93-68 CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE: August 9, 1993
RESOLUTION NO: 93-68
MOTION BY: Senn SECONDED BY: Dockendorf
A RESOLUTION APPROVING CONTRACT AMENDMENT TO WEST 78TH STREET
DETACHMENT AND DOWNTOWN IMPROVEMENT PROJECT 92-3 FOR EXTENDED
WORK HOURS AND OVERTIME COMPENSATION
WHEREAS, the unseasonably wet and cool spring and summer has been very detrimental
to all types of construction projects; and
WHEREAS, the West 78th Street Detachment and Downtown Project is currently 3
weeks behind schedule, the contractor is requesting that the Council authorize the City Engineer
to administratively approve work on Sunday, as needed, if a rain day should occur during the
normal work week; and
WHEREAS, the timely completion of this portion of the project west of Kerber
Boulevard and the installation of traffic signals are critical elements in the opening of the Target
store in October.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council approves the
contract amendment to West 78th Street Detachment and Downtown Improvement Project 92-3,
for extended work hours and overtime compensation as follows:
le
The city engineer be authorized to approve work on a Sunday if a work day
during the week is lost due to weather.
2. The City share 50% of the premium pay portion of the labor overtime hours.
e
The Stage I completion date be revised to September 21, 1993 and Stage II
completion be revised to November 8, 1993.
Passed and adopted by the Chanhassen City Council this 9th day of August, 1993.