95-98 CITY OF CHANHASSEN
CA FI VEil A ND HENNEPIN COUNTIES, MINNE$OTA
DA TE: September 25, 1995
RESOLUTION NO: 95-98
MOTION BY: Mason
SECONDED B Y: Dockendorf
A RESOLUTION APPROVING CHANGE ORDER NO. 2 FOR
WA TER SUPPLY WELL NO. 7, PROJECT 94-3
WHEREAS, on July 25, 1994, the City Council awarded the bid for the above
mentioned project with Change Order No 1 being approved on November 14, 1994; and
WHEREAS, Change Order No. 2 involves the following:
Part1.
Backfilling and grading of the wellsite area with an add amount of
$19,874.57.
Part 2.
Additional costs due the contractor for delays in being able to start
the drilling operations with an add amount of $3,279.10.
Part 3.
Deduct item for less favorable prices on granular borrow
and Class 5 in the weft drilling contract with a deduct amount
of $8,436.00
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council
hereby approves Change Order No. 2 to the Water Supply Well No. 7, Project No. 94-3,
contract in the amount of $14, 717. 67 yielding a revised contract amount of $179, 713. 67
Passed and adopted by the Chanhassen City Council this 25th day of
September, 1995.
ATTEST:
Do[~ Ash--~orth, ~"~lerk/Manager
YES
NO
ABSENT
Chmiel
Berquist
Senn
Dockendorf
Mason
None
None