D-4. Avienda Schedule Update -1- --"L"\
Avienda Entitlement Schedule
2016 2017
Task Name Start Date End Date Comments Nov Dec Jan Feb Mar Apr May June July Aug
11111111111.111111111111111111.111111111111111111. MUM I
Council Orders AUAR Update 11/28/16 11/28/16
Applicant submits $94,570 escrow to City for AUAR 11/29/16 11/29/16
AUAR Update 11/29/16 04/10/17
Task 1 - update development scenarios 11/29/16 11/29/16 no build, preferred
and preserve
wetland #1
update 11/29/16 01/27/17
Meeting with Staff and Developer 12/05/16 12/05/16
Workshop with Staff and Developer 01/09/17 01/09/17
Meeting with Elected Officials 02/13/17 02/13/17
community open house 02/15/17 02/15/17
Task 2 - Review and Redline Current AUAR 01/02/17 02/10/17
review and redline 01/02/17 02/10/17
Work Shop with city staff 01/30/17 01/30/17
Task 3 - Review and Update Mitigation Plan 01/02/17 02/27/17
Review and Update 01/02/17 02/10/17
Workshop with City Staff 02/20/17 02/20/17
Task 4 - Facilitate Formal Review Process 02/21/17 04/10/17
Planning Commission Public Hearing 02/21/17 02/21/17
City Council authorize EQB submittal 02/27/17 02/27/17
Submit to EQB 02/27/17 02/27/17
Notice published in EQB Monitor 03/06/17 03/06/17
10 day objection period/Resolve EQB Comments 03/20/17 03/31/17
Workshop with staff 04/03/17 04/03/17
Council adopts AUAR (If comments are resolved) 04/10/17 04/10/17
PUD Rezoning and Preliminary Plat A proval
MSA Design Variance Application (If Needed) 01/24/17 03/22/17 If needed for Bluff timummommimmimmilk
Creek Boulevard
Council Authorizes MSA variance submittal 01/24/17 01/24/17 .,,R
Variance Application deadline 03/01/17 03/01/17 •
State Action on Variance 03/22/17 03/22/17 •
Application submittal for PUD Rezoning and 03/17/17 03/17/17 0
Preliminary Plat (PP)
Neighborhood Meeting TENTATIVE 02/15/17 02/15/17
Planning Commission Meeting and Public Hearing 04/18/17 04/18/17 City Cancelled 4/4
110
PC meeting
Cit Council Amoval 05/08/17 05/08/17 lb
Avienda Entitlement Schedule
Revise Approved Delineation 01/06/17 02/03/17 110....s"....
Sequencing Plan/Permit Preparation 06/15/16 01/06/17 e'...""�"��"�
Request PJD 10/21/16 awaiting USACE
response
WCA/USACE Permit Application 01/06/17 04/18/17
USACE Process 01/06/17 08/07/17
Final Plat and Site Plan (phase 1)
Application submittal for Final Plat and Site Plan 06/16/17 06/16/17
(phase 1)
Neighborhood Meeting TENTATIVE
Planning Commission Meeting and Public Hearing 07/18/17 07/18/17
City Council Approval 08/14/17 08/14/17