96-103DATE:
MOTION BY:
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
November 25~ 1996 RESOLUTION NO: 96-103
Berquist SECONDED BY: Senn
A RESOLUTION APPROVING CHANGE ORDER NO. 2 FOR
LYMAN BOULEVARD, PROJECT NO. 93-32B
WHEREAS, on October 9, 1995, the City Council awarded the bid for the above
mentioned project with Change Order No. 1 being approved on February 26, 1996; and
WHEREAS, Change Order No. 2 consists of four primary elements as follows:
1. Lower watermain at T.H. 101 and Lyman Boulevard.
2. Change in outlet structure.
3. Excavating drain tile and pumping pond along Lyman Boulevard.
4. Addition of storm sewer through the Sunny Slope area.
WHEREAS, the total of Change Order No. 2 is $37,228.33, with $14,418.17 to be
reimbursed by the developer of the Fawn Hill development.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council
hereby approves Change Order No. 2 in the amount of $37,228.33, yielding a revised
contract amount of $2,498,386.38 for the Lyman Boulevard and Lake Riley Area Trunk
Utility Improvement Project No. 93-32B
Passed and adopted by the Chanhassen City Council this 25th day of November, 1996.
ATTEST:
Don Ashworth, City Clerk/Manager ~)onald J. Chr~el, Mayor
YES
Dockendorf
Mason
Senn
Berquist
NO
None
ABSENT
Chmiel