1d Plans/Specs, MUSA Imporvements, Phase I - #04-05
CITY OF
CHANHASSEN
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317
Administration
Phone 952.227.1100
Fax 952.227.1110
Building Inspections
Phone 952.227.1180
Fax 952.227.1190
Engineering
Phone 952.227.1160
Fax 952.227.1170
Finance
Phone 952.227.1140
Fax 952.227.1110
Park & Recreation
Phone 952.227.1120
Fax 952.227.1110
Recreation Center
2310 Coulter Boulevard
Phone 952.227.1400
Fax 952.227.1404
Planning &
Natural Resources
Phone 952.227.1130
Fax 952.227.1110
Public Works
1591 Park Road
Phone 952.227.1300
Fax 952.227.1310
Senior Center
Phone 952.227.1125
Fax 952.227.1110
Web Site
www.ci.chanhassen.mn.us
LL
-
MEMORANDUM
TO:
Todd Gerhardt, City Manager
FROM:
"'""? (:) .
Paul Oehme, Die of Public Works/City Engineer \ .
DATE:
c/<j( ~
September 12, 2005
SUBJ:
Approve Plans & Specifications and Authorize Ad for Bids
2005 MUSA Improvements - Bid Package #1
Project No. 04-05
REQUESTED ACTION
The City Council is requested to approve the final plans and specifications and
authorize advertisement for bids for Bid Package #1 for the 2005 MUSA
Improvements (Bluff Creek Lowlands Public Infrastructure).
BACKGROUND
On February 28,2005, the City Council ordered the 2005 MUSA Improvements
not associated with the TH 212 project. These improvements include various
street and utility improvements within the 2005 MUSA area as detailed in the
August, 2004 Feasibility Report prepared by Kimley-Horn and Associates.
On March 28, 2005, the City Council approved a Consultant Work Order with
Kimley-Horn and Associates for preliminary design services for the 2005 MUSA
Improvements. The proposed roadway and utility plans developed through the
preliminary design process were presented to the City Council at a work session
on August 8, 2005. These improvements are as follows:
1. Roadway Improvements
· East-West Collector Roadway between Audubon Road and Powers
Boulevard.
· East-West Collector Roadway/Audubon Road Turn Lanes and Traffic
Signal.
2. Watermain Improvements
· Extension of existing trunk watermain at Lyman Boulevard to the
proposed location of the East-West Collector Roadway.
· Trunk watermain along the East-West Collector Roadway between
Audubon Road and Powers Boulevard.
The City ot Chanhassen · A growing community with clean lakes, quality schools, a charming downtown, thriving businesses, winding trails, and beautiful parks A great place to live, work, and play
Todd Gerhardt
September 12, 2005
Page 2
3. Sanitary Sewer Improvements
. Extension of trunk sanitary sewer from an existing lift station along
the south side of Lyman Boulevard east of Audubon Boulevard.
. Trunk sanitary sewer along the East-West Collector Roadway between
Audubon Road and Powers Boulevard.
4. Storm Drainage Improvements
. Storm sewer and ponding improvements along the East-West Collector
Roadway between Audubon Road and Powers Boulevard.
On August 22, 2005, the City Council authorized the preparation of final plans
and specifications for the project and approved a consultant work order with
Kimley-Hom and Associates for the final design services. Based upon current
estimates, the total estimated project cost of these infrastructure improvements is
approximately $8.5 million.
DISCUSSION
Two separate bid packages are being prepared for the project to allow some of the
construction to occur in 2005. Staff is requesting City Council approval of the
plans and specifications for only Bid Package #1 at this time. The improvements
are shown on the attached drawing. The following is a description of the
improvements included as a part of Bid Package #1.
Bid Package #1 - Bluff Creek Bridge and Trunk Watermain and Sanitary Sewer
. Installation of trunk watermain along the east side of Bluff Creek between
Lyman Boulevard and the East-West Collector Roadway.
. Installation of trunk sanitary sewer along the east side of Bluff Creek between
Lyman Boulevard and the East-West Collector Roadway.
. Construction of a bridge across Bluff Creek including the realignment of a
portion of the creek channel.
The proposed schedule for the Bid Package #1 improvements is as follows:
Approve Plans & Specifications and Authorize Ad for Bids
Accept Preliminary Assessment Roll & Call Assessment Hearing
Bid Opening
Assessment Hearing and A ward Contract
Start Construction
Construction Complete
Sept. 12,2005
Sept. 26, 2005
Oct. 14,2005
Oct. 24, 2005
Nov. 7, 2005
Feb. 3,2006
G:\ENGIPUBLlGQ4-05 2005 MUSA\91205 bkgd 2005 MUSA Approve Plans phase 1.OOc
Todd Gerhardt
September 12,2005
Page 3
These improvements are proposed to be constructed during the late fall/early
winter months of 2005 to take advantage of frozen ground conditions and low
flows in Bluff Creek.
The ability to construct Bid Package #1 during 2005 is dependent upon the City
receiving right-of-way/easements or a right-of-entry from the Degler property.
Staff is currently in discussions with the Degler's to obtain the required right-of-
way/easements or right-of-entry. We are working to have this issue resolved prior
to the October 24, 2005 date for the award of the construction contract for Bid
Package #1.
A copy of the final plans and specifications for Bid Package #1 are available for
review in the Engineering Department.
Future Bid Package #2 will include the remainder of the proposed public
infrastructure improvements for the 2005 MUSA area. Staff is currently planning
to have the final plans and specifications for Bid Package #2 completed for City
Council approval on January 23, 2006. Construction of the Bid Package #2
improvements is planned to begin in May, 2006.
Attachment
c: Jon Horn, Kimley-Hom & Associates
Kate Aanenson, Community Development Director
G:\ENGIPUBLlCI04-05 2005 MUSA\91205 bkgd 2005 MUS A Approve Plans phase l.doc
,
./
u
) \ / L _ ..L::- 'S
\ I ....-/ /' I ~
~ L~OU~(CSAH 18)
\
1
.J
r--
I
-------r- .
~
I,' 0,
, L~
'iD~~
I
1
",I
r-
PROPOSED 21"
'fR~NK SANITARY
SEWER
II : :.v~il \S~
I " {:' I
I" :'
I
I
II r-- \
!] ('-- )
,---J
I
I
-r---r-----
I I ~ I
"'-- /
,
, ,
, , .
I ~. .. . ...
'\ . . . ..
\ ..,' .
. .
, '
I. .. .. ." ..
" .
~
~,
~/' ,
""'Ef
o
I
250
500
I
HORIZONTAL
SCALE IN FEET
2550 uNIVERSITY AVE. WEST, SUITE 345N
ST. PAUL. MINNESOTA 55114
TEL NO. (651) 645-4197
FAX. NO. (651) 645-5116
CITY OF CHANHASSEN
BLUFF CREEK LOWLANDS
PUBLIC INFRASTRUCTURE IMPROVEMENTS
CITY PROJECT NO. 04-05
BID PACKAGE 1
Cl1Y OF
CHANHASSEN
~_.. Kimley-Horn
~ _ ~ and Associates, Inc.