5. Downtown Improvement Project Change Order • 1 . ,...._______, I _ CITY OF \ _,I , CHANHASSEN 1 \ 1/4), '° 690 COULTER DRIVE •• P.O. BOX 147 •• CHANHASSEN, MINNESOTA 55317 _. 1 (612) 937-1900 MEMORANDUM ITO: Don Ashworth, City Manager FROM: Gary Warren, City Engineer I -. DATE: March 10, 1988 1 SUBJ: Approval of Change Order No. 1, Shafer Contracting, Inc. Downtown Redevelopment Project Phase I File No. 86-11A I . Attached you will find a memo from Gary Ehret of BRW which in 1 detail summarizes the request for Change Order No. 1 for Shafer Contracting on the Downtown Redevelopment Project. I have spent the better part of a day on February 22 , 1988 reviewing each of II these items in detail with BRW staff. I found that both Shafer Contracting and BRW have maintained excellent records documenting the exact quantities of materials utilized on the project. II am sure if one takes the time to go down the itemized list con- tained in Mr. Ehret' s letter that there will be a number of things that are familiar such as item #37, water used for dust 1 control, item #42, signage used throughout the project area emphasizing the downtown business availability and access, etc. Likewise, there are quantity underruns and other deducts which are anticipated on this contract as indicated in the letter. Mr. I Ehret and I will be happy to go into more detail on any of the items as requested Monday night. II therefore recommend approval of Change Order No. 1 in the amount of $291, 201. 66 as itemized in the March 9 , 1988 correspon- dence from BRW and establishing a revised contract estimated I ceiling of $2,725,772 . 96. The contract completion date remains June 1 , 1988. I Attachments: 1. March 9 , 1988 correspondence from BRW 2 . Change Order No. 1 I I I PLANNING TRANSPORTATION ENGINEERING ARCHITECTURE BENNETT. RINGROSE, WOLSFELD, JARVIS. GARDNER. INC. • THRESHER SQUARE • 700 THIRD STREET SOUTH • MINNEAPOLIS, MN 55415 • PHONE 612/370-0700 March 9, 1988 a NASSEN City of Chanhassen CITY HORN Cr�Nt1MHr� 690 Coulter Drive Ill ORN Chanhassen, MN 55317 ' MAR 181988 Attn: Mr. Gary Warren, P.E. City Engineer ENGINEERING DEPT. RE: Contract Status Downtown Redevelopment Project ' CP 86-11 Dear Mr. Warren: ' Partial Payment #6 for Shafer Contracting was submitted to your office for review, approval , and payment in the amount of $100,158.21 on March 8, 1988. This payment is based upon $1,728,953.62 of approved work todate on the downtown project. The partial payment has been made based upon completed work items which have contract unit bid prices. Several areas of work have been completed but contract unit bid prices are not in force so these items have not been paid. I Change Order Number One (1) to the downtown project is being submitted for approval and City Council action at this time. This change order is intended to cover items of work not covered by the original contract bid items, as well as to modify those current bid items which have significantly changed thru the course of the project. This letter and change order are intended to provide both you and the City Council the following information: 1. Contract Status Update ' 2. Projected Contract Status 3. Summary Explanation of Change Order Number One In regard to the contract status update, upon approval of the City Council , the revised contract will be: Original Contract Amount $2,434,571.30 I Change Order Number One (1) 291,201.66 Revised Contract Amount $2,725,772.96 DAVID J BENNETT DONALD W RINGROSE RICHARD P WOLSFELD PETER E JARVIS LAWRENCE J GARDNER THOMAS F CARROLL CRAIG A AMUNDSEN DONALD E HUNT MARK G SWENSON JOHN B McNAMARA DONALD L CRAIG RICHARD D.PILGRIM DALE N BECKMANN DENNIS J SUTLIFF MINNEAPOLIS DENVER PHOENIX I Mr. Gary Warren ' March 9, 1988 Page 2 i Change Order Number One addresses all significant contract additions or ' increases todate; however, it does not address contract deletions, reductions, or potential changes this spring. We have reviewed the contract as well as the work completed todate and have found that there will be additional significant ' changes to the contract prior to completion of the project. Included in these changes are contract quantity underruns, change order deductions, and reduced compensation due to the contractor's failure to meet the project specifications. ' In order to illustrate the projected contract status we offer the following summary: Original Contract Amount $2,434,571.30 Add Change Order Number One (1) 291,201.66 Add Change Order Number Two (2) (Future) 5,000.00 Deduct Projected Quantity Underruns <29,000.00> Deduct Contractor Penalties <3,500.00> ' Deduct Future Change Order <18,750.00> PROJECTED CONTRACT STATUS $2,679,522.96 It is important to note that this projected contract status is based wholly upon the scope of work identified in Shafer Contracting's current contract. Any ' scope of work changes, whether reductions or additions, obviously have an impact on this projection. ' Finally, we offer an encapsulated explanation of the changes illustrated in Change Order Number One, which is attached to this letter. As you are aware, we have reviewed each of the change order items with you previously and BRW will provide detailed support documentation for each of the changes. ' We offer the following line item summary by bid schedule and item number: ' Bid Schedule A - General Work Item No. Change Summary 3, 4 Quantity understatement in bid documents. 22 Fencing salvaged for construction of north side parking lot. i28, 29, 31 Quantity overruns precipitated by substantially increased areas of excavation due to expansion of work or the revised ' roadway section which included a uniform two-foot subcut over a substantial portion of the project. i i r ' , Mr. Gary Warren March 9, 1988 Page 3 Item No. Change Summary 33 Aggregate Class Two was used with limited discretion, ' assisting business traffic, both customers and owners/ operators, in traveling to the downtown businesses. 37 Water was used with limited discretion in attempting to control dust throughout the project. 40 Old building rubble was excavated from the site of the tem- ' porary north side parking lot. 41 Overtime costs incurred, due to authorization to contractor ' to work overtime to complete TH 101 improvements as quickly as possible. 42 Signage used throughout the project area to alert motorists to the special conditions in the downtown area. 43 Detour signage necessary at railroad crossing with Great ' Plains Boulevard/TH 101. 44, 45, 46 Items of work without a contract bid price. ' 47 The contract specified disposal of excavated material within 1/2-mile of project site. 6,255 cubic yards were hauled to sites outside of the 1/2-mile radius. * Please note that costs associated with Items 22, 28, 31, 33, and 40, in the approximate total amount of $11,000.00 are a part of the temporary north side parking lot construction and as such should not be charged to the downtown project. Bid Schedule (B) - Roadway/Parking Lot Item No. Change Summary ' 1 Additional aggregate base has been used in several areas out- side of the original contract including the paved median areas, access road, and north side parking lot. 22 Item of work without a contract bid price. Used for dust control . ' 23, 24 Protective fencing used for pedestrian traffic control in uncompleted work areas during winter shutdown. r I Mr. Gary Warren ' March 9, 1988 Page 4 25 Traffic barrier as required by MnDOT for railroad detour. 26 Extra costs associated with placement of concrete curb and gutter after November 1, 1987. * Please note that a portion of the costs associated with Bid Item Number 1 in the amount of $9,300.00 is a part of the temporary north side parking lot construction and as such should not be charged to the downtown project. ' Bid Schedule (C) - Storm Sewer ' Item No. Change Summary 22 Quantity understatement in bid documents ' .38 Buried concrete chunks discovered, excavated, and disposed of while excavating for storm sewer. 39 Item of work not covered by contract bid price. Used to con- nect Chanhassen State Bank roof drains to storm sewer system. 40 Specially constructed manhole used in storm sewer alignment offset at Laredo Drive (Manhole 11X) . 41 Interim connections between new and existing storm sewer at ' Great Plains Boulevard and TH 101 for winter shutdown. 42 Item of work not covered by contract bid price. Used to con- nect Chanhassen State Bank roof drains to storm sewer system. 43 Item of work not covered by contract bid price. Special ' casting used for driveway change at Browns Amoco. - Bid Schedule (D) Sanitary Sewer Item No. Change Summary 14 Trench stabilization rock overrun due to very poor soil con- 29 encountered while installing sewer. 29 thru 38 Items of work not covered by contract bid price. ' 39 Sanitary sewer backfill behind Colonial Square used to replace unsuitable material . I 1 II Mr. Gary Warren March 9, 1988 II Page 5 I Bid Schedule (E) - Watermain Item No. Change Summary t 41 thru 46 Items of work not covered by contract bid price. 47 Costs incurred when a stop order was given the contractor II upon commencement of jacking excavation on TH 101. 48 Repairs to existing water services for Klingelhutz Realty I when services failed at connection to old main. Bid Schedule (F) - Site Work. I Item No. Change Summary 16 Contractor reinstalled existing Type C signs for winter II operation. Please advise me if I can offer additional clarification to any of the change I order items, or if further definition of the contract status is desired. Sincerely, I BE RINGROSE- LSF lorARVIS-GARDNER, INC. A. .��et, P.E. Project Engineer I GAE/sk Attachment II 1 I II II II II ..1.--r. Copy I .. Cit." LJ�/�}f i� CITY OF CHANHASSEN Contractor Copy Inspector Cop/ IICONTRACT CHANGE ORDER I Project: Downtown Redevelopment Project Improvement Project No. : 86-11 Change Order No. : One (1) Date: March 14, 1988 IIContractor: Shafer Contracting, Inc. IDescription of contract changes: ADD IBid Schedule (A) - General Work Unit IIItem No. Item Unit Quantity Price Extension 3 Clearing Tree 200 $ 50.00 $ 10,000.00 I 4 Grubbing Tree 200 50.00 10,000.00 22 Salvage Split Rail Fence LF 500 1.50 750.00 28 Common Excavation CY 8,159 2.00 16,318.00 29 Subgrade Excavation CY 11,000 2.00 22,000.00 a II 31 Granular Borrow CY 9,650 5.00 48,250.00 33 Aggregate Surfacing Cl . 2 Ton 1,550 7.00 10,850.00 37 Water 1,000 300 10.00 3,000.00 I 40 Rubble Excavation CY 1,259 5.00 1 7,487.56 6,295.00 41 Overtime Costs LS 7,487.56 42 Specialty Signs LS 1 7,500.00 7,500.00 43 Railroad Detour Signage LS 1 8,350.00 8,350.00 I44 Salvage Castings EA 14 150.00 2,100.00 45 Abandon Manhole EA 4 200.00 800.00 46 Abandon Hydrant EA 1 150.00 150.00 I47 Excavation Haul Premium CY 6,255 1.35 8,444.25 Subtotal $ 162,294.81 IIADD Bid Schedule (B) - Roadway/Parking Lot IUnit Item No. Item Unit Quantity Price Extension I1 Aggregate Base Placed Ton 13,000 $ 6.10 $ 79,300.00 Cl . 5 II 22 Calcium Chloride (80#) Bag 6 50.00 300.00 23 F & I Plastic Snow Fence LF 100 2.50 250.00 24 F & I Wood Snow Fence LF 250 2.50 625.00 25 F & I Precast Barrier LF 110 25.00 2,750.00 II26 Winter Concrete Costs LS 1 500.00 500.00 Subtotal Addition $ 83,725.00 I1of3 II r ADD Bid Schedule (C) - Storm Sewer I Unit Item No. Item Unit Quantity Price Extension II 22 72" RC Pipe Sewer LF 110 $ 155.00 $ 17,050.00 38 Concrete Excavation CY 360 14.00 5,040.00 39 12" PVC Storm Sewer LF 252 14.00 3,528.00 II 40 Construct Special Manhole EA 1 1,865.00 1,865.00 41 Connect to Existing EA 2 500.00 1,000.00 Storm Sewer (Special ) II 42 Construct MH - Design H EA 1 650.00 650.00 43 Install Special Casting EA 1 162.18 162.18 Subtotal $ 29,295.18 II ADD Bid Schedule (D) - Sanitary Sewer I Unit II Item No. Item Unit Quantity Price Extension 14 Crushed Rock Pipe Bedding Ton 350 $ 20.00 $ 7,000.00 D 29 6" PVC Sanitary Sewer LF 57 11.00 627.00 II 30 6" PVC Bend EA 5 25.00 125.00 31 8" PVC Tee EA 1 40.00 40.00 32 8" PVC Bend EA 2 50.00 100.00 II 33 10" PVC Wye EA 2 100.00 200.00 34 6" CI Plug EA 4 50.00 200.00 35 6" CI Wye EA 3 150.00 450.00 36 6" CI Bend EA 1 125.00 125.00 I 37 8" CI Plug EA 2 75.00 150.00 38 Reconstruct Manhole LF 13 200.00 2,600.00 39 Trench Backfill CY 350 2.00 700.00 II Subtotal $ 12,317.00 ADD I Bid Schedule (E) - Watermain Unit I Item No. Item Unit Quantity Price Extension 41 6" Hydrant Extension EA 2 $ 450.00 $ 900.00 I 42 Stop Box Rods EA 8 15.00 120.00 43 6" CI Sleeve EA 2 100.00 200.00 II 44 8" CI Sleeve EA 3 100.00 300.00 45 10" CI Sleeve EA 1 150.00 150.00 46 10" MJ Plug EA 1 100.00 100.00 47 WM Conflict/Jacking LS 1 200.00 200.00 II 48 Watermain Services Repair LS 1 949.67 949.67 Subtotal $ 2,919.67 I 2 of 3 ADD IBid Schedule (F) - Site Work I Unit Item No. Item Unit Quantity Price Extension 16 Reinstall Existing EA 13 $ 50.00 $ 650.00 IType C Sign Subtotal $ 650.00 ICONTRACT SUMMARY Current Contract Amount $2,434,571.30 ISchedule (A) Additional $162,294.81 Schedule (B) Additional 83,725.00 I Schedule (C) Additional 29,295.18 Schedule (D) Additional 12,317.00 Schedule (E) Additional 2,919.67 II Schedule (F) Additional 650.00 • Contract Change Order No. 1 Total Additional $ 291,201.66 t, IIAmended Contract Amount $2,725,772.96 IICurrent Completion Date June 1, 1988 Additional Days Due to Change Order 0 IAmended Completion Date June 1, 1988 IAPPROVALS: IIISSUED BY: B net Ringros-- .o f- •-Jarvis-Gardner, Inc. BY: e -- 7/. 7 0 i Date: h II ACCEPTED BY: Shafer Contracting, Inc. IIBY: Date: IIAPPROVED BY: City of Chanhassen IBY: Date: I3of3 I I 1 1 1 1 1 • 1 41:=1 1 1 1111111Nri 111111wr I