2i 2006 St Imp Project Feas Study CITY OF CHANHASSEN 7700 Market Boulevard PO Box 147 Chanhassen, MN 55317 Administration Phone: 952.227.1100 Fax: 952.227.1110 Building Inspections Phone: 952.227.1180 Fax: 952.227.1190 Engineering Phone: 952.227.1160 Fax: 952.227.1170 Finance Phone: 952.227.1140 Fax: 952.227.1110 Park & Recreation Phone: 952.227.1120 Fax: 952.227.1110 Recreation Center 2310 Coulter Boulevard Phone: 952.227.1400 Fax: 952.227.1404 Planning & Natural Resources Phone: 952.227.1130 Fax: 952.227.1110 Public Works 1591 Park Road Phone: 952.227.1300 Fax: 952.227.1310 Senior Center Phone: 952.227.1125 Fax: 952.227.1110 Web Site www.ci.chanhassen.mn.us I ,)..Jv MEMORANDUM cJ- "'V' . TO: Paul Oehme, City Engineer/Dir. of Public Works " FROM: Alyson Fauske, Assistant City Engineer CAt cJ~'" DATE: January 9,2006 SUBJ: Receive Feasibility Study and Call for Public Hearings for the 2006 Street Improvement Project No. 06-01 BACKGROUND On September 26, 2005, Council authorized the preparation of the 2006 Street Improvement Feasibility Report. On December 8, 2005, staff held an open house meeting with residents in the Koehnen neighborhood to discuss the proposed street and utility reconstruction project. On December 15,2005 staff held an open house meeting with residents in the Chanhassen Hills neighborhood to discuss the proposed street rehabilitation project. DISCUSSION The street improvements proposed for 2006 were identified using the City's Pavement Management Program and because of the utility problems in these areas. Streets are recommended for reconstruction in the Koehnen area. These streets are 35 years old and are in need of replacement and do not have concrete curb and gutter. The reconstruction area includes approximately 1.05 miles of street, including West 63rd Street, Koehnen Circle East, Koehnen Circle West, Cardinal Avenue, Blue Jay Circle, Audubon Circle and Yosemite Avenue (from 6440 Yosemite Avenue to the City limits). Concrete curb and gutter will be included in the street design. Also, the street improvement project will include replacement of all watermain, replacement of some sanitary sewer, installation of storm sewer and construction of storm water treatment ponds. The watermain in this area is cast iron, which has resulted in 23 documented watermain breaks. It is recommended to replace the watermain in this area along with the water services in the right-of-way. Televising of the sanitary sewer indicates that portions of this utility are "egged", sagging and/or cracked. Bolton & Menk, the consultant engineer the City has The City 01 Chanhassen . A growing community with clean lakes, quality schools, a Charming downtown, thriving businesses, winding trails, and beautiful parks. A great place to live, work, and play. Paul Oehme January 9,2006 Page 2 contracted for this project, recommends that portions of the sanitary sewer exhibiting "extreme" sagging or segments that are cracked be replaced. Storm sewer will be installed and will outlet to one of three ponds that will be constructed in conjunction with the project. The ponds will treat the runoff before discharging to other water bodies. Forty percent (40%) of the street rehabilitation costs are proposed to be assessed to the benefiting property owners within the project area. The preliminary assessment amount for the Koehnen area is $7,100110t and is proposed to be assessed over a lO-year period at 6% interest. Approximately 25 residents attended the Koehnen area open house on December 8,2005. The following generalizes the questions and comments received at the open house: . Why are the anticipated assessment costs so high? . Who decided that these roads need to be reconstructed? . Why is the City's standard cul-de-sac 90 feet in diameter? It seems large. . Upgrading Yosemite will increase the traffic volume on the road. . Will trees be removed? . What is the proposed timeline for this project? All property owners' questions were answer at the meeting or with a follow up letter or phone call. The project and the feasibility report also include resurfacing or rehabilitation of the streets in the Chanhassen Hills neighborhood. These streets are 15 years old and are recommended for milling and overlaying. Improvement consists of milling the pavement and paving a minimum of 2" bituminous. Damaged "alligatored" pavement areas will be removed and repaved prior to the overlay. Severely damaged curb will be replaced. Some draintile will be included in the project. Forty percent (40%) of the street rehabilitation costs are proposed to be assessed to the benefiting property owners within the project area. The preliminary assessment amount for the Chanhassen Hills area is $1,698.15110t and is proposed to be assessed over an 8-year period at 6% interest. Four residents attended the Chanhassen Hills area open house on December 15, 2005. The following generalizes the questions and comments received at the open house: Paul Oehme January 9, 2006 Page 3 . Why doesn't the City pay for the entire project cost? . Who decided these streets need to be worked on? . What is the project schedule? . Will Draintile be included in the project? All property owners' questions were answer at the meeting or with a follow up letter or phone call. Final assessment amounts will be based on the consultation report the Engineering Department is working on with the City Attorney. This report is expected to be completed by the end of January, 2006. Also included in this year's street project are proposed improvements to the parking lots at Lake Ann Park. Most of the drives and parking areas are in very poor condition and are in need of reconstruction. The improvements include reconstruction of the roadways, realignment of roadways, reconstruction of parking areas and overlay of parking areas. Also included will be placement of concrete curb and gutter in parking areas. These components of the project and the feasibility report will be presented to City Council at the next meeting prior to the public hearing. Copies of the feasibility report are available in the Engineering Department. Funding for this project is proposed as follows: ITEM ESTIMA TED COST Street Reconstruction $ 1,561,073.00 Rehabilitation Area (Chanhassen Hills) 661,300.00 Subtotal, Streets $ 2,222,373.00 Lake Ann Park $ 321,235.00 Storm Sewer 586,011.00 Sanitary Sewer Reconstruction 185,679.00 Watermain Reconstruction 544,585.00 TOTAL $ 3,859,883.00 2006 CIP 2006 CIP Budget Project Number Amount $ 500,000.00 ST-012 (MSA) 1,600,000.00 ST-012 ST -018 (Pvmt. 125,000.00 Mgmt.) $ 2,225,000.00 $ 350,000.00 PK&T -051 400,000.00 SWMP-019 310,000.00 SS-014 440,000.00 W -024 $ 3,725,000.00 Paul Oehme January 9,2006 Page 4 The estimated costs for storm sewer improvements are higher than the budgeted amount since the detailed storm sewer design was not complete when the budget amount was determined. The estimated watermain costs are high due to the unforeseen increase in the cost of watermain pipe. The tentative schedule for this project is as follows: Public Hearing Koehnen Area Public Hearing Chanhassen Hills Area Bid Opening Neighborhood Meeting Assessment Hearing! A ward Contract Neighborhood Meeting Start Construction Construction Complete January 23,2005 February 13, 2005 March 16,2006 April 5, 2006 April 23, 2006 May 3, 2006 May 15, 2006 August 25, 2006 RECOMMENDA TION Staff recommends that City Council accept the feasibility study and call for public hearings for the 2006 Street Improvement, Project No. 06-01. Attachments: 1. Resolution 2. Location Maps 3. CIF Pages c: Marcus Thomas, Bolton & Menk G:\ENG\PUBLIC\06-01 2006 Street Improvements\01-09-06 CC approve feas report. doc CITY OF CHANHASSEN CARVER AND HENNEPIN COUNTIES, MINNESOTA DATE: Januarv 9. 2006 RESOLUTION NO: 2006- MOTION BY: SECONDED BY: A RESOLUTION ACCEPTING FEASIBILITY STUDY; CALL FOR PUBLIC HEARINGS - PROJECT NO. 06-01 WHEREAS, pursuant to resolution of the Council adopted September 29, 2005, a report has been prepared by Bolton & Menk, Inc. with reference to the above-referenced project, and this report being received by the Council January 9,2006, and WHEREAS, the report provides information regarding whether the proposed project is necessary, cost-effective, and feasible, NOW, THEREFORE, BE IT RESOLVED by the Chanhassen City Council: 1. The Council will consider the improvement of such project in accordance with the report and the assessment of abutting property for all or a portion of the cost of the improvement pursuant to Minnesota Statutes, Chapter 429 at an estimated total cost of the improvements of $3,859,883.00. 2. A public hearing shall be held on such proposed improvement on the 23rd day of January, 2006 for the Koehnen Area Improvement and the 13th day of February, 2006 for the Chanhassen Hills Area Improvements, in the Council Chambers of City Hall at 7:00 PM and the clerk shall give mailed and published notice of such hearing and improvement as required by law. Passed and adopted by the Chanhassen City Council this 9th day of January, 2006. A TIEST: Todd Gerhardt, City Manager Thomas A. Furlong, Mayor YES NO ABSENT c:t .9 ~ = ,.. u 8 u ~ ~ ~ ~ 51 \0 o o N I: Ii ,; i ::-1 L_ 3ffW3SQ,,) i , ~U, 1! .........\-T-!~~-iS~~~""~~ i: .~I , ". - i -\>."'i. ... , :i c~~e~__- j i I[ " I, I I' 1;- Ii " Ii Ii Ii_____ _"'_. I' ' I: " " 'i " " Ii I Ii I Ii I' Ii 'i Ii I, Ii ,i " ,i Ii Ii " ....-. I ,,~ " U ':I:, .") ,0 .000 ; j : !' _0" _ H i~_ _ ... 1C/) :-'-'-'uoqnpnv iU l,- iM '<0 i_...,__~ ____ ie/) .~ i en"",---',- " 'co iw lQ) l(j iL- 1(3-- .. Ie '0) Ie l.c [0) r~ ,--_.,,--/- ----, -.--; i i-.--- , , i ~---- u" ---I ! ~" '~ ':>.0 i\,\0Q; , if--iABr--ani8 , I too iu la.... IC"") !<O ! ...... 'IJI !~ I ---.-----: " ! I I ' leu!pJe:) L. .' '__ , I; I' I[ .___m:, Ii- I: L.__ Ii " I- t Iii I) : I, Ii ( I' I, I I' I I , l~! ,.- , I i, I, ~' ....... ie/) r~--- !o) i ~.... 1.- i() j--.c---- to) Ie 1 ~..____._ 0) o ~ -----{ , ~. ,(J \ :..... I --!e !~ r~ ; ro ! ',_;' _._ -'-'<1) , .....e '.c " .' r"\{\'< _ .. 0. '~v.. "-flee. -- / ~\{\g/ . \ .. ~ (b , c:' ,'co i ..JI ~\ '-:;) '~'-'-- -'. --:::,.0 }i:) --0, ':J, \ .v\_ .' '" ~velJ!fji-" .., -"" "'-" --., "-: .... ,(3 ',0) '0) i'O i'.C m -it:: :co a.. . '/~0 ,~ Q '.. .... '- c::- eo '(I) co (b ~ ,'ir -\~-\" C~\.- 1 = o ~ P:: \0 o ,..- ;3 tll A. ,..- rIJ ... (.) Il) '0' ~ ~ ~ "5 ~ ,..- ~ ~ ,..- c:; .9 u ~ ~ (/) Q) ~ ~ Q) ~ \D o o N ror .. ."-.!..--.,....N--T-~Fhl--i _ ).. :.q r i. _ L_1.,.:..., "' .' -----, , . . ./""\' '--, , .. --~ .......1. r' : ; I :..' .... . I '1___ l ........_. ' ,..--_~_~'j If- i' ",., ..- ! i ~S:::" . o rtf). ': ':J..i ,.... -, I }([) i ScJ(3 z <.Ii( L..akef\l1r1 ~,.~4 > ' "tot {r ,,:;} *..........~.'lio\ ~.. .'"f. ";I" :; W 78th Street W 78th 5 Proposed Lake Ann Park Improvements N + .-...._. Reconstruction ""'-' Realignment of Street ~ Expand/Reconstruction Parking Lot ...... Remove Street Current Park Streets 18881 Reconstruction Parking Lot B Concessions ""'-' New Curb Current Parking Lots August 8, 2005 g: \ellg \101eell \ellg projects \ Palll \ LnkeAIIIIPk Capital Improvement Program City of Chanhassen, MN ST-012 2006 thru 2010 Contact Unassigned Department Street bnprovements Account # 1 Account # 3 (hUJA '-', J t, ..10; , v:Jl yf) ,\IV Type Improvement Useful Life Unassigned Category Streets/Highways Priority n1a Project # Project Name Annual Street Improvement Program Account #2 Total Project Cost $9,900,000 Description Annual project to rehabilitate and reconstruct streets in the City. Current 5-year plan shows the following neighborhood areas: 2006 2007 2008 2009 2010 Residential Koehnen Area S ShoreDr Laredo Dr/Ln Chaparral Erie Ave Area Chan Hills Area Bighorn Dr Saratoga Dr/Cir Lone Cedar Area Kiowa Trail ~Jill]~ ch; PI'if.W ,.... TJ}. Triple Crown Est MSA Audubon Rd So W 78th St Justification The City uses a Pavement Management System to monitor the condition of the City streets. While proper maintenance extends the life of the street and is cost effective, a street will eventually deteriorate to a point that further maintenance is no longer cost effective. Rehabilitation projects extend the life of the street. In cases with utility or sub grade issues, reconstruction of the street is necessary. A feasibility study is written to consider the merits of the project and scope of work. Expenditures Construction 2006 2,100,000 2,100,000 2007 3,200,000 3,200,000 2008 1,400,000 1,400,000 2009 1,300,000 1,300,000 2010 1,900,000 1,900,000 Total 9,900,000 9,900,000 Total Funding Sources 2006 2007 2008 2009 2010 Total Assessment/Revolving Assess 1,600,000 1,100,000 1,400,000 1,000,000 1,900,000 7,000,000 MSA 500,000 2,100,000 300,000 2,900,000 Total 2,100,000 3,200,000 1,400,000 1,300,000 1,900,000 9,900,000 Operational Impact/Other This project may decrease maintenance costs. Page 1 Friday, November 04, 2005 Capital Improvement Program City of C1u1iIhassen, MN ST-018 2006 thru 2010 Project # Project Name Pavement Management Account # 1 420-0000-4751 Account # 3 Account #2 Contact Paul Oehme Department Street Improvements Type Maintenance Useful Life 7-10 years Category StreetslHighways Priority n/a Total Project Cost $1,925,000 Description This project will provide maintenance such as crack sealing, seal~oating, pothole patching for city streets. The projects will be detennined annually based on the pavement condition index as generated by the pavement management program. Justification This will provide a centralized funding mechanism that will help reduce the effect on General Fund operating expenditures. Expenditur~s Maintenance 2006 385,000 385,000 2007 385,000 385,000 2008 385,000 385,000 2009 385,000 385,000 Total Funding Sources MSA Tax Levy 2006 168,500 216,500 385,000 2007 134,250 250,750 385,000 2008 117,125 267,875 385,000 2009 117,125 267,875 385,000 Total 2010 385,000 385,000 Total 1,925,000 1,925,000 2010 117,125 267,875 385,000 Total 654,125 1,270,875 1,925,000 OperritionoI Impact/Other This will reduce the need to reconstruct streets and will allow us to more closely match the life of streets to the utility lines that lie underneath them. This will allow better coordination when we need to replace water and sewer lines with replacing roads. . Page 88 Tuesday, November OJ, 2005 . Capital Improvement Program City ofChanhassen, MN 2006 thrn 2010 Contact Department Park & Trail Improvements Account # 1 101-0000-4702 Account # 3 Type Improvement Useful Life 30 Years Category Park Priority nla Project # PK&T-051 Project Name Lake Ann Park Road and Parking Lot Rehabilitation Account #2 Total Project Cost $395,000 Description Reconstruction and resurfacing of six parking lots and 1/2 mile of asphalt roadway in lake Ann Park. Justification This portion of the existing improvements are 20-35 years old and have reached the end of their useful life. The poor conditions of these hard surface areas are a significant distraction to the overall quality of the remainder of the park's attractions. Expenditures Construction 2006 395,000 395,000 2007 2008 2009 2010 Total 395,000 395,000 Total Funding Sources . General Fund 2006 395,000 395,000 2007 2008 2009 2010 Total 395,000 395,000 Total Operational Impact/Other Page 55 Tuesday, November 01,2005 Capital Improvement Program City of Chanhossen, MN SWMP-019 2006. thru 2010 Contact Unassigned Department Surface Water Management Type Improvement Useful Life Unassigned Category SWMP Priority nla Project # Project Name Street Improvement Projects - Storm Water Mgmt Account # 1 720-0000-4702 Account # 3 Account #2 Total Project Cost $1,100,000 Description An annual amount set aside for storm water management infrastructure construction or expansion associated with street improvement projects undertaken by the engineering and public works departments. Justification. Street improvement projects frequently require construction or expansion of storm water management infrastructure in order to comply with federal, state and local regulations, as well as protecting existing and proposed development adjacent to the projects: Expenditures Construction 2006 400,000 400,000 2007 150,000 150,000 2008 300,000 300,000 2009 100,000 100,000 2010 150,000 150,000 Total 1,100,000 1,100,000 Total Funding Sources Surface Water Utility Fund Total 2006 400,000 400,000 2007 150,000 150,000 2008 300,000 300,000 2009 100,000 100,000 2010 150,000 150,000 Total 1,100,000 1,100,000 OperatiolUll Impact/Other Inventory, inspection and maintenance of new infrastructure will be required. Citywide. No map Page 91 Tuesday, November 01,2005 Capital Improvement Program City of Chanhassen, MN S8-014 2006. thru 2010 Contact Unassigned Department Sanitary Sewer Improvements Account # 1 Account #2 Account # 3 Type hnprovement Useful Life Unassigned Category Utilities Priority nla Project # Project Name Sanitary Sewer Replacement Total Project Cost $810,000 Description. Replacement or rehabilitation of existing sanitary sewer lines in conjunction with the reconstruction of the City street. Justification The City considers the condition of the existing utilities in the process to select streets for rehabilitation in an effort to realize cost savings by consolidating these projects. . Expenditures Construction 2006 310,000 310,000 2007 2008 250,000 250,000 2009 2010 250,000 250,000 Total 810,000 810,000 Total Funding Sources Sewer Utility Fund 2006 310,000 310,000 2007 2008 250,000 250,000 2009 2010 250,000 250,000 Total 810,000 810,000 Total Operationol Impact/Other This project will decrease maintenance costs. Page 78 Tuesday, November 01, 2005 Capital Improvement Program City ofChonhassen,MN 2006 thru 2010 Contact Unassigned Department Water System Improvements Type Improvement Useful Life Unassigned Category Utilities Priority n1a Project # W-024 Project Name Watermain Replacement Account # 1 Account # 3 Account #2 Description. Replacement of existing water main lines in coordination with the recOIlstruction of the City street. Total Project Cost $1,240,000 Justification The City considers the condition of the existing utilities in the process to select streets for rehabilitation in an effort to realize cost savings by consolidating these projects and also to avoid potential cuts in recently improved streets. If significant repairs are necessary to the existing water main, replacement may be the most cost effective option. Given the highly corrosive soils in the City, water main replacement is an ongoing project in the City. Expenditures Construction 2006 440,000 440,000 2007 2008 350,000 . 350,000 2009 2010 450,000 450,000 Total 1,240,000 1,240,000 Total Funding Sources Water Utility Fund 2006 440,000 440,000 2007 2008 350,000 350,000 2009 2010 450,000 450,000 Total 1,240,000 1,240,000 Total Operational Impact/Other These projects will decrease maintenance costs. Page 102 Tuesday, November 01, 2005