G-1. Minnewashta Manor Area Street & Utility Reconstruction Project 2016-01: Project Update �\ T Y • � w q CITY Of CIIANIIASSEN S Chanhassen is a Community for Life-Providing for Today and Planning for Tomorrow MEMORANDUM TO: Todd Gerhardt, City Manager FROM: Paul Oehme, Director of Public Works/City Enginee DATE: September 25, 2017 SUBJ: Minnewashta Manor Area Street & Utility Reconstruction Project No. 16-01: Project Update BACKGROUND On August 24, 2015, the City Council authorized preparation of the feasibility study. On November 18, 2015, an open house was held to discuss the proposed project. On December 14, 2015, the City Council accepted the feasibility study and called the public hearing. At the January 25, 2016 meeting, the City Council held the public hearing and authorized the preparation of plans and specifications. On February 22, 2016 the City Council approved the plans and specifications and authorized the advertisement for bids. The original bid opening for this project was held on March 24, 2016. Only one bid was submitted and was over the engineer's estimate and the budget for the project. On April 24, 2016, the City Council rejected this bid. Property owners were notified of the project delay. An open house was held on January 18, 2017 to provide a project update to the residents and answer questions about the proposed assessments. On January 23, 2017, the City Council approved a construction contract. PROJECT SUMMARY This project includes the reconstruction of approximately 1.1 miles of streets, replacement of all of the water main, sanitary sewer replacement and repair, and miscellaneous storm sewer improvements. The project area is shown below: PH 952.227.1100• www.ci.chanhassen.mn.us • FX 952.227.1110 7700 MARKET BOULEVARD • PO BOX 147 • CHANHASSEN • MINNESOTA 55317 ,A _ No s Iw. .f 'r s�.-, o - ''. •1 . ,40;Slrr.• •~O "e1" V r - ('is Y } -, "" Y .«. r r lam; , t ♦ , ' ma y 1 '"111 ,, ��. *+r't x ;, 5 a Lane- 1"- , 1 1 .\ ,,' ik •�;40. i, 3`s O ch r- t,' 4:0, r '�! y. : 1, Ar. °ryf �" ; .t,S r, ,tom Y'4° - . , r-%r Y J� frJ/ J s to _, . r �' e' ' " - `° t�' 41 Sa k ` � it �' d , i LC e gy -idle a' r f. .Y,?'0 1 row►; r SCHEDULE The contract project schedule was as follows: Tree removal and reclaiming pavement begins May 30, 2017 Utility work begins June 12, 2017 Substantial Completion September 1, 2017 Install Wearcourse June 29, 2018 The project was proposed to be completed in 2 phases to limit impacts to the entire neighborhood as shown on the following exhibit. 1 P - ' - .// / HIGHWAY No. 7 If Co -- 7 ... 0. '1 I ,, i I do 1, � E0 ORC � } f- -1/ f I LAKE j / p I N N E ; A S H T A %. Y(. _ — MINNa ASH,A S NOV' LEGEND / \ A ' wig PHASE \ , \ _ fif/:f ' PHASE II 0 '- Pi4fR YRSOOE C" 6 O The project started on time but was delayed significantly due to small utility impacts. During predesign, all of the small utilities were marked in the field and surveyed and shown on the plans. Unfortunately, the marked utilities were not in the locations of the utilities when the contractor started the project. The contractor had to wait on many occasions for the private utilities to be relocated. Also, the contractor had to work around small utilities which slowed them down. There was also 11 rain delay days. Due to these delays, staff does not think all of the project will be completed this year. All of Phase 1 will be completed this year plus some of Phase II as shown on the following exhibit: I 7. - - -- HIGHWAY Na 7 I���.,-� AD 4 141 k R0 64y ' , 1 cRT �j � j i 1 i r, I 7 / c‘os° i i j 1 '"/y // _I 1 y it, i LAKE / / / � y INNEWASHTA // C� VP' \ P2 0. V 1 \S NOP\��N NINNEIYASH A i \ � LEGEND / \ \_ 69: 5 ? PHASE ~o- p1 FR-j'fn WANE.` PHASE II Phase I Weeks of 9/25 & 10/2: Utility, water main and storm sewer work begins. Week of 10/9: Road building on Tanagers Lane and North Manor Road. Week of 10/16: Concrete curb, gutter and driveway work. Week of 10/23: Grading and paving. Week of 10/30: Backfilling behind the curb, topsoil, landscaping, driveways and sod placement. Unfortunately, Washta Bay Road will not be complete before the end of the construction season. This section of road is proposed to be completed in 2018. Because Washta Bay Road will not be completed this year, staff feels the assessments for this road should be deferred until the road is substantially completed in 2018. All of Phase 1 parcels with the additional streets completed this year are proposed to be assessed as per the original schedule where interest starts accruing in October 2017. In order to change the assessment time, a public hearing is required. Staff is proposing to hold this public hearing on October 9, 2017. A neighborhood meeting to discuss this change is also proposed for October 5, 2017. If Phase II can start in early May 2018, the project is anticipated to be substantially completed mid July 2018. g:\eng\public\_2016 projects\16-01 street and utility reconstruction\communication\092517bkgd project update.docx