1c. Plans & Specs for Construction of Well No. 5 Ic- CITY OF 4 CHANHASSEN • • ' 690 COULTER DRIVE • P.O. BOX 147 • CHANHASSEN, MINNESOTA 55317 (612) 937-1900 • FAX (612) 937-5739 MEMORANDUM TO: Don Ashworth, City Manager ' FROM: Gary Warren, City Engineer DATE: November 2, 1989 SUBJ: Authorize Preparation of Plans and Specifications for Construction of Well No. 5 and 6 Project No. 89-4 I As will be recalled, the City Council commissioned Bruce A. Liesch Associates, Inc. to prepare a feasibility study to investigate the siting of wells in the City and, in addition, to review the feasibility of expanding the capacity of our existing wells 2 and 3. This draft report was completed and accepted by the Council earlier this year. This led to to a recommendation to perform test pumping on wells 2 and 3 to further evaluate their capacity for expansion. This was recently completed and the attached addendum report prepared by Bruce A. Liesch Associates, Inc.. summarizes the findings and further defines the City ' s options. ' Subsequent to the preparation of this addendum report, a centri- fugal sand tester was installed on pump discharge headers to wells 2 and 3 to identify the sand content of the discharge. Unfortunately, the sand testing results were disappointing in that well 3 showed an inordinate amount of sand is being deve- loped from the well. It is difficult to say if this is a charac- teristic of the Prairie du Chien-Jordan aquifer or strictly representative of the way that the well was developed . In either case, this has precluded pursuing the less-costly option of expanding existing well 3 by adding a higher capacity pump. Review of the well log and pump tests conducted at well No. 2 at South Lotus Lake have revealed that potential exists for sinking a glacial drift well at well house No. 2 . There are a few more preliminary steps involved in the process and more risk since the gravel strata is less predictable than the deeper bedrock wells; however, the construction cost savings are also significant, i .e. $155 ,000 versus $395 ,000 . The City of Maple Grove, for example, has a number of "drift" wells. Due to the system hydraulics, i .e. distribution piping constraints, we could add approximately I I Don Ashworth November 2 , 1989 Page 2 ' 400 to 500 gpm to the City ' s pumping capacity by spring of 1990 if this option were pursued and everything worked out. This step still is an interim measure in that the City ' s 1985 water study anticipated adding another major bedrock well (1000 to 1500 gpm) into the system by 1992. Since this can be a ' lengthy process , construction should be in 1990 . It has not been decided at this point where the exact location of the bedrock well will be and this will be a part of the prelimi- nary investigations of the design effort. The construction cost of a new bedrock well is estimated to be $395 ,000 assuming the new well can be integrated into one of our existing well houses . ' This would be hammered out early on in the design effort as noted in the attached scope of services supplied by Bruce A. Liesch Associates , Inc. The specific design recommendations and esti- mated construction cost would then be presented to the Council for further authorization. Expenditures of this magnitude would exceed the City ' s Water Expansion Fund balance ($317 ,000 ) . It also would appear more appropriate, since the additional capacity is necessary to meet recent and anticipated future growth of the City , that these ' improvements be bonded for and paid back over a period of time from future trunk funds . It is therefore recommended that financing for these improvements be accomplished with the sale of a revenue bond issue with proceeds from the Water Expansion Fund ' ( 402 ) pledged to pay off the bonds over a period of years. A two-pronged approach is therefore recommended for meeting the ' City ' s water system needs: 1 . Authorize commencing with necessary investigations and engi- neering for constructing a glacial drift well at well house No. 2 at South Lotus Lake; estimated design service $13, 960 . 2 . Authorize commencing with the design of a bedrock (Prairie du Chien ) well at pump house No. 3; estimated design services $21, 360 . It is recommended that the firm of Bruce A. Liesch Associates, Inc. be directed to perform this work for the City in accordance with their attached scope of services dated November 2, 1989 . ' Attachments 1 . Generalized cost comparisons for water supply options. 2 . Proposal for design services dated November 2 , 1989 . c: Hal Summitt, Bruce A. Liesch Associates , Inc. r I I Page 3 I Manager' s Comments: Funding options should be reviewed by the City' s financial advisor. I DWA (11-2-89 ) I I I I I I I I I I I I I I I I BRUCE A. LIESCH ASSOCIATES, INC. HYDROGEOLOGISTS • ENGINEERS • ENVIRONMENTAL SCIENTISTS 3020 Harbor Lane•Minneapolis,MN 55447.612-559-1423•FAX No 559-2202 City of Chanhassen Generalized Cost Comparison for Water Supply Options ' Based on discussions with the Chanhassen Engineering Department subsequent to review of our draft "Preliminary Water Supply Investigation" , Bruce A. Liesch Associates, Inc. has prepared this summary of development options. The summary includes a brief discussion of each option and estimated range of costs. I. IN CR EAS E C AP ACI TY OF EXISTING WELL This may be an option at existing Prairie du Chien-Jordan wells (Wells 2 and 3) . The results of pumping tests conducted at these wells suggest additional capacity is available based on calculated aquifer coefficients and observed well yield. However, information ' collected subsequent to the pumping tests suggests the possibility for sand pumping at higher rates. This possibility should be further assessed prior to making permanent improvements to either well. Pump performance curves and development details have been reviewed ' for Well 3 and reveal that some problems were encountered during well development. Apparently the lower portion of the open borehole at Well 3, which was open to the Jordan Sandstone ' Formation, was backfilled with "pea rock" in an attempt to reduce sand pumping. The records do not clearly indicate the sequence of events. However it appears as though the sandstone portion of the borehole was blasted with dynamite and bailed out during the period ' from February 22 to March 6, 1973. A test pump was then installed in the well and operated at rates ranging from 550 to 1739 gpm while producing excessive amounts of sand. Then the test pump was I apparently pulled from the well and again blasted with dynamite in the upper portion of the open borehole on April 6 and 10, 1973. The well depth was reported at 390 feet during the second round of blasting rather than the original depth of 500 feet. A diag.ram_-of ' the well which shows "pea rock" backfill from 370 to 500 feet Vas included in the driller's well report. Test pumping continued from April 16 to Hay 16, 1973 at rates ranging from 200 to 1900 gpm. During this period the specific capacity of the well appeared to increase with continued pumping and removal of sand. With Prairie Du Chien-Jordan wells water enters the borehole from ' both formations. The Prairie Du Chien formation consists primarily ., of dolomitic limestone through which water moves in fractures and ' crevices. The Jordan is a sandstone formation where water moves through porespaces between individual grains. The percent of well yield which may be attributed to each formation will vary with fracturing in the dolomite and permeability of the sandstone. The propensity for sand pumping will depend on the degree of cementation within the sandstone, grain size and the velocity of water moving through the well. The only factor that can easily be controlled is, of course, the velocity of water by adjusting the pumping rate. Inasmuch as the sandstone portion of the borehol e at Well 3 has been filled with pea rock we would anticipate reduced yield from the sandstone along with increased entrance velocity in the remaining, open portion of the borehole. The available data does not clearly indicate at what rate does sand pumping occur. This should be examined prior to making well improvements. Our review of the existing pump data suggests that the pumping rate of Well 3 could be increased to approximately 1250 gpm pumping to a nearby hydrant rather than into the system under normal system pressure. If this can be arranged a centrifugal sand tester could be installed on the pump discharge line to measure I sand content at the higher rate. For testing beyond about 1250 gpm it will be necessary to remove the existing pump and temporarily install and operate a higher capacity test pump. ' Pumping the well with existing pump to waste (hydrant) and installation of a sand tester could be accomplished by the City. ' Some additional costs for oversight of the pumping procedure and analysis of sand pumping data could be anticipated and should not ' exceed approximately $2,000. 00. If a test at a higher rate is warranted a drilling contractor would be required. Removal of the existing pump: installation, operation and removal of a test pump; and reinstallation of the original pump ' would cost on the order of $10,000 to $12,000, with an additional cost of approximately $3,000 for oversight and analysis of the ' data. ' If additional capacity is available, pump sizing, purchase and installation could be anticipated on the order of $40,000 to I $60,000 for a 1600 gpm vertical turbine or submersible installation. II. BEDROCK WELL The preliminary report indicates that a Prairie du Chien-Jordan well could be developed in the northeastern portion of the City and a Mount Simon-Hinckley well over a larger area. More information is available regarding the Prairie du Chien-Jordan aquifer and well construction and yields would be similar to the existing City Wells 2 and 3. Costs could be anticipated as ' follows: Well and Pump: $250,000.00 Puaphouse and Controls: $100,000 .00 ' or r 11 Pitless adapter in combination with existing well house $ 30,000. 00 I Engineering/design/inspection and testing $ 50,000 . 00 Pump house and engineering costs would be similar for a Mount Simon-Hinckley installation with the well and pump perhaps costing ' an additional $50,000.00. Note that at present the Minnesota Department of Natural Resources appears to be discouraging 1 development of this aquifer where other options are available. The feasibility of a Mount Simon-Hinckley well, from a permitting standpoint, should be examined if this option is seriously considered. III. GLACIAL DRIFT WELL As stated in the preliminary report, this option may require an investigation phase to locate a suitable site and to verify well yield, design and water quality. Owing to the many uncertainties associated with drift aquifer it is extremely difficult to even "ball park" total project costs. Depending on the general area chosen for investigation a geophysical investigation may be warranted. In any case, a test drilling and aquifer testing program would be advisable in an area without existing high capacity drift wells. Site investigation costs including , contractor costs, water quality analysis and professional fees could range from $30,000 to $50,000. If favorable aquifer ' conditions are encountered well and pump costs for a 300 foot glacial drift well producing 1000 gpm may range from $120,000 to $160,000. Pumphouse and control costs would be similar to those for a bedrock well. Inspection and testing costs may be lower owing to anticipated shorter construction time. Sincerely, mes de Lambert ' ydrogeologist R44:COST1024 BRUCE A. LIESCH ASSOCIATES, INC. HYDROGEOLOGISTS • ENGINEERS • ENVIRONMENTAL SCIENTISTS 3020 Harbor Lane•Minneapolis,MN 55447.612-559-1423•FAX No 559-2202 November 2, 1989 Mr. Gary Warren ' City Engineer City of Chanhassen P.O. Box 147 Chanhassen, MN 55317 RE: Proposa4 for Design Services for New Wells Dear Mr. Warren: We are pleased to submit the attached proposal for design and ' construction services for construction of new wells in Chanhassen. We have broken the costs down into two projects; construction of a Prairie du Chien well at pumphouse 3 and construction of a well ' at pumphouse 2. As you are aware, these costs are roughly estimated at this tine and can be refined depending on the location of the wells. ' As always, we propose to bill our services at hourly rates for time actually spent on the project. Therefore, we anticipate the actual costs to be less. 1 If you have any questions, please contact us. ncerely, 1\W-A (34-A-th1/4-)& ' Ja es Bullert, P.E. Bruce A. Liesch Associates, Inc. JB/ms R44:CHAN11-2 11 r I SCOPE OF SERVICES WELL DESIGN CHANHASSEN, MINNESOTA SERVICES WILL INCLUDE: ' 1. An evaluation of optional locations for the new wells (pumphouse 2, pumphouse 3 or other) considering aquifer conditions, water main hydraulics and existing pumphouse configuration. 2. Preparation of plans for a new bedrock well at pumphouse 3 and a new drift well at pumphouse 2, detailing: o watermain piping from well to pumphouse and pumphouse to ' street, if necessary. o piping revisions in pumphouses ' o revisions to chlorination and fluoridation systems 3. Preparation of specifications detailing: o well construction for two wells ' o piping o valves ' o chlorination and dechlorination systems o electrical service and controls - both wells Services not included and considered extra if required: ' o Design of new pumphouse or addition to existing pumphouse o Major watermain design (over 700 feet) o Services related to land acquisition 1 I I • ESTIMATED ENGINEERING FEES 1) New Prairie du Chien Well at pumphouse 3 ' Design Services ' Aerial Photography & Site Survey $ 1,000 Evaluation of Optional Locations Sr. Engineer 60 Hours @ $75 $ 4, 500 Site & Watermain Plan Sr. Engineer 16 Hours @ $75 $ 1, 200 Jr. Engineer 40 Hours @ $50 $ 2,000 Piping & Construction Details Jr. Engineer 40 Hours @ $50 $ 2,000 Prepare Specifications Sr. Engineer 40 Hours @ $75 $ 3,000 ' Clerical 24 Hours @ $24 $ 576 Well Design Hydrogeologist 40 Hours @ $75 $ 3,000 Clerical 16 Hours e $24 $ 384 Electrical Engineering (Exe. Assoc. - Consultant) Subcontract $ 3,000 Miscellaneous Mileage, Materials, Etc. S 700 $21 ,360 ' Construction Services Project Bidding Sr. Engineer 60 Hours @ $75 $ 4,500 Construction Management Sr. Engineer 120 Hour $75 $ 9,000 ' Jr. Engineer 40 Hour $50 $ 2,000 Shop Drawings Review/Hydraulic Review Sr. Engineer 40 Hours @ $75 $ 3,000 Project Inspection Sr. Engineer 60 Hours @ $75 $ 4, 500 Field Inspector 150 Hours @ $50 $ 7,500 Start Up/Checkout/Operator Training Sr. Engineer 16 Hours @ $75 $ 1,200 Electrical Engineer (Exe. Assoc. ) $ 1,500 Well Construction Observation ' Sr. Hydrologist 100 Hours @ $75 $ 7, 500 Jr. Hydrologist 150 Hours @ $50 $ 7.500 $48,200 I I I 2) New Drift Well at Pumphouse 2 Design Services Site & Watermain Plan , Sr. Engineer 8 Hours @ $75 $ 600 Jr. Engineer 40 Hours @ $50 $ 2,000 • Piping & Construction Details Jr. Engineer 24 Hours @ $50 $ 1,200 Prepare Specifications Sr. Engineer 40 Hours @ $75 $ 3,000 Clerical 24 Hours @ $24 $ 576 Well Design Hydrogeologist 40 Hours @ $75 $ 3,000 Clerical 16 Hours @ $24 $ 384 Electrical Engineering (Exe Assoc. -Consultant) $ 2, 500 Miscellaneous Mileage, Haterials,etc. S 700 $13,960 Construction Services 1 Project Bidding Sr. Engineer 60 Hours @ $75 $ 4, 500 Construction Management Sr. Engineer 80 Hours @ $75 $ 6,000 Jr. Engineer 40 Hours @ $50 $ 2,000 Shop Drawing Review Sr. Engineer 40 Hours @ $75 $ 3,000 Project Inspection Sr. Engineer 60 Hours @ $75 $ 4,500 Field Inspector 80 Hours @ $50 $ 4,000 Start-up/Checkout/Operator Training Sr. Engineer 16 Hours @ $75 $ 1,200 Electrical Engineer (Exe. Associate ) $ 1,000 Test Well Observation & Evaluation Sr. Hydrogeologist 40 Hours @ $75 $ 3,000 Jr. Hydrogeologist 60 Hours @ $50 $ 3,000 Production Well Construction Observation Sr. Hydrogeologist 40 Hours @ $75 $ 3,000 Jr. Hydrogeologist 80 Hours @ $50 $ 4.000 $39,200 TOTAL ENGINEERING FEES: $122,720 1 1 I CONSTRUCTION COST ESTIMATE NEW WELLS CITY OF CHANHASSEN 1 ) Construct new Prairie du Chien Well at Pumphouse 3 - 1000 to 1500 gpm Construct New Well - 16" diameter, 450 ' deep $200,000 New Well Pump - 200 hp $ 35,000 ' 10" Watermain Well to Pumphouse $ 55,000 Modifications to Pumphouse $ 25,000 Electrical Power & Controls $ 40,000 Replace Existing Pump 43 $ 35,000 ' Remove Booster Pump S 5,00'0 ESTIMATED COST $395,000 ' NOTE: Cost does not include land acquisition. 2 ) Construct New Drift Well at Pumphouse 2 500 gpm Construct Test Well $ 20,000 Construct New Well - 12" diameter $ 80,000 Well Pump $ 10,000 ' Watermain $ 10,000 Modifications to pumphouse $ 15,000 Electrical Power & Controls $ 20,000 ESTIMATED COST $155,000 R44:CHAN 1 I I p Don Ashworth November 2 , 1989 Page 2 ' 400 to 500 gpm to the City ' s pumping capacity by spring of 1990 if this option were pursued and everything worked out. ' This step still is an interim measure in that the City ' s 1985 water study anticipated adding another major bedrock well (1000 to 1500 gpm) into the system by 1992. Since this can be a ' lengthy process , construction should be in 1990 . It has not been decided at this point where the exact location of the bedrock well will be and this will be a part of the prelimi- nary investigations of the design effort. The construction cost of a new bedrock well is estimated to be $395 ,000 assuming the new well can be integrated into one of our existing well houses . ' This would be hammered out early on in the design effort as noted in the attached scope of services supplied by Bruce A. Liesch Associates , Inc . The specific design recommendations and esti- mated construction cost would then be presented to the Council for further authorization. Expenditures of this magnitude would exceed the City ' s Water Expansion Fund balance ($317 ,000 ) . It also would appear more appropriate, since the additional capacity is necessary to meet recent and anticipated future growth of the City, that these improvements be bonded for and paid back over a period of time from future trunk funds . It is therefore recommended that financing for these improvements be accomplished with the sale of a revenue bond issue with proceeds from the Water Expansion Fund ' ( 402 ) pledged to pay off the bonds over a period of years. A two-pronged approach is therefore recommended for meeting the City ' s water system needs: 1 . Authorize commencing with necessary investigations and engi- neering for constructing a glacial drift well at well house No. 2 at South Lotus Lake; estimated design service $13, 960 . 2 . Authorize commencing with the design of a bedrock (Prairie du Chien) well at pump house No. 3; estimated design services $21, 360 . It is recommended that the firm of Bruce A. Liesch Associates, Inc. be directed to perform this work for the City in accordance with their attached scope of services dated November 2, 1989 . ' Attachments 1 . Generalized cost comparisons for water supply options. ' 2 . Proposal for design services dated November 2, 1989 . c: Hal Summitt, Bruce A. Liesch Associates , Inc. r I