MEMORANDUM
TO: Mayor and City Council
1 FROM: Don Ashworth, City Manager
1 DATE: September 26 , 1988
SUBJ: Funding of Design for New Highway 212
Attached please find correspondence received from Holmes and
Graven asking member cities of the Southwest Corridor
1 Transportation Coalition to consider making contributions to
accelerate the construction of Highway 212 .
1 Mayor Hamilton or Councilman Horn may wish to provide their
thoughts on this subject. My initial reaction is that the propo-
sal appears solely to be one of accelerating the project' s
schedule by 16 to 21 months if the cities/counties were to pro-
vide the $400 ,000 contribution. I believe it is critical to the
long range planning of our community to have TH 212 become a
reality. If this proposal is one of saying that without the
1 $400,000 contribution, TH 212 may never occur, consideration
should be given to the proposal. However, if the proposal is
solely one of being able to accelerate the construction of TH
212, the price tag for such acceleration appears to be exor-
bitant.
Barring comments to the contrary from either Mayor Hamilton or
1 Councilman Horn, this office would recommend that the City
Council instruct this office to prepare a letter back to Holmes
and Graven as depicted above.
i
1
(;./-/
1
1
1
HOLMES & GRAVEN
CHARTERED
Attorneys at Law 470 Pillsbury Center,Minneapolis,Minnesota 55402
JEFFREY R.BRAUCHLE (612)337.9300 DANIEL R.NELSON
ROBERT C.CARLSON BARBARA L.PoRTWOOD
ROBERT L.DAVIDSON Raplfax(612)3379310 JOHN C.IICLEY
ROBERT J.DEIKE ARLIN B.WAELTI
STEFANIE N.GALEY LARRY M.WERTHEIM
DAVID L.GRAVEN
REYNAL-D L.HARP
JAMES S.HOLMES ROBERT A.ALSOP
JOHN R.CARSON WRITER'S DIRECT DIAL MARY J.BRENDEN
CHRISTINE
JOHN M.LEFEvRE,JR. M. NS
ROBERT J.LINDALL JOHN R.GREEN
S
MARK A.LINDGREN JOHN N.GREEN
LAURA K.MOLLET STEVEN ND
DUANE G..JOHNSON
BONNIE L.WILKINS
September 9 , 1988
Mr. Dave Pokorney Mr . Don Ashworth
City Administrator City Administrator
City of Chaska City of Chanhassen
One City Hall Plaza 690 Coulter Drive
205 East Fourth Street Chanhassen, Minnesota 55317
Chaska, Minnesota 55318 '
Mr. Carl Jullie Mr . Patrick Murphy
City Manager Director of Public Works
City of Eden Prairie Hennepin County
8950 Eden Prairie Road 320 Washington Avenue South
Eden Prairie, Minnesota 55344 Hopkins, Minnesota 55343
Mr. Roger Gustaf son
Director of Public Works
Carver County Courthouse
Chaska, Minnesota 55318
RE: Funding of Design for New Highway 212
Our File No. LN400-51
Gentlemen :
As you may know, the Southwest Corridor Transportation Coalition
proposes that the various affected governmental entities commit
to jointly funding the design of new U.S . Highway 212 between
Interstate 494 and existing 212 west of Chaska. Because of
previous and separately funded EIS work we understand that it may
be possible to design a four lane : road from I-494 to Hennepin
County Road 4 with a two lane road from County Road 4 to existing
U.S . 212 for approximately one million dollars.
We propose that the Cities of Chaska, Chanhassen and Eden Prairie
and Carver and Hennepin Counties jointly offer to fund $400 ,000
of this cost, payable in the years 1989 , 1990, and 1991, if MnDot
will agree to fund the remainder. We would offer our assistance
in obtaining federal funds to reduce the MnDot share, if federal
funds can be obtained for this purpose (we think this possibility
may exist) . '
SEP 1 ;; 1988
CITY OF CHAN'r,ASJk.1N ,
I -
We propose that these contributions and the payment schedules be
as follows:
IPayable 1989 Payable 1990 Payable 1991 Total
I Chanhassen $ 33 ,333
$ 33 ,333 $ 33 ,333 $ 33 ,333 $100 ,000
Chaska $ 33 ,333 $ 33 ,333 $100 ,000
Eden Prairie 0 $ 50 ,000 $ 50 ,000 $100 ,000
Carver County $ 16 ,667 $ 16 ,667 $ 16 ,667 $ 50 ,000
IHennepin Co. $ 16 ,667 $ 16 ,667 $ 16 ,667 $ 50 ,000
TOTALS $100 ,000 $150 ,000 $150 ,000 $400 ,000
IThe proposed schedule for Eden Prairie is intended to recognize
other proposals now under consideration for funding of the
Highway 212/ring road interchange in Eden Prairie.
We are aware that your organizations are each now engaged in
budgeting for 1989 . We hope that you are willing to assist in
I this effort and that this request is early enough for you to
include this item in your 1989 budget.
I We are advised that it is potentially possible that commencement
of construction of the four lane segment of 212 between I-94 and
County Road 4 could be accelerated by 16 months and that
completion of that project could be accelerated by 21 months if
Iwe are willing to make this commitment.
I am sure that you will agree that it has been very exciting to
I see significant progress on Highway 5 and Highway 212 in the last
year . In large measure this success has been due to the
willingness of your units of government to contribute to the cost
Iof design and environmental work.
We will be happy to do what we can to respond to any questions
which you might have. We look forward to hearing from you at
I your earliest opportunity. Thank you for your cooperation and
consideration.
IVery truly yo rs,
a .
IRobert J . Lindall
•
RJL:kar
Icc : Robert Roepke, Mayor , City of Chaska
Tom Hamilton, Mayor, Chanhassen
I Gary Peterson, Mayor, Eden Prairie
Clark Horn, Alderman, Chanhassen
Patricia Pidcock , Councilmenber, Eden Prairie
I Tracy Swanson, Carver County Commissioner
Al Klingelhutz, Carver County Commissioner
Dick Feerick, Southwest Corridor Coalition Chair
I