CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
November 14, 1994
MOTION BY: Mason
RESOLUTION NO: 94-120
SECONDED BY: Dockendoff
A RESOLUTION APPROVING CHANGE ORDER NO. 1,
WELL NO. 7, PROJECT 94-3
WHEREAS, on July 25, 1994, the City Council awarded the bid for Well No. 7, Project
No. 94-3; and
WHEREAS, the contract documents specified a start date of August 15, 1994 or as late
as October 3, 1994; and
WHEREAS, the contract specified if the start date is delayed, the completion date for the
project shall be extended an equal number of calendar days; and
WHEREAS, the site was not available to the contractor until October 25, 1994.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approves Change Order No. 1 to the Well No. 7, Project No. 94-3, extending the original contract
completion date by an additional 62 days due to the delay in the actual start of the project.
Passed and adopted by the Chanhassen City Council this 14th day of November, 1994.