MEMORANDUM
TO: Don Ashworth, City Manager Cste ubmhed ,a evmni :inn
FROM: Jim Chaffee, Public Safety Director
1 Sete :submitted to COLMe$
DATE: June 7, 1989
1 SUBJ: Change Order No. 5 , Fire Station/City Hall Expansions
1 Please find attached Change Order No. 5 for the remodel and addi-
tion at the Fire Station and the addition at City Hall. These
items are either code required or items that will provide the
1 finishing touches to the completed project. This should be the
final change order to come through and will still be within the
budgeted funds.
1 Recommendation
It is the recommendation of staff to proceed with Change Order
1 No. 5 in the total amount of $3, 093 . 00 for the Fire Station and
City Hall to bring it up to code and final completion.
i
1
1
1
1
1
1
11
1
CHANHASSEN CITY HALL/CHANHASSEN FIRE STATION 11 PROJECT NO 87126/87146
A. FIRE STATION
II
Item No. 1 Reinstall the existing air
intake line for the air compressor II as directed by the Owner. Add $ 291 .00
Item No. 2 Installation of pad under carpet
at stairways; to increase life of II stair carpet. Add $ 67 . 00
Item No. 3 Add switch control to both the II relocated east light pole and the
west light pole. Add $ 446 . 00
Item No. 4 Update the existing basement
exhaust flue as required to
current building code
requirements Add $ 615 . 00
II
Item No. 5 Install dropped soffit headers
at room 214 and furring for roof II drain pipe at room 213. Add $ 197 .00
Item No. 6 Add 4 duplex outlets in room 204
and provide additional control
II
switch location for exhaust fan
EF-2 . Add $ 564.00
Item No. 7 Provide safety stops at the two II
existing overhead doors and three
additional radio receivers . Add $ 530 . 00
SUB TOTAL: FIRE STATION $ 2710.00 II
II
II
II
ATTACHMENT TO CHANGE ORDER NUMBER 5 1
s
i
DOW
B. CITY HALL:
Item No. 1 Install sound insulation above
ceiling as directed by owner. Add $ 183.00
Item No. 2 Apply cement finish to exposed
concrete block in courtyard Add $ 200 .00
SUB TOTAL: CITY HALL $ 383 .00
TOTAL $ 3093 .00
ATTACHMENT TO CHANGE ORDER NUMBER 5 2