7. Market Square 72 inch storm sewer extension 7
1
CITYOF
,, i
1 CHANHASSEN
'
690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317
1 (612) 937-1900 • FAX (612) 937-5739 kilo ay My 7Rfttfilsttmn°
liOne
V LLf-
MEMORANDUM 9ii~Pitocw
il TO: Don Ashworth, City Manager uor 9- &-'- 4)
( Gets Su -% _ :. 7,c. ,-is$k1
IFROM: Gary Warren, City Engineer 11
DATE: September 5 , 1990 a De. AFT/;c aago
I SUBJ: Award of Bids , Market Square 72-inch Storm Sewer Extension
Project No. 90-13
1 As will be recalled, Council authorized advertising for bids at
the August 13 , 1990 meeting . The project in question completes
I the 72-inch storm sewer which lies along the southerly boundary
of the Market Square property near the railroad tracks . This
project is necessary in order to better facilitate the site
development for Market Square and also to improve and minimize
I the safety hazards that the open ditch swale poses under
high-flow conditions .
I Bids were opened on August 30, 1990 and two bids were received as
noted in the attached correspondence from BRW. We find the low
bid of $87, 290 to be responsive to the solicitation. The City is
I very familiar with Northdale's work and we find this bid to be
acceptable and within their capabilities.
It is therefore recommended that Improvement Project No. 90-13 be
Iawarded to Northdale Construction in the amount of $87 ,290 .
ktm
IAttachment: Letter from BRW dated September 5, 1990.
c: Gary Ehret, BRW
ITodd Christopherson, AMCON
I
I
I
I
i . ,
r^r=."=-J 1 t 1 t.I PLANNING
TRANSPORTATION
ENGINEERING
URBAN DESIGN
IBRW-INC THRESHER SQUARE 700 THIRD STREET SOUTH MINNEAPOLIS.MINNESOTA 55415 PHONE 612'370-0700 FAX 612/370-1378
IISeptember 5, 1990
Mr. Gary Warren, PE
IICity Engineer
City of Chanhassen
690 Coulter Drive
IIChanhassen, MN 55317
RE: CONTRACT AWARD
I MARKET SQUARE STORM SEWER EXTENSION PROJECT
CP 90-13
IIDear Mr. Warren:
On Thursday, August 30, 1990, bids were received and opened for the above
Ireferenced project. The bids which were received are as follows:
IIBidder Amount
1. Northdale Construction $ 87,290.00
I2. G.L. Contracting $ 95,861.00
Engineer's Estimate $ 91,075.00
II
All bids were submitted with proper bid guarantees in the amount of ten percent
I (10%) of the total bid price as required by the project specifications. A
tabulation was performed to verify the bid amounts, and both bids were found to
be correct. A bid tabulation summary sheet is attached for your information.
IIThe original Engineer's Estimate presented to the City Council as a part of the
approval of the project plans and specifications was $99,500.00. Subsequent to
City Council approval , the Market Square developer expressed some concern
Iregarding the project cost, and suggested that a portion of the earthwork for the
project could be performed by his grading contractor. The project plans and
specifications were modified to include a reduction in the earthwork required for
IIthe project, resulting in a reduction in our Engineer's Estimate to $91,075.00.
IAN AFFILIATE OF THE BENNETT.RINGROSE.WOLSFELD.JARVIS.INC GROUP
DAVID J BENNETT DONALD W RINGROSE RICHARD P WOLSFELD PETER E JARVIS THOMAS F CARROLL CRAIG A.AMUNDSEN DONALD E HUNT MARK G SWENSON
JOHN B McNAMARA RICHARD D PILGRIM DALE N.BECKMANN DENNIS J.SUTLIFF JEFFREY L BENSON RALPH C BLUM DAVID L GRAHAM GARY J ERICKSON
MINNEAPOLIS DENVER PHOENIX TUCSON ST.PETERSBURG SAN DIEGO
II
Mr. Gary Warren, PE
September 5, 1990
Page 2
•
The low bidder is Northdale Construction with a total bid price of $87,290.00.
The Northdale Construction bid is $3,785.00 below our Engineer's Estimate, a
difference of approximately four percent (4%) . Although only two bids were
received for the project, it appears that pricing was competitive.
Northdale Construction has been the contractor for other projects in which BRW,
Inc. , has been involved as well as for other projects in the City of Chanhassen.
We feel that they are an adequate contractor and are capable of performing the
work required by this project. We, therefore, recommend award of the Market
Square Storm Sewer Extension Project, CP 90-13, to Northdale Construction for the
low bid price of $87,290.00.
Subject to City Council approval , we anticipate commencing construction by
September 17, 1990. All work required by the project will be completed by
October 19, 1990. It should be noted that this schedule assumes that Riley-
11
Purgatory-Bluff Creek Watershed and Soo Line Railroad permit approval will be
obtained by the developer prior to the scheduled start of construction. Any
delay in permit approvals may impact the project schedule. '
Please call if you have any questions, or if we can provide any additional
information. 1
Sincerely,
BRW,
Gary A. Ehret, PE
Project Manager
GAE/lml
Attachment ,
cc: File 7-9019 '
1
I NE I N I MN EN MN NE N EN 1 1
••
3RW FILE: 7-9019
09/04/90
DID TAB SUMMARY SHEET
MARKET SQUARE STORM SEWER
EXTENSION PROJECT
CITY OF CHANHASSEN PROJ. 90-13
BID # CONTRACTOR SCHEDULE A Grand Total
1 NORTHDALE CONSTRUCTION CO. INC 87290.00 87290.00
2 G.L. CONTRACTING. INC. 95861.00 95861.00
(
(
. i
J
( BID SCHEDULE A - STORM SEWER
t ITEM NO./ CONTRACT NORTHDALE CONSTRUCTIO G.L. CONTRACTING, INC
MNDOT NO. ITEM UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1/ SALVAGE 72" APRON EA 2.00 750.00 1500.00 686.60 1373.20 ,
2104.523 W/ TRASHGUARD
/ 2/ SALVAGE EXISTING RIPRAP CY 100.00 5.00 500.00 10.30 1030.00
t 2105.533 CL II
3/ 72" RCP CL II LF 268.00 135.00 36180.00 154.30 41352.40
2503.541
t 4/ 33" RCP CL II LF 8.00 50.00 400.00 45.50 364.00
2503.541
5/ 12" RCP CLII LF 75.00 20.00 1500.00 20.80 1560.00
2503.541
( 6/ 12" RC APRON WITH EA 2.00 500.00 1000.00 425.80 851.60
2501.515 TRASHGUARD
7/ SPECIAL STORM STRUCTURE LS 1.00 12000.00 12000.00 23607.20 23607.20
W/ CASTING
8/ PIPE SUBGRADE CORRECTIONLF 225.00 66.00 14850.00 47.20 10620.00
9/ STRUCTURE EXCAVATION CY 2000.00 1.50 3000.00 1.10 2200.00
( 2451.501 CLASS U
10/ GRANULAR BACKFILL (CV) CY 2000.00 6.50 13000.00 4.60 9200.00
2451.503
l
11/ STABILIZING AGGREGATE TN 300.00 7.50 2250.00 8.70 2610.00
2105.543
12/ SEEDING AC 0.80 1200.00 960.00 1122.00 897.60
2575.501
13/ EROSION CONTROL SILT LF 50.00 3.00 150.00 3.90 195.00
' FENCE, TYPE I
SUBTOTALS: 87290.00 95861.00
(