLAND ALTERATION PERMIT APPROVAL, LAKE RILEY WOODS SOUTH, GEORGE NELSON ASSOCIATES. II Barbara Dacy: It's obvious from the staff update that we wanted to follow up on the street connection issue regarding this subdivision with the adjacent II subdivision to the west. That being Great Plains Golf Estates. Larry Brown 1 II 28i 11 O ANTSSEN CITY COUNCIL REGULAR•MEETING AUGUST 8, 1988 I - Mayor Hamilton called the meeting to order. The meeting was opened with the ' Pledge to the Flag. COUNCILMEMBERS PRESENT: Councilman Boyt, Councilman Horn, Councilman Ceving and Councilman Johnson ' STAFF PRESENT: In Ashworth, Roger Knutson, Gary Warren, Larry Brown, Barbara Lacy, Jo Ann Olsen, Jim Chaffee and Todd Gerhardt ' APPROVAL OF AGENDA: Councilman Johnson moved, Mayor Hamilton seconded to approve the agenda as amended with the following additions: Councilman Geving wanted to discuss communications under Council Presentations and to move item 7 ' to the first item after Visitor Presentation; Councilman Horn wanted to discuss streets; Councilman Hoyt wanted to discuss the carousel building and building construction hours; and Mayor Hamilton wanted to discuss the Brooks Superette parking area. All voted in favor and the motion carried. CONSENT AGENDA: Councilman Horn moved, Councilman Geving seconded to approve the following Consent Agenda items pursuant to the City Manager's recommendations: b. Approval of Liquor Licenses: 1. Brooks Superette, 594 West 78th Street, Off-Sale Non-intoxicating License. 2. Chanhassen Rotary Club, On Sale Temporary Beer License. ' c. McGlynn Bakeries, Southwest Corner of Highway 5 and Audubon Road: • 1. Subdivision Request to Subdivide 70 Acres into One Industrial Lot and ' Two Outlots. 2. Site Plan Review for a 161,700 Sq. Ft. Building for Office and Food Processing. d. Approval of Conditional Use Permit to Construct an 80 sq. ft. Pylon Sign, SuperAmerica Station, 615 Flying Cloud Drive. g. Zoning Ordinance Amendment to Provide Minimum Building and Parking Setbacks for Business, Commercial and Industrial Lots Adjacent to Railroads and Residential Zoning Districts. j. Final Plat Approval, George Way. ' • 1. Approval of Accounts. • m. City Council Minutes dated July 25, 1988 Park and Recreation Commission Minutes dated July 26, 1988 All voted in favor and the motion carried. 1 I CITY OF „iO4,0„ 1 _, _ .0 , CHANHASSEN 1 ,‘,,,,,., . 690 COULTER DRIVE • P.O. BOX 147• CHANHASSEN, MINNESOTA 55317 (612)937-1900 * FAX (612) 937-5739 I October 15, 1990 1 I Mr. Scott Harri VanDoren Hazard Stallings I 3030 Harbor Lane No. , #104 Plymouth, MN 55447 Dear Mr. Harri: I I have reviewed your submission for administrative site plan approval for the parking lot expansion for McGlynn Bakeries. Under ' the authority granted me by the Zoning Ordinance, I hereby approve Site Plan #88-3 based upon my findings that it constitutes a minor amendment to the approved site plan and is consistent with prior I City actions regarding this site. We further note that the new approval requires no variances and does not represent a significant increase in intensity of use. Our approval is subject to adherence to the following conditions: I 1. The applicant shall install all berming and landscaping to screen the lot in accordance with the approved plans. A I letter of credit has been received in the amount of $211,346.00 to cover the costs of the improvements. 2. The applicant shall supply storm sewer design calculations to I the City Engineer for review. 3. All sanitary sewer manholes shall be constructed with internal I chimney seals. 4. Erosion control fence shall be modified to Type III (hay I bales, silt fence and snow fence) . All erosion control measures shall be placed prior to commencement of any grading and once in place shall remain in place throughout the II duration of the construction until established vegetative cover has been produced, at which time the removal shall be the responsibility of the applicant. 5. Relocation of sanitary sewer and water lines shall be inspected by the City or by a representative appointed by the City. The applicant shall be responsible for all inspection I 1 11 11 Mr. Scott Harri October 15, 1990 Page 2 fees related to the said relocation of sanitary sewer and Iwater lines. 6. The applicant shall obtain and comply with all conditions of a Watershed District permit. 7. Working hours shall be between the hours of 7:00 a.m. and 6:00 p.m. with no work allowed on Sundays or holidays. 8. Sanitary sewer and water lines shall be tested in accordance with City of Chanhassen specifications. I 9. The letter of credit supplied, as outlined above, shall also cover the compliance with Engineering conditions of approval and shall be used to cover inspection fees. I10. This approval is limited to the work illustrated on plans dated October 1, 1990. No other work is authorized or IIapproved. II (2X//4,1/- 7e.4)-14-4-147LAI Paul Krauss, AICP Scott Harri IIPlanning Director for McGlynn Bakeries k4? I Date cc: Michael McGlynn II I II I I 1 • . I CITY OF 411101r. 1k*,iii f CHANHASSE N 1 - 690 COULTER DRIVE • P.O. BOX 147• CHANHASSEN, MINNESOTA 55317 I(612) 937-1900 • FAX(612) 937-5739 I MEMORANDUM TO: Paul Krauss, Director of Planning I FROM: Dave Hempel, Sr. Engineering Technician At?( DATE: October 12, 1990 1 SUBJ: Review of McGlynn Bakery Parking Lot Expansion and I Utility Relocation LUR 90-29 • Upon review of the grading, drainage and utility plans prepared II by Van Doren-Hazard-Stallings dated October 1, 1990, I offer the following conditions for approval: I 1. The applicant shall supply the storm sewer design calculations to the city engineer for review. 1 2 . All sanitary sewer manholes shall be constructed with internal chimney seals. 3 . Erosion control fence shall be modified to Type-III (hay I bales , silt fence and snow fence) . All erosion control measures shall be placed prior to commencement of any grading I and once in place shall remain in place throughout the duration of the construction until established vegetative cover has been produced, at which time removal shall be the II responsibility of the applicant. 4. Relocation of sanitary sewer and water lines .shall be inspected by the City or a representative appointed by the I City. The applicant shall be responsible for all inspection ' fees related to the relocation of said sanitary sewer and water lines. , 5 . The applicant shall obtain and comply with all conditions of the Watershed District permit. 6 . Working hours shall be between the hours of 7:00 AM and 1 6 :00 PM with no work allowed on Sundays or holidays. I 11 1 Paul Krauss October 12, 1990 Page 2 7 . All sanitary sewer and water lines shall be tested in accordance with the City of Chanhassen 's specifications. ' 8 . To guarantee compliance with the conditions of approval, the applicant shall furnish the City with a Letter of Credit from a bank or cash escrow in the amount of $6,000.00. The ' security will be released by the City upon satisfaction that the conditions contained herein have been complied with. ' jms c: Gary Warren, City Engineer Charles Folch, Assistant City Engineer ., 1 • 1 I Planning Commission Meeting September 19, 1990 - Page 16 possibly 5:30 or 6:00 and we'd have the board set up so people could come in and ask questions and get an understanding for what's happening . I would work with the newspapers so the newspapers understood . Again reiterated the process and told people what 's changed since the last time so they can see if their question's been resolved or not. ' Conrad: So when you worked with the newspapers, you 're going to show, they could carry a map showing the final . They show a map? Krauss: I 'm hoping they can. It 's tough for them to transcribe that to a scale that they can print . I 'll work with them on that. In fact I 've got one of the reporters coming in here tomorrow . I Batzli : Full page . Krauss: Well that 's what it would take . ' Batzli : So in black and white you'd be able to tell the different zones . Krauss: They probably would ask us to pay for that . We could do that . I 'll try to find out what that will cost . We'll do that . Now, one of the reasons for the delay , last time we met I gave you a copy of the memo that ' was our response to the Metro Council . We've been doing follow up work with that . I 'm not sure if we had met . Yeah, we did with Rich Thompson prior to the last meeting . I 've been in contact with Rich and he has set up a meeting here with about 5 or 6 Metro Council staff people next Monday afternoon . What we hope comes out of that is a better understanding of where everybody 's coming from . What the issues are . What we 've done and how we 've arrived at everything and then we 're going to give them a tour oll the community because it's a safe bet that most of them haven't seen it . The meeting with Mr . Thompson last week or 2 weeks ago went very satisfactory in terms of his open mindedness in how this could proceed . I think that if we shoot for that October 24th date, we will at least have a II comfort of knowing that this meeting is behind us and that hopefully we 've gotten some , if not agreement, understanding from the Metro Council on I where we 're coming from on this thing. Now I know we discussed that last time and we 're not waiting for them to say yeah or nay on our plan and I don't think we have any intention of asking you to change that but I 'd lik to get this meeting out of the way. Steve Keefe is also having a breakfas meeting out here . The Chair of the Metro Council is coming out here next week . The Mayor 's involved with both of these meetings. Marcy Waritz , our Council representative will be probably at both of these meetings as well . 111 Conrad: That sounds real good Paul . I 'm impressed with all that activity . Krauss: If we went to October 24th, does that meet your needs as well? It's an alternate Wednesday night . Would you prefer , I can have Vicky giv a call around . Conrad: Now that's MEA weekend. But MEA doesn't start until Thursday. , Krauss: Is that one of the conditions. . . I Conrad: Well I 'm going to take some time off. I Planning Commission Meeting September 19 , 1990 - Page 17 Batzli : What better way to spend your time off. Relax . Krauss: If that doesn 't work let me know and, our agendaes are obviously getting somewhat light . Now we 've got some items in the pipeline but maybe we can jungle a meeting or possibly even a cancel a regular meeting and ' shift some stuff to a later one and just hold it because clearly we have to have a dedicated meeting for the comprehensive plan. ' Emmings: Or what 's the regular meeting date proceeding that October 24th? October 17th. Maybe that regular meetinb could be the. Conrad: Let me check on my schedule. ' Krauss: I 'll have Vicky contact everybody on the Planning Commission tomorrow so we can check that out . And I think that does it for me . One last thing . We had an item here from McGlynn's and I told you I 'd try to tell you in advance if we had any administrative site plan approval that may be coming down the pipe . McGlynn's is adding employees at a rapid clip .; and has run out of parking spaces and needs to expand their parking lot . Emmings: Another one? Olsen: They have room to do it . Krauss: Except they have room to do it , yeah . I 've worked with them and .' we 've sort of clapped out a plan for how they could get sufficient stalls to get them through the winter simply by, it doesn't take a lot of grading but it 's an add on to some parking lot that they have now . I would be requiring a landscaping plan for buffering from Timberwood and all that . I ' think the parking lot expansion itself is fairly innocuous and falls within the perview of administrative approval . You should be aware though however that McGlynn is doing a box office business there and is going to be advancing their construction schedule and expansions . They will also be coming in probably in a meeting later in November for a site plan approval for a fairly significant building expansion. Emmings: Is this on their frozen stuff like this? Krauss: Well apparently what this is for , as I understand it , and I don't ' know if this was trade secret or not I 'm giving away but they got a large contract to supply breakfast pastries to 60% of the Burger Kings in the world and it 's a new product and they need to expand to accommodate that . ' Now the parking problem that they have is a problem they're experiencing now with their staff without the expansion which is why I feel I can do that under administrative approval . They will need a larger parking lot for this building and that will all come down to your approval of the site plan. Emmings: Do you think we need to scale up our parking requirements for these growing businesses? Krauss: That's like so many things we do Steve. It falls into the category of they're each so different that you can't guess . It really is tough. 1 Planning Commission Meeting September 19, 1990 - Page 18 1 Emmings: Who knows they're going to get a contract for 60% of the Burger Kings or something? I mean no, it's something like that that does it • probably . Krauss: Even from business to business you know. When we worked with PMTII Al Iverson was in here last week talking about parking on the property next" door . Well , Al 's had a very significant parking problem on his site which we 're trying to take care of with his new addition and that's because his employment grew by leaps and bounds and he's got a medical products assembly function where you tend to pack more people in a building . Emmings: Maybe what we have to do is say our parking requirements are I going to remain the same but we also want to be sure that you 've got some land you can expand parking into should you need it . I mean maybe we have to have some kind of a set , be able to show something to set aside to get some more parking on there because , now it 's come up 3 cases that I know o so it must mean something 's not working right . Krauss: Well I don 't know. I think by and large the parking standards have worked fairly well . It 's the exceptional ones that throw you and whe� a business is growing as fast , I mean Tim can explain this phenomenum more than I but when you 're growing that fast , you don't have the capital to IN expand facilities and you tend to get the people on and the product out anil you 're cramming more and more into the site . It gets ahead of the construction aspect of it . Conrad: Okay. Anything else on that subject? Paul has a note to us . Metro Council rural development standards. Tim, did you get a chance to review that? ' Erhart: Yeah, and I was real excited about it. I think we've finally found something out of Met Council that they 're seeing what 's happened will this 2 1/2 acre lot and I think they've got a move in the right direction here and according to Paul , I guess this is already an adapted policy change . Conrad: So if we like the concept of this, what do we need to do? Krauss: I think you need to put it on a work program and tell us to bring ' back something to you that would bring that about. I mean it's clearly going to require a change in the ordinance and may require a change to some of our policies . I would want to speak to, this came from Carl Loren who I 've never been quite clear as to his title but he's fairly high up in the heirarchy at the Metro Council . I 'd like to confirm some things with him because this is, they are talking about rural development issues. Rural area development issues and this policy is probably going to be refined in that case but you may have read in the paper that Anoka County is basicall thumbing their nose at the Metro Council . They're also telling the Metro Council that their policies are wrong because their policies, for them, II because the policies were designed in the interest of protecting farmland and Anoka County was never known for it's farmland. But Anoka County, you 've got some of the communities up there who never anticipate developin at suburban densities. They're perfectly content to continue developing with hobby farms and that kind of thing and since they don't want any sewe and theoretically don't want any roads , they can pretty much tell Metro CITY OP CHANHASSEN 690 COULTER DRIVE CHANHASSEN, MN 55317 (612) 937-1900 DEVELOPMENT REVIEW APPLICATION APPLICANT: Van Doren Hazard Stallings OWNER: McGlynn Bakeries ADDRESS: 3030 Harbor Lane North, #104 ADDRESS: One McGlynn Drive Minneapolis, MN 55447 Chanhassen, MN 55317 TELEPHONE (Day time) 553-1950 TELEPHONE: 474-7444 REQUEST ♦ Conditional Use Permit - $150 ♦ Subdivision: ♦ Interim Use Permit - $150 Preliminary Plat: ♦ Land Use Plan Amendment - $100 - Sketch Plan - $200 ♦ Planned Unit Development: - Create less than 3 lots - $100 - Sketch Plan - $200 - Create more than 3 lots - $100 + $15 acre + $5 per lot - Preliminary Development Plan lot created $300 + $15 acre - Final Plat - $100 - Final Development Plan - $200 - Metes and Bounds - $100 - Amendment to Final Development Plan - $300 + $15 acre - Consolidate Lots - $100 TOTAL PUD TOTAL SUBDIVISION ♦ Site Plan Review - $150 ♦ Wetland Alteration Permit: ♦ Administrative Site Plan - Individual Single Family Review - $150 X Lots - $25 ♦ Vacation of Utility or - All Others -- $150 Street Easement - $100 ♦ Variance - $75 ♦ Rezoning - $250 ♦ Zoning Appeal - $75 ♦ Zoning Ordina.r,e Amendment - No Chwe A list of all property owners within 500 feet of the boundaries of the property must be included with the application. Twenty-six full size folded copies of the plans must be submitted. * NOTE - When multiple applications are processed, the appropriate fee shall be charged for each application. CHANHASSEN PLANNING COMMISSION REGULAR MEETING NOVEMBER 7, 1990 • Chairman Conrad called the meeting to order at 7:38••p.m . . • MEMBERS PRESENT: Steve Emmings , Ladd Conrad, Brian Batzli , Jim Wildermuth and Joan Ahrens MEMBERS ABSENT: Tim Erhart and Annette Ellson STAFF PRESENT: Paul Krauss , Planning Director ; Jo Ann Olsen, Senior Planner ; and Sharmin Al-Jaff , Planner 1 PUBLIC HEARING: SITE PLAN AMENDMENT FOR MCGLYNN BAKERIES TO ADD A 52,972 SQUARE FOOT MANUFACTURING ADDITION AND A 3,600 REFRIGERATION EQUIPMENT ADDITION TO THE EXISTING BUILDING ON PROPERTY ZONED IOP AND LOCATED AT ONE MCGLYNN DRIVE. Jo Ann Olsen presented the staff report on this item . Krauss: There 's one additional thing I might add too . The applicant is attempting to get the building in the ground expeditiously . They have a rapid work schedule and we tried to be accommodating with that . What they would like to do is be able to put the foundation of the building in early . What we 've come to accept , if you 're willing, is basically this . If the review goes through smoothly tonight for their application , we discussed this with the City Council on Monday. The City Council , assuming everything goes well here , is willing to allow staff to issue a foundation permit which would be totally at the builder 's risk should the Council come up with new conditions but it would allow them to get into the ground starting next week . The Council will have final say on the site plan itself . We 'll get it on the next meeting but because of the schedules that we have coming up , because of the holidays , they would lose sufficient time that they probably wouldn 't be able to get the building started this week. Again, this is all contingent upon a successful review here tonight but the Council was willing to go along with that . Conrad: Jo Ann, what 's the new building versus the old building on that? Olsen: The gray area . . . Conrad: Okay , good . Thanks. We'll open it up for comment. If people from McGlynn would like to make a presentation, we'd start it off with that . Scott Harri : Thank you Mr . Chairman. Thank you staff . My name is Scott Harri and I 'm from Van Doren, Hazard, Stallings. Our role in the project has been to prepare the submittal that you have before you in part and as co-authored with the applicant 's architects , .Setter , Leach & Lindstrom . With us tonight is , on my far right is Dan McGlynn with McGlynn Bakeries . Dick Erickson with Setter , Leach & Lindstrom and Tom Roberts with C .F . Haglund. C .F . Haglund is the construction manager and contractor for McGlynn Bakeries on the project and as I mentioned, Setter , Leach is doing the architectural work on the project . We'd like to show you , as staff had mentioned. . . If you look at this top elevation you will see the trees and plantings that we would be proposing as an alternate means to 1 Planning Commission Meeting November 7 , 1990 - Page 2 satisfy. . .as staff had indicated earlier . . . What we 're proposing on this thing in order to bring down the height and massing of the building itself is we're proposing I guess an alternating section of. evergreen trees that would be approximately 14 to 16 foot in height interspersed with deciduous trees which would lend I guess year round, a variety of color to that wall and hopefully reduce the long distance type of concerns that staff had indicated. Secondly, what we would like to do and the other thing that Jo Ann had mentioned was as part of the project evolving beyond the submittal , what you 've seen there is the architectural development of a smoking shelter and outdoor break area . To that extent the contractor would like to build most of the surface improvements out there this fall if possible , if weather permits . Thus we 've moved ahead with some of the design and I would like to have Dick Erickson I guess make a very brief presentation on what that feature looks like . At this point we 've got some architectural I drawings , so Dick? And then following what , he's got some perspectives and then I have a site plan that shows what the surface improvements and landscaping would be in that area . Dick Erickson: On the existing south side of the office , this is a thumb nail sketch of the office . . .in the background . We 're developing. . .and canopy and under the canopy a small enclosed shelter where employees can come out at their break and have a cigarette . This shelter is there because after relatively . . .It 's actually and enclosed glass area not too dissimilar to a city bus stop . The canopy will project out . . .across the canopy as a roof element and then the glass portion of the enclosure would be . . .color on the first and second level and in the corner of the office here there are two major . . .and we 're using that same idea . . . I just wanted to give you an orientation. This canopy area again is right by this triangular area shown on the plan right here . Sitting in this I guess open space . What we have proposed for that area is, in that nitch right there , the canopy area . . .right here the main entrance to a large employee lockers . . .through this sidewalk system right in here . There 's an outdoor patio area here with picnic tables on it surrounded by some landscaping . There 'd be a large berm that we had built over here to somewhat screen this lower level break room and lunch room from the parking lot here so the views are somewhat protected from the lower level of the building so this sidewalk system over here will just be kind of a . . .supplements the packet and submittal and comments that staff has made. I think Dan would like to say a few words . . Dan McGlynn: Good evening. I 'm Dan McGlynn from McGlynn Bakeries. I just I wanted to come up and say hello. I haven't been to a Council meeting yet or Planning Commission yet. My brother 's been handling most of that. I just want to say that we 've really enjoyed our move in to Chanhassen. Because of the way we were structured in Eden Prairie , we were forced to look for other places to build. Chanhassen has been a great spot so far and everyone with the city has been more than accommodating for us to grow as fast as we 'd like to . We 're experiencing some very rapid growth in our company . Moving in just in December for the offices and a little bit of production in November , it 's amazing to us that we 're already asking to add on to our building since we weren't expected to need that space for another 5 years and it looks like we'll use the space very quickly with our fast growth but we 've now got over 300 employees. It 's become a major campus for us and we really appreciate what the City's .done to accommodate us in being able to maintain our fast growth because without that , we'd be in 1 I Planning Commission Meeting November 7 , 1990 - Page 5 concern about some lighting. Unshielded lighting that was directed towards ' their neighborhood . We addressed the lighting . We asked the project manager to change those fixtures which they did and we've not since heard anything on the odor . Wildermuth: Okay . It looks like a good project to me and it's nice to seel somebody doing well enough to expand . Batzli : I think I just have two questions . I like the addition and the report and I like the landscaping here. I think that'd be attractive and it's nice to see some break in the evergreens. My question was , there's a 4 difference in plans and there's a large dollar figure in your administrative approval . The question is, they 've given a letter of credit to the City apparently to cover the cost of the berming and landscaping . Does that change at all with what they 've got here? Krauss : There 's going to be an increment , yes . Olsen: Another letter of credit . J Batzli : An additional letter of credit? But that 's in addition to the $6,000.00 one is it not? Krauss: The one that we have now covers the parking lot installation and the buffer of that . What we 're looking at to get to now is the incremental ! cost of landscaping that 's being proposed specifically around the building proper . Olsen: It 's an addition to the $6 ,000.00 though too for this part of the I project . What you 're looking from Dave 's memo? Batzli : Right . But there was in the administrative approval we got a letter of credit for $211 ,000.00? Olsen: They essentially covered the cost of all of that . Batzli : Right . And so there would be an additional letter of credit after that? Okay . Do we need to do something in our approval? Krauss: No. It 's in the zoning ordinance now. It's done as a matter of routine . Batzli : Okay. And there was apparently some plans submitted to you for the grading dated a different date than the plans we have . Were those changed at all in our plans? Krauss: No . Batzli : Okay . Those were the only two questions. Emmings: I don 't have anything additional . What 's here seems reasonable to me . Conrad: The landscape plan here that was presented tonight , that falls on the south side of the parking lot? Planning Commission Meeting 9 November 7 , 1990 - Page 6 Olsen: ' The building . ' Conrad: Of the building? Olsen: Right up against the wall . Conrad: So the landscape plan that I see in the packet , this is in addition to what , the landscape plan in the packet so we really have sheltered , okay . There are no berms on the south side of the parking lot . I don 't know what addition has been put on the parking lot . How much has been put there? Are we talking big addition or small addition? I don't rhave a clue . Olsen: On the parking lot side? rConrad: Yes . Olsen: Yeah . It 's kind of see where the original one ended here? ' Conrad: Yeah . Okay , to the west . Okay , show me the new stuff . What's new? All that? Okay . Olsen: And the berming , it just drops right down. Down into that little area . ' Conrad: Right . So we haven't asked for berming . We've asked for trees . Olsen: Yeah , lots of landscaping . Krauss: There is heavy berming and landscaping however along the west _elevation of the parking lot which faces Timberwood . Conrad: And that 's where I was going . Getting there kind of slow but . Olsen: Almost naturally right now . rConrad: So this is probably our only time that we can really get into any kind of concern with the westerly side right now? Olsen: They 'll be coming in for an expansion. Conrad: To the west? Olsen: Whole new building. . .so there 's a potential that there will be another building expansion to the west where at that point you would even ' landscape further . Conrad: But is the landscape plan to the west of the parking lot , is that ' the final landscape plan that will have their . The building may expand to the west but how about to the west of the parking lot? Are we looking at the final landscape plan for the shielding of the parking lot? Olsen: Of the parking lot? I Planning Commission Meeting November 7 , 1990 - Page 7 1 Conrad: More than likely . And that is right now trees and berm or what that? Krauss: There 's an extensive change in elevation. It's on the order of what Scott , 10 feet? Olsen: You can kind of see. . .and this is where there 's expansion . Right now we 're not . . . ' Conrad: Okay. Scott Harri : 'Right now this property slopes up on this side up here to a large plateau area and then slopes down about 10 feet from the elevation of this proposed parking lot over here. And then the trees would be inbetween the parking lot and this plateau area . ' Conrad: Okay , that helps . We 're all comfortable? Wildermuth: I particularly like the south treatment . Conrad: Jim , you brought up a good point on the smell . I 've never though that but it sounds like we've had one complaint . Emmings: I 'd have a comment on that . You may be getting a lot more complaints because I remember I read an article , this has to be 20 years I ago . Someone had done some studies in areas where they had bakeries in Europe and there were bakery smells in the air and they found that the birth rates around there were higher than they were and I think maybe we I should warn the Timberwood people . And I 'm glad I don 't live there . Conrad: Was there a serious side to that article? Emmings: No, it was serious . That study was probably funded by the military . Conrad: Anything else? Is there a motion? ' Wildermuth: I 'd make a motion that the Planning Commission recommend approval of site plan #88-3 and the conditional use permit #88-2 for McGlynn Bakeries for expansion to a production plant area and refrigeration equipment room as shown on the site plan dated October 16, 1990 with the following conditions 1 thru 6 . With the understanding that the letter of I credit and cash escrow amounts would be increased commensurate with. Krauss: Could we modify condition number 1 which implies that we were going with an architectural approach to the south elevation. That 's since I been surplanted by the landscaping plan. That the approval should be amended to include the landscaping along the south elevation that was presented to the Planning Commission this evening . Wildermuth: So incorporated . Conrad: Where do you want to incorporate that? i Olsen: In condition 1 . Planning Commission Meeting - November 7 , 1990 - Page 8 Wildermuth: Probably replacing the architectural features as landscaping ' features . Batzli : Second. ' Wildermuth moved, Batzli seconded that the Planning Commission recommend approval of Site Plan #88-3 and Conditional Use Permit #88-2 for McGlynn Bakeries for expansion to the production plant area and refrigeration ' equipment room as shown on the site plan dated October 16, 1990 with the following conditions: ' 1 . The applicant provide staff with a plan indicating how the landscaping features of the office will be extended to the production plant addition . 2. The applicant shall provide additional Colorado Green Spruce along the ' south entrance leading into the southerly parking lot . 3 . Comply with conditions of approval of staff 's administrative approval of the parking lot expansion ( Attachment ) . ' 4 . The applicnat shall obtain and comply with all conditions of the Watershed District permit . ' 5 . Working hours shall be between 7:00 a .m . and 6:00 p .m . Monday through Saturday with no work allowed on Sundays and holidays . 6. To guarantee compliance with the conditions of approval , the applicant ' shall furnish the City with a letter of credit from a bank or a cash escrow in the amount of $6 ,000 .00 . The security will be released by the City upon satisfaction that the conditions contained herein have ' been complied with . All voted in favor and the motion carried unanimously. ' PUBLIC HEARING: ZONING ORDINANCE AMENDMENT TO AMEND SECTION 20-263 (2), RECREATIONAL BEACHLOTS TO ALLOW PORTABLE CHEMICAL TOILETS ON RECREATIONAL BEACHLOTS. Public Present: ' Name Address Gene & Nancy Christensen 6561 Kirkwood Circle President , Minnewashta Creek Homeowners Association ' Sharmin Al-Jaff presented the staff report . Chairman Conrad called the public hearing to order . Nancy Christensen: I 'm Nancy Christensen and I live at 6561 Kirkwood Circle and I 'm the President of the Minnewashta Creek Homeowners Association and we earlier requested this variance and whatever else we asked for . I 've been working on this thing for a long time and I guess 1 • TYOF .11 IHASSEN u OX 147 • CHANHASSEN, MINNESOTA 55317 )3 900 • FAX (612) 937-5739 • 1 147 :redit No. 1039 1 :ount of McGlynn Bakeries, Inc. and in your 2r of Credit in the amount of $118,688.00 nc ent (#88-3) ft drawn on sight on the undersigned bank. to Bakeries wishing to apply under Letter of Credit No. 1039, dated Lr construction of the new rst Bank National Association. r :eiving final site plan and ►r ral by the City Council. On or City Manager of the City of Chanhassen. lanimously approved by the change to Condition #1 to t at 7001 France Avenue South, Edina, pi a adjacent to the south wall 2:00 p.m. on October 31 , 1991 . °• : of the wall. As stated in November 1, 1990, the City forth in full our understanding which shall :e hood that the proposal for amended, amplified, or limited by reference r odified by the City Council , or agreement, whether or not referred to refore, the City is willing roposed expansion with the t assignable. More than one draw may be made • __ Lon for the expansion prior to plan and conditional use be governed by the Uni form Customs and ,Y .tted solely at McGlynn's edits (1983 Revision), International Chamber that, if the City Council 400. p] a, any footing improvements an red or modified solely at t drawn under and in compliance with this uly honored upon presentation. to with the understanding that TION lanning Commission and City 1/0( tZ tant Viq President 1 I . , Van Doren LETTER OF TRANSMITTAL I Hazard Stallings, Inc. 3.0 „ate Loos North. DA TE/Yo V. ? /990 I NO. 67- *51-$o Waters ers Pfes Suite 104 / Minneapolis, Minnesoto 55447 ATTENTION I 612/553-1950 Jo Any 04.060, iv Ale/nil ,Bay .eriy . Air 7Q1fe m,f , ahcG I T0: Criv oi.. ChAn Izasseh Plarpf el palnsid h _ • WE ARE SENDING YOU XAttached ❑Under separate cover via the following items: ❑ Shop drawings 0 Prints 0 Plans 0 Samples 0 Specifications " ' ❑Copy of letter 0 Change order ❑ COPIES DATE NO. DESORPTION Ii C►19/r1Gt r e, jfi im AfG I I ITHESE ARE TRANSMITTED as checked below: ❑ For approval ❑Approved as submitted ❑Resubmit copies for approval 1 n For your use 0 Approved os noted ❑Submit copies for distribution ❑As requested 0 Returned for corrections ❑Return corrected prints I ❑ For review and comment 0 ❑FOR BIDS DUE 19 ❑PRINTS RETURNED AFTER LOAN TO US 1 REMARKS: I I I COPY TO: Very truly yours. VAN DOREN-HAZARD-STALLINGS, INC. ISIGNED: 7 Ca 4 H 4144. V melamine en rot•Mee./May ee i r et enee. I II II ENGINEERS ESTIMATE for MCGLYNN BAKERIES I PARKING LOT EXTENSION & SERVICE DRIVE (Additional Work Not Included in Administrative Approval) I UNIT ITEM QUANTITY PRICE AMOUNT GRADING Common Excavation 4000 C.Y. 2.50 10,000.00 Silt Fence 300 L.F. 2.50 750.00 II PAVING C1.5 Aggregate Base (Mod. ) 2276 Tons 8.50 19,346.00 1 100% Crushed 2331 Bituminous Base Course 376 Tons 30.00 11,200.00 2341 Bituminous Wearing Course 283 Tons 35.00 9,905.00 ' B612 Curb & Gutter 1100 L.F. 5.50 6,050.00 STORM SEWER 12" RCP 359 L.F. 20.00 7, 180.00 I Catch Basins 2 EA. 800.00 1,600.00 Manholes 2 EA. 1,000.00 2,000.00 LANDSCAPING I Sidewalk 1644 S.F. 1.50 2,466.00 Irrigation System Lump Sum 2,000.00 2,000.00 Rock Mulch 555 S.Y. 8.00 4,440.00 Plant Materials a. Parking Lot & Perimeter Lump Sum 4,000.00 4,000.00 b. Building Buffer Lump Sum 9,600.00 9,600.00 1 Sod 1685 S.Y. 2.00 3,370.00 Seeding 1.0 AC 2,500.00 2,500.00 IGHTING SYSTEM II Lighting System Lump Sum 2,500.00 2,500.00 r PROJECT TOTAL $98,907.00 1 L G ,er' e f orsd•f a0171-• — *' 1201, Eff• Cotirtr [ �C�, �b S, II ESTEXTSD.M44 I 1