97-58 CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE: August 11~ 1997
MOTION BY: Engel
RESOLUTION NO: 97-58
SECONDED BY:
Berquist
A RESOLUTION APPROVING CHANGE ORDER NO. 3 FOR LYMAN BOULEVARD/
LAKE RH~EY AREA TRUNK UTILITIES, PROJECT NO. 93-32B
WHEREAS, on October 9, 1995, the City Council awarded the bid for the above mentioned project with
Change Order No. 1 being approved on February 26, 1996 and Change Order No. 2 being approved November 25,
1996; and
WHEREAS, Change Order No. 3 consists of four primary elements as follows:
Furnish 7,100 cubic yards of additional material on east surcharge area.
Negotiated and paid at the unit price of $6.54 per cubic yard. Quantity
was not included in original bid quantity.
46,452.00
Placement of 1-1/2" foundation rock to maintain access for residents. Material
was used on rain days and to provide temporary roads during the project.
Contractor furnished and placed 2,308.16 ton at a unit price of $5.93 per ton.
13,687.39
Excavation ofponding areas associated with storm sewer improvements. Ponding
areas were to be graded by the developer prior to the City's project. Developer
did not grade when anticipated. Contractor removed 7,000 cubic years at
common excavation unit price of $3.50 per cubic yard.
$24,500.00
4. Removal of 7,100 cubic years of surcharge material at common excavation unit
price of $3.50 per cubic yard. Quantity was not included in original bid quantity. $24,850.00
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby approves Change
Order No. 2 in the amount of $109,489.39 yielding a revised contract amount of $2,607,875.77.
Passed and adopted by the Chanhassen City Council this 11th day of August, 1997.
ATTEST:
Don Ashworth, City Manager Nancy Mancino, Mayor