WHEREAS, on September 14, 1992, the City Council awarded the bid for Upper Bluff
Creek Trunk Utility Improvement Project No. 91-17; with Change Order No. 1 being approved
December 14, 1992; and
WHEREAS, Change Order No. 2 will be administrated through the Upper Bluff Creek
Trunk Utility Project, for the purpose of constructing a portion of the trunk sanitary sewer
through a wetland area adjacent to the Lake Ann Interceptor for the Johnson/Dolejsi/Tumer
Project No. 92-5.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approves Change Order No. 2 for Upper Bluff Creek Trunk Project No. 91-17, for the purposes
of completing the wetland sanitary sewer crossing for the Johnson/Dolejsi/Tumer Project No. 92-
5, with an estimated cost of $67,690, with the following conditions:
1. The work being initiated prior to spring thaw.
2. All associated costs be the responsibility of Project No. 92-5.
Passed and adopted by the Chanhassen City Council this 22nd day of February, 1993.