MEMORANDUM k'ndorst ✓_._._..
ITO: Don Ashworth, City Manager Re;x3^ci _ --st/
Date-2.7"A 41 I FROM: Larry Brown, Staff Engineer D to Submtcd to Commi;siox
DATE: September 21 , 1988 Date Zu5t.fttoJ to Cosfcii
SUBJ: Carver Beach Estates, Acceptance of Utilities
File No. 84-9 (private)
IAttached is a letter from the City' s consultant on the subject
project certifying that the utility portion of the project has
I been completed in general conformance with the plans and specifi-
cations as is therefore ready for the City' s acceptance. Staff
has reviewed this project and finds that the utilities are
acceptable.
It is therefore recommended that the City accept the utilities
for Carver Beach Estates, Project No. 84-9. This acceptance is
I conditioned upon receipt of the contractor ' s one-year maintenance
bond, effective from the date of this acceptance.
IAttachment: Letter from Boeck Engineering dated September 1 , 1988.
I
I
I
I
I
I
I
September 1 , 1988
Mr . Gary Warren, P.E.
Chanhassen City Engineer
690 Coulter Drive
Chanhassen, MN 55317
RE: Carver Beach Estates , Improvements
City Project No. 84-9
Dear Gary,
All of the storm and sanitary sewer , water main, concrete curb and
gutter and street base and surfacing , except for the bituminous
wearing course , have been completed in accordance with the plans and
specifications . The utilities were completed as of December 1 , 1987 .
Subsequently all of the minor punch list items corrections have been
completed . The final bituminous wearing course installation will be '
installed later this month, in accordance with your directions . The
sub-grade aggregate and bituminous base have all proven to be
excellent and warrant the construction of the final bituminous wearing
course.
We hereby request that the City accept the utility construction as of
December 1 , 1987 , and the street construction, except for the wearing
course, as of May 15 , 1988 . The street signs and street lighting has
also been completed as required . Tree planting will be completed as
each house is constructed and the landscaping work is underway. Please
let me know if you require additional information.
Very truly yours ,
Boeck-Kevitt Partnership
AIOOP
Je ' rey R. Boeck, -
Managing Partner
JRB/cb