2002-66• CITY OF CHANHASSEN CARVER AND HENNEPIN COUNTIES, MINNESOTA DATE: July 30, 2002 RESOLUTION NO: 2002-66 MOTION BY: Peterson SECONDED BY: Bovle A RESOLUTION APPROVING CHANGE ORDER NO. 1 CHANHASSEN LIBRARY PROJECT WHEREAS, on February 11, 2002, the City Council approved plans and specifications on the above-mentioned project; and WHEREAS, the attached change order provides a breakdown of costs associated with each change order item. NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby approves Change Order No. 1 for the Chanhassen Library Project in the amount of $52,508. Passed and adopted by the Chanhassen City Council this 22nd day of July 2002. ATTEST: • A"_xxf T d Gerhardt, City Manager YES Jansen Ayotte Labatt Boyle Peterson 0 Linda C. Jansen, Mayor NO ABSENT None None • • Change Order Project: Chanhassen Public Library 690 City Center Dr. Chanhassen, MN 55317 Contractor: Kraus Anderson Const'n Co 2500 Minnehaha Ave Mpls, MN 55404 The Contract is changed as follows: ■ Contractor ■ Owner ■ Architect in M + E Consults in Structural Consults C�zv MS&R Change Order Number: 1 Date: 18 June, 2002 Architect's Project No.: 2001021.00 Contract Date: 28 May 2002 Contract For: General Construction PR 1.2 Modification to interior door add $268.00 PR 1.3 Change countertops to solid surface add $3,885.00 PR 1.5 Change tile base to carpet base add $101.00 PR 1.7 Delete clearstory entry deduct $25,076.00 PR 1.8 Take Bid Alternate #9 sidewalk on east side of parking deck add $3,500.00 PR 1.11 Additional VAV boxes add $3,675.00 PR 1.12 Change water service from 6" to 8" dia add $554.00 PR 1.13 Change to sanitary waste line deduct $33.00 PR 1.14 Change cover to hot water radiation deduct $1.400.00 Subtotal this page -.58;226.00" p east` Not valid until signed by the Owner, Architect and Contractor The original Contract Sum was.............................................................................................$4,865,000.00 Net Change by previously authorized Change Orders........................................................................ $00.00 The Contract Sinn prior to this Change Order was................................................................. $4,865,000.00 The Contract Sum will be increased by this Change Order in the amount of ............................... $67;316:-00 _SL;S�C`<•t The new Contract Sum including this Change Order ivill be .................................................$4;932;316:00 The Contract Time will be increased by........................................................................................... b Days The date of Substantial Completion, resulting from this Change Order is...............................22 June, 2003 Archite tl Contractor Owner Meyer, cherer & Roc •c stle, Ltd. Kraus A 'derson Construction Co. City of Chanhassen 119 N n treet 2500 iq�}�/ ehaha Ave 90 City Center Dr Minnea ,o�is, MN 55401 Mpls MN ' 4 �� Chanhassen, MN 55317 By–�— ----- By By --__-- Date .9 %i/ D Z Date-----------_— 1 Date----��=�'–• � ��Z (� — I � l L:\2001021 CFIA\d oc\2001021 cool .doc • 0 June 18, 2002 Chanhassen Public Library Continuation Of Change Order Number 1 The Contract changes are continued as follows: PR 1.19 Change in electrical service YX....1' 'u�...nb.. .,.al¢rncorl•,ro•.. ,.,cn.,: �•,r::.�, ,..._. PR 1.SK 113 & 114 Add two masonry monument sign bases PR 1.SK 115 & 116 Add sliding grille PR 1.SK 117 Add parking barrier PR 1.SK 118 Relocate engine heater posts for city vehicles • PR 1.SK 120, 121, 122 & 123 Add the fireplace PR 2.SK 130, 131, 132, 133 & 134 Modifications to site utilities PR 2.SK 125 Add stairs to sidewalk btwn ramp and city hall PR 2.SK 125 Add railings to stairs PR 2.SK 125 Railing painting PR 2. Miscellaneous Six month rental for barricade and flasher SCO 1 Change to precast piers to support parking lighting ASI 1 Modifications to parking deck stairs Subtotal page two Total Changc Ordcr both pagcs L:UOO 1021 CHA\doc\2001021 cool .doc MS&R add $9,157.00 A4W add $14,308.00 add $7,196.00 add $7,901.00 add $6,691.00• add $11,790.00 add $3,855.00 add $1,665.00 add $936.00 add $335.00 add $421.00 add $971.00 add $1.808.00 S67,316.00 4 S�2j So g