2018-24CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE: March 12, 2018 RESOLUTION NO: 2018-24
MOTION BY: McDonald
BY: Campion
A RESOLUTION APPROVING CHANGE ORDER NO.2 FOR CLAIMS AND
ADDITIONAL CHARGES FOR BOX CULVERT WORK
FOR THE PARK ROADIPARK PLACE IMPROVEMENT PROJECT NO. 16-04
WHEREAS, change orders are necessary to make adjustments to contract amounts due to
changes in conditions that may arise during construction; and
WHEREAS, this change order is intended to incorporate additional materials needed to
support Bridge No. l OJ39 (box culvert) into the project construction contract; and
WHEREAS, the original bid amount for this project is $856,210.45 and the cost of Change
Order No. 1 is $69,156.70; and
WHEREAS, the total amount of the construction contract will now be $925,367.15.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approves Change Order No. 2 in the amount of $69,156.70 for additional materials needed to
support Bridge No. l OJ39 (box culvert) in City Project No. 16-04.
Passed and adopted by the Chanhassen City Council this 12ah day of March, 2018.