D-5. 2017 Street Rehabilitation Project No. 17-01: Approve Quote/Award Contract for Construction Inspections n � 0 d w CITY OF ClIANIIASSEN S. Chanhassen is a Community for Life-Providing for Today and Planning for Tomorrow H. .A, MEMORANDUM TO: Paul Oehme, Director of Public Works/City Engineer V FROM: Stephanie Smith, Project Engineerr4tp, DATE: April 24, 2017 SUBJ: 2017 Street Improvement Project No. 17-01: Award Consultant Contract for Construction Inspection and Surveying PROPOSED MOTION "The City Council approves a resolution awarding a consultant contract for Construction Inspection and Surveying services on the 2017 Street Improvement Project No. 17-01 to Hansen Thorp Pellinen Olson, Inc. (HTPO) in the amount of$33,205.00. City Council approval requires a simple majority vote of the City Council present." BACKGROUND At the April 10, 2017 meeting, City Council approved 4. it • ���� � the contract to rehabilitate streets and do utility work in %,;;;' 't�® i t°t the Lake Susan Hills neighborhood. . A �� r '� • i. The proposed altid ref� y� improvements generally °y'"1°' 9✓;` , +'47" '+i;;.: consist of reclaiming the b oga ►�s ` ; pavement surface and the �� , , ' aggregate base underneath itiOr4 ..tf` the pavement. Minor leo .11V,wy 041 6 drainage improvements y` � and some draintile fiNat r~,,,jt; '�„ M installation are also V,. ; „.., included within the project %%,® area. For the municipal water system, gate valve and Vt.-% 'r VT j y�; r, � `Q.1 `� " hardware replacements are proposed along with minimal ,1/40V)430•� � y � hydrant replacement. Sanitarysewer work proposed • �� ;Otis 1.1"�` includes spot repairs of damaged manhole structures and �yw4)'',4110:04Y . inflow/infiltration remediation within the manholes. � �'�� f . PH 952.227.1100• www.ci.chanhassen.mn.us• FX 952.227.1110 7700 MARKET BOULEVARD • PO BOX 147 • CHANHASSEN • MINNESOTA 55317 Paul Oehme 2017 Street Rehabilitation Project: Award Consultant Contract April 24,2017 Page 2 ENGINEERING SERVICES For the 2017 construction season, the City has approved a reconstruction project in the Minnewashta Manor neighborhood (Project#16-01) and proposed a rehabilitation project on Park Road (Project#16-04). Due to the time demands of these projects, the City Engineering Department does not have sufficient staff time to perform construction observation for the 17-01 Lake Susan Hills Street Rehabilitation project. Staff proposes contracting with a consultant for engineering services for this project. The engineering services would include construction observation/oversight and as-built surveying work after the project is completed. Staff evaluated the hourly rate for construction observation and as-built surveying from two companies: Hansen Thorp Pellinen Olson, Inc. (HTPO) and Kimley-Horn &Associates. Hansen Thorp Kimley-Horn & Pellinen Olson, Inc. Associates Cost for 255 Hours of Construction $31,365.00 $34,425.00 Observation (at$123.00/hour) (at $123/hour) (at $135/hour) $1,840.00 $1,072.94 Cost for 16 Hours of Surveying (at $115/hour) (at $67.06/hour) Total of Cost for Engineering Services $33,205.00 $35,497.94 The proposed HTPO team has previously provided engineering services to the City of Chanhassen and their work in Chanhassen and other communities has been satisfactory. The consultant contract will be a time and materials based work not-to-exceed amount totaling $33,205.00 for all construction observation and surveying work. As with all engineering contracts, the consultant must submit periodic invoices that staff will review before processing. The consultant will be required to submit timesheets verifying the hours worked on the project and expense sheets. Staff will review the invoices and expense sheets for accuracy and conformance to the contract. Paul Oehme 2017 Street Rehabilitation Project: Award Consultant Contract April 24,2017 Page 3 FUNDING Funding for this project is budgeted for in the 2017 CIP. The following is a breakdown of the project costs and funding for the project as approved at the April 10, 2017 Council Meeting: Improvement Funding Source Project Cost Amount Budgeted Streets Assessments/Revolving $ 935,700.88 $1,260,000 Assessment Fund Stormwater Surface Water Utility $ 38,596.92 $ 50,000 Fund Water Water Utility Fund $ 58,203.05 $ 75,000 Sanitary Sewer Sewer Utility Fund $ 101,798.12 $ 180,000 $1,134,298.97 $1,565,000 The project costs shown above include 5% for construction contingency and indirect costs such as soils testing and $33,205.00 for construction inspection and as-built surveying by HTPO. SCHEDULE The following schedule is proposed for the project: Construction Start June, 2017 Substantial Completion August, 2017 Attachments: Resolution G:\ENG\PUBLIC\_2017 PROJECTS\I7-01 Street Rehab\Communication\170424 approve consultant contract.docx CITY OF CHANHASSEN CARVER AND HENNEPIN COUNTIES,MINNESOTA DATE: April 24, 2017 RESOLUTION NO: 2017-XX MOTION BY: SECONDED BY: A RESOLUTION APPROVING A CONSULTANT CONTRACT WITH HANSEN THORP PELLINEN OLSON,INC. (HTPO)FOR CONSTRUCTION INSPECTION AND SURVEYING FOR THE 2017 STREET IMPROVEMENT PROJECT NO. 17-01 BE IT RESOLVED that the City of Chanhassen enter into a consultant contract, in the amount of$33,205.00,with Hansen Thorp Pellinen Olson,Inc. (HTPO) for construction inspection and surveying for the following scope of work: The consultant work in general includes: Construction observation/oversight and as-built surveying work after the project is completed. NOW THEREFORE,BE IT RESOLVED by the Chanhassen City Council: 1. Enter into a consultant contract with Hansen Thorp Pellinen Olson, Inc. (HTPO)to provide construction inspection and surveying for the 2017 Street Improvement Project No. 17-01. Passed and adopted by the Chanhassen City Council this 24th day of April, 2017. ATTEST: Todd Gerhardt, City Manager Denny Laufenburger, Mayor YES NO ABSENT