Loading...
1k. 1&2 Woodridge Hts-Grading Plan & Extension to Landscape Requirements CITY OF CHAHHASSEH 1 ~, -1...2 --Ii...., .......1' ,.. 690 COULTER DRIVE. P.O. BOX 147. CHANHASSEN, MINNESOTA 55317 (612) 937-1900 . FAX (612) 937-5739 MEMORANDUM TO: Charles Folch, Director of Public Works FROM: Dave Hempel, Assistant City Engineer Jill Sinclair, Environmental Resource Specialis DATE: December 3,1997 SUBJ: Approve Revised Grading Plan and Approve Request for Time Extension for Landscape Improvements - W oodridge Heights and W oodridge Heights 2nd Additions - Project No. 97-5 SITE GRADING Over the course of site grading it was found that earthwork quantities were significantly off. The project generated approximately 20,000 cubic yards of excess material on the site. The combination of revising lot elevations as well as exporting the material from the site, the developer has disposed of all of the excess material. At the time of construction staff felt that the revisions to the grading plan were not significant enough to halt construction and bring the revised plans back to the City Council for approval. All the grading work has been completed per the revised plan and all disturbed areas re-seeded. Most of the grading changes occurred between Manchester Drive and Briarwood Court and adjacent to Highgate Circle. Since the approved grading plan has now been revised it is appropriate to request the City Council approve the revised grading plan and amend the development contract accordingly. It is therefore recommended that the City Council approved the revised grading and erosion control plan dated July 15, 1997, revised October 21, 1997, prepared by Westwood Professional Services, Inc. conditioned upon the developer executing Addendum A to the development contract for Woodridge Heights and pay the City an administration and recording fee of $300. LANDSCAPING Due to time constraints during the 1997 planting season, Centex Homes was unable to complete the required landscaping along Lake Lucy Road and Block 3, Woodridge Heights as specified in Charles Folch December 3, 1997 Page 2 the Development Contract for W oodridge Heights. Centex Homes requests an extension until June 15, 1998. Staff concurs with the extension and recommends adding the condition that buffer yardilandscaping in the rear yards of Block 3, Woodridge Heights, along Lake Lucy Road and on the slope of Outlot A, Woodridge Heights 2nd Addition also be installed by June 15, 1998. Since the original deadline was a condition of plat approval, the City Council will need to approve this request and amend the development contract accordingly. It is therefore recommended that the City Council grant the developer a time extension to June 15, 1998 to complete the buffer yard landscape improvements in the rear yards of Block 3, Woodridge Heights, along Lake Lucy Road and Outlot A, Woodridge Heights 2nd Addition. c: Ryan Gideon, Centex Homes Attachments: 1. 2. 3. Revised grading plan. Letter dated November 10, 1997 from Dwight Jelle, Westwood. Letter dated October 29,1997 from Ryan Gideon, Centex Homes. g:'eng't'rojects\woodridge'addendum memo.doc